Created byFuzzy Cloud

Supreme Court of India

M.P. HOUSING BOARDversusANIL KUMAR KHIWANI

Citation
2005 INSC 140
Decided
14 March 2005
Disposal
Appeal(s) allowed

Holding

Interim injunctions should not be granted in self‑financing construction schemes where price escalation is permissible, and the developer may adjust the cost proportionately to the estimated price.

Summary

The M.P. Housing Board advertised residential and commercial units, stating an estimated cost of Rs 39 lacs for a showroom. The respondent, Anil Kumar Khiwani, applied and paid the 10 % registration amount based on that advertisement. After detailed project reports, the Board revised the actual cost to Rs 71 lacs and gave contributors the option to withdraw, which the respondent refused. He filed a suit for declaration and a temporary injunction restraining the Board from allotting the showroom to anyone else; the trial court granted the injunction, which the High Court upheld. On appeal, the Supreme Court held that courts should be cautious in granting interim injunctions in self‑financing schemes because such orders can jeopardise the entire project, and that the Board is entitled to adjust the price in accordance with actual construction costs, subject to proportionality. The Court set aside the lower courts’ orders and remitted the matter to the trial court for fresh consideration of the price adjustment. No costs were awarded.

Issues considered

  • Whether the advertisement constituted a fixed‑price offer of Rs 39 lacs or merely an estimated cost subject to revision.
  • Whether the Board may increase the price of a unit in a self‑financing scheme after registration.
  • Whether an interim injunction under Order 39 of the CPC should be granted in such circumstances.
  • Whether the trial court erred in restraining the Board from allotting the showroom pending final determination.

Legislation cited

Subjects

self‑financing schemeinterim injunctioncost escalationadvertisement offerCivil Procedure CodeOrder 39housing boardconstruction costestimated costpublic policy

Judgment

                        M.P. HOUSING BOARD                                     A
                                    v.
                       ANIL KUMAR KHIW ANI

                           MARCH 14, 2005

           [ARIJIT PASAYAT AND S.H. KAPADIA, JJ.]                              B

       Code of Civil Procedure, 1908-0rder 39 Rule I-Commercial
Complex-Scheme of construction-Under self financing scheme-
Advertisement in newspapers inviting offers giving estimated cost-Application
by a buyer-Subsequentlycost enhanced-Refusal to pay the enhanced cost- C
Cancellation ofregistration-Suit by buyer-Interim injunction by trial Court-
Confirmed by High Court-On appeal, held : Grant of interim injunction not
justified-Courts should be slow in interfering at interim stage with schemes
based on costing-Interim injunction at initial stage would result in entire
collapse of project-Matter remitted to trial Court-Urban Development.         D
      Appellant-Board issued advertisements in a local newspaper and
'Times of India' inviting offers to subscribe to residential and commercial
schemes. As per the advertisement in 'Times of India' the cost of a
showroom in a commercial complex was Rs. 39 lacs while according to
advertisement in the local newspaper, Rs. 39 lacs was the estimated cost. E
Respondent-buyer, on the basis of advertisement in 'Times of India' ·
applied for a showroom, with Rs. 3.90 lacs i.e. 10% of the cost towards .
registration amount. Thereafter, the appellant after preparing detailed
project report and getting approval from the concerned autl·orities,
worked out the actual cost which came to Rs. 2000 per sq. ft. and the cost
of show room came to Rs. 71 lacs. Hence appellant called upon all the ' F
contributors including the respondent giving an option to withdraw from
the Scheme if they did not agree with the proposed actual cost. Respondent
was not willing either to withdraw from the Scheme or to accept the
actual cost.

      Appellant called upon the respondent to deposit Rs. 71 lacs which
                                                                               .G
was objected by respondent. Ultimately appellant cancelled the registration
of the appellant.

      Respondent filed a suit for declaration and injunction and application
                                   765                                         H
    766                   SUPREME COURT REPORTS                   [2005] 2 S.C.R.

A for temporary injunction. Trial Court by its interim order restrained the
    Board from allotting the showroom in dispute to any other person till
    final disposal of the suit. Appeals against order of trial Court was
    dismissed by High Court.

          In appeal to this Court appellant contended that in advertisement
B. in 'Times of India' the word 'estimated' inadvertently stood omitted;
    and that respondent was fully aware that Rs. 39 lacks was the estimated
    cost as terms and conditions attached to the application form filled in by
    the respondent specifically stated so.

        , Respondent contended that the impugned orders should not be
C   interfered with as they were confined only to a particular unit; that
    appellant was bound by its offer as contained in 'Times of India; and
    that in view of the terms and conditions in the document, matter cannot
    be interfered with as the document was not placed befor.e t~e Courts
    below.
D
          Allowing the appeals, the Court

          HELD: 1. Courts should be slow 'in interfering a.t int~.rim stage
    with schem~s which are based on costing. India is. ha".ing cost-push

E
    economy. In a self-financing scheme based on costing, an interim
    injunction has a cascading effect. Failure on the part of even one
    contributory in contributin'g the amount to the cost results in total failure
                                                                                    -
    of the project. The developer,
                             '    .
                                      like the
                                             . Housing. Board, makes an initial
    investment by borrowing funds from the market. Therefore, an interim
    injunction at the initial stage of the· project would result in the total
    collapse of the entire project. It would also affect the contributions made'
F   by other co-purchas~rs. Several components go into costing, including
    the lease ren,t payable to the Sta~e Government. These aspects have not
    been considered by the trial Court. (771-D-E]                        · ..

          /~dore Development Authority v. Sadhana Agarwal (Snit.) ana Ors.,
GI (19951 3 sec 1, relied on.
         Kanpur Development Authority v. Smt. Sheela Devi and'Ors., AIR
    (2004) SC 400, distinguished.
                                                                      '!

          Gujarat Bottling Co. Ltd. v. Coca Cola Co., (1995) 5 SCC 545, referred
H to.
             M.P. HOUSING BOARD v.KHIWANI [KAPADIA, J.]                767

      2. The developer in the present case has an absolute right to increase A
the cost of flats initially announced as estimated cost. The final cost
should be proportionate to the estimated cost mentioned in the offer
keeping in mind the rate of inflation, escalation of the prices of inputs,
escalation in the prices of the construction material and labour charges.
These factors have got to be taken into account on the basis of the evidence B
which may be considered at the time of final hearing of the suit. In the
present case, however, the appellant has not placed before the trial Court
the documentS mentioned herein and, therefore, the matter is remitted to
the trial Court for fresh decision, in accordance with law. [771-F-G]

        CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1731 of C
2005.

     From the Judgment and Order dated 2. 7.2004 of the Madhya Pradesh
High Court in M.A. No. 161l of 2003.

                                  WITH
                                                                              D
        C.A. No. 1732 of 2005.

      Ravindra Shrivastava, B.S. Banthia, Naveen Sharma and Kuna! Verma,
for the Appellant.

     Sudhir Chandra, P.K. Bansal, Akshay Arora, Pankaj Kumar Singh, J.P.N.    E
Gupta and K. Janjani for the Respondent.

        The Judgment of the Court was delivered by

        KAPADIA, J. Leave granted.
                                                                                  F
      These civil appeals by grant of special leave are directed against a
common Order dated 2. 7.2004 passed by the High Court of Madhya Pradesh
at Jabalpur in M.A. No. 1611 of 2003 and M.A. No. 1628 of 2003.

       Since the impugned order is common in both the appeals, the same are G
jointly disposed of by this judgment.

     For the sake of convenience, we may mention briefly the facts of Civil
Appeal No. 1731 of 2005 [arising out of SLP (C) No. 22560 of 2003].
                                                                              I
     On 18th January, 2000, M.P. Housing Board, appellant herein, issued H
    768                     SUPREME COURT REPORTS                      [2005] 2 S.C.R.

A an advertisement in local newspaper "Dainik Bhaskar" inviting offers to
    subscribe to two schemes floated by the Board, namely, Katara Hills
    Residential Scheme and Centre Point Commercial Scheme. In these appeals,
    we.are concerned with the booking ofa showroom in the commercial'complex.
    According to the said advertisement, the estimated cost of a showroom and
B   departmental store in the commercial complex (Centre Point), having built up
    area of 3550 sq. ft. on the upper ground level, was Rs. 39 lacs. The registration
    amount was Rs. 3 .90 lacs i.e. 10% of the estimated cost of Rs. 39 lacs. What
    was proposed to be constructed was a seven storeyed commercial complex of
    showrooms, shops, halls etc. near New Market Stadium, Bhopal. To give
    publicity to the said schemes, brochures were also distributed.
c         On the basis of the above advertisement, Anil Kumar Khiwani, the
    respondent herein, submitted an application in the prescribed form enclosing
    his cheque for Rs. 3.90 lacs, being 10% of the estimated cost of the showroom.
    On 25.9.2000, a temporary registration was made in favour of the said
    respondent. On the same date, he was informed in writing that temporary
D   registration stood granted to him and further particulars would be conveyed
    to him on a later date regarding the total consideration. Thereafter, the appellant
    herein took steps to prepare a detailed Project Report, which was approved
    by the Town Planning Authority, the Municipal Corporation and a Committee
    known as Building High-rise Committee. The appellant also called upon the
E   State government to forward the actual land cost and the lease rent, which the
    State proposed to charge. The appellant also called upon the electricity board
    to forward to them the estimated strengthening charges. After getting all
    these informations and approvals, tenders were invited and after receiving the
    tenders, the actual cost was worked out which came to Rs. 2000 per sq. ft.

F          Accordingly, by letter dated 27.9.2001, the respondent herein was called
    upon to give his consent within one month. By the said letter, each of the
    contributors including the respondent was given an option to withdraw from
    the scheme if he did not agree to the proposed actual cost of Rs. 2000 per
    sq. ft. The contributors were told to collect the registration amount with
    interest @ 8% per annum from the board if they opted for withdrawal from
G   the commercial scheme, provided they opted for refund by 10.10.2001.

           By letter dated 16. I 0.200 I, the respondent wrote to the board stating
    that he was not willing to accept the price nor was he willing to withdraw the
    registration amount.

H         By letter dated 27.11.2001, the board called upon the respondent to pay
            M.P. HOUSING BOARD v.KHIWANI [KAPADIA, J.]                     769
an amount of Rs. 71 lacs for the showroom on the upper ground floor A
admeasuring 3550 sq. ft. This was objected to by the respondent vide notice
given to the board. Ultimately, on 29.6.2002, the appellant cancelled the
registration and called upon the respondent to collect the registration amount
of Rs. 3.90 lacs with interest @ 8% calculated up to June 30, 2002.

      On 15.7.2002, the present suit was filed for declaration and injunction    B
in the Court of Additional District Judge, Bhopal (hereinafter referred to as
"the trial Court"), being Civil Suit No. 39-A of 2002. In the said suit, an
application was moved under order 39 rules l and 2 CPC.

      By impugned order dated 22.4.2003, the trial Court prima facie came
to the conclusion that the board was guiity of inordinate delay in the C
implementation of the scheme; that the board had demanded almost twice the
amount indicated in the advertisement after accepting the advance and
consequently, the board was restrained from allotting the showroom in question
to any other person, till the final hearing and disposal of the suit. By the
impugned order, the trial Court permitted the board to call upon the contributor D
to deposit Rs. 39 lacs in four instalments in terms of the schedule indicated
in the above advertisement.

     Aggrieved by the said decision, the matter was carried in appeal. By
the impugned decision dated 2.7.2004, the High Court dismissed the
Miscellaneous Appeal No. 1611 of 2003 as well as Miscellaneous Appeal            E
No. 1628 of 2003. Hence, these appeals.

      Normally, this Court is reluctant to interfere with the interim orders
passed under order 39 rules l and 2 CPC. However, in the present case, we
are concerned with construction of a seven storeyed commercial premise$
under a self-financing scheme floated by the appellant. In the said complex,     F
there are showrooms, departmental stores and halls for commercial uses.

      The question involved in this case is - whether the offer contained in
the above advertisement was for a fixed amount of Rs. 39 lacs?

        In the present case, the advertisement inserted by the appellant in "Times G
of India'' indicated Rs. 39 lacs as cost of the built-up area admeasuring 3550
sq. ft., whereas the advertisement inserted in the local newspaper "Dainik
Bhaskar" indicated Rs. 39 lacs as estimated cost for the aforestated built-up
area.
    770                    SUPREME COURT REPORTS                    [2005] 2 S.C.R.

A          According to the respondent herein, investment was made by him on
    the basis of the advertisement in "Times of India". According to .the
    respondent, Rs. 39 lacs was a fixed cost and, therefore, the board was not
    entitled to raise the price to Rs. 71 lacs, particularly when it was guilty of
    delay in completing the project. It was submitted that the board was not
B   entitled to approbate and reprobate and that it was bound by its offer of Rs.
    39 lacs as contained in advertisement in "Times of India".

           In this case, we are concerned with a self-financing scheme under
    which a commercial complex is constructed. In a self~financing scheme,
    costing plays an important role. The building in question comprises of various
C   units. These units are self-financed. A buyer of the unit has to fund the cost
    of construction. A buyer under such a scheme cannot be pennitted to buy a
    unit at a price which is less than the cost of construction. In a self-financing
    scheme, pricing is .generally based on ·cost of construction unlike sale of
    houses after they are completed, in which cases pricing is generally market
    related. In the case of a self-financing scheme, no buyer can claim a right to
D   purchase any unit at a price lower than the actual construction cost, as the
    board raises its funds in tum from the banks and other financial institutions
    to whom the board is required to pay interest periodically. In the case of a
    self-financing scheme, even if there is failure on the part of one contributor
    to pay the costs, the entire scheme falls in jeopardy and, therefore, there is
E   no merit in the contention advanced on behalf of 'the respondent that the
    impugned orders should not be interfered with as they are confined only to
    a particular unit purchased by the respondent.

         It was l9'.ged on behalf of the appellant that there was a mistake in the
 ' advertisemeii:t inserted ·in "Times of India'', inasmuch as· the word
F "estimated" stood omitted inadvertently from the fourth column dealing
   with cost, though it has been so mentioned in the advertisement in the local
   newspaper "Dainik Bhaskar". It was further contended on behalf of the
   appellant that the respondent had filled-in an application fonn to which the
   tenns and conditions of allotment were attac.hed. ·Clause I 0 of the .conditions
   read as follows :
G
            "The· cost of plot/house/flat which is mentioned in the table, is
            estimated. If there is ariy increase then the same will be infonned to
            the allottee.''

          It was, therefore, submitted that the respondent was fully aware that the
H amount of Rs. 39 lacs mentioned in the advertisement was an estimated cost
-
                M.P. HOUSING BOARD v.KI-llWANI [KAPADIA . .I.]                 771

    and not a fixed cost.                                                             A
           On the other hand, it was urged on behalf of the respondent that the
    document on which reliance is placed by the board was not placed before the
    trial Court as well as before the High Court and, therefore, no interference
    was called for in the matter. It was urged on behalf of the respondent that the
    respondent was ready and willing to deposit Rs. 39 lacs at the earliest and       B
    that the board should be restrained from charging and recovering the entire
    amount of Rs. 71 lacs, pending hearing and final disposal of the suit. In this
    connection, reliance was also placed on the decision of this Court in Indore
    Development Authority v. Sadhana Agarwal (Smt.) and Ors., reported in
    [l 995] 3 SCC l as also the decision of this Court in Kanpur Development          C
    Authority v. Smt. Sheela Devi and Ors., reported in AIR (2004) SC 400.

          Time has come when the Courts should b~ slow in interfering at interim
    stage with schemes which are based on costing. India is having cost-push
    economy. In a self-financing scheme based on costing, an interim injuncti~n
    has a cascading effect. Failure on the part of even one contributory .in D
    contributing the amount to the cost results in total failure of the project. The
    developer, like the housing board, makes an initial investment by borrowing
    funds from the market. Therefore, an interim injunction at the initial stage of
    the project would result in the total collapse of the entire project. It would
    also affect the contributions made by other co-purchasers. Several components
    go into costing, including the lease rent payable to the State Government. E
    These aspects have not been considered by the trial Court.

           Our observation~ herein however should not be read to mean that the
    developer in the present case has an absolute right to increase the cost of flats
    initially announced as estimated cost. The final cost should be proportionate F
    to the estimated cost mentioned in the offer keeping in mind the rate of
    inflation, escalation of the prices of inputs, escalation in the prices of the
    construction material and labour charges. These factors have got to -be taken
    into account on the basis of the evidence which may be considered at the
    time of final hearing of the suit. In the present case, however, the appellant
    has not placed before the trial Court the documents mentioned hereinabove G
    and, therefore, we are remitting the matter to the trial Court for fresh decision,
    in accordance with law.

          In the case of Gujarat Bottling Co. Ltd. v. Coca Cola Co., reported in
    [1995] 5 SCC 545 this Court, while discussing the factors to be considered
    by the Courts in exercise of the discretion under order 39 rules 1 and 2 CPC, · H
    772                   SUPREME COURT REPORTS                     [2005] 2 S.C.R.

A has observed as follows :
          ''The grant of an interlocutory injunction during the pendency of
          legal proceedings is a matter requiring the exercise of discretion of
          the court. While exercising the discretion the court applies the
          following tests - (i) whether the plaintiff has a prima facie case; (ii)
B         whether the balance of convenience is in favour of the plaintiff; and
          (iii) whether the plaintiff would suffer an irreparable injury if his
          prayer for interlocutory injunction is disallowed. The decision whether
          or not to grant an interlocutory injunction has to be taken at a time
          when the existence of the legal right assailed by the plaintiff and its
          alleged violation are both contested and uncertain and remain uncertain
c         till they are established at the trial on evidence. Relief by way of
          interlocutory injunction is granted to mitigate the risk of injustice to
          the plaintiff during the period before that uncertainty could be resolved.
          The object of the interlocutory injunction is to protect the plaintiff
          against injury by violation of his right for which he could not be
D         adequately compensated in damages recoverable in the action if the
          uncertainty were resolved in his favour at the trial. The need for such
          protection has, however, to be weighed against the corresponding
          need of the defendant to be protected against injury resulting from his
          having been prevented from exercising his own legal rights for which          ..'
          he could not be ade~uately compensated. The court must weigh one
E         need against another and determine where the ''balance of
          convenience" lies. In order to protect the defendant while granting
          an interlocutory injunction in his favour the court can require the
          plaintiff to furnish an undertaking so that the defendant can be
          adequately compensated ifthe uncertainty were resolved in his favour
F         at the trial.

                Under Order 39 of the Code of Civil Procedure, jurisdiction of
           the Court to interfere with an order of interlocutory or temporary
            injunction is purely equitable and, therefore, the Court, on being
            approached, will, apart from other considerations, also look to the
G           conduct of the party invoking the jurisdiction of the Court, and may
          . refuse to interfere unless his conduct was free from blame. Since the
            relief is wholly equitable in nature, the party invoking the jurisdiction
           of the Court has to show that he himself was not at fault and that he
            himself was not responsible for bringing about. the state of things
            complained of and that he was not unfair or inequitable in his dealihgs
H
                 M.P. HOUSING BOARD v.KHIWANI [KAPADIA, J.)                        773
             with the party against whom he was seeking relief. His conduct should        A
             be fair and honest. These considerations will arise not only in respect
             of the person who seeks an order of injunction under Order 39 Rule
             l or Rule 2 of the Code of Civil Procedure, but also in respect of the
             party approaching the Court for vacating the ad interim or temporary
             injunction order already granted in the pending suit or proceedings."        B
             The judgment of this Court in the case of Indore Development Authority
    . (supra) supports the appellant herein. In that case, an advertisement was
      issued by the development authority in the year 1977 inviting applications.
      from persons interested in purchase of flats on hire-purchase basis. The,
      estimated cost for the LIG flat was mentioned at Rs. 45,000. In the proforma C
      attached to the application for registration, the development authority had'
      stated that the price mentioned by them was a probable price and that the
      definite price shall be intimated at the time of allotment. The purchasers were
      given possession in the year 1984. They instituted writ petition before the
      High Court challenging the demand raised by the development authority
      based on escalation. The writ petition was allowed by the High Court. This ' D
      Court, in the facts and circumstances of that case, came to the conclusion thaf
      the High Court should not have interfered with the hike in the cost of
      construction. This Court observed that the development authority owed a
      duty to explain and satisfy the Court the reasons for such high-escalation but
      this did not warrant the High Court while exercising the jurisdiction to examine E
      every detail of the cost of construction. Accordingly, this Court allowed the
      appeal filed by the development authority observing :

             "9 ...... Although this Court has from time to time, taking the special
             facts and circumstances of cases in question, has upheld the excess
             charged by the development authorities over the cost initially               ,p
             announced as estimated cost, but it should not be understood that this
             Court has held that such development authorities have absolute right
             to hike the cost of flats, initially announced as approximate or estimated
             cost for such flats. It is well known that persons belonging to middle
             and lower income groups, before registering themselves for such flats,
             have to take their financial capacity into consideration and in some         G
             cases it re~ults in great hardship when the development authorities
             announce an estimated or approximate cost and deliver the same at
-            twice or thrice of the said amount. The final cost should be
             proportionate to the approximate or estimated cost mentioned in the
             offers or agreements. With the high rate of inflation, escalation of the     H
    774                   SUPREME COURT REPORTS                      [2005] 2 S.C.R.

A          prices of construction materials and labour charges, if the scheme is
           not ready within the time-frame, then it is not possible to deliver the
           flats or houses in question at the cost so announced. It will be advisable
           that before offering the flats to the public such development authorities
           should fix the estimated cost of the flats taking into consideration the
           escalation of the cost during the period the scheme is to be completed.
B          In the instant case the estimated cost for the LIG flat was given out
           at Rs. 45,000. But by the impugned communication, the appellant
           informed the respondents that the actual cost of the flat shall be Rs.
            1,16,000 i.e. the escalation is more than 100%. The High Court was
           justified in saying that in such circumstances, the Authority owed a
c          duty to explain and to satisfy the Court, the reasons for such high
           escalation. We may add that this does not mean that the High Court
           in such disputes, while exercising the writ jurisdiction, has to examine
           every detail of the construction with reference to the cost incurred.
           The High Court has to be satisfied on the materials on record that the
           Authority has not acted in an arbitrary or erratic manner.
D
           10. So far the facts of the present case are concerned, it is an admitted
           position that in the pro forma attached to the application for
           registration, the appellant said that the price mentioned by them was


E
           a probable and estimated cost, the definite price shall be intimated at
           the time of the allotment. Thereafter, the appellant had been informing      --·•
           the respondents and others who had got themselves registered, from
           time to time regarding the escalation in the cost of the flat. One of
           the reasons for the rise of the price for the LIG flat from Rs. 60,000
           to Rs. 1, 16,000 appears to be the increase in the area of the flat itself
           from 500 sq. ft. to 714.94 sq. ft. From 1982 to 1984, possession of
F          the flats could not be delivered because of the dispute pending in the
           Court which also contributed to the increase in the cost of the flat.
           Admittedly, the respondents calt\e in possession of the flats in the
           year 1984. In the facts and circumstances of the case, we are satisfied
           that no interference was called for by the High Court."

G         The judgment of this Court in the case of Kanpur Development Authority
    (supra), on which reliance is placed on behalf of the respondent, has no
    application to the facts of the present case as in that matter there was an
    express clause in the brochure that the escalation shall not exceed l 0%. In
    the present case, there is no such clause in the brochure. In the present case,
H   we are concerned with a commercial complex constructed under a self-
            M.P. HOUSING BOARD v.KHIWANI [KAPADIA, J.)                      775
financing scheme and not with the residential houses as was the case in the A
matter of Kanpur Development Authority (supra). Hence, the said judgment
has no application to the facts of the present case.

      Before concluding, we may point out that the observations made herein
are only to give reasons in support of this judgment and they will not bind
the parties hereto in the proceedings before the trial Court.                      B
      Subject to above, both the appeals are allowed; the impugned judgment
and orders are set aside and the matter is remitted to the trial Court for fresh
decision, in accordance with law. However, in the facts and circumstances of
this case, there will be no order as to costs.
                                                                                   c
K.K.T.                                                        Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "self‑financing scheme"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.