Created byFuzzy Cloud

Supreme Court of India

LEVEL 9 BIZ PVT. LTD.versusHIMACHAL PRADESH HOUSING AND URBAN DEVELOPMENT AUTHORITY & ANOTHER

Citation
2024 INSC 257
Decided
2 April 2024
Disposal
Appeal(s) allowed

Holding

The Supreme Court held that the High Court's order was void for ignoring the independent committee’s findings and for treating a Letter of Intent as creating a right, and therefore quashed the order, allowing the appeal and imposing costs on HIMUDA.

Summary

Level 9 Biz Pvt. Ltd. challenged a Himachal Pradesh High Court order that allowed HIMUDA to withdraw its cancellation of an earlier tender and let the originally successful bidder, M/s Vasu Constructions, execute the project on the same terms despite the tender having been cancelled on grounds of irregularities. The High Court had disposed of the writ petition by merely recording the statements of HIMUDA and the bidder, without hearing the other interested parties or considering the findings of an independent committee that had recommended cancellation. The Supreme Court examined whether such a disposal was permissible, whether a Letter of Intent creates any enforceable right, and whether HIMUDA, as a State entity, acted malafide. It held that the Letter of Intent is only an expression of intent and does not confer any right, and that the High Court failed to apply its mind, ignored the committee’s findings, and thus erred. Consequently, the Supreme Court set aside the impugned order, allowed the appeal, and imposed a heavy cost on HIMUDA, while directing that a fresh tender process be conducted lawfully.

Issues considered

  • Whether the High Court could lawfully dispose of the writ petition by merely accepting the statements of the parties without hearing other affected parties and without applying mind to the independent committee's findings.
  • Whether a Letter of Intent issued in a tender process creates any enforceable right or binding contract.
  • Whether HIMUDA, as a State entity under Article 12, can be held liable for malafide collusion and be ordered to pay costs.
  • Whether the order of the High Court should be quashed for lack of proper reasoning and disregard of statutory and procedural requirements.

Legislation cited

Subjects

Cancellation of initial tendering processTenderIrregularities and illegalitiesNotice inviting tenderLetter of intentBurden on the public exchequerMisuse process of lawCostFresh tender processAgreement/contract

Judgment

                  [2024] 4 S.C.R. 1 : 2024 INSC 257

                       Level 9 Biz Pvt. Ltd.
                                v.
               Himachal Pradesh Housing and Urban
                 Development Authority & Another
                      (Civil Appeal No. 4626 of 2024)
                                02 April 2024
              [Bela M. Trivedi* and Pankaj Mithal, JJ.]

                           Issue for Consideration
       Matter pertains to the correctness of the order passed by
       the High Court disposing the writ petition by accepting the
       statements of the respondent no. 1-tenderee and respondent
       no. 2-successful bidder, permitting the respondent no.1 to
       withdraw the cancellation of initial tendering process order and
       permitting the respondent no. 2 to execute the project on the
       same terms and conditions as in the initial tender, though the
       said tender was already withdrawn by the respondent no.1 in
       view of the report of the independent Committee confirming
       gross irregularities and illegalities committed by the officers of
       the respondent no.1.

                                  Headnotes
       Tender – Notice inviting tender – Issuance of letter of intent in
       favour of the successful bidder by the tenderee – Challenge
       to, by the unsuccessful bidder – Cancellation of initial tender
       process by the tenderee and withdrawal of the letter of intent
       issued in favour of the successful bidder on account of
       pending litigations in the High Court – Thereafter, issuance of
       fresh NIT by tenderee – Challenge to – High Court disposed
       of the writ petition by merely accepting the statement of the
       tenderee that it had no objection to go ahead with the initial
       tendering process and the statement of the initial successful
       bidder that it was ready to execute the project on the same
       terms and conditions as initially agreed, though the said
       tender was already withdrawn by the tenderee in view of the
       irregularities and illegalities committed by it, as recorded by
       an independent committee appointed by the High Court in
       earlier writ petitions – Correctness:


* Author
2                                                              [2024] 4 S.C.R.

                      Digital Supreme Court Reports


     Held: No right whatsoever created in favour of the respondent no.
     2-successful bidder, and the respondent no. 1 HIMUDA-tenderee
     cancelled the tender and issued fresh NIT, as such the respondent
     no. 1 could not have agreed to allow the respondent no. 2, who
     was found to be not technically qualified, to go ahead with the
     execution of the project in question and that too without giving
     the other two parties any opportunity to negotiate – Respondent
     no. 1 in collusion with the respondent no. 2, took the High Court
     for a ride and misused the process of law for covering up the
     irregularities and illegalities committed in the tender process by the
     officers of the respondent no. 1 – High Court also could not notice
     the ill-intention of the respondent nos. 1 and 2 and disposed of
     the petition, permitting them to go ahead with the original tender
     – Thus, the impugned order having been passed without proper
     application of mind and without assigning any cogent reason for
     brushing aside the findings recorded by the Independent Committee
     and the observations made by the Single Bench, is quashed
     and set aside – Also, the respondent no.1, though ‘State’ within
     the meaning of Art. 12, acted malafide and in collusion with the
     respondent no.2, and took the High Court for a ride, heavy cost
     of Rs. 5,00,000/- imposed on the respondent no. 1 – Constitution
     of India – Art. 12. [Paras 11-14]
     Tender – Notice inviting tender – Letter of Intent – Nature of:
     Held: Letter of Intent is merely an expression of intention to enter
     into a contract – It does not create any right in favour of the
     party to whom it is issued – There is no binding legal relationship
     between the party issuing the LOI and the party to whom such
     LOI is issued – Detailed agreement/contract is required to be
     drawn up between the parties after the LOI is received by the
     other party. [Para10]

                                 List of Acts
     Constitution of India.

                              List of Keywords
     Cancellation of initial tendering process; Tender; Irregularities
     and illegalities; Notice inviting tender; Letter of intent; Burden on
     the public exchequer; Misuse process of law; Cost; Fresh tender
     process; Agreement/contract.
[2024] 4 S.C.R.                                                         3

     Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban
                   Development Authority & Another

                           Case Arising From
     CIVIL APPELLATE JURISDICTION : Civil Appeal No. 4626 of 2024
     From the Judgment and Order dated 18.10.2022 of the High Court of
     Himachal Pradesh at Shimla in CWP No. 1481 of 2021
                        Appearances for Parties
     P.S. Patwalia, Sr. Adv., Ritesh Khatri, Ms. Deveshi Chand, Advs. for
     the Appellant.
     Anoop G. Chaudhari, Navin Pahwa, Sr. Advs., Shankar Divate, J. P.
     Mishra, D. K. Thakur, Rajeev Kumar Gupta, Tavleen Singh, Joginder
     Mann, Ms. Vallabhi Shukla, Divyansh Thakur, Bimlesh Kumar Singh,
     Kanwal Chaudhary, Neeraj Agarwal, Santosh Kumar Yadav, Ms.
     Niharika, Nishant Anand, Advs. for the Respondents.
                Judgment / Order of the Supreme Court

                               Judgment
     Bela M. Trivedi, J.
1.   Leave granted.
2.   The Appellant – Level 9 BIZ Pvt. Ltd., who was not a party to the
     proceedings, being Civil Writ Petition No. 1481 of 2021, filed by
     the Respondent No.2 – M/s. Vasu Constructions in the High Court
     of Himachal Pradesh at Shimla, has challenged the impugned
     order dated 18.10.2022 passed by the High Court in the said
     proceedings. The High Court passed the impugned order disposing
     of the said CWP by merely accepting the statement made on behalf
     of the Respondent No.1 – Himachal Pradesh Housing and Urban
     Development Authority (HIMUDA) that it wanted to withdraw the
     cancellation of initial tendering process order dated 05.02.2021,
     and the statement made on behalf of the Respondent No. 2 that it
     was ready to execute the project on the same terms and conditions
     and the rates as per the initial tender dated 15.11.2018, though
     the said tender was already withdrawn by the Respondent no. 1
     HIMUDA in view of the irregularities and illegalities committed by it,
     as recorded by an independent committee appointed by the High
     Court in earlier writ petitions filed by the present appellant and one
     Dalip S. Rathore.
4                                                        [2024] 4 S.C.R.

                     Digital Supreme Court Reports


3.   The broad facts giving rise to the present appeal may be stated
     as under: -

     DATES             EVENTS
     15/16.11.2018     Notice Inviting Tender (NIT) was issued by
                       HIMUDA (R-1) for the construction of proposed
                       commercial complex of Vikas Nagar, Shimla, at
                       estimated cost of Rs.45,05,62,074/-
     15.12.2018        Technical Bids were opened and on the same
                       day Financial Bids were also opened. (Appellant
                       & R-2 were the only found to be qualified – But
                       the Appellant was L2)
     17.12.2018        LOI was issued by the R-1 in favour of R-2.
     24.12.2018        One Unsuccessful bidder Dalip S Rathore
                       filed Writ Petition being CWP 3021 of 2018
                       challenging the technical specifications &
                       ineligibility of Respondent No.2, also seeking
                       cancellation of the Tender. The High Court
                       issued notice.
     02.01.2019        R-1 HIMUDA withdrew the LOI dated 17.12.2018
                       of R-2 M/S Vasu Constructions stating that the
                       case is pending in the High Court and the work
                       will be awarded only as per the decision of the
                       High Court.
     05.01.2019        R-1 HIMUDA constituted a committee, which
                       reviewed the tender process and concluded that
                       there were many lapses which warranted actions
                       against the erring officials.
     07.01.2019        Another Committee constituted by R-1
                       submitted a report that Shri Dalip Singh was
                       not qualified and M/s. Vasu Constructions was
                       qualified.
     23.02.2019        Appellant – Level 9 BIZ Pvt. Ltd. filed a writ
                       petition CWP 363 of 2019, praying for rejection
                       of Technical Bid and Financial Bid of the R-2 M/s.
                       Vasu Constructions
[2024] 4 S.C.R.                                                         5

     Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban
                   Development Authority & Another


      25.11.2020     High Court passed a detailed order on 25.11.2020
                     in CWP No. 3021/2018 and 363/2019.
                     In Para 29 High Court observed-
                          “[..] this Court is prima facie of the
                          view that some of the officers manning
                          high positions in HIMUDA have not
                          acted responsibly and in the interest
                          of organization, rather have attempted,
                          directly or indirectly, to give undue
                          benefit to some of the contractors.
                          Having seen the record, this Court is
                          compelled to draw a conclusion that the
                          officers responsible for evaluation of the
                          tender in question, did not scrutinize the
                          documents submitted by the tenderers
                          along with their bids properly and, with
                          a view to ensure ouster of some eligible
                          contractors and awarding the same to
                          their favourites, have made an attempt
                          to justify their action by giving totally
                          implausible reasoning.”
                     In para 31, High Court observed-
                          “But, for the reasons, best known
                          to the authority, it still proceeded to
                          award the tender in favour of M/s. Vasu
                          Construction Company.”
                     The High Court therefore to instill confidence in
                     the general public and to ensure transparency in
                     the system, constituted an independent committee
                     to enquire into the tender process in question, and
                     directed the committee to submit its report in a
                     sealed cover to the Court.
      02.01.2021     Committee constituted by High Court filed its report.
      08.01.2021     High Court disposed of both Petitions being Nos.
                     3021/2018 and 363/19 and directed registry
                     to initiate separate proceedings against erring
                     officials, observing as under: -
6                                           [2024] 4 S.C.R.

     Digital Supreme Court Reports



           14. Since the committee, after having
           perused the records, has arrived at
           a definite conclusion that on account
           of shortcomings/irregularities, tender
           in question requires to be cancelled,
           nothing much is left for this court to
           adjudicate in these matters. Leaving
           everything aside, learned counsel for the
           petitioners in both the petitions, being
           satisfied with the findings of enquiry
           committee as well as suggestions made
           therein, are not willing to prosecute
           the cases further and have prayed to
           dispose of the same as having been
           rendered infructuous.
           15. In view of aforesaid, both the
           petitions are disposed of as infructuous
           alongwith all pending applications.
           Interim directions, if any, stand vacated.
           However, liberty is reserved to the
           parties to file fresh petition(s), if any, if
           they still remain aggrieved.
           16. However, this court, having taken
           note of the fact that the enquiry committee
           despite having found officers lacking in
           discharge of their duties, has failed
           to fix responsibility and recommend
           action, criminal or departmental, deems
           it necessary to direct the Registry
           of this Court to register separate
           proceedings, enabling this Court to pass
           appropriate orders so as to ensure strict
           compliance of recommendations given
           in the report of enquiry committee and
           pass appropriate orders with regard
           to initiation of criminal/ departmental
           proceedings against the erring officials.
[2024] 4 S.C.R.                                                        7

     Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban
                   Development Authority & Another


                          Registry is directed to register separate
                          proceedings and list the same on
                          17.3.2021. The order dated 25.9.2020,
                          this judgment and the enquiry report
                          submitted by the committee constituted
                          by this Court, shall form part of the fresh
                          proceedings.
      05.02.2021     Respondent No.1 cancelled the Tender in view
                     of the Order dated 08.01.2021 passed by the
                     High Court.
      03.03.2021     Respondent No.2 filed a new Writ Petition against
                     Respondent No.1, i.e., CWP 1481 of 2021
                     challenging order dated 05.02.2021.
                     Respondent no. 2 also filed separate two LPAs
                     being LPA No. 6/2021 and 12/2021 against the
                     common order dated 08.01.2021 passed in CWP
                     No. 3021/2018 and CWP No. 363/2019 by the
                     Single Bench.
      17.11.2021     R-1 HIMUDA issued fresh NIT for the same work.
      01.12.2021     The Division Bench of High Court passed an
                     interim order in LPA No. 6/2021, 12/2021 and CWP
                     No. 1481/2021 staying the NIT dated 17.11.2021
                     till further orders.
      18.10.2022     The Division Bench disposed of the Writ Petition
                     No. 1481/2021 upon statement of the Executive
                     Engineer of Respondent No.1 observing as under:
                     7. Learned counsel for the respondent on
                     instructions of Mr. Rajesh Thakur, Executive
                     Engineer, HIMUDA, Division, Shimla-9, has
                     submitted that the competent authority wants
                     to withdraw the cancellation of initial tendering
                     process order dated 5th February, 2021, bearing
                     No. 5806-11, as the public is deprived from the
                     facilities, which would have been available to them
                     after completion of the project. The project cost is
                     going to be enhanced due to delay in execution
                     of the project, which will cause additional burden
8                                                          [2024] 4 S.C.R.

                    Digital Supreme Court Reports



                      on the public exchequer. The various Government
                      departments/PSUs are facing acute shortage of
                      office accommodation, therefore, in larger public
                      interest, the authority has no objection to go ahead
                      with initial tendering process, in case the petitioner
                      is ready to execute the work at the same rate and
                      terms and conditions as were agreed at the time
                      of finalization of the initial NIT dated 15.11.2018
                      (Annexure P-2). The time period for execution
                      of work will start from date of fresh award letter
                      which will be issued in favour of the petitioner
                      within 15 days.
                      8.Learned Senior counsel for the petitioner, on
                      instructions from the petitioner, has submitted
                      that offer made by the respondent is acceptable
                      to the petitioner and petitioner is ready to execute
                      the project on the same terms and conditions
                      and rates as per initial tender dated 15.11.2018
                      (Annexure P-2).
     Nov. 2022        Contract Agreement was signed between
                      Respondent 1 & 2. Work started.
     12.12.2022       The Appellant filed the SLP challenging the
                      impugned order dated 18.10.2022 and the Court
                      while issuing notice, granted stay of operation of
                      the impugned order dated 18.10.2022.
4.   The question that has been posed before us in the instant appeal
     is, whether the High Court could have disposed of the CWP filed
     by the respondent no. 2 by simply accepting the statements
     made on behalf of the learned advocates for the respondent no.
     1 and respondent no. 2, virtually permitting the respondent no.1
     HIMUDA to withdraw the cancellation of initial tendering process
     order dated 05.02.2021 and permitting the respondent no. 2 M/s
     Vasu Constructions to execute the project on the same terms
     and conditions and at the rates as per the initial tender dated
     15.11.2018, though the said tender was already withdrawn by
     the Respondent No.1 HIMUDA in view of the report made by the
     independent Committee constituted by the High Court confirming
     gross irregularities and illegalities committed by the officers of
[2024] 4 S.C.R.                                                               9

     Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban
                   Development Authority & Another

     HIMUDA and in view of the order dated 08.01.2021 passed by
     the Single Bench?
5.   As could be seen from the chronology of events, the appellant and
     the respondent No. 2 were declared qualified in the Technical Bids
     opened on 15.12.2018 and on the same day, the financial bid of the
     said two parties were also opened. The respondent no.2 being L-1,
     the Letter of Intent dated 17.12.2018 was issued by the Respondent
     No.1 in favour of the respondent no.2. Subsequently, an unsuccessful
     bidder M/s Dalip Singh Rathore filed a writ petition being No.
     3021/2018 in the High Court, alleging irregularities and illegalities in
     the tender process and challenging the eligibility of the respondent
     no. 2, also seeking cancellation of the Tender. The appellant also
     filed CWP No. 363/2019 praying for the rejection of the Technical
     and Financial Bids of the respondent no.2. The respondent no.1
     HIMUDA in the meantime appointed a committee on 01.01.2019 to
     review the tender process. The respondent no.1 also vide the letter
     dated 02.01.2019 withdrew the Letter of Intent issued in favour of
     the respondent no.2. Subsequently, the High Court also appointed
     an Independent Committee to look into the alleged illegalities and
     irregularities vide the order dated 25.11.2020, in order to instill
     confidence in the general public and to ensure transparency in the
     system.
6.   As transpiring from the order dated 08.01.2021, the said Independent
     Committee submitted the report, arriving at a definite conclusion that
     the officers responsible for evaluation of the tender had not acted
     responsibly and fairly, as a consequence of which both M/s Vasu
     Constructions Company (respondent no.2 herein) and M/s Level 9
     Biz Pvt. Ltd. (the appellant herein) were wrongly declared eligible in
     the Technical Bid. The Committee had concluded that since both the
     bidders were not technically qualified as per the terms and conditions
     of the NIT, the tender needed to be cancelled. The recommendations
     made by the said Committee, except the recommendation for deletion
     of condition with regard to NPA, were stated to have been accepted
     by the Enquiry Committee of the respondent no. 1 HIMUDA. The High
     Court recorded the statements of the concerned counsels for the
     parties and disposed of the petitions being CWP Nos. 3021/2018 and
     363/2019 vide Order dated 08.01.2021 observing that the petitions
     had been rendered infructuous, however reserved a liberty for the
     parties to file fresh petition(s), if any, if they still remained aggrieved.
10                                                           [2024] 4 S.C.R.

                      Digital Supreme Court Reports


7.    Subsequently, the respondent no.1 HIMUDA cancelled the tender
      on 05.02.2021 in view of the said order dated 08.01.2021 passed
      by the High Court. The said action of the respondent no.1 came to
      be challenged by the Respondent No.2 M/s Vasu Constructions by
      filing a petition being CWP No. 1481/2021. The respondent no. 2
      also filed two LPAs being 6/2021 and 12/2021 being aggrieved by
      the common Order dated 08.01.2021 passed by the Single Bench.
      The Division Bench of the High Court disposed of the CWP No.
      1481/2021 vide the impugned order dated 18.10.2022 accepting the
      statements made by the learned counsels for the respondent nos.
      1 and 2 as stated hereinabove.
8.    We are at loss to understand as to how the said petition filed by
      the respondent no.2 could have been disposed of by the Division
      Bench by merely recording and accepting the statements of the
      learned counsels for the respondent nos. 1 and 2, when the tender
      in respect of NIT dated 15.11.2018 was cancelled by the respondent
      no.1 HIMUDA on account of the gross irregularities and illegalities in
      the tender process found by the Independent Committee constituted
      by the High Court and on account of the order passed by the High
      Court on 08.01.2021? We are also at loss to understand as to how
      the Executive Engineer of HIMUDA, could have made the statements
      before the Division Bench that the competent authority of the
      respondent no.1 wanted to withdraw the cancellation of the initial
      tendering process order dated 05.02.2021 and that the respondent
      no. 1 had no objection to go ahead with the initial tendering process,
      in case the respondent no.2 was ready to execute the work on
      the same terms and conditions as were agreed at the time of
      finalization of NIT dated 15.11.2018, when the respondent no. 1
      itself had decided to cancel and in fact cancelled the initial tendering
      process vide its order dated 05.02.2021 accepting the findings of
      the committee constituted by the High Court to the effect that there
      were irregularities and illegalities committed by the officers of the
      HIMUDA in processing the tender and that the respondent no. 2 was
      not technically qualified?
9.    When the common order dated 08.01.2021 was passed in the Writ
      Petition No. 3021 of 2018 filed by the petitioner Dalip Singh and Writ
      Petition No.363 of 2019 filed by the present appellant, recording the
      said findings of the committee appointed by it, pursuant to which
      order, the respondent no.1 had cancelled the tender on 05.02.2021,
[2024] 4 S.C.R.                                                          11

     Level 9 Biz Pvt. Ltd. v. Himachal Pradesh Housing and Urban
                   Development Authority & Another

     and had issued a fresh NIT on 17.11.2021, it was incumbent on the
     part of the respondent no. 2 to implead the said two petitioners as
     the party respondents in the new petition filed by it i.e. 1481/2021,
     and it was also incumbent on the part of the High Court to give
     opportunity of hearing to the said petitioners before passing the
     impugned order disposing of the said petition merely recording the
     statements of the learned counsels for the respondent nos. 1 and
     2, and permitting the respondent nos. 1 and 2 to go ahead with
     execution of the work as per the initial tender which was already
     cancelled by the respondent no.1.
10. Though it is true that initially an LOI was issued by the respondent
    no. 1 in favour of the respondent no. 2 on 17.12.2018, but the same
    was withdrawn by the respondent no. 1 as per the letter dated
    02.01.2019 on account of pending litigations in the High Court. In
    any case, it hardly needs to be reiterated that the Letter of Intent is
    merely an expression of intention to enter into a contract. It does not
    create any right in favour of the party to whom it is issued. There
    is no binding legal relationship between the party issuing the LOI
    and the party to whom such LOI is issued. A detailed agreement/
    contract is required to be drawn up between the parties after the LOI
    is received by the other party more particularly in case of contract
    of such a mega scale.
11. Since, there was no right whatsoever created in favour of the
    respondent no. 2, and since the respondent no. 1 HIMUDA had
    already accepted the recommendations of the Committee appointed
    by the High Court and the order dated 08.01.2021 passed by the
    High Court, and had cancelled the tender and issued fresh NIT on
    17.11.2021, the respondent no. 1 could not have agreed to allow the
    respondent no. 2, who was found to be not technically qualified, to
    go ahead with the execution of the project in question and that too
    without giving the other two parties any opportunity to negotiate. If the
    respondent no. 1 was so keen to provide the facilities to the public
    without causing any additional burden on the public exchequer, all
    the three parties who had participated in the original tender should
    have been given the opportunity to negotiate with it.
12. Having regard to the entire chain of events, and the conduct of
    the respondent nos. 1 and 2, we have no hesitation in holding that
    the respondent no. 1 in collusion with the respondent no. 2, had
12                                                           [2024] 4 S.C.R.

                      Digital Supreme Court Reports


      taken the High Court for a ride and misused the process of law for
      covering up the irregularities and illegalities committed in the tender
      process by the officers of the respondent no. 1, and for anyhow
      awarding the contract to the respondent no. 2 under the guise of
      the court’s order. It is a matter of surprise for us that the High Court
      also could not notice the ill-intention of the respondent nos. 1 and 2
      and disposed of the petition, permitting them to go ahead with the
      original tender, ignoring the reports of the independent committee
      and the observations made by the Single Bench in the Order dated
      08.01.2021 with regard to the irregularities and illegalities committed
      by the officers of the respondent no. 1 HIMUDA.
13. The impugned order having been passed without proper application of
    mind and without assigning any cogent reason for brushing aside the
    findings recorded by the Independent Committee and the observations
    made by the Single Bench in the order dated 08.01.2021, the same
    deserves to be quashed and set aside. Since, we have found that
    the respondent no.1 HIMUDA, though ‘State’ within the meaning
    of Article 12 of the Constitution of India, had acted malafide and in
    collusion with the respondent no.2, and had taken the High Court for
    a ride, the present appeal deserves to be allowed with heavy cost.
14. In that view of the matter, the impugned order passed by the High
    Court is set aside. The appeal is allowed with cost of Rs. 5,00,000/-
    to be deposited by the respondent no. 1 HIMUDA with the Supreme
    Court Advocates-on-Record Association, within two weeks from today.
    However, it is clarified that the respondent no.1 shall be at liberty
    to initiate a fresh tender process in accordance with law and after
    following the due process of law.

      Headnotes prepared by: Nidhi Jain                    Result of the case:
                                                              Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Cancellation of initial tendering process"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.