KARNATAKA POWER TRANSMISSION CORPORATION LIMITED AND ANOTHERversusM/S. DEEPAK CABLES (INDIA) LTD.
- Citation
- 2014 INSC 258
- Decided
- 7 April 2014
- Disposal
- Appeal(s) allowed
- Bench
- ANIL R DAVE
Holding
Clause 48, read with clause 4.1, does not amount to an arbitration agreement; consequently, the provisions of Section 11(5) and 11(6) cannot be invoked to appoint an arbitrator.
Summary
Karnataka Power Transmission Corporation (KPTC), a state utility, awarded a sub‑station contract to Deepak Cables. During performance, Deepak Cables raised a claim and, after the engineer failed to decide within 30 days under clause 48 of the contract, filed an application under Sections 11(5) and 11(6) of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator. The High Court treated clause 48 as an arbitration clause and appointed a sole arbitrator, a decision appealed before the Supreme Court. The Supreme Court examined the wording of clause 48 and the complementary clause 4.1, which expressly provided that all disputes would be decided by a competent court at Bangalore, and held that the clauses were intended only for speedy settlement by the engineer, not for arbitration. Relying on Section 7 of the Act, the Court found no intention to refer disputes to an arbitral tribunal, and therefore the High Court’s appointment of an arbitrator was erroneous. The appeals were allowed and the High Court order set aside.
Issues considered
- The language of clause 48 (and clause 4.1) of the contract constitutes an arbitration agreement within the meaning of Section 7 of the Arbitration and Conciliation Act, 1996.
- Whether Section 11(5) and 11(6) of the Act can be invoked to appoint an arbitrator when the contract does not contain a valid arbitration clause.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11(5), s. 11(6), s. 7
Subjects
Judgment
[2014] 4 S.C.R. 771
KARNATAKA POWER TRANSMISSION CORPORATION A
LIMITED AND ANOTHER
v.
MIS. DEEPAK CABLES (INDIA) LTD.
(Civil Appeal No. 4424 of 2014)
B
APRIL 07, 2014
[ANIL R. DAVE AND DIPAK MISRA, JJ.]
Arbitration and Conciliation Act, 1996: s.11 (6) -
Appointment of arbitrator - Dispute between the parties - C
Respondent seeking appointment of arbitrator - Resisted by
appellant on the ground that the agreement did not provide
for arbitration - Held: Clause 48 of the agreement provided
that when disputes or differences of any kind arise between
the parties relating to the performance of the works during D
progress of the works or after its completion or before or after
the termination, abandonment or breach of the contract, it is
to be referred to and settled by the engineer - There is also a
stipulation that his decision in respect of every matter so
referred to shall be final and binding upon the parties until the E
completion of works and is required to be given effect to by
the contractor who shall proceed with the works with due
diligence - This clause did not provide any procedure to even
remotely indicate that the concerned engineer was required
to act judicially as an adjudicator by following the principles
F
of natural justice or to consider the submissions of both the
parties - This only depict that the said clause was engrafted
to avoid delay and stoppage of work and facilitate smooth
carrying on of the work - The language employed in the clause
did not spell out the intention of the parties to get the disputes G
adjudicated through arbitration - Apart from that clause 4. 1 of
the agreement stated that it was specifically agreed by and
between the parties that all the differences or disputes arising
?ut of the Agreement or touching the subject matter of the
771 H
772 SUPREME COURT REPORTS [2014) 4 S.C.R.
A Agreement would be decided by a competent Court at
Bangalore - Thus, clause 48, read in conjunction with clause
4.1, clearly established that there was no arbitration clause
in the agreement.
Appellant No. 1, a State Transmission utility invited
8
tenders for establishing sub-stations. Respondent-
company was successful bidder and contract was
entered with it. Dispute arose and tile respondent filed
application under Section 11 (5) and (6) of the Arbitration
and Conciliation Act, 1996 before the High Court for
C appointment of an arbitrator. The application was resisted
by the appellant on the ground that clause 48 did not
provide for arbitration and same cannot be co...,strued as
an arbitration clause. The High Court held that a plain
reading of clause 48 would indicate that it partak~ the
D character of an arbitration clause and, accordingly,
appointed a sole arbitrator to adjudicate the matters in
dispute. Hence these appeals.
Allowing the appeals, the Court
E
HELD: 1. Section 7 of the Arbitration and Conciliation
Act, 1996 states that unless an arbitration agreement
stipulates that the parties agree to submit all or certain
disputes which have arisen or which may arise in respect
.F of defined legal relationship, whether contractual or not,
there cannot be a reference to an arbitrator. It conveys
that there has to be intention, expressing the consensual
acceptance to refer the disputes to an arbitrator. In the
absence of an arbitration clause in an agreement, as
defined in sub-section (4) of Section 7, the dispute/
G disputes arising between the parties cannot be referred
to the arbitral tribunal for adjudication of the dispute.
[Para 9] [779-F-H; 780-A]
2. Clause 48 is to the effect that it provides for the
H parties to amicably settle any disputes or differences
KARNATAKA POWER TRANSMISSION CORP. LTD. v. 773
DEEPAK CABLES (INDIA) LTD.
arising in connection with the contract. This is the first A
part. The second part is that when disputes or differences
of any kind arise between the parties to the contract
relating to the performance of the works during progress
of the works or after its completion or before or after the
termination, abandonment or breach of the contract, it is B
to be referred t,o and settled by the engineer, who, on
being requested by either party, shall give notice of his
decision within thirty days to the owner and the
contractor. There is also a stipulation that his decision in
respect of every matter so referred to shall be final and c
binding upon the parties until the completion of works
and is required to be given effect to by the contractor who
shall proceed with the works with due diligence. To
understand the intention of the parties, this part of the
clause is important. On a studied scrutiny of this
D
postulate, it is graphically clear that it does not provide
any procedure which would remotely indicate that the
concerned engineer is required to act judicially as an
adjudicator by following the principles of natural justice
or to consider the submissions of both the parties. That
apart, the decision of the engineer is only binding until E
the completion of the works. It only casts a burden on the
contractor who is required to proceed with the works
with due diligence. Besides that during the settlement of
disputes and the court proceedings, both the parties are
obliged to carry out the necessary obligation under the F
contract. The said clause has been engrafted to avoid
delay and stoppage of work and for the purpose of
smooth carrying on of the works. The burden is on the
contractor to carry out the works with due diligence after
getting the decision from the engineer until the G
completion of the works. Thus, the emphasis is on the
performance of the contract. The language employed in
the clause does not spell out the intention of the parties
to get the disputes adjudicated through arbitration. It
does not really provide for resolution of disputes. Apart H
774 SUPREME COURT REPORTS [2014] 4 S.C.R.
A from that clause 4.1 of the agreement stated that it was
specifically agreed by and between the parties that all the
differences or disputes arising out of the Agreement or
touching the subject matter of the Agreement would be
decided by a competent Court at Bangalore. Clause 48,
B read in conjunction with clause 4.1, clearly establishes
that there is no arbitration clause in the agreement. The
High Court has fallen into grave error by considering the
said clause as providing for arbitration. [Para 22, 23 and
24) (789-F-H; 790-A-G; 791-E-F]
c Jagdish Chander v. Ramesh Chander and Ors. (2007)
5 sec 719: 2007 (5) SCR 720 - relied on.
Smt. Rukmanibai Gupta v. Collector, Jabalpur and Ors.
(1980) 4 SCC 556; State of UP. v. Tipper Chand (1980) 2
D SCC 341; Dewan Chand v. State of Jammu and Kashmir AIR
1961 J & K 58; Ram Lal v. Punjab State AIR 1966.Punj 436
: 68 Punj LR 522 : ILR (1966) 2 Punj 428; State of Orissa
and Anr. etc. v. Sri Damodar Das AIR 1996 SC 942: 1995
(6) Suppl. SCR 800; State of Orissa and Ors. v. Bhagyadhar
E Dash (2011) 7 SCC 406: 2011 (8) SCR 967 - Distinguished.
M.K. Shah Engineers & Contractors v. State of M.P.
(1999) 2 SCC 594: 1999 (1) SCR 419; Wellington
Associates Ltd. v. Kirit Mehta (2000) 4 SCC 272; Punjab State
and Ors. v. Dina Nath (2007) 5 SCC 28: 2007 (6) SCR 536;
F Chief Conservator of Forest v. Rattan Singh AIR 1967 SC
166 : 1966 Supp SCR 158; Governor-Genera/ v. Simla
Banking and Industrial Company Ltd. AIR 1947 Lah 215 :
226 IC 444; K.K. Modi v. K.N. Modi and Ors. (1998) 3 sec
573: 1998 (1) SCR 601; M. Dayanand Reddy v. A.P.
G Industrial Infrastructure Corporation Limited And Ors. (1993)
3 SCC 1.37: 1993 (2) SCR 629; Bharat Bhushan Ba.nsal v.
UP. Small Industries Corporation Ltd., Kanpur AIR 199~ SC
899: 1999 (1) SCR 181; Bihar State Mineral Development
Corporation and Anr. v. Encon Builders (I) (P) Ltd. (2003) 7
H SCC 418: 2003 (2) Suppl. SCR 812; State of Orissa and Ors.
KARNATAKA POWER TRANSMISSION CORP. LTD. v. 775
DEEPAK CABLES (INDIA) LTD.
v. BhagyadharDash (2011) 7 SCC 406: 2011 (8) SCR 967 A
- referred to.
Case Law Reference:
19.99 (1) SCR 419 Referred to Para 6
B
(2000) 4 sec 212 Referred to Para 6
2007 (5) SCR 720 Relied on Para 6
(1980) 4 sec 556 Distinguished Para 7
2007 (6) SCR 536 Referred to Para 7
c
1966 Supp SCR 158 Referred to Para 11
(1980) 2 sec 341 Distinguished Para 12
226 IC 444 Referred to Para 13
AIR 1961 J & K 58 Distinguished Para 13 D
AIR 1966 Punj 436 Distinguished Para 13
1995 (6) Suppl. SCR 800 Distingusihed Para 14
1998 (1) SCR 601 Referred to Para 15
1993 (2) SCR 629 Referred to Para 15 E
1999 (1) SCR 181 Referred to Para 16
2003 (2) Suppl. SCR 812 Referred to Para 17
2011 (8) SCR 967 Distinguished Para 20
F
CIVIL APPELLATE JURISDICTION : Civil Appeal No.
4424 of 2014.
From the Judgment and Order dated 01.03.2013 of the
High Court of Karnataka at Bangalore in C.M.P. No. 7 of 2013.
WITH G
C.A. Nos. 4425, 4426, 4427, 4428, 4429, 4430 and 4431
of 2014.
K.V. Vishwanathan, ASG, S. Sriranga, Balaji Srinivasan,
Mayank Kshirsagar, Vaishali Dixit, Abhishek Kaushik for the
Appellants. H
776 . SUPREME COURT REPORTS [2014] 4 S.C.R
!
A Dushyant Dave, Shyam Divan, L.M. Chidanandayya, S.
Udaya Kumar Sagar, Bina Madhavan, Praseen E. Joseph,
Shivendra Singh, Sinha Shrey Nikhilesh (for Lawyer's Knit &
Co.) for the Respondent.
The Judgment of the Court was delivered by
B
DIPAK MISRA, J. 1. Leave granted in all the special leave
petitions.
2. The controversy involved in these appeals, preferred by
c special leave, being similar, they were heard together and are
disposed· of by a common judgment. For the sake of
convenience, we shall state the facts from Civil Appeal arising
out of Special Leave Petition 29011 of 2013.
3. The appellant No. 1 is a company wholly owned by the
D Government of Karnataka and, being a State transmission
utility, is a deemed licencee in the State. It invited tenders for
establishing 2x8 MVA, 66/11 Sub-stations at Tavarekere in
Channagiri Taluk, · Davanagere District, which included the
supply materials, erection and civil works on partial turnkey
E basis. The respondent-company participated in the bid and it
was successful in the tender and, accordingly, a letter of intent
was sent to it. After taking recourse to certain procedural
aspects, a contract was entered into between the appellant-
company and the respondent. During the performance of the
F contract, the respondent raised a claim before the engineer as
per clause 48 of the general conditions of the contract and
called upon the engineer to settle certain disputes arising in
connection with the contract. As the concerned engineer did not
do anything within the prescribed period of thirty days as
G provided un~er clause 48.2, the respondent filed CMP No. 62
of 2011 unaer Section 11 (5) and (6) of the Arbitration and
Conciliation Act, 1996 (for brevity "the Act") before the High .
Court of Karnataka at Bangalore for appointment of an
arbitrator.
H
KARNATAKA POWER TRANSMISSION CORP. LTD. v. 777
DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
4. The said application was resisted by the present A
appellants on the singular ground that clause 48 does not
provide for arbitration and the same, under no circumstances,
could be construed as an arbitration clause. To substantiate the
said submission, reliance was placed on clause 4.1 of the
agreement. It was put forth that as there is no arbitration clause, B
no arbitrator could be appointed. The designated Judge of the
Chief Justice placed reliance on the proceedings in W.P. No.
28710/09 (M/s. Subhash Projects & Marketing Limited v.
Karnataka Power Transmission Corporation Limited) disposed
of on 10.6.2010 wherein the appellant-company, being a State c
owned Corporation, had not disputed clause 48.2 as an
arbitration clause and, on that foundation, opined that it was
precluded from denying the same in the case under
consideration. The learned designated Judge interpreted
clauses 48 and 4.1 of the agreement and came to hold that a D
plain reading of clause 48 would indicate that it partakes the
character of an arbitration clause and, accordingly, appointed
a sole arbitrator to adjudicate the matters in dispute.
5. }Ne have heard Mr. K.V. Vishvanathan, learned senior
counsel appearing for the appellants, and Mr. Dushyant Dave E
and Mr.. Shyam Divan, learned senior counsel appearing for the
respondents.
6. Mr. Vishvanathan, learned senior counsel appearing for
the appellants, assailing the impugned order, has submitted that F
clause 48 of the agreement cannot be remotely construed as
an arbitration clause and hence, the designated Judge could
not have invoked the power under Section 11(5) & (6) of the
Act for appointment of an arbitrator. It is urged by him that an
order passed in a writ petition, which was instituted in a G
different context, could not have been placed reliance upon for
construing the said clause as an arbitration clause. It is
submitted by him that in the absence of an express intention
for referring the matter to an arbitrator, it cannot be so inferred .
from such a clause and, more so, when there is a specific· H
778 SUPREME COURT REPORTS [2014] 4 S.C.R.
A clause, i.e., clause 4 in the agreement which provides for
settlement of disputes that stipulates that all the references and
disputes arising out of the agreement or touching the subject-
matter of the agreement shall be decided by a competent court
at Bangalore. To bolster his contentions, he has commended
B • us to the decisions rendered in M.K. Shah Engineers &
Contractors v. State of M.P. 1 , Wellington Associates Ltd. v.
Kirit Mehta 2 and Jagdish Chander v. Ramesh Chander and
others3 .
7. Mr. Dushyant Dave and Mr. Shyam Divari, learned
C senior counsel appearing for the respondents in all the appeals,
in oppugnation, have submitted that when clause 48 is read as
a whole, it is clear as crystal that the intention of the parties is
to get the matter referred to an arbitrator and clause 4.1 ·only
determines the place of territorial jurisdiction and has nothing
· D to do with any stipulation for arbitration. It has been strenuously
urged that clause 48 has to be interpreted on the touchstone
of the language employed in Section 7 of the Act and when it
is scrutinized on that anvil, there remains no trace of doubt that
clause 48 has all the attributes and characteristics of an
E arbitration agreement. Learned senior counsel have placed
reliance on Smt. Rukmanibai Gupta v. Collector, Jaba/pur and
others" and Punjab State and others v. Dina Nath 5 •
8. Before we advert to the rival submissions advanced at
F the Bar, we think it appropriate to refer to Section 7 of the Act
and what it conveys and, thereafter, refer to few authorities to
understand what constitutes an arbitration clause in an
agreement entered into between two parties. Section 7 of the
Act reads as follows:
G
1. (1999} 2 sec 594.
2. (2000} 4 sec 212.
3. (2007} 5 sec 719.
4. (1980} 4 sec 556.
H s. (2007) 4 sec 28.
KARNATAKA POWER TRANSMISSION CORP. LTD. v. 779
DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
"7. Arbitration agreement. - (1) In this Part, "arbitration A
agreement" means an agreement by the parties to submit
to arbitration all or certain disputes which have arisen or
which may arise between them in respect of a defined
legal relationship, whether contractual or not.
B
(2) An arbitration agreement may be in the form of an
arbitration clause in a contract or in the form of a separate
agreement.
(3) An arbitration agreement shall be in writing.
c
(4) An arbitration agreement is in writing if it is contained
in -
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or other means . D
of telecommunication which provide a record of the
agreement; or
(c) an exchange of statement of claim and defence in which
the existence of the agreement is alleged by one party and E
not. denied by the other.
(5) The reference in a contract to a document containing
an arbitration clause constitutes an arbitration agreement
if the contract is in writing and the reference is such as to
make that arbitration clause part of the contract." F
9. From the aforesaid provision, it is graphically clear that ·
unless an arbitration agreement stipulates that the parties
agree to submit all or certain disputes which have arisen or
which may arise in respect of defined legal relationship, whether G
contractual or not, there cannot be a reference to an arbitrator.
To elaborate, it conveys that there has to be intention,
expressing the consensual acceptance to refer the disputes to
an arbitrator. In the absence of an arbitration clause in an
agreement; as defined in sub-section (4) of Section 7, the · H
780 SUPREME COURT REPORTS [2014] 4 S.C.R.
A dispute/disputes arising between the parties cannot be referred
to the arbitral tribunal for adjudication of the dispute.
10. In Smt. Rukmanibai Gupta (supra), while considering
Clause 15 of the agreement therein, a two-Judge Bench opined
that the clause spelt out an arbitration agreement between the
8
parties. The said clause was as follows:-
"Whenever any doubt, difference or dispute shall hereafter
arise touching the construction of these presents or
anything herein contained or any matter or things
c connected with the said lands or the working or non-
working thereof or the amount or payment of any rent or
royalty reserved or made payable hereunder in the matter
in difference shall be decided by the lessor whose
decision shall be final."
D
The learned Judges, to appreciate the tenor and purport·
of the said clause, referred to Section 2(a) of the 1940 Act and
reproduced a passage from Russell on Arbitration, 19th Edn.,.
P. 59 which reads as follows: -
E "If it appears from the terms of the agreement by which a
matter is submitted to a person's decision that the intention
of the parties was that he should hold an inquiry in the
nature of a judicial inquiry and hear the respective cases
of the parties and decide upon evidence laid before him,
F then the case is one of an arbitration"
11. The Court also referred to Chief Conservator of Forest
v. Rattan Singh 6 and ruled that:
"In the clause under discussion there is a provision for
G referring the disputes to the lessor and the decision of the
lessor is made final. On its true construction it spells out
an arbitration agreement"
H 6. AIR 1967 SC 166: 1966 Supp SCR 158.
KARNATAKA POWER TRANSMISSION CORP. LTD. v. 781
DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
12. At this juncture, it is apposite to refer to a three-Judge A
Bench decision in State of U. P. v. Tipper Chand 7 where the
Court was interpreting Clause 22 in the agreement which was
under consideration so as to find out whether the stipulations
therein spelt out an arbitration clause. The clause involved in
the said case read as follows:- B
"Except where otherwise specified in the contract the
decision of the Superintending Engineer for the time being
shall be final, conclusive and binding on all parties to the
contract upon all questions relating to the meaning of the C
specifications, design, drawing and instructions
hereinbefore mentioned. The decision of such Engineer as
to the quality of workmanship, or materials used on the
work, or as to any other question, claim, right, matter or
things whatsoever, in any way arising out of or relating to
the contract, designs, drawing specifications, estimates, D
instructions, orders, or these conditions. or otherwise
concerning the works, or the execution or failure to execute
the same, whether arising during the progress of the work,
or after the completion or abandonment of the contract by
the contractor, shall also be final, conclusive and binding E
on the contractor."
Interpreting the said clause, the Court opined thus:-
"Admittedly the clause does not contain any express
F
arbitration agreement. Nor can such an agreement be
spelled out from its terms by implication, there being no
mention in it of any dispute, much less of a reference
thereof. On the other hand, the purpose of the clause
clearly appears to be to vest the Superintending Engineer
with supervision of the execution of the work and G
administrative control over if from time to time."
13. In that context, the three-Judge Bench approved the
decisions of the High Courts in Governor-General v. Simla
1. (1980) 2 sec 341. H
782 SUPREME COURT REPORTS [2014] 4 S.C.R.
A Banking and Industrial Company Ltd. 8 , Dewan Chand v. State
of Jammu and Kashmir9 and Ram Lal v. Punjab State 10
wherein the clauses were different. In that context, it was opined
that the High Courts had rightly interpreted the clause providing
for arbitration. We think it apt to reproduce the delineation by
B the learned Judges:-
"ln the Jammu and Kashmir case the relevant clause was
couched in these terms:
"For any dispute between the contractor and the
c Department the decision of the Chief Engineer
PWD Jammu and Kashmir, will be final and binding
upon the contractor."
The language of this clause is materially different from the
clause in the present case and in our opinion was correctly
D interpreted as amounting to an arbitration agreement. In
this connection the use of the words "any dispute between
the contractor and the Department" are significant. The
same is true of the clause in Ram Lal case which ran thus:
"In matter of dispute the case shall be referred to
E the Superintending Engineer of the Circle, whose
order shall be final."
We need hardly say that this clause refers not only to a
dispute between the parties to the contract but also
specifically mentions a reference to the Superintending
F
Engineer and must therefore be held to have been rightly
interpreted as an .arbitration agreement." ·
14. At this stage, it is useful to refer to a three-Judge Bench
decision in State of Orissa and another etc. v. Sri Damodar
G Das11 wherein the Court posed the question whether there was
an agreement for the resolution of disputes as enshrined under
8. AIR 1947 Lah 215 : 226.IC 444.
9. AIR 1961 J & K 58.
10. AIR 1966 Punj 436 : 68 Punj LR 522 : ILOR (1966) 2 Punj 428.
H 11. AIR 1996 SC 942.
KARNATAKA POWER TRANSMISSION CORP. LTD. v. 783
DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
Clause 25 of the agreement. The said clause read as follows:- A
"25. Decision of Public Health Engineer to be final. -
Except where otherwise specified in this contract, the
decision of the Public Health Engineer for the time being
shall be final, conclusive and binding on all parties to the
contract upon all questions relating to the meaning of the B
specifications; drawings and instructions hereinbefore
mentioned and as to the quality of workmanship or
materials used on the work, or as to any other question,
claim, right, matter or thing, whatsoever in any way arising
out of, or relating to, the contract, drawings, specifications, c
estimates, instructions, orders or these conditions, or
otherwise concerning the works or the execution or failure
to execute the same, whether arising during the progress
of the work or after the completion or the sooner
determination thereof of the contract." D
The three-Judge Bench referred to the principles stated in
Tipper Chand (supra) and observed as follows:-
"We are in respectful agreement with the above ratio. It is
obvious that for resolution of any dispute or difference E
arising between two parties to a contract, the agreement
· must provide expressly or by necessary implication, a
reference to an arbitrator named therein or otherwise of
any dispute or difference and in its absence it is difficult
to spell out existence of such an agreement for reference F
to an arbitration to resolve the dispute or difference
contracted between the parties. The ratio in Smt.
Rukmanibai Gupta v. Collector does not assist the
· respondent."
G
15. In K.K. Modi v. K.N. Modi and others12 , a two-Judge
Bench was interpreting Clause 9 of the agreement which read
as follows:-
12. (1998) 3 sec 573. H
784 SUPREME COURT REPORTS (2014] 4 S.C.R.
A "Implementation will be done in consultation with the
financial institutions. For all disputes, clarification etc. in
respect of implementation of this agreement, the same
shall be referred to the Chairman, IFCI or his nominees
whose decisions will be final and binding on both the
B groups."
The court referred to a passage from Russell on Arbitration,
21st Edn., at p. 37, para 2-014 and the decisions in
Rukmanibai Gupta (supra) and M. Dayanand Reddy v. A.P.
Industrial Infrastructure Corporation Limited And Others13 and
C came to hold that the said clause was not an arbitration clause
and hence, the proceedings before the Chairman, IFCI could
not have been treated as arbitration proceedings .. It was so held
on the following ground:-
D "Undoubtedly, in the course of correspondence exchanged
by various members of Groups A and B with the Chairman,
IFCI, some of the members have used the words
"arbitration" in connection with clause 9. That by itself,
however, is not conclusive. The intention of the parties was
E not to have any judicial determination on the basis of
evidence led before the Chairman, IFCI. Nor was the
Chairman, IFCI required to base his decision only on the
material placed before him by the parties and their
submissions. He was free to make his own inquiries~ He
F had to apply his own mind and use his own expertise for
the purpose. He was free to take the help of other experts.
He was required to decide the question of valuation and
the division of assets as an expert and not as an arbitrator.
He has been authorised to nominate another in his place.
But the contract indicates that he has to nominate an
G
expert. The fact that submissions were made before the
Chairman, IFCI, would not turn tile decision-making
process into an arbitration."
H 13. (1993) sec 137.
KARNATAKA POWER TRANSMISSION CORP. LTD. 785
v. DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
16. In Bharat Bhushan Bansal v. UP. Small Industries A
Corporation Ltd., Kanpur 14 , clauses 23 and 24 of the
agreement were projected to make the foundation of an
· arbitration clause. That read as follows:-
"Decision of the Executive Engineer of the UPSIC to be
B
final on certain matters.
23. Except where otherwise specified in the contract, the
decision of the Executive Engineer shall be final, conclusive
and binding on both the parties to the contract on all
questions relating to the meaning, the specification, design, c
drawings and instructions hereinbefore mentioned, and as
to the quality of workmanship or materials used on the
work or as to any other question whatsoever in any way
arising out of or relating to the designs, drawings,
specifications, estimates, instructions, orders or otherwise D
concerning the works or the execution or failure to execute
the same whether arising during the progress of the work,
or after the completion thereof or abandonment of the
contract by the contractor shall be final and conclusive and
binding on the contractor. E
Decision of t11e MD of the UPSIC on all other matters shall
be final
24. Except as provided in clause 23 hereof, the decision
of the Managing Director of tre UPSIC shall be final,
F
conclusive and binding on both the parties to the contract
upon all questions relating to any claim, right, mafo.:r 0r thing
in any way arising out of or relating to the contract or these
conditions or concerning abandonment of the contract by
the contractor and in respect of all other matters arising
out of this contract and not specifically mentioned herein." G
Interpreting the said clauses, the Court opined thus:-
"ln the present case, reading clauses 23 and 24 together',
14. AIR 1999 SC 899. H
786 SUPREME COURT REPORTS [2014] 4 S.C.R.
A it is quite clear that in respect of questions arising from or
relating to any claim or right, matter or thing in any way
connected with the contract, while the decision of the
Executive Engineer is made final and binding in respect
of certain types cif claims or questions, the decision of the
B Managing Director is made final and binding in respect of
the remaining claims. Both the Executive Engineer as well
as the Managing Director are expected to determine the
question or claim on the basis of their own investigations
and material. Neither of the clauses contemplates a full-
C fledged arbitration covered by the Arbitration Act."
17. In Bihar State Mineral Development Corporation and
another v. Encon Builders (/) (P) Ltd. 15, while dealing with the
arbitration clause of an arbitration agreement under the Act the
Court stated thus:
D
"(1) There must be a present or a future difference in
connection with some contemplated affair.
(2) There must be the intention of the parties to settle such
difference by a private tribunal.
E ,
(3) The parties must agree in v1lriting to be bound by the
decision of such tribunal.
(4) The parties must be ad idem".·
F In the said case, it has also been opined that the Act does
not prescribe any form of an arbitration agreement. The term
'arbitration' is not required to be specifically mentioned in the
agreement but what is required is to gather the intention of the
parties as to whether they have agreed for resolution of the
G disputes through arbitration.
18. In Dina Nath (supra), the clause in the agreement read
as follows: -
H 15. (2003) 1 sec 418.
KARNATAKA POWER TRANSMISSION CORP. LTD. 787
v. DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
. "4. Any dispute arising between the department and the A
contractor/society shall be referred to the Superintending
Engineer, Anandpur Sahib, Hydel (Construction) Circle No.
1, Chandigarh for orders and his decision will be final and
acceptable/binding on both parties."
The two-Judge Bench, basically relying on Tipper Chand B
(supra) which has approved the view of Jammu and Kashmir
High Court in Dewan Chand (supra), treated the aforesaid
clause as providing for arbitration because it categorically
mentioned the word "dispute" which would be referred to the
Superintending Engineer and further that his decision would be C
final and acceptable to/binding on both the parties.
19. In Jagdish Chander (supra), the Court, after referring
to the earlier decisions, culled out certain principles with regard
to the term "arbitration agreement". The said principles D
basically emphasize on certain core aspects, namely, (i) that
though there is no specific form of an arbitration agreement,
yet the intention of the parties which can be gathered from :the
terms of the agreement should disclose a determination and
obligation to go to arbitration; (ii) non-use of the words E
"arbitration" and "arbitral tribunal" or "arbitrator" would not
detract from a clause being interpreted as an arbitration
agreement if the attributes or elements of arbitration agreement
are established, i.e., (a) The agreement should be in writing.
(b) The parties should have agreed to refer any disputes
(present or future) between them to the decision of a private F
tribunal. (c) The private tribunal should be empowered to
adjudicate upon the disputes in an impartial manner, giving due
opportunity to the parties to put forth their case before it. (d)
The parties should have agreed that the decision of the private
tribunal in respect of the disputes will be binding on them; and G
(iii) where there is specific exclusion of any of the attributes of
an arbitration agreement or contains anything that detracts from
an arbitration agreement, it would not be an arbitration
agreement. In this context, the two-Judge Bench has given
some examples and we think it apt to reproduce the same: - H
788 SUPREME COURT REPORTS [2014] 4 S.C.R.
A "For example, where an agreement requires or permits an
authority to decide a claim or dispute without hearing, or
requires the authority to act in the interests of only one of
the parties, or provides that the decision of the authority
will not be final and binding on the parties, or that if either
B party is not satisfied with the decision of the authority, he
may file a civil suit seeking relief, it cannot be termed as
an arbitration agreement."
20. In State of Orissa and others v. Bhagyadhar Dash 16,
the Court, while discussing about the non-requirement of a
C particular form for constituting an arbitration agreement and
ascertainment of the intention for reference to arbitration, as has
been stated in Rukmanibai Gupta (supra), observed thus: -
"16. While we respectfully agree with the principle stated
D above, we have our doubts as to whether the clause
considered in Rukmanibai Gupta case would be an
arbitration agreement if the principles mentioned in the
said decision and the tests mentioned in the subsequent
decision of a larger Bench in Damodar Das are applied.
Be that as it may. In fact, the larger Bench in Damodar Das
E
clearly held that the decision in Rukmanibai Gupta was
decided on the special wording of the clause considered
therein: (Damodar Das case, SCC p. 224, para 11)
"11 .... The ratio in Rukmanibai Gupta v. Collector
F does not assist the respondent. From the language
therein this Court inferred, by implication, existence
of a dispute or difference for arbitration."
21. Keeping in mind the principles laid down by this Court
in the aforesaid authorities relating to under what circumstances
G a clause in an agreement can be construed as an arbitration
agreement, it is presently apposite to refer to clause 48 of the
agreement. The said clause reads as follows: - ""
"48.0 Settlement of disputes:
H 1e. c2011) 1 sec 406.
KARNATAKA POWER TRANSMISSION CORP. LTD. v. 789
DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
48.1 Any dispute(s) or difference(s) arising out of or in A
connection with the Contract shall, to the extent possible,
be settled amicable between the parties.
48.2 If any dispute or difference of any kind whatsoever
shall arise between the owner and the Contractor, arising
B
out of the Contract for the Performance of the Works
whether during the progress of the Works or after its
completion or whether before or after the termination,
abandonment or breach of the contract, it shall, in the first
place, be referred to and settled by the Engineer, who,
within a period of thirty (30) days after being requested by C
either party to do so, shall give written notice of his decision
to the owner and the contractor .
. 48.3 Save as hereinafter provided, such decision in
respect of every matter so referred shall be final and D
binding upon the parties until the completion of the works
and shall forthwith be given effect to by the contractor who
shall proceed with the works with all the due diligence.
48.4 During settlement of disputes and Court proceedings,
both parties shall be obliged to carry out their respective E
obligations under the contract."
22. On a careful reading of the said clause, it is
demonstrable that it provides for the parties to amicably settle
any disputes or differences arising in connection with the
F
contract. This is the first part. The second part, as is
perceptible, is that when disputes or differences of any kind
arise between the parties to the contract relating to the
performance of the works during progress of the works or after
its completion or before or after the termination, abandonment G
or breach of the contract, it is to be referred to and settled by
the engineer, who, on being requested by either party, shall give
notice of his decision within thirty days to the owner and the
contractor. There is also a stipulation that his decision in
respect of every matter so referred to shall be final and binding
upon the parties until the completion of works and is required H
'
790 SUPREME COURT REPORTS [2014] 4 S.C.R.
A to be given effect to by the contractor who shall proceed with
the works with due diligence. To understand the intention of the
parties, this part of the clause is important. On a studied scrutiny
of this postulate, it is graphically clear that it does not provide
any procedure which would remotely indicate that the concerned
B engineer is required to act judicially as an adjudicator by
following the principles of natural justice or to consider the
submissions of both the parties. That apart, the decision of the
engineer is only binding until the completion of the works. It only
casts a burden on the contractor who is required to proceed
c with the works with due diligence. Besides the aforesaid, during
the settlement of disputes and the court proceedings, both the
parties are obliged to carry out the necessary obligation under
the contract. The said clause, as we understand, has been
engrafted to avoid delay and stoppage of work and for the
purpose of smooth carrying on of the works. It is interesting to
0
note that the burden is on the contractor to carry out the works
with due diligence after getting the c!ecision from the engineer
until the completion of the works. Thus, the emphasis is on the
performance of the contract. The language employed in the
clause does not spell out the intention of the parties to get the
E disputes adjudicated through arbitration. It does not really
provide for resolution of disputes.
23. Quite apart from the above, clause 4.1 of the
agreement is worthy to be noted. It is as follows: -
F "4.1 It is specifically agreed by and between the parties
that all the differences or disputes arising out of the
Agreement or touching the subject matter of the
Agreement, shall be decided by a competent Court at
Bangalore."
G
24. Mr. Vishwanathan, learned senior counsel for the
appellants, laying immense emphasis on the same, has
submitted that the said clause not only provides the territorial
jurisdiction by stating a competent court at Bangalore but, in
H essence and in effect, it stipulates that all the differences or
KARNATAKA POWER TRANSMISSION CORP. LTD. 791
v. DEEPAK CABLES (INDIA) LTD. [DIPAK MISRA, J.]
disputes arising out of the agreement touching the subject- A
matter of the agreement shall be decided by a competent court
at Bangalore. Mr. Dave, learned senior counsel for the
respondents, would submit that it only clothes the competent
court at Bangalore the territorial jurisdiction and cannot be
interpreted beyond the same. The submission of Mr. Dave, if B
properly appreciated, would convey that in case an award is
passed by the arbitrator, all other proceedings under any of the
provisions of the Act has to be instituted at the competent court
at Bangalore. This construction, in our opinion, cannot be placed
on the said clause. It really means that the disputes and c
differences are left to be adjudicated by the competent civil
court. Thus, clause 48, as we have analysed, read in
conjunction with clause 4.1, clearly establishes that there is no
arbitration clause in the agreement. The clauses which were
interpreted to be arbitration clauses, as has been held in Ram D
Lal (supra) and Dewan Chand (supra) which have been
approved in Tipper Chand (supra), are differently couched. As
far as Rukmanibai Gupta (supra) is concerned, as has been
opined in Damodar Das (supra) and also in Bhagyadhar Dash
(supra), it has to rest on its own facts. Clause in Dina Nath E
(supra) is differently couched, and clause 48, which we are
dealing with, has no similarity with it. In fact, clause 48, even if
it is stretched, cannot be regarded as an arbitration clause. The
elements and attributes to constitute an arbitration clause, as
has been stated in Jagdish Chander (supra), are absent.
Therefore, the irresistible conclusion is that the High Court has F
fallen into grave error by considering the said clause as
providing for arbitration.
25. Consequently, the appeals are allowed and the
judgments and orders passed by the High Court are set aside. G
Howexer, regard being had to the facts and circumstances of
the case, there shall be no order as to costs.
D.G. Appeals allowed.
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.