KANORIA CHEMICALS AND INDUSTRIES LTD. AND ANR.versusSTATE OF U. P. AND ORS. AND VICE VERSA
- Citation
- 1992 INSC 11
- Decided
- 16 January 1992
- Disposal
- Disposed off
- Bench
- S RANGANATHAN
Holding
Section 60(5)(a) confers a valid, retrospective and repeatable power on the Board to revise rates, without obligating it to disclose detailed calculations, and while it may set rates above HV‑2, no justification existed here, so the rates must be the HV‑2 tariff.
Summary
Kanoria Chemicals & Industries Ltd. entered into a 1963 contract with the Uttar Pradesh Government for electricity at concessional rates. The Uttar Pradesh Electricity Laws (Amendment) Act, 1983 amended Section 60 of the Electricity (Supply) Act, 1948, allowing the State and the Board to revise rates retrospectively from May 20, 1983. The Board fixed rates higher than the uniform HV‑2 tariff, which the company challenged, arguing that the Board must consider special factors, disclose its calculation method, and could not charge rates above HV‑2. The Supreme Court held that Section 60(5)(a) validly permits retrospective and multiple revisions, does not require detailed disclosure of calculations, and allows rates higher than HV‑2 if justified. However, in this case no justification existed, so the rates were ordered to be the HV‑2 tariff from 20‑May‑1983 to 31‑Mar‑1989. The appellant's appeal was partially allowed and the Board's appeal dismissed.
Issues considered
- The validity and scope of Section 60(5)(a) of the Electricity (Supply) Act, 1948 as amended by the Uttar Pradesh Amendment Act, 1983, including its retrospective effect and the power to revise rates more than once.
- Whether the Board and State must consider specific individual factors under Section 60(5)(a) distinct from those considered under Section 49 when fixing rates for a particular consumer.
- Whether the Board is required to disclose the precise methodology or calculations used to arrive at the revised rates.
- Whether the Board may fix rates higher than the uniform HV‑2 tariff for a bulk consumer with a prior concessional contract.
- The effect of the differing English and Hindi versions of the Amendment Act on the interpretation of the statutory provision.
Legislation cited
- Electricity Laws (Uttar Pradesh Amendment) Act, 1983 (Act 12 of 1982)s. 3, s. 4, s. 5, s. 7 (amending Section 60)
- Electricity (Supply) Act, 1948s. 49, s. 59, s. 60(5), s. 64
- Electricity Supply Act, 1948 (as amended by Act 18 of 1983)s. 59(1)
- Indian Electricity Act, 1910s. 22-B
Subjects
Judgment
KANORIA CHEMICALS AND INDUS1RIES LTD. AND ANR. A
y v ..
STAIB OF U. P. AND ORS. AND VICE VERSA
JANUARY 16, 1992
[S. RANGANATHAN, FATHIMA BEEVI AND N. D. OJHA, JJ.] B
Electricity (Supply) Act, 1948: Section 60 (As introduced by section
7 of Electricity Laws (U.P. Amendment) Act, 1983.
Company-Electricity Board-Contract for supply of electricity at
concessional rates on special considerations-Power of Electricity Board to C
revise rates-V.P. Gazette Notification dated 29.10.82--Schedule-Levy of
HV-2 rates i.e. uniform tariff applicable to "bulk power" consumers in
substitution of contracted rates-Validity of-Held fixation of rates was not
vitiated-Revision of rates can be given retrospective effecl-Failure to
specify the precise manner in which the rates were arrived at does not
vitiate the rates fixed-Power to revise tariff can be exercised more than D
once-Electricity Board can fix rates higher than HV-2 rates-But levy of
rates higher than HV-2 rates on the Company held not justified under the
circumstances.
)·. Section 49-Electricity Board-Revision of rates-Factors to be taken
into account-Di.,·tinction between section 49 and 60 explained. E
Electricity Laws (U.P. Amendment) Act, 1983 (Act 12 of 1982):
Section 7-Difference in English and Hindi version of Act, Absence of
words "for the first time" in Hindi version of Act-Effect of.
The appellant-company set up a caustic soda industry at Renukoot F
involving the use of electricity as the main raw material. On 30.9.63 it
entered into a contract with the State of Uttar Pradesh for supply of
electricity for a period of 25 years from 1.4.64, to the extent of 6.5 NW
from the Rihand Hydel station at a fixed rate of 2.5 paise per unit and
an additional supply of 1.5 NW from an inter-connection at the rate of G
5 NP per unit. The terms of the contract provided that the transmission
and distribution losses were to be borne by the company and that the
rates could be raised after sixteen years but any enhancement in rates
was not to exceed 10 per cent of the rates agreed upon.
Subsequently, the UP Government enacted the Electricity Laws H
(Uttar Pradesh Amendment) Act, 1983 which came into force from
151
152 SUPREME COURT REPORTS (1992] 1 ~. c. R.
20.5.1983. Section 7 of the said Act amended section 60 of the Eleetricity
A Supply Act, 1948 by inserting sub-sections (3) to (5) with retrospective
effect from April 1, 1965. The Amended Act enabled the State and the
Board to modify the rates of supply of Electricity to appellant under the
contract of 30.9.63. Simultaneously the Parliament also amended Sec-
tion 59 of the Electricity Supply Act by the Act 18 of 1983 enabling the
Electricity Board to fix the tariff in such a way so as to build up a
B statutory surplus fixed by the State Government.
On the passing of the Amendment Act, the Electricity Board in-
formed the appellant-company that the rates were proposed to be
revised and later it informed the appellant-company that on 28.9.83 the
State Government, by its Gazette Notification dated 29th October, 1982,
C had approved the levy of HV-2 rates (i.e. uniform tariff applicable to
'Bulk power' consumers) in substitution of the rates mentioned in the
·agreement of 30th September, 1963. The effect of the revision was to
oblige the appellant-company to pay 57.71 paise per unit for 1983-84
and 61.60 paise per unit for 1984-85. Accordingly, supplementary bills
were raised demanding Rs. 3.07 crores from the appellant-company. -,,
D The appellant filed a writ petition in the High Court of Allahabad
assailing the Validity of section 7 of the amending Act and the right of
the Board to enhance the rates.
By its order dated 2.4.87 the High Court allowed the writ petition
and quashed the approval dated 28.9.83 given by the State Government
E to the new rates and the consequential demands of the Electricity Board
but left it to the Board and State to fix revised rates afresh by directing
the respondents (1) not to charge the uniform tariff rate for the period
beginning from 20th May, 1983 till the rates were fixed in accordance
with section 60(5) (a); and (ii) that the rates applicable to the appellants
F should be determined having regard to the individual circumstances of
the appellant.
The Electricity Board and the State Government preferred an
appeal to this Court. Aggrieved by the fact that in applying the HV -2
rates the Board and the ·State had not taken into account the special
G factors relevant to the supplies made to it, the appellant also filed an
appeal in this Court.
In the meantime, pursuant to the directions of the High Court the
Board fixed the revised rates on 28.3.88 for the supply from 20th May,
H 1983 which were much higher than the HV-2 rates fixed earlier and
KANORIA CHEMICALS v. STATE 153
quashed by the High Court.
A
The appeals came to be heard by this Court on April 10, 1991
when this Court directed that the appellant should make a representa·
tion to the State Electricity Board setting out the individual factors
which should be taken into account in fixing the rates applicable to
them within the meaning of section 60(5) (a) of the 1948 Act and that
the State Government should reconsider the fixation after considering B
the recommendations made by the Board as well as the representations
of the appellant.
Accordingly the State reconsidered the matter and by its order
dated 31.8.92 approved the rates fixed by the State Government on C
28.3.88.
The appellant challenged the validity of the rates fixed contend·
ing that (i) the fixation of rates as on 31.8.1992 was not valid because
(a) the respondents have not complied with this court's directions dated
10.4.1991 as they have neither disclosed the factors based on which the
rates were revised in March 1988 nor indicated ·the monetary incidence D
or impact of the factors taken into account; (b) in the process of re·
fixation of the rates there was no genuine exercise .to consider relevant
factors in determining the rate under section 60 (5) (a); (c) that the
Board had not set out anywhere the precise manner in which the rates
recommended by them were arrived at; (ii) Section 60 cannot be
interpreted so as to give power to the Board to fix rates retrospectively E
because (a) such an interpretation precludes the Board and the State
from revising the rates prospectively; (b) if the power is held exercis-
able more than once, it will permit successive revisions each supersed-
ing the earlier one, a position that could lead to harrassment; (c) that
the Hindi version of the Amendment Act is differently worded and does F
not contain the words "for the first time" found in the English version
y and in case of a conflicting version between Hindi and English version
the Hindi text should be the key to find out the true intention of the
Legislature; and (iii) in view of the facts (a) that the company estab-
lished its industry in a backward area at the request of the State and
in public interest; (b) the transmission and distribution losses are borne G
by the appellant and (c) electricity is one of the raw materials needed
for its industry the appellant should be charged less than the HV-2
rates.
On behalf of the Electricity Board it was contended that the H
154 SUPREME COURT REPORTS [1992] l S. C.R.
A demand or rates higher than HV·2 rates was justified because (a) the
Company has been getting substantial supplies or electricity at nominal
rates from 1963 to.1983; (b) The Board has incurred heavy losses over
the years by supplying electricity at concessional rates; and (c) there
was a necessity to build up a statu.ory surplus prescribed by section 59.
B Allowing the Company's appeal in part and dismissing the Elec·
tricity Board's appeal, this Court,
HELD: I. The fixation or revised rates is not vitiated. [173-E]
2. Section 60 does not require the Board or the State Government
C to explain each and every step in its calculation. All that the Electricity
Board has to do is to take into consideration the ractors relevant under
section 60(5) and propose rates for fixation to the State Government. It
is in order to ensure that these recommendations take into account all
relevant ractors that an opportunity has been provided to the consumer
to satisry the Board as well as the State Government that the rixation
D has taken into account certain relevant factors. Therefore, the rate
revision proceedings were not vitiated for the reason that the Board has
not set out the precise manner in which the rates recommended by them
were arrived at. [172 D-E, 172-C]
2.1 Apart from the general factors which have been taken into·
E account in fixing the general tariff rates, the Board has, in making its
recommendations, taken into account the purpose ror which supply was
required by the appellant along with the factor of recurring losses
incurred by the Board year after year and its statutory requirements to
maintain a minimum surplus or 3 per cent as required under section 59
or the Supply Act, 1948. [173-D]
F
2.2 The rates recommended by the State Electricity Board and
approved by the State Government were within the knowledge or the
appellant-company. The appellant-company filed its representation.
After considering the representation, the Board made its recommenda-
G lions to the State Government and a copy or the recommendations were
also available to the appellant. The appellant bad run opportunity to
meet the various points set out in the recommendations of the Board.
The comments or both the Board and the Appellant were taken into
account by the State Government before finally. approving or the rates
proposed by the Board. Therefore, the appellant-company bad full
H opportunity to place all its special reature before the Board and the
KANO RIA CliEMICALS v. STATE 155
State Government. [171H, 172A,B, 173E)
A
2.3 If one compares the two provisions viz. sections 49 and 60 one
will find that most of the elements are common to the two provisions.
Both under section 49 and section 60 the authorities have to take into
account the geographical position or any area, the nature or supply and
purpose for which supply is required and any other relevant factor.
The only difference between the two provisions is that since section 49 B
deals with a general fixation while section 60(5) deals with a rixation for
a particular individual case, there may be some special factors to be
taken into account which may or may not be germane while rixing the
general lllriff under section 49. [172H, 173-A)
Indian Aluminium Company Ltd. v. Kera/a State Electricity Board, C
(1976) 1 S.C.R. 70; cited.
3. A retrospective effect to the revision or rates is clearly envis-
aged by section 60. One can easily conceive a weighty reason for saying
so. If the section were interpreted as conferring a power or revision only
prospectively, a consumer affected can easily frustrate the effect or the D
provision by initiating proceedings seeking an injunction restraining the
Board and thus getting the revision deferred indefinitely. Or, again, the
revision or rates, even if effected promptly by the Board and State, may
prove infructuous for one reason or another. Therefore, it would be a
very impractical interpretation or the section to say that the revision or
rates can only be prospective. [174E-G] E
\
3.1 The mandate or section 60 is only that the rates to be charged
on supplies for which payment becomes due after 20.8.83 shall be as
rixed by the Board. The powers of the Board in rixing the rates-
including the dates from which they will be operative are not restricted F
in any manner. The Board is at complete liberty to rix different rates
from different dates and that scheme or rixation will be read with the
y
contract. Only the Board cannot revise the rates in respect or supplies
for which payment under the contract fell due before the Amendment
Act came into force. (175-B-C]
G
3.2 The power under section 60 is exercisable more than once.
However, while making a subsequent revision, the authorities will not
normally tamper with an earlier revision or alter the dates of effective-
ness rixed for the earlier revision without a valid reason to do· so. If this
is done, it will be open to a court to examine the basis thereof and H
156 SUPREME COURT REPORTS [1992] 1 S. C.R.
sustain it only where the earlier rJXation was based on an error or
A misconception or the like and called for modification. [175D-F]
3.3 Although the Hindi version of the Amendment Act is differ-
ently worded and does not contain the words ''for the first time" found
in the English version, the Hindi version does not really alter the
position; actually it is the presence of the words "for the first time" in
B the English version that create ambiguity. Without these words, the
clause clearly provides that all supply of electricity, for which payment
is to be made after 20.5.83, i.e. coming into force of the Amendment
Act, will be charged at the rates to be rlXed by the Board. Therefore,
the rJXation by the Boa.rd of rates from 20.5.83, and, at different rates
C for different period of time, is unexceptionable. [175F-H, 176-A]
Maia Badal Pandey v. Board of Revenue, (1974) U.P.T.C. 570; re-
ferred to.
4. There are no obstacles, statutory or theoretical, standing in the
way or the Board fixing rates for the company which will be higher than
D the rates applicable to bulk consumers. The provision in s. 60(5)(a) is
intended to enable the Board and State to cut off the shackles cast by
an ancient contract entered into at a time when conditions were totally
different. It confers an absolute and unrestricted enabling power to
revise the rates· in an appropriate mallner. [174-A]
E While revising rates, the only limitation which the statute requires
the authorities to keep in mind are the factors mentioned in the section.
Whether the revised rates for the consumer governed earlier by the
contract should be higher or lower than, or equal to, the tariff rates
would depend on a large number or considerations, in particular, the
basis on which, and the point of time at which, those general rates were
F
rJXed. In principle , it is quite conceivable that, in an appropriate case,
a consideration of the relevant factors may justify even a rate higher
than the general tariff rates intended fer the particular category or
consumers. [174B-D]
G 4.1 However, there is no material to justify any departure from
the HV -2 rates in the case or the appellant. The special circumstances
pleaded by the appellant-company have Jost their importance with the
passage or time. The conditions that prevailed in 1963 are not valid and
the appellant has had the benefit or concessional rates for twenty years.
H The consideration that electricity is a ''raw material" in the assesee's
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.J 157
business is, again irrelevant for it can mean nothing more than that the A
appellant needs substantial quantities of the energy and there is no
reason why it should not pay for it at the normal market rates.
Therefore, the appellant has no valid justification for staking a claim to
less than the HV-2 rates. [177-B-DJ
4.2 Equally, the authorities have no case to raise the rates beyond
the HV-2 rates. The huge losses that the Board has been incurring and B
the statutory justification for escalation in the rates keeping in view the
necessity to build up a surplus is an aspect of working which should
affect all the consumers equally. May be the Board can, in appropriate
circumstances, seek to make up for a part of the losses by hiking up the
rates to one particular category of consumers but that would not be
justified here as the transmission and distribution losses in respect of C
the supply to the appellant are borne by it and, in the absence of some
special vital reason, it would not be equitable to fJX the rates of supply
to the appellant above the rates applicable to other HV-2 consumers.
Therefore, there is no justification to charge more than HV-2 rates
from the appellant. [177EG, 178-B]
D
4.3 The determination of 1988 and 1991 are quashed. The State
Electricity Board is directed to charge the appellant-Company from
20.5.83 to 31.3.89 al the HV-2 rates applicable to other consumers.
[178-B]
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1306 of E
1988.
From the Judgment and Order dated 2.4.1987 of the Allahabad High
Court in Writ Petition No. 1818 of 1984.
F
H.N. Salve, P.P.Tripathi, Manoj Swarup and KJ. Johan for the Ap-
pellants.
B.Sen, Gopal Subramaniam, Prashant Kumar and Mrs. S. Dikshit for
the Respondents.
G
The Judgment of the Court was delivered by
RANGANATHAN, J. There was a time when, in ahnost every State
in India, people were invited to avail of the supply of the electric energy
produced in the State and offered special concessions when they agreed to H
158 SUPREME COURT REPORTS [1992] I S. C.R.
A do so in bulk under long-tenn contracts. A situation, however, has since
developed when the demand for the energy increased so rapidly that, despite
the quantity of available electric energy also having gone up tremendously
the rates of supply agreed upon became uneconomical. The State and its
instrumentalities, who were supplying the energy, found themselves without
power to revise the rates to meet the altered situation until the legislature
came to the rescue. It is this situation in the case of Kanoria Chemicals and
B Industries Ltd. (hereinafter referred to as 'the appellant') which has given
rise to these appeals.
The Electricity (Supply) Act, 1948, (hereinafter referred to as 'the
1948 Act') entrusted the control over the generation and distribution of
electric energy to -Electricity Boards constituted under the Act. In the State
C of Uttar Pradesh, the U.P. State Electricity Board (hereinafter referred to as
'the Board,) was constituted on 1.4.1959. At that time, the State Govern-
ment (hereinafter referred to as 'the State') was in the process of establish-
ing the Rihand Hydro-Electric Genecating Plant, which become operational
w.e.f. 1.2.62, and attained an ultimate installed capacity of 300 M.W. The
control of this remained with the State till 31.3.1965. Since the supply of
D electrical energy was then available in abundance and only the eastern area
of the State was served by the plant, the State considered it expedient to
enter into contracts with bulk purchasers both with a view to ensure
maximum utilisation of the electricity available and with a view to the
industrialisation of the eastern areas of the State. In particular the State was
keen on the industrial development of the district of Mirzapur, which was
E considered to be an extremely backward area. The State was keen that
power intensive units be set up in close proximity of Rihand so that
electricity could be supplied to these units from the Rihand power plant.
One feature of the supply of electricity from Rihand was that the metering
was done at the point of generation so that transmission and distribution
losses and costs could be borne by the consumers of electricity.
F
The appellant set up an industry for manufacture of caustic soda at
Renukoot sometime in 1964. According to the appellant, this industry
involved the use of electricity as the main raw material, the other raw
material needed being salt. It is said that there were considerable disadvan-
G tages in setting up the proposed caustic soda unit in the district of Mirzapur,
principally due to its distant location from areas from which salt had to be
transported. The appellant, it is said, could easily have set up its factory in
some other State with greater facilities and advantages but it was induced
to set up the caustic soda plant ai Pipri in the district of Mirzapur on
H account of the assurance given by the State that it will supply hydro electric
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.] 159
power to the assessee from the Rihand power plant on a long term basis at
a cheap rate. It is claimed that, but for this promise, the appellant would A
never have chosen Pipri or the district of Mirzapur for the location of this
plant.
After elaborate discussions between the State Government and the
I promoters of the appellant company, the plant was set up at Pipri and a
contract was entered into between the State Government and the appellant B
on 30.9.1963 ensuring the supply of electricity from the point of generation
to the appellant for a period of 25 years from 1.4.1964. The supply, to the
extent of 6.5 MW. was to be from Rihand hydel station at a fixed rates of
2.5 paise ier unit. An additional supply of 1.5 MW was also promised from
.-L an inter-connection at the rate of 5 N.P. per unit. The rates could be revised
after the first sixteen years but any enhancement in rates was not· to exceed c
10 per cent of the rates agreed upon.
~~t,
<\ The State agreed further to supply 4.5 MW to the appellant from the
\;ii
Obra Hydro-Electric Project on such rates as would be fixed subsequently.
It may be mentioned that this clause gave rise to disputes which were
referred to arbitration. An award was made by justice D.P. Madan, a retired D
judge of this Court, which was made a decree of this Coun by an order
dated 1.4.1987. Under the award, the rate of supply was fixed at 8.69 paise
per unit. The State's grievance is that it incurred a loss of Rs. 10.55 crores
by supplying electricity from Rihand between 1.4.64 and 19.5.83 at
concessional rates instead of applying the uniform tariff applicable to other
"bulk power" consumers, briefly referred to as "HV-2 rates." It says also E
H that it likewise suffered a loss of 12.4 crores due to the supply at 8.69 paise
instead of normal rates, from Obra between 1.4.71 and 31.3.89, when the
I agreement, came to an end by efflux of time.
'
~ .__,.----;;
Obviously, it was not economical to continue supplying energy at the
preposterously low rates to which the State had committed itself in 1963 on
F
account of the conditions that prevailed at the time of the agreement. The
\ powers of the State or the Boards to revise contractual rates unilaterally
were examined by this Coun in Indian Aluminium Company Ltd. v. Kera/a
State Electricity Board [1976] 1 SCR 70. It is sufficient to say that, after
considering the provisions of section 49 and 59 of the Supply Act, the Coun G
held that the Electricity Boards were not entitled to enhance charges in
derogation of stipulations contained in agr,eements enfered into between
parties. This decision led to the provisions of iRe•Supply Act being amended
by various States. The States of Karnataka, Orissa and Rajasthan brought
in amendments enabling the Electricity Board to supersede contracts and H
"'"
•
160 SUPREME COURT REPORTS [1992] I S. C.R.
A revise the rates contained in earlier agreements. The U.P. Government, also
enacted the Electricity Laws (Uttar Pradesh Amendment), Act, 1983, to vest
the State's agreement with the Board and to enable the Board to revise the
contractual rates. The Act came into force from 20.5.1983. Section 7 of the
said Act amended Section 60 of the Supply Act, 1948 by inserting the
following sub-sections (3) to (5) with retrospective effect from April I,
B 1965 :
(3) All expenditure which the State Government may, not later
than two months from the commencement of the Electricity
Laws (Uttar Pradesh Amendment) Act, 1983, declare to have
been incurred by it on capital account in connection with the
purposes of this Act in respect of the Rihand Hydro Power
c System shall also be deemed to be a loan advanced to the Board
under section 64 on the date of commencement of this sub-
section and all the assets acquired by such expenditure shall vest
in the Board with effect from such commencement.
(4) The provisions of the sub-sections (I) and (I-A) shall,
D subject to the provisions of sub-section (5) apply in relation to
the debts and obligations incurred, contracts entered into and
matters and things obliged to be done by, with or for the State
Government in respect of the Rhinand Hydro Power system
after the first constitution of the Board and before the com-
mencment of this sub-section as they apply in relation to debts
E and obligations incurred, contracts entered into, matters and
things engaged to be done by, with or for the State Govemement
for any of the purposes of this Act before the first constitution
of the Board.
(5) All such contracts entered into by the State Govemement for
F
supply of electrical energy based on or connected with the gen-
eration of electricity from the Rihand Hydro Electric Generat-
ing Station to any consumer and any contract entered into by the
Board on or after April I, 1965 for the supply of electrical
energy to such consumer shall operate subject to the modifica-
G tions specified in the following clauses, which shall have effect
from the date of the commencement of the Electricity Laws
(Uttar Pradesh Amendment) Act, 1983 (hereinafter referred to
as the· said date):-
H
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.) 161
-· -(
(a) the rates to be charged by the Board for the energy
supplied by it to any consumer under any contract for which the A
payment will be due for the first time on or after the said date
shall be such as may with the previous approval of the State
Government be fixed by the Board, having due regard to the
...'' geographical position of the area of supply, the nature of the
supply and purpose for which supply is required and any other B
1 :\
-_,
"';'
(• .;,: relevant factor.
(b) If the State Government directs the Board under Section
22-B of the Indian Electricity Act, 1910 or under any other law
for the time being in force to reduce the supply of energy to a
consumer and thereupon the Board reduces the supply of energy · C
to such consumer accordingly, the consumer concerned shall
not be entitled to any compensation for such reduction, and if
the consumer consumes energy in excess of the reduced limit
fixed under the said section 22-B or any other law for the time
being in force as the case may be, then the Board shall have the
right to discontinue the supply to the consumers without notice,
and without prejudice to the said right of the Board, the D
consumer shall be liable to pay for such excess consumption at
double the normal rate fixed under clause (a);
(c) Any arbitration agreement contained in such contract
shall be subjects to the provisions of this sub-section.
Parliament also, at about the same time, amended s. 59 of the Act by
Act 18 of 1983. The amended s. 59(1), which is sufficient for our purpose
reads thus :
59. General principles for Board's finance - (1) The Board shall, F
after taking credit for any subvention from the State Govern-
ment under Section 63, carry on its operation under this Act and
adjust its tariffs so as to ensure that the total revenues in any
year of account shall, after meeting all expenses properly
chargeable to revenues, including operating, maintenance and
management expenses, taxes (if any) on income and profits de- G "
predation and. interest payable on all debentures, bonds and
loans, leave such surplus as is not less than three per cent, or
such higher percentage, as the State Government may, by
notification in the official ·Gazette, specify in this behalf, of the
value of the fixed assests of the Board in service at the H
162 SUPREME COURT REPORTS [1992] 1 S. C.R.
beginning of such year.
A
Explanation - For the purposes of this sub-section, "value of the
fixed assets of the Board in service at the beginning of the year"
means the original cost of such fixed assets as reduced by the
aggregate of the cumulative depreciation in respect of such
assets calculated in accordance with the provisions of this Act
B and consumers' contributipns for service lines.
It has been pointed out to us that the U.P. Slate amendment is
somewhat different from those of the other Slates. The Kamataka legisla-
ture amended s. 49 of the 1948 Act and the Orissa and Rajasthan
legislatures inserted s. 49A in the said Act These provisions enabled the
C Boards to prescribe lariffs and these rates were to prevail over those
specified in the agreement. The latter two amendments actually declare the
relevant clauses in the agree.ment void from inception. The U.P. amend-
ment however, retains the effectiveness of the earlier conlracts and only
reads into them the rates that may be prescribed by the Board. This is the
first difference. The second is that while the other legislations affect all
D agreements entered into before a specified date, the U.P. amendment is
restricted to contracts for supply of electricity from the Rihand Hydro-
Electric Generating Station. We are informed that, when the above
amendment was sought to be effected, the only outstanding conaact of the
State for the supply of electricity from the Rihand Hydro-Electric Gener-
ating Station was the conaact with the appellant on the 301h of September,
E 1963. There had been two agreements entered into for supply of electricity
from !his power station but !he olher one wilh Hindustan Aluminium
Company had become ineffective since !hat company gave up its claim to
supply from the above power plant in 1975-76 having been successful in
putting up a power plant for its captive use. Thus, though lhe Act purports
F to be one of general application, it was r~ally intended to enable lhe State
and lhc Board to modify the rates of supply cf dectricity to appellant under
the contract of 30.9.1963.
At !his stage it may be useful to refer also to the terms of s. 49 of
the Act It reads lhus :
G
(1) Subject to the provisions of !his Act and or regulations, if
any, made in !his behalf, !he Board may supply electricity to
any person not being a licensee upon such terms and conditions
as lhe Board thinks fit and may for !he purposes of such supply
H frame uniform tariffs.
- KANORIA CHEMICALS v. STATE [RANGANATHAN, J.] 163
(2) In fixing the uniform tariffs the Board shall have regard to A
all or any of the following factors, namely :-
(a) the nature of the supply and the purposes for which it is
required :
- (b) the co-ordinated development of the supply and distribu-
tion of electricity within the State in the most efficient and B
economical manner, with particular reference to such develop-
ment in areas not for the time being served or adequately served
by the licensee•
(c) the simplification and standardisation of methods and
rates of charges for such supplies : C
(d} the extension and cheapening of supplies of electricity to
sparsely developed areas.
(3) Nothing in the foregoing provisions of this section shall
derogate from the power of the Board, if it considers it neces- D
sary or expediant to fix different tariffs :or the supply of
electricity to any person not being a licensee, having regard to
the geographical position of any area, the nature of the supply
and purpose for which supply is required and any other relevant
factors.
E
(4) In fixing the tariff and conditions for the supply of electric-
ity, the Board shall not show undue preference to any person.
After the statute was thus amended, the Additional Chief Engineer of
the Board wrote to the appellant on 6.2.1984 stating that, though the bills F
were being drawn on the basis of the agreement, the rates were subject to
revision with effect from May 20, 1983 with the approval of the State
Government and that a supplementary bill would be sent for the arrears as
and when the rates were revised in pursuance of section 60(5) (a). On 5th
April, 1984, the appellant filed Writ Petition No. 1818 of 1984 in the High
Court of Allahabad assailing the validity of section 7 of the amending Act G
and the right of the Board to enhance the rates. While admitting the writ
petition, the High Court passed.an interim order to the effect that the StJtte
Government should provide and opportunity of hearing to the appellant
before bringing about any cliange in the terms and conditions of the
Agreement or tariff rates and that no revised rates shall be charged from the H ··
164 SUPREME COURT REPORTS [1992] 1 S. C.R.
A appellant till it is heard, and the matter decided, by the Slate Government.
On June 11, 1984, the Law Officer of the Board wrote to the appellant
requesting it to give in writing the points which they wanted to urge before
the rates were approved by the Slate Government. According to the
appellant, this was not sufficient compliance with the court's order and it
moved the High Court for amending its petition and made further applica-
tions to the Court. It may be mentioned that the sland taken up by the Board
B in the writ petition was that the writ petition was premature as the Slate's
approval had not been obtained and no injury had been caused to the
appellant. But, suddenly, on 31.1.85, the Board wrote to the appellant
informing it that the Slate Government had approved the levy of rates as
per Schedule HV-2 (as defined in the U.P. Gazettee Notification dated 29th
October, 1982) applicable to heavy power consumers in substitution of the
C rates mentioned in the agreement of 20th September, 1963. It was slaled-
curiously enough-that the approval of the Slate Government had been
given on 28.9.1983.The effect of the revision was to oblige the petitioner
to pay 57.71 paise per unit for 1983-84 and 61.60 paise per unit for 1984-
85 . An idea of the magnitude of the revision can be had by pointing out
that supplementary bills raised on the basis of the revision for the period
D 20.5.83 to 31.12.1984 were to the tune of Rs. 3.07 crores. The appellant's
allegation is that no such approval had been given and it is asserted that the
internal correspondence between Board and Slate would show that the legal
Department of the Board had raised certain objections to the levy of HV-
2 rates on the appellan~ and that consequently Board had sent a fresh
proposal in December 1983 seeking approval of the Slate Government for
E imposing a flat rate in respect of supplies to the appellant in place of earlier .
proposal. It is also Slated no proposal was made, or approval sough~ for
imposing the revised rates w.e.f. 20.5.1983.
The Board, however, proceeded to make demands against the appel-
F lant on the basis of the revised rates. According to the Board, reference was
made to a resolution dated 30.1.85 to the withdrawal on that date of the
proposal for a flat rate in place of HV-2 rates. Thus, demands on the basis
of HV-2 rates were sought to be sustained. The demands amounted to
several crores of rupees and disconnection was threatened in case of non-
payment. The appellant oblained certain interim orders from High Court
G (which have been subsequently considered and modified from time to time
by this court during the pendency of these appeals). It is, however, not
necessary to refer to these interim orders as the final liability of the
appellant will have to be decided on the basis of the orders of this Court
on the appeals.
H
KANORIA CHEMICALS v. STATE [RANOANATHAN, J.] 165
The writ petition was heard by a Bench of two judges. Both judges
repelled the challenge to the validity of the Amendment Act but differed on A
some of the points which came up for their consideration. Srivastava, J. was
of the opinion that the intention and purpose of the Amendment Act was
to revise the existing contractual rate of energy charges and charge higher
rates upto the extent of uniform tariff rates for the supply of electricity to
the consumers whose contract stood modified by the said statute. The rates
so fixed had to be dependant upon the factors enumerated in section 60(5). B
According to him, the material on record showed that the factors enumer-
ated in section ~60(5) had not been taken into account by the Board before
fixing the rates or by the State Government in according its approval to the
same. The Board and the Government appeared to have acted upon a
J
consideration of the factors mentioned in section 49(2) of the Act of 1948
while framing a uniform tariff but this was not sufficient compliance with C
the provisions of section 60(5). On the other hand, Mathur. J. was of the
opinion that the move for amendment of the Act and enforcement of HV-
2 tariff was initiated by the Board and that the notings contained a detailed
justification for enforcing the said tariff. It also appeared from the statement
of objects and reasons of the amending bill that the supply of electricity at
concessional rates despite losses and the desirability of replacing the said D
rate by uniform tariff came up for discussion in the State Legislature and
that the Board did not act wrongly or illegally if it felt that it had no option
but to apply uniform rates in view of the statement contained in the objects
and reasons of the bill and the discussion in the State Legislature. He was
also of the opinion that the factors contemplated by section 60(5) (a) were
similar to those envisaged by section 49(2), and since consideration had E
been given to the latter factors while framing the uniform tariff, no consid-
eration of factors relevant to individual consumers was called for. The two
learned judges thus differed on the following two points :
(a) Whether the language of section 60 (5) (a) of U.P. Act No. 12 F
of 1983 required consideration of factors prescribed in section
60 (5) (a) viz., geographical position of the area of supply, the
nature of supply and purpose for which supply is required and
other relevant factors with reference to petitioner company for
revising the existing contractual rate of H.C. tariff?
G
(b) Whether the factors mentioned in section 49(2) of Electricity
(Supply) Act, 1948, having already been considered at the time
of framing uniform tariff no fresh consideration of any factors
mentioned in section 60(5Xa) of U.P. Aci No. 12 of 1983 was
required when the uniform tariff itself was being fixed while H
166 SUPREME COURT REPORTS (1992] 1 S. C.R.
revising the rate ?
A
The difference of opinion was, therefore, referred to a third Judge,
Mehrotra, J. This learned Judge answered the question referred to him as
follows :
(a) The language of section 60(5)(a) of U.P. Act 12 of 1983
B requires considertation of factors prescribed in it with reference
to the petitioner company for revising the existing contractual
rate; and
(b) Fresh consideration of the factors mentioned in section
60(5)(a) was required irrespective of the fact that factors mentioned
c in section 49(2) of the Electricity (Supply) Act, 1948 had
already been considered at the time of framing of the unifonn
tariff which was being fixed for the petitioner company while
revising the rates.
Consequent on the opinion of this learned Judge the writ petition was
D allowed and a writ of certiorari was issued quashing the approval dated
28.9.1983 given by the State Government to the new rates and the
consequent resolutions, sanctions, bills and demands of the Board and the
State Government. A writ of mandamus was also issued commanding the
respondents not to charge the unifonn tariff rate for the period begining
from 20th May, 1983 till the rates were fixed in accordance with section
E 60(5) (a) of U.P. Act no. 12 of 1983. The Order disposing of the Writ
Petition finally is dated 2.4.1987.
Immediately the judgement was pronounced the State Electricity
Board and the State Government sought a certificate of fitness for preferring
F an appeal to this Court and the High Court granted the certificate, as prayed
for. \his appeal has not been numbered on account of delay. Though the
High Court had quashed the revision of the rates, it had left it to the Board
and State to fix revised rates afresh. That apart, the appellant had also a
grievance that, in applying the HV-2 rates which were applicable to other
consumers, the Board and the State had not taken into account the special
G factors relevant to the supplies made to it. The appellant also, therefore,
filed S.L.P. No. 13967 of 1987 for leave to appeal from the judgment dated
2.4.1987. Leave has been granted by this Court on 8.4.1988 and the appeal
of the company has been registered as C.A. 1306 of 1988.
H In the meantime the Board and State were, apparently carrying on an
\
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.] 167
exercise for the revision of the rates afresh as directed by the High Coun
and, on 28.3.1988, the Board purponed IO fix the following reivsed rates for A
the supply from 20th May, 1983.
Period Rate (Paise per unit)
20.5.1983 to 31.3.1984 70.21
B
1.4.1984 to 31.3.1985 74.93
1.4.1985 to 31.3.1986 85.14
~ I.4.1986 to 31.3.1987 88.60
c
It will be observed that rates thus fixed, and said to have been
approved by the State Government, were much higher than the HV-2 rates
fixed earlier, objected IO by the appellant and quashed by the High Court.
Having done this, this Board sought leave to withdraw the appeal preferred
by it. So far the appellant's appeal was concerned, it was contended that the
appellant's remedy was to challenge the revision of 28.3.1988, if so D
advised, in fresh proceedings. This was the position when these appeals
came to be heard by us on April IO, 1991.
We h~ard the appeals at length and reserved orders. In doing so we
passed the following order :
E
"The appeals penain to the fixation of tariff rates for supply of
electricity to the appellants caustic soda plant at Renukoot. The
appellants originally came to coun challenging the levy of the
electricity charges on the basis of HV-11 rates applicable gener-
ally to consumers drawing supply from the U.P. State Electricity
Board. However, the High Court held that the rates applicable F
to the appellants should be determined having regard to the in-
dividual circumstances of the appellants. This was by a majority
judgment in the High Coun. Subsequently, the Electricity Board
has proposed, and the State Government has approved, certain
rates for the period from 20.5.1983 to 31.3.1987 which are G
somewhat higher than the HV-11 rates originally appcc-ved. This
is the bone of conlroversy between the parties.
We find that the .State Government and Board have filed no
counter affidavits in regard to the challenge by the appellants to
the revision of rates effected subsequent to the High Court H
,.>,
168 SUPREME COURT REPORTS [1992) I s. c. R.
judgment In the circumstances, before we pronounce our judg-
A ment we think that, in the interests of justice, it would be proper
to direct the State Board and the State Government to recon-
sider the fixation effected by them on the basis of the following
directions :
I. Within a period of three weeks from today, the appellants will
B file before the State Electricity Board (with a copy to the State
Government) a representation setting out what, according to
them, are the individual factors which should be taken into
account in fixing the rates applicable to them within the
meaning of section 60(5)(a), 1948 as amended in 1983.
c 2. The State Electricity Board will consider this representation
and make appropriate recommendations to the State Govern-
ment However, before doing so, and particularly if the Baard
intends to take into account any factors other than those
mentioned in the appellants' representation, they should indicate
the factors which they so wish to take into account, in their rec-
D ommendations to the State Government A copy of the recom-
mendations should be forwarded to the appellants within seven
weeks from today.
3. On receipt of the recommendations made by the Board, the
appellants may submit to the State Government, if they so
E desire, any representation which they wish to make regarding
the recommendations within a period of three weeks thereafter.
4. The State Government will consider the recommendations of
the State Board as well as the representations made by the
appellants to the Board as well as to themselves and approve of
F +.- ..
the rates which they consider proper in the circumstances of the
case by a reasoned order, giving a broad indication of the
factors which they have taken into account in fixing the rates. '
This decision should be arrived at within a period of four weeks
from the date of the receipt of the representation of the
G appellants.
5. As indicated above, since the High Coun has decided that in
f1Xing the rates the individual circumstances of the appellants
should be taken into account, the State Board as well as the
H State Government should take into consideration the special
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.) 169
circumstances of the appellants in fixing the rates.
A
~-
6. The Government's order may also, in case different rates for
different periods are fixed, indicate the respective dates from ,
which the several rates will come. into operation. The rates and
dates so fixed by the Government, will naturally be subject to the
decision on these appeals." B
Subsequent to our order, the appellailt made a representation to the Board
on 29.4.91. The Board made its recommendations thereon to the State Govern·
ment on 26.6.91. Thereafter the appellant made its representation to the State
Government on 22.7.91. The State Government has subsequently passed an
order on 31.8.91 and submitted the same to us. !tis perhaps sufficient to extract C
the concluding paragraphs of the order.
"After analysing the contentions of Kanoria Chemicals and the
State Electricity Board, the State Govt. comes to the conclusion
that M/s. Kanoria Chemicals and Industries Ltd. has taken benefit D
of establishing this unit in a backward area for the last 19 years and
there is no justification in giving this benefit in continuously future
also because this area has been developed in comparison to earlier
years. The request of M/s. Kanoria Chemicals and Industries Ltd.
that the factors shown by State Electricity Board should be limited
to Rihand Hyde! Power Station, is without justification since at E
present, they are getting supply from U.P. Grid and not rrom
Rihand Power Station. Hence, the point of view of the State
Electricity Board is justifiable.
8. After due consideration of representation dated 24.2.91 and F
22.7.91 of M/s. Kanoria Chemicals and Industries Ltd. and the
recommendations of the State Electricity Board dated 26.6.91, the
State Govt comes to the conclusion that M/s. Kanoria Chemicals
and Industries Ltd. has failed to indicate any fact which comes
under the provisions of Sec. 60(5Xa) of the Electricity (Supply) G
Act. 1948 and which has not been considered by the State Electric·
ity Board while fixing the rates in March, 1988. Not only this, the
State Electricity Board while fixing the rates in March 88 has kept
in mind the decision of Hon. High Court of Allahabad and H
170 SUPREME COURT REPORTS [1992] 1 S. C.R.
complied with the provisions of sec. 60(5)(a) of the Electricity
A
(Supply) Act, 1948. Since keeping in view the factors enumerated
in sec. 60(5)(a) of the Electricity (Supply) Act, 1948, the Rules
were revised in March, 1988 in the following manner, hence there
appears no necessity to change these rates :-
B S.No. Period Rate
I. 20.5.83 to 31.3.84 70.21 paise/unit
2. 1.4.84 to 31.3.85 74.93 paise/unit ...
c
3. 1.4.85 to 31.3.86 85.14 paise{unit
4. 1.4.86 to 31.3.87 88.60 paise/unit
In other words, the State and Board adhere to the rates fixed on 28.3.88.
D
It may be interesting to set out a comparative table of the revisions
effected by the Board originally (which was quashed by the High Court) and
-'
the rates now approved :
E Period HV-2 rate Revised rate
'
Paise/unit paise/unit
20.5.83 to 31.3.84 55.71 70.21
F
1984-85
1985-86
59.86
63.89
74.93
85.14
A ~
1986-8' 80.88 88.60
*1987-88 84.64 88.60
G *1988-89 93.39 88.60
* The revised rates for 1987-88 and 1988-89 are stated to be
provisional but so far till today no fresh rates have been fixed in
respect of these periods.
H
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.] 171
.._,,,
-- The resultant position is that the appellant is now facing huge
- (
demands in respect of the period since 20.5.1983 and till 31.3.1989 when A
the agreement expires, at rates which will be higher than the HV -2 rates
which had been sought to be applied in the first instance. The appellant
vehemently challenges the fixation of rates on 28.3.88 and 31.8.91.
A good part of the argument before us in these appeals, in the first
instance, was addressed on the question whether the State Government was B
obliged to give a hearing to the consumer before revising the rates under
section 60(5) and whether the factors relevant under s.60(5) can be said to
have been taken into account on the ground that they had already been
taken into acrount while fixing uniform rates under s.49. In this context,
reference was made to several decisions and contentions were canvassed in
regard to the nature of the process of fixation of rates of charges for supply C
of electricity. It is, however, unnecessary to go into all these aspects
because, in pursuance of the directions of this Court dated 10.4.1991, the
matter has been re-considered by the Board and the State Government and
fresh rates have been fixed along with the respective dates of operation after
hearing the appellant's representatives.
D
/ Broadly two principal submissions have been addressed before us at
this stage on behalf of the appellants. The first is that the fixation of rates
as on 31.8.1991 is not valid as the respondents have not complied with the
directions given by this Court in the order dated 10.4.1991. It is argued that
the respondents have neither disclosed the factors based on which the rates
were revised in March 1988 nor have they indicated the monetary incidence E
or impact of the factors taken into account, though a specific request was
made in this regard by the appellant to the Board and to the State
Government The appellan~ it is said, has been gravely prejudiced and
handicapped, in the absence of any such disclosure, in making any effective
representation. Further in the final order dated 31.8.91, the State Govern- F
ment has stated that the fixation of rate by the State Government was based
upon the consideration of facts and data communicated by the Board to the
State Government in March 1988 bu~ admittedly, no facts, data or basis had
been placed before this court at.the time of the original writ petition on the
bal;is of which the State Government had fixed the rates in March, 1988
compelling this Court to remand the matter for fresh consideration. Sud- G
denly the Board, while concluding its recommendation to the State Govern-
ment on 26.9.91 reminded the State Government that prior approval of the
State Government for the rates had already been obtained in March 88 and
persuaded the State Governmerit to mechanically uphold the pre-deteHJJined
rates. Finally, it is contended that even in this process of re-fixation of the H
172 SUPREME COURT REPORTS [1992) l S.C.R.
A rates there was no genuine exercise to consider relevant factors in detennin- '-
ing the rate under section 60(5)(a).
We do not think that there is any force in these contentions. By the
time the matter came up before us for hearing in the first instance the State
Government had already passed its order of revision dated March 28,1988.
B The rates which had been recommended by the State Electricity Board and
approved by the State Government were within the knowledge of the
appellant. It was of course necessary and equitable that, before giving effect
to these rates (if not even before they were recommended), the consumer
should have had an opponunity of placing before the Electricity Board and
the State Government its side of the picture. This opponunity has, however,
been provided by to the appellant The appellant has also filed its represen-
C talion. After considering the representation, the Board made its recommen-
dations to the State Government and a copy of these recommendations were
also available to the appellant. The appellant also had full opponunity to
meet the various points set out in the recommendations of the Board. The
comments of both the Board and the appellant have been taken into account
by the State Government before finally approving of the rates proposed by
D the Board. The grievance of the appellant seems to be that the Board has
not set out anywhere the precise manner in which the rates recommended
by them were arrived at and that this has considerably handicapped any
effective representation being made by it to the Board and to the State
Government We do not think the proceedings are vitiated for this reason.
It is true that the actual computations of the rates were not set out by the
E Board in its recommendations made in 1983 or 1985 or 1988 but the proper
approach to the issue is not the one adopted by the petitioner. The section
does not require the Board or the State Government to explain each and
every step in its calculation. All that the State Government has to do is to
take into consideration the factors relevant under section 60(5) and propose
F rates for fixation to the State Government It is in order to ensure that these
recommendations take into account all relevant factors that an opponunity
has been proviC:ed to the consumer to satisfy the Board as well as the State
Government that the fixation has not taken into account cenain relevant
factors. We, therefore, think the appellant must be held to have been given
a fair opponunity under s. 60(5)(a) so Jong as it had an opportunity to
G explain to the Board and the State Government the factors individual to its
case and also as to how and why the rates recommended by the Board need
modification. Moreover, the issue here was in a narrow compass for the
following reason. On the passing of the Amendment Act, the Board decided
to substitute the contract rates by the HV-2 rates. But this was rendered
H infructuous because of the tenns of section 60(5)(a) which, it was said, were
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.] 173
different from those of s.49. If the factors under section 49 were alone to
be taken into account then the consumers, one and all, would have been A
-· liable to pay for the electricity at the tariff rates. The claim of the appellant
was that in applying these rates certain factors individual to it had not been
taken into account. If one compares the two provisions, one will find that
most of the elements are common to the two provisions. Both under section
49 and section 60 the authorities have to take foto account the geographical
position of any area, the nature of supply and purpose for which supply is B
required and any other relevant factor. The only difference between the two
provisions is that since section 49 deals with a general fixation while section
60(5) deals with a fixation for a particular individual case, there may be
some special factors to be taken into account which may or may not be
germane while fixing the general tariff under section 49. Hence the only
point which needed to be considered, when the matter was reexamined C
pursuant to our directions, was whether, having regard to the factors
prevailing in the case of the appellant the rates to be fixed should be higher
or lower than the HV-2 rates or whether they should be the same. It was
open to the petitioner to contend, as it in fact did, that there are special
features in its case which make it legitimate to fix some concessional rates
as compared to other consumers. On the other hand, it is equally open to D
the State Electricity Board to contend that having regard to the prevalence
of certain circumstances, the rates to be fixed should be higher than the
tariff rates applicable generally. This is a shon aspect on which both parties
have made their positions clear. Apart from the general factors which have
been taken into account in fixing the general tariff rates, the Board has, in
making its recommendations, taken into account the purpose for which E ·
supply was required by the petitioner along with the factor of recurring
losses incurred by the Board year after year and its statutory requirements
to maintain a minimum surplus of 3 per cent as required under section 59
of the Supply Act, 1948. We are, therefore, satisfied that the appellant had
full opponunity to place all its special features before the Board and the F
State Government and that all aspects have been fully considered by the
authorities. The fixation of rates on 31.8.1991 is not, therefore, vitiated for
the reasons urged by the appellant.
The only other aspect that requires consideration is regarding the
maintainability of the rates as now fixed by the Board and the State. Three G
questions arise in regard to this :
(i) Can the Board fix rates higher than HV-2 rates in respect of
bulk consumers like the company for whom a concessional rate
had been granted on special considerations? H
174 SUPREME COURT REPORTS [1992] 1 S. C.R.
(ii) Can the Board detennine rates in 1991 and make them retro-
A spective w.e.f. 1983?
(iii) Was there material for the Board to fix the rates which they
have eventually fixed?
We find that the answer to the first two questions posed above can
B only be in the affirmative. On the first issue, there are no obstacles,
statutory or theoretical, standing in the way of the Board fixing rates for the
company which will be higher than the rates applicable to bulk consumers.
The provision in s.60(5)(a) is intended to enable the Board and State to cut
off the shackles cast by an ancient contract entered into at a time when
conditions were totally different. It confers an absolute and on.restricted )._
C enabling power to revise the rates in an appropriate manner and contains no
_restriction of the nature suggested for the appellant. Jn doing this, the only
limitation which the statute requires the authorities to keep in mind are the
factors mentioned in the section. Whether the revised rates for the consumer
governed earlier by the contract should be higher or lower than, or equal
to, the tariff rates would depend on a large number of considerations, in
D particular, the basis on which, and the point of time at which, those general
rates were fixed. In principle, it is quite conceivable that, in an appropriate
case, a consideration of the relevant factors may justify even a rate higher
than the general tariff rates intended for the particular category of consum-
ers. We shall examine later whether this was justified in the present case.
At the moment, all we are concerned with is the legality of fixing such
E higher rates and we see no difficulty in this either on the language of the
Statute or on other considerations.
A retrospective effect to the revmon also seems to be clearly
envisaged by the section. One can easily conceive a weighty reason for
F saying so. If the section were interpreted as conferring a power of revision ..ill
only prospectively, a co~sumer affected can easily frustrate the effect of the .JI
provision by initiating proceedings seeking an injunction restraining the >
Board and State from revising the rates, on one ground or other, and thus
getting the revision deferred indefinitely. Or, again, the revision of rates,
even if effected promptly by the Board and State, may prove infructuous for
G one reason or another. Indeed, even in the present case, the Board and State
were fairly prompt in taking steps. Even in January 1984, they warned the
appellant that they were proposing to revise the rates and they did this too
as early as in I985. For reasons for which they cannot be blamed this
proved ineffective. They revised the rates again in March 1988 and August
H 1991 and, till today, the validity of their action is under challenge. In this
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.] 175
state of affairs, it would be a very impractical interpretation of the section A
•
-,.'
to say that the revision of rates can only be prospective.
The language of the section also supports this view. Slightly rearrang-
ing the syntax of the clause to facilitate easier understanding, what it
provides is that the revised rates fixed by the Board shall be the rates to be
charged by the Board for the energy supplied by it to any consumer for
which the payment will be due for the first time on or after the 20th May, B
1983. In other words, the rates eventually fixed will, by force of statute,
apply to all supply of electricity for which the charges become payable in
terms of the contract, after 20.5.1983. There are three objections suggested
against this interpretation. The first is that it precludes the Board and State,
where they choose to do so, from revising the rates prospectively or with
effect from such dates, after 20.5.1983, which they may consider appropri- C
ate. We think this consequence does not flow from the language of the
provision. The mandate is only that the rates to be charged on supplies for
which payment becomes due after 20.8.83 shall be as fixed by the Board.
The powers of the Board in fixing the rates-including the dates from
which they will be operative-are not restricted in any manner. The Board
is at complete liberty to fix different rates from different dates and that D
scheme of fixation will be read with the contract. Only the Board cannot
revise the rates in respect of supplies for which payment under the contract,
fell due before 20.5.83. The second objection, which is a follow up of the
first, is that if the power u/s 60 is held exexcisable more than once, the inter-
pretation will permit successive revisions, each superseding the earlier one,
a position that could lead to immense harassment. We have no doubt the E
power u/s 60 is exexcisable more than once. All the same, the answer to the
appellant's objection is that, while this could be a basis of substantial
harassment if repeated revisions are automatically dated back to 20.5.83 (as -
argued, on the first point, for the assessee), it loses all foxce on our
interpretation leaving it open to the Board and State to fix the dates with F
effect from which revisions will be effective. In view of this, one can take
it that, while making a subsequent revision, the authorities will not
normally tamper with an earlier revision (s) or alter.the dates of effective-
ness fixed for the earlier revision (s) without a valid reason to do so. If this
is done, it will be open to a court to examine the basis thereof and sustain
it only where the earlier fixation was based on an error or misconception G
or the like and called for modification. The third objection is that the Hindi
version of the Amendment Act is differently worded and does not contain
the words "for the first time" found in the English version. Reliance is
placed on the decision of a Bench of seven judges of the Allahabad Higli
Court in Mata Badal Pandey v. Board of Revenue, (1974) U.P.T.C. 570 to H
176 SUPREME COURT REPORTS (1992] 1 S. C.R.
the effect that, where there appems a doubt or ambiguity on a plain reading
A of the English words as to the true intention of the legislature and the Hindi
version is conflicting or different. the Hindi text will be the key for finding
the answer. We do not think the Hindi version really alters the position;
actually it is the presence of the words "for the first time" in the English
version that create an ambiguity. Without these words, the clause clearly
B provides that all supply of electricity, for which payment is to be made after
20.5.83, will be charged at the rates to be fixed by the Board. We, therefore,
reject the appellant's contention and hold that the fixation by the Board of
rates from 20.5.83 and, at different rates for different periods of time, is un-
exceptionable.
This takes us to the real and crucial question in the case as to whether
C rates to be fixed in the present case should, on proper considerations, be less
than, equal to or higher than the general HV-2 rates. The appellant contends
that it should be charged at the cost of generation plus a re.asonable margin
of profit or at the rate at which the supply is made to the Madhya Pradesh
State Electricity Board. At any rate, it is said, the rates charged to the
appellant should be less than HV-2 rates. For this it relies on: (a) the special
D circumstance that the appellant, at great detriment to itself, agreed to set up
a caustic soda plant in a backward area at the request of the State
Government and in public interest only because of a promised concession
in rates of electricity supply; (b) the fact that the supply to the appellant
is metered at the point of generation with the result that the IJlmsmjssion
and distribution losses, in so far as the appellant is concerned, are borne by
E the appellant and not by the Board as in the case of other consumers and
(c) the important fact that electricity, in the case of the appellant, is one of
.:ie only two raw materials needed for its business. On the other hand, for
the Electricity Board, it is contended that the appellant should be called
Up.ln to pay higher than HV-2 rates for the following reasons :
F
(i) The appellant has been having substantial supplies of
electricity at nominal rates of 2.5 paise and 2.75 paise per unit
between 1%3 and 1983.
(ii) The supply to the assessee is being made only from the
G State Grid and there is no reason why it should draw the supply
at lower rates than others:
(iii) The Board had been incurring heavy losses over the years.
This is to a considerable extent due to the spiralling demand for
H electricity, the Board's responsibilities under the statute to co-
KANORIA CHEMICALS v. STATE [RANGANATHAN, J.] 177
ordinate development of the supply of energy throughout the A
State and the necessity to supply energy at concessional rates to
certain sectors such as the agricultural sector.
(iv) The Board is also entitled, under s.59 of the 1948 Act, to
take into account the necessity of building up a surplus, statu·
torily fixed, in the fixation of rates of supply to all or any of its B
con§!!mers.
We have given careful thought to the considerations urged before us
and we are of opinion that there is no material to justify any departure from
the HV-2 rates in the case of the appellant We find no force in the
contentions put forward on behalf of the appellant to reduce the rates
applicable to the appellant below HV -2 level. The special circumstances C
pleaded have lost their importance with the passage of time. It is obvious
that the conditions that prevailed in 1963 are not valid and the appellant has
had the benefit of concessional rates for twenty years. No doubt the benefits
would have continued for five more years but for statutory intervention. But
the statute permits a reconsideration of the situation as in May 1983 and it
is unarguable, it seems to us, that the rate of 2.75 p. should continue even D
after 1983 or that the appellant should be entitled to any special concession.
The consideration that electricity is a "raw material" in the assessee's
business is, again, irrelevant for it can mean nothing more than that the
appellant needs substantial quantities of the energy and there is no reason
why it should not pay for it at the normal mruket rates. The point regarding
take off of supply at the generating point will no doubt have some relevance E
on the question of rates and we shall refer to this aspect later in the context
of the pleas put forward by the Board. We are, therefore, of the view that
the appellant has no valid justification for staking a claim to less than the
HV-2 rates.
F
Equally, it seems to us, the authorities have no case for seeking to
raise the rates beyond the HV-2 rates. They are supplying energy to the
appellant from the grid since 1968 and they cannot justifiably seek to
demand higher rates from the appellant than from the HV-2 consumers.
This is sought to be justified on the basis of the huge losses that the Board
has been incurring and the statutory justification for escalation in the rates G
keeping in view the necessity to build up a surplus. This, however, is an
aspect of working which should affect all the consumers equally. May be
the Board can, in appropriate circumstances, seek to make up for a part of
the losses by hiking up the rates to one particular category of consumers but
that would not be justified here as the transmission and distribution losses H
,_'
178 SUPREME COURT REPORTS (1992] I S. C.R.
in respect of the supply to the appellant are borne by it and, in the absence
A of some special vital reason, it would not be equitable to fix the rates of -~
supply to the arpellant above the rates applicable to other HV-2 consWDCIS.
Some reference was made to the difficulties in completely fitting the
scheme of computations for detennining the HV-2 rates into the scheme
,under the appellant's contract It is, how~ver, unnecessary to go into that
aspect as we are only on the question of rates and holding that there is no
B justification for charging more than -HV-2 rates from the appellant More-
over, the appellant has been paying for the Obra supply at HV-2 rates since
1989. We have also been infonned that in 1972 the appellant took a further
additional supply of 8 MW and agreed to pay therefor at HV-2B rates as
applicable to other Bulle Power Consumers in the State.
C In these circumstances, we have reached to the conclusion that there
is no justifica lion to charge more than HV-2 rates from the appellant We,
therefore, allow this appeal in part, quash the determinations of 1988 and
1991 and direct that the appellants should be charged from 20.5.83 to
31.3.89 at the HV-2 rates applicable to other consumers. The appeal of the
appellant is panly allowed to the above extent. The Board's appeal has not
yet been numbered as it is delayed by a few days. It was, however, stated'
that the Board wishes to withdraw its appeal because of the subsequent
developments. For these reasons and also in view of our above conclusion
the Board's appeal also stands dismissed. In the circumstances, we direct
each party to bear its own costs.
T.N.A. C.A. 130&'88 Panly allowed.
C.A. 128i'J2 dismissed.
.,.
fa
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.