Created byFuzzy Cloud

Supreme Court of India

KALPRAJ DHARAMSHI & ANR.versusKOTAK INVESTMENT ADVISORS LTD. & ANR.

Citation
2021 INSC 173
Decided
10 March 2021
Disposal
Disposed off

Holding

The Supreme Court held that the appeals were filed within the limitation period by applying Section 14 principles, KIAL did not waive or acquiesce its rights, and the NCLAT erred in interfering with the CoC’s commercial wisdom, leading to the quashing of the NCLAT order and restoration of the NCLT orders.

Summary

The corporate debtor Ricoh India Ltd. initiated a corporate insolvency resolution process under the IBC, inviting resolution plans. Kotak Investment Advisors Ltd. (KIAL) submitted its plan on time, while Kalpraj submitted a belated plan which was later accepted by the Committee of Creditors (CoC) and approved by the NCLT. KIAL challenged this approval in the NCLT, filed a writ petition in the Bombay High Court alleging violation of natural justice, and subsequently appealed to the NCLAT. The NCLAT allowed KIAL's appeal, holding the appeal was within the limitation period and that KIAL had waived its rights. The Supreme Court applied the principles of Section 14 of the Limitation Act, finding KIAL was bona fide prosecuting the writ petition, thus the appeal was timely; it also held that KIAL did not waive or acquiesce its rights and that the CoC's commercial decision is non‑justiciable. Consequently, the Court set aside the NCLAT order, restored the NCLT orders approving Kalpraj's plan, and directed the NCLAT to dispose of pending appeals promptly.

Issues considered

  • Whether the appeals filed by KIAL before the NCLAT were within the limitation period prescribed under Section 61 of the IBC and the Limitation Act.
  • Whether Section 14 of the Limitation Act applies to proceedings before a quasi‑judicial tribunal such as the NCLAT.
  • Whether KIAL’s conduct amounts to waiver or acquiescence, thereby estopping it from challenging Kalpraj’s resolution plan.
  • Whether the High Court could entertain a writ petition despite the existence of an alternate statutory remedy.
  • Whether the NCLAT was justified in interfering with the commercial decision of the CoC to approve the resolution plan.

Legislation cited

Subjects

Insolvency and Bankruptcy CodeLimitation ActSection 14WaiverAcquiescenceCommittee of CreditorsResolution PlanNCLTNCLATArticle 226Commercial wisdomAppeal limitation

Judgment

                        [2021] 2 S.C.R. 677                             677


                KALPRAJ DHARAMSHI & ANR.                                A
                                 v.
       KOTAK INVESTMENT ADVISORS LTD. & ANR.
               (Civil Appeal Nos. 2943-2944 of 2020)
                         MARCH 10, 2021                                 B

           [A.M. KHANWILKAR, B. R. GAVAI AND
                  KRISHNA MURARI, JJ.]
       Insolvency and Bankruptcy Code, 2016:
       ss. 10, 61, 238A – Proceedings or appeals before the             C
adjudicating Authority, appellate tribunal etc – Application of
Limitation Act – On facts, application u/s. 10 by Corporate Debtor
for initiation of Corporate Insolvency Resolution Process –
Successively five Form G notified – Resolution applicant-KIAL
submitted Resolution Plan (RP) within the stipulated time and
resolution applicant-Kalpraj submitted plan after the stipulated time   D
– Objection raised by KIAL – Subsequently on direction by
Committee of Creditors (CoC), submission of revised plan by KIAL
and Kalpraj – Thereafter, approval of revised plan submitted by
Kalpraj – KIAL challenged the approval of Kalpraj’s Resolution
Plan before NCLT – Plan of Kalpraj approved by NCLT – Thereafter,       E
KIAL filed Writ Petition before the High Court which was dismissed
on the ground of alternate remedy – KIAL then filed appeal before
NCLAT which was allowed, rejecting Kalpraj submission that appeal
were filed beyond the limitation period prescribed in IBC – On
appeal, held: Provisions of s. 14 of the Limitation Act are available
to KIAL – Applying the principles underlying s. 14, KAIL entitled to    F
exclusion of the period during which it was bona fide prosecuting
a remedy before the High Court in good faith and with due diligence,
thus, the appeals filed before NCLAT within the limitation – Though
an alternate remedy was available to it, it was approaching the
High Court since the issue with regard to functioning of NCLT also      G
fell for consideration – High Court dismissed the writ petition
relegating KIAL to an alternate remedy available in law – High
Court could have exercised extra-ordinary jurisdiction u/Art. 226
inasmuch as, the grievance was regarding procedure followed by
NCLT to be in breach of principles of natural justice – Limitation
Act, 1963 – s. 29(2) – Constitution of India – Art. 226.                H
                                677
678            SUPREME COURT REPORTS                       [2021] 2 S.C.R.


A            Waiver and acquiescence – Inference of – Objection by KIAL
      to the acceptance of belated Resolution Plan of Kalpraj – However,
      when no choice left, KIAL submitted revised Resolution Plan –
      Conduct of KIAL, if amounts to waiver and acquiescence by KIAL
      so as to estop it from challenging the participation of Kalpraj –
      Held: KIAL had objected to participation of other applicant
B
      submitting plan after the due date as per the last Form G and also
      reiterated its objection to the participation of Kalpraj – It cannot
      be said that having participated by submitting the revised plans,
      KIAL is estopped from challenging the decision of Resolution
      Professional (RP) or CoC on the ground of acquiescence and waiver
C     – Merely because, the revised plans are not submitted with the words
      “without prejudice”, would not make any difference – KIAL had no
      other option than to submit its revised plans in view of clause 11.2
      of the Process Memorandum – Had it not responded, it had to run
      the risk of being out of competition – Also it is not established that
      KIAL had given up/surrendered its rights to take recourse to the
D
      legal remedies, and that on account of waiver or acquiescence the
      parties had altered their position to their detriment.
             ss. 10, 30, 31 – Submission and approval of Resolution plan
      – Decision of Committee of Creditors-CoC accepting the resolution
E     plan of Resolution applicant-Kalpraj – NCLAT annulled decision
      of CoC to accept the Resolution Plan – Interference with the decision
      of CoC by NCLAT – Correctness of – Held: Statute has not invested
      jurisdiction and authority either with NCLT or NCLAT, to review
      the commercial decision exercised by CoC of approving the resolution
      plan or rejecting the same – Commercial wisdom of CoC is not to be
F     interfered with, except within the limited scope u/ss. 30 and 31 of
      the Code – Decision of CoC was taken by a thumping majority of
      84.36% – Only creditor voted in favour of KIAL is having voting
      rights of 0.97% – In view of the paramount importance given to the
      decision of CoC, NCLAT not correct in law in interfering with the
G     commercial decision taken by CoC – Furthermore, for a long period,
      there was no restraint on implementation of the resolution plan of
      Kalpraj, which was duly approved by NCLT and during the said
      period, Kalpraj has spend a huge amount for implementation of
      the plan – Thus, the decision taken by CoC in accordance with its
      commercial wisdom which is duly approved by NCLT, would prevail.
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                       679


      Corporate Insolvency Resolution Process – Initiation of –           A
Resolution Plan from prospective resolution applicants – Decision
of Committee of Creditors – Justiciability of, in the court of law –
Discussed.
       Limitation Act, 1963: s. 14 – Proceedings before the quasi-
judicial tribunal – Applicability of s. 14 – Held: Though strictly, the   B
provisions of s. 14 would not be applicable to the proceedings before
a quasi-judicial tribunal, however, the principles underlying the
same would be applicable – Proper approach would be of advancing
the cause of justice, rather than to abort the proceedings – Litigant
would be entitled for exclusion of the period, during which he was
bona fide prosecuting such a wrong remedy.                                C

      Doctrines/Principles: Principle of waiver and acquiescence
– When can be inferred – Held: Waiver is an intentional
relinquishment of a right, advantage, benefit, claim or privilege –
For applying the principle of waiver, it has to be established, that
though a party was aware about the relevant facts and the right to        D
take an objection, he has neglected to take such an objection – It
has to be established that a party expressly or by its conduct acted
in a manner, which is inconsistent with the continuance of its rights
– Whereas, acquiescence would be a conduct where a party is sitting
by, when another is invading his rights – Acquiescence must be            E
such as to lead to the inference of a licence sufficient to create a
new right in the defendant.
      Disposing of the appeals, the Court
       HELD: 1.1 Though the provisions of the Limitation Act, as
far as may be, would apply to the proceedings or appeals before           F
the Adjudicating Authority, NCLAT, the Debt Recovery Tribunal
or the Debt Recovery Appellate Tribunal, where a period of
limitation for initiation of proceedings is provided under any
special or local law, different from the period prescribed by the
Schedule, the provisions of Section 3 shall apply, as if such period      G
were the period prescribed by the Schedule. It would further
reveal, that for the purpose of determining any period of limitation
prescribed for any suit, appeal or application by any special or
local law, the provisions contained in sections 4 to 24 (inclusive),
shall apply only in so far, and to the extent to which, they are not
                                                                          H
680            SUPREME COURT REPORTS                        [2021] 2 S.C.R.


A     expressly excluded by such special or local law. [Para 37]
      [712-D-G]
             1.2 Since under IBC Code there is a period different from
      the one which is prescribed by the Schedule to the Limitation
      Act, the limitation for an appeal would be governed by Section 61
B     of the I&B Code, which is a special statute. As such, an appeal
      will have to be preferred within a period of thirty days from the
      date on which the order was passed by NCLT. However, if NCLAT
      is satisfied, that there was sufficient cause for not filing the appeal
      within a period of thirty days, it may allow an appeal to be filed
      within a further period of fifteen days. As such, the normal period
C     of limitation prescribed under the I&B Code is thirty days, with
      a provision for allowing the filing of an appeal within a further
      period of fifteen days, if NCLAT is satisfied, that there was
      a sufficient cause for not filing the appeal within thirty days.
      [Para 39][713-A-D]
D           1.3 When a litigant bona fide under a mistake litigates before
      a wrong forum, he would be entitled for exclusion of the period,
      during which he was bona fide prosecuting such a wrong remedy.
      Though strictly, the provisions of Section 14 of the Limitation
      Act would not be applicable to the proceedings before a quasi
E     judicial Tribunal, however, the principles underlying the same
      would be applicable i.e. the proper approach will have to be of
      advancing the cause of justice, rather than to abort the
      proceedings. [Para 51][720-D-F]
             1.4 The judgment of NCLT is dated 28.11.2019. As such,
F     as per Section 61(2) of the I&B Code, the appeal was required to
      be filed on or prior to 28.12.2019. The appeal could have been
      filed within a further period of fifteen days, if NCLAT was satisfied,
      that there was sufficient cause for not filing the appeal within a
      period of thirty days. As such, the said period would come to an
      end on 12.1.2020. The certified copy of the impugned judgment
G     of NCLT was made available on 18.12.2019. If the allowance for
      the said period is granted, the appeal should have been preferred
      on or prior to 2.2.2020. However, in the instant case, the appeal
      is filed on 18.2.2020. [Para 40][713-D-F]

H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                       681


      1.5 Immediately after NCLT pronounced its judgment on               A
28.11.2019 and even before the certified copy was made available
on 18.12.2019, KIAL had filed writ petition before the Division
Bench of the High Court on 11.12.2019 on the principal ground,
that the procedure followed by NCLT was in breach of principles
of natural justice. Such a ground could be legitimately pursued
                                                                          B
before a writ court. In that sense, it was not a proceeding before
a wrong court, as such. [Para 54][723-B-D]
     1.6 It is a settled principle of law, that non-exercise of
jurisdiction by the High Court under Article 226 of the
Constitution is not a hard and fast rule, but a rule of self-restraint.
When the proceedings invoked before a statutory authority are             C
de hors the jurisdiction or when they are in breach of principles
of natural justice, the party would be entitled to invoke the
jurisdiction of the High Court under Article 226 of the
Constitution. [Paras 59, 61][724-G-H; 725-H; 726-A]
      1.7 In the instant case, perusal of the writ petition would         D
reveal, that it was the specific case of KIAL, that its application,
objecting to the application of RP for approval of the resolution
plan was heard by a Member (Judicial), whereas, the final orders
were passed by a Bench consisting of Member (Judicial) and
Member (Technical). It has specifically averred, that though an           E
alternate remedy was available to it, it was invoking the
jurisdiction of the High Court since the question involved was
also with regard to the manner in which the jurisdiction was
exercised by NCLT. It could thus be seen, that KIAL was bona
fide prosecuting the proceedings before the High Court in good
faith. Perusal of the dates would also reveal, that KIAL was              F
prosecuting the proceedings before the High Court with due
diligence. Even before the availability of the certified copy, it had
knocked the doors of the High Court. The matter before the
High Court was hotly contested and ultimately, the petition was
dismissed by an elaborate judgment relegating KIAL to the                 G
alternate remedy available to it in law. As such, the conditions
which enable a party to invoke the provisions of Section 14 of the
Limitation Act are very much available to KIAL. If the period
during which KIAL was bona fide prosecuting the writ petition

                                                                          H
682            SUPREME COURT REPORTS                      [2021] 2 S.C.R.


A     before the High Court and that too with due diligence, is excluded
      applying the principles underlying Section 14 of the Limitation
      Act, the appeals filed before NCLAT would be very much within
      the limitation. KIAL would be entitled to exclusion of the period
      during which it was bona fide prosecuting the remedy before the
      High Court with due diligence. [Para 64][726-E-H; 727-A-C]
B
            1.8 In the instant case, KIAL had approached the High Court
      making a specific grievance, that NCLT had adopted a procedure
      which was in breach of the principles of natural justice. It is
      specifically mentioned in the writ petition, that though an alternate
      remedy was available to it, it was approaching the High Court
C     since the issue with regard to functioning of NCLT also fell for
      consideration. It is thus apparently clear, that KIAL was bona
      fide prosecuting a remedy before the High Court in good faith
      and with due diligence. In a given case, the High Court could
      have exercised jurisdiction under Article 226 of the Constitution
D     inasmuch as, the grievance was regarding procedure followed by
      NCLT to be in breach of principles of natural justice. That would
      come within the limited area earmarked by this Court for exercise
      of extraordinary jurisdiction under Article 226 despite availability
      of an alternate remedy. Therefore, KIAL was entitled to extension
      of the period during which it was bona fide prosecuting a
E     remedy before the High Court with due diligence. [Paras 83,
      85][735-A-D; 736-A]
            Consolidated Engineering Enterprises vs. Principal
            Secretary, Irrigation Department and others (2008) 7
            SCC 169 : [2008] 5 SCR 1108; M.P. Steel Corporation
F           vs. Commissioner of Central Excise (2015) 7 SCC 58;
            State of Goa vs. Western Builders (2006) 6 SCC 239 :
            [2006] 3 Suppl. SCR 288; Embassy Property
            Developments Pvt. Ltd. vs. State of Karnataka and
            Others 2019 SCC Online 1542 – relied on.
G           Commissioner of Sales Tax, U.P. vs. Madan Lal Das &
            Sons, Bareilly (1976) 4 SCC 464 : [1977] 1 SCR 683
            – per incuriam.
            Union of India vs. Popular Construction Co. (2001) 8
            SCC 470 : [2001] 3 Suppl. SCR 619; Singh
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.            683


    Enterprises vs. Commissioner of Central Excise,            A
    Jamshedpur & Ors. (2008) 3 SCC 70 : [2007]
    13 SCR 952; Chhattisgarh State Electricity Board vs.
    Central Electricity Regulatory Commission & Ors.
    (2010) 5 SCC 23 : [2010] 4 SCR 680; Neeraj Jhanji
    vs. Commissioner of Customs & Central Excise (2015)
                                                               B
    12 SCC 695; Ketan V. Parekh vs. Special Director,
    Directorate of Enforcement & Anr. (2011) 15 SCC 30 :
    [2011] 14 SCR 1204; Commissioner of Customs and
    Central Excise vs. Hongo India Private Limited and
    another (2009) 5 SCC 791; Bengal Chemists and
    Druggists Association vs. Kalyan Chowdhury (2018) 3        C
    SCC 41 : [2018] 2 SCR 1099 - distinguished.
    Commissioner of Sales Tax. U.P., Lucknow vs. Parson
    Tools and Plants, Kanpur (1975) 4 SCC 22: [1975] 3
    SCR 743 – held distinguished.
    Whirlpool Corporation vs. Registrar of Trade Marks,        D
    Mumbai & Ors. (1998) 8 SCC 1 : [1998] 2 Suppl. SCR
    359; Babu Ram Prakash Chandra Maheshwari vs.
    Antarim Zilla Parishad Muzaffar Nagar [1969] 1 SCR
    518; Nivedita Sharma vs. Cellular Operators Association
    of India & Ors. (2011) 14 SCC 337; Bharat Bank Ltd.,       E
    Delhi vs. Employees of the Bharat Bank Ltd., Delhi
    [1950] SCR 459; Town Municipal Council, Athani vs.
    Presiding Officer, Labour Courts, Hubli and others etc.
    (1969) 1 SCC 873 : [1970] 1 SCR 51; Nityananda M.
    Joshi and others vs. Life Insurance Corporation of India
    and others (1969) 2 SCC 199: 1970 (1) SCR 396;             F
    Bhudan Singh and another vs. Nabi Bux and another
    (1969) 2 SCC 481: [1970] 2 SCR 10; J. Kumaradasan
    Nair and another vs. Iric Sohan and others (2009) 12
    SCC 175: [2009] 3 SCR 238; Kerala State Electricity
    Board, Trivandrum vs. T.P. Kunhaliumma (1976) 4 SCC        G
    634 : [1977] 1 SCR 996; Officer on Special Duty (Land
    Acquisition) and another vs. Shah Manilal Chandulal
    and others (1996) 9 SCC 414: [1996] 2 SCR 366 -
    referred to.

                                                               H
684            SUPREME COURT REPORTS                       [2021] 2 S.C.R.


A           2.1 KIAL had no choice than to accept the terms of the
      contract. Paragraph 5(b) of the covering letter for submission of
      resolution plan by KIAL is a part of a covering letter format,
      which is provided in the Process Memorandum itself. The
      covering letter is in Format I and the party desiring to participate
      in the Resolution Plan Process has no other option, than to sign
B
      the dotted lines. Hence, the parties cannot be said to have equal
      bargaining power and the applicants have no other choice than to
      sign on the documents prescribed in the format. Paragraph 5(b)
      of the covering letter format, requires a party to undertake, that
      it will accept all the decisions made by CoC, RP and/or the
C     Adjudicating Authority and that the decisions taken will be binding
      on it. It also requires the applicant, to sign on the document
      thereby, providing expressly waiving any and all claims with
      respect to the Resolution Plan Process. In turn, it provides for a
      party to agree to a stipulation, that even if RP or CoC acts in any
      manner, which is not permissible in law, still the resolution
D
      applicant would be bound by such a decision and shall waive any
      or all its claims in respect of the Resolution Plan Process.
      [Para 95][739-H; 740-A-D]
            2.2 In the first place, RP and the resolution applicant cannot
      be said to be the contracting parties having equal bargaining
E     power. Secondly, since RP functions under the I&B Code for
      discharging the duties bestowed upon him and assisting the
      process for finalization of resolution plan for survival of the
      Corporate Debtor, it cannot be said that it is a purely commercial
      transaction between RP and the resolution applicant. There is no
F     reason, as to why the said principle should not be applicable when
      RP and CoC are acting under the statutory provisions under the
      Code. Thus, KIAL cannot be held to be bound by such
      unconscionable clause in the letter, which is in a prescribed format.
      [Paras 97, 99, 100][740-E-F; 741-B-D]
G           Halsbury’s Laws of England, Vol. 16(2), 4th Edn., Para
            907, 1471 – referred to
              2.3 For considering, as to whether a party has waived its
      rights or not, it will be relevant to consider the conduct of a party.

H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                        685


For establishing waiver, it will have to be established, that a party      A
expressly or by its conduct acted in a manner, which is inconsistent
with the continuance of its rights. However, the mere acts of
indulgence will not amount to waiver. A party claiming waiver
would also not be entitled to claim the benefit of waiver, unless it
has altered its position in reliance on the same. For applying the
                                                                           B
principle of waiver, it will have to be established, that though a
party was aware about the relevant facts and the right to take an
objection, he has neglected to take such an objection. [Paras 104,
107][742-F-G; 743-E-F]
        2.4 For constituting acquiescence or waiver it must be
established, that though a party knows the material facts and is           C
conscious of his legal rights in a given matter, but fails to assert
its rights at the earliest possible opportunity, it creates an effective
bar of waiver against him. Whereas, acquiescence would be a
conduct where a party is sitting by, when another is invading his
rights. The acquiescence must be such as to lead to the inference          D
of a licence sufficient to create a new right in the defendant. Waiver
is an intentional relinquishment of a right. It involves conscious
abandonment of an existing legal right, advantage, benefit, claim
or privilege. It is an agreement not to assert a right. There can
be no waiver unless the person who is said to have waived, is
fully informed as to his rights and with full knowledge about the          E
same, he intentionally abandons them. [Para 112][747-E-G]
        2.5 As per the invitation of EOI published on 9.7.2018, the
last date for submission of EOI was 8.8.2018. The first Form G
was also issued on 9.7.2018, according to which, the last date for
submission of resolution plan was 21.9.2018. KIAL had submitted            F
its EOI on 7.8.2018. First Process Memorandum was issued on
17.8.2018. However, since there was no response, four more Form
G were issued on various dates. The last of such Form G was
issued on 11.12.2018, according to which the last date for
submission of resolution plan was 8.1.2019. KIAL submitted its
resolution plan on 8.1.2019. Subsequently, Kalpraj submitted its           G
resolution plan on 27.1.2019. On KIAL coming to know about
the same, on 29.1.2019 itself, it had sent an email protesting to
RP against acceptance of belated resolution plan of Kalpraj. [Paras
116, 117][748-F-H; 749-A]
                                                                           H
686            SUPREME COURT REPORTS                      [2021] 2 S.C.R.


A            2.6 It could be seen that immediately within a day of the
      submission of the plan by Kalpraj, KIAL objected to the
      acceptance of its plan after 8.1.2019, when no extension of time
      for the same was notified. It is specifically stated, that the said
      severely jeopardized its position and was against the spirit of the
      Code, especially when KIALs resolution plan was opened
B
      immediately and discussed at length with various stakeholders.
      KIAL has therefore requested for sharing the requisite
      information providing for extension of time for bid submission. It
      is further stated, that in the event no such notification was issued,
      all plans submitted after 8.1.2019 should be held to be invalid.
C     After the said email was addressed by KIAL to RP, it received
      an email from RP on 30.1.2019. It is stated in the said email dated
      30.1.2019, that subsequent to the resolution plan submitted on
      8.1.2019, CoCs representative and RP had a detailed discussion
      with its team on the changes required to be made in the resolution
      plan. Vide the said email dated 30.1.2019, KIAL was requested
D
      to submit the amended resolution plan by 3 p.m. on 1.2.2019. On
      1.2.2019, left with no choice, KIAL submitted its revised
      resolution plan. [Paras 118, 119][749-E-H; 750-A]
             2.7 On 10.2.2019 KIAL sent another email. It was stated
      therein that it has been quite sometime, that it had sought a
E     response from RP on his decision to accept another resolution
      plan well after the expiry of the deadline for submission of the
      same. It was reiterated, that such an action, after opening of the
      bids and having detailed discussions on the same was not only
      prejudicial to its interest but against the spirit of the I&B Code.
F     It was reiterated, that the I&B Code, provides equal treatment
      to all potential resolution applicants within the framework of law
      and fixes personal responsibilities upon CoC members and RPs
      in the event of instances of discrimination or departure from the
      established law. [Para 121][750-D-F]
G           2.8 Perusal of the record would reveal, that RP had replied
      to KIAL by email dated 11.2.2019. It was stated in the said email,
      that his act of acceptance of resolution plans, submitted after the
      due date, was under the overall supervision of CoC and as per
      the opinion given by CoCs legal counsel and RPs legal counsel.

H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                    687


It was also submitted, that this was in the spirit of value            A
maximisation of assets of the Corporate Debtor. Further, it is in
dispute, as to whether RP had again directed KIAL and Kalpraj
vide email dated 11.2.2019 to submit revised plan. It is asserted
on behalf of the KIAL, that such email was received by it, whereas
it is denied by RP. In any event, it is not in dispute, that both
                                                                       B
KIAL and Kalpraj submitted their revised plans on 12.2.2019.
[Paras 122 - 123][750-F-H; 751-A]
       2.9 On 13/14.2.2019, the resolution plan of Kalpraj was
accepted by CoC. On 18.2.2019, RP filed M.A. No.691/2019
before NCLT for approval of the resolution plan of Kalpraj. KIAL
filed its M.A. on 14.3.2019 before the Adjudicating Authority          C
objecting to the approval of resolution plan of Kalpraj. It could
thus, be clearly seen, that KIAL had raised its objection
immediately after the Kalpraj submitted its resolution plan. Not
only that, but, it had also reiterated its objection to the
participation of Kalpraj. Insofar as, submission of amended plans      D
is concerned, it had no other option than to submit its revised
plan. It is thus clear that, had KIAL not responded to the email
of RP and submitted its revised plan, it had to run the risk of
being out of fray. [Paras 124-126][751-A-C, E-F]
      2.10 Taking into consideration the fact, that KIAL had           E
objected to participation of any other applicant submitting plan
after the due date as per the last Form G and also reiterated its
objection, it cannot be held, that having participated by submitting
the revised plans, KIAL is estopped from challenging the process
on the ground of acquiescence and waiver. Merely because, the
revised plans are not submitted with the words “without                F
prejudice”, would not make any difference. [Para 132][753-A-B]
      2.11 The conduct of the party is relevant for considering,
whether it can be held, that a case is made out of waiver or
acquiescence. None of the appellants have been in a position to
establish, that KIAL had given up/surrendered its rights to take       G
recourse to the legal remedies. In any case, the appellants had
also not been in a position to establish, that on account of any
such waiver or acquiescence any of the appellants had altered

                                                                       H
688           SUPREME COURT REPORTS                      [2021] 2 S.C.R.


A     their position to their detriment. As such, it cannot be held, that
      KIAL had waived or acquiesced its rights to challenge the decision
      of RP or CoC. [Paras 132-134][753-C-E]
            Central Inland Water Transport Corporation Limited
            and another vs. Brojo Nath Ganguly and another (1986)
B           3 SCC 156 : [1986] 2 SCR 278; Vodafone International
            Holdings BV vs. Union of India and another (2012) 6
            SCC 613: [2012] 1 SCR 573 – relied on.
            ITC Ltd. vs. Blue Coast Hotels Limited & Ors. (2018)
            15 SCC 99 : [2018] 5 SCR 516; Tarapore & Company
C           vs. Cochin Shipyard Ltd., Cochin & Anr. (1984) 2 SCC
            680: [1984] 3 SCR 118 - Distinguished
            Assistant General Manager and others vs. Radhey
            Shyam Pandey (2020) 6 SCC 438; Pioneer Urban Land
            and Infrastructure Limited vs. Govindan Raghavan
D           (2019) 5 SCC 725 : [2019] 5 SCR 1169; Manak Lal
            vs. Dr. Prem Chand 1957 SCR 575 = AIR 1957 SC
            425; Krishna Bahadur vs. Purna Theatre and others
            (2004) 8 SCC 229 : [2004] 3 Suppl. SCR 833; State
            of Punjab vs. Davinder Pal Singh Bhullar and others
            (2011) 14 SCC 770 : [2011] 15 SCR 540; Galada power
E           and Telecommunication limited vs. United India
            Insurance Company Limited and another (2016) 14
            SCC 161: 2016 (4 ) SCR 69 – referred to.
             3.1 For deciding key economic question in the bankruptcy
      process, the only one correct forum for evaluating such
F     possibilities, and making a decision was, a creditors committee,
      wherein all financial creditors have votes in proportion to the
      magnitude of debt that they hold. The Bankruptcy Law Reforms
      Committee-BLRC has observed, that laws in India in the past
      have brought arms of the Government (legislature, executive or
G     judiciary) into the question of bankruptcy process. This has been
      strictly avoided by the Committee and it has been provided, that
      the decision with regard to appropriate disposition of a defaulting
      firm, which is a business decision, should only be made by the
      creditors. It has been observed, that the evaluation of proposals

H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                      689


to keep the entity as a going concern, including decisions about         A
the sale of business or units, restructuring of debt, etc., are
required to be taken by the Committee of the Financial Creditors.
It has been provided, that the choice of the solution to keep the
entity as a going concern will be voted upon by CoC and there
are no constraints on the proposals that the resolution professional
                                                                         B
can present to CoC. The requirements, that the resolution
professional needs to confirm to the Adjudicator, are: (i) that the
solution must explicitly require the repayment of any interim
finance and costs of the insolvency resolution process will be
paid in priority to other payments; (ii) that the plan must explicitly
include payment to all creditors not on the creditors committee,         C
within a reasonable period after the solution is implemented; and
lastly (iii) the plan should comply with existing laws governing
the actions of the entity while implementing the solutions.
[Para 138][760-B-G]
      3.2 There should be freedom permitted to the overall               D
market, to propose solutions on keeping the entity as a going
concern. The details as to how the insolvency is to be resolved
or as to how the entity is to be revived, or the debt is to be
restructured will not be provided in the I&B Code but such a
decision will come from the deliberations of CoC in response to
the solutions proposed by the market. [Para 139][760-G-H;                E
761-A]
      3.3 The appeal is a creature of statute and that the statute
has not invested jurisdiction and authority either with NCLT or
NCLAT, to review the commercial decision exercised by CoC of
approving the resolution plan or rejecting the same. The limited         F
judicial review, which is available, can in no circumstance trespass
upon a business decision arrived at by the majority of CoC.
[Paras 149, 152][766-B-C, G-H]
      3.4 The legislative scheme is unambiguous. The
commercial wisdom of CoC is not to be interfered with, excepting         G
the limited scope as provided under Sections 30 and 31 of the
I&B Code. [Para 155][768-A-B]
      3.5 It was submitted that since there has been a material
irregularity in exercise of the powers by RP, NCLAT was justified
                                                                         H
690            SUPREME COURT REPORTS                       [2021] 2 S.C.R.


A     in view of the provisions of clause (ii) of sub section (3) of Section
      61 of the I&B Code to interfere with the exercise of power by
      RP. However, it could be seen, that all actions of RP have the
      seal of approval of CoC. No doubt, it was possible for RP to have
      issued another Form G, in the event he found, that the proposals
      received by it prior to the date specified in last Form G could not
B
      be accepted. However, it has been the consistent stand of RP as
      well as CoC, that all actions of RP, including acceptance of
      resolution plans of Kalpraj after the due date, albeit before the
      expiry of timeline specified by the Code for completion of the
      process, have been consciously approved by CoC. The decision
C     of CoC is taken by a thumping majority of 84.36%. The only
      creditor voted in favour of KIAL is Kotak Bank, holding company
      of KIAL, having voting rights of 0.97%. In view of the paramount
      importance given to the decision of CoC, which is to be taken on
      the basis of commercial wisdom, NCLAT was not correct in law
      in interfering with the commercial decision taken by CoC by a
D
      thumping majority of 84.36%. [Para 156][768-B-F]
              3.6 After the resolution plan of Kalpraj was approved by
      NCLT on 28.11.2019, Kalpraj had begun implementing the
      resolution plan. NCLAT had heard the appeals on 27.2.2020 and
      reserved the same for orders. There was no stay granted by
E     NCLAT, while reserving the matters for orders. After a gap of
      five months, NCLAT passed the final order on 5.8.2020. Thus,
      for a long period, there was no restraint on implementation of
      the resolution plan of Kalpraj, which was duly approved by NCLT.
      It is the case of Kalpraj, RP, CoC and Deutsche Bank, that during
F     the said period, various steps have been taken by Kalpraj by
      spending a huge amount for implementation of the plan. No doubt,
      this is sought to be disputed by KIAL. However, it is not
      necessary to go into that aspect of the matter in light of the
      conclusion, that NCLAT acted in excess of jurisdiction in
      interfering with the conscious commercial decision of CoC.
G     [Para 157][868-F-H; 769-A]
            3.7 In pursuance of the order dated 5.8.2020 passed by
      NCLAT, CoC has approved the resolution plan of KIAL on
      13.8.2020. However, since the decision of NCLAT dated 5.8.2020

H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                    691


does not stand the scrutiny of law, it must follow, that the           A
subsequent approval of the resolution plan of KIAL by CoC
becomes non est in law. For, it was only to abide by the directions
of NCLAT. Nothing would turn on it. The decision of CoC dated
13/14.2.2019 is a decision, which has been taken in exercise of
its commercial wisdom. As such, the decision taken by CoC dated
                                                                       B
13/14.2.2019, which is taken in accordance with its commercial
wisdom and which is duly approved by NCLT, will prevail. Further,
NCLAT was not justified in interfering with the stated decision
taken by CoC. [Para 158][769-B-D]
      K. Sashidhar vs. Indian Overseas Bank & Ors. (2019)
      12 SCC 150: [2019] 3 SCR 845; Committee of Creditors             C
      of Essar Steel India Limited through Authorised
      Signatory vs. Satish Kumar Gupta & Ors. (2019) SCC
      Online SC 1478 – relied on.
      Maharashtra Seamless Limited vs. Padmanabhan
      Venkatesh and others (2020) 11 SCC 467; Arcelormittal            D
      India Private Limited vs. Satish Kumar Gupta and others
      (2019) 2 SCC 1 : [2018] 12 SCR 362 – referred to
      4 The order passed by NCLAT dated 5.8.2020 is quashed
and set aside and the orders passed by NCLT dated 28.11.2019
are restored and maintained. Insofar as, the Civil Appeals arising     E
out of D.No. 24125 of 2020 filed by Fourth Dimension Solutions
Limited, since the appeal against the order of NCLT is still pending
before NCLAT, NCLAT is directed to decide the appeal as
expeditiously as possible, and in any case, within the stipulated
period. [Paras 159-160][769-D-G]                                       F
      Innoventive Industries Ltd. vs. ICICI Bank & Anr. (2018)
      1 SCC 407: [2017] 8 SCR 33; Kumar Dutta prop. K.D.
      Trading vs. Simplex Infrastructure Ltd. 2019 SCC
      Online NCLAT 575; Asha Goyal vs. Pharma Traders
      Pvt. Ltd. 2019 SCC Online NCLAT 150; Radhika                     G
      Mehra vs. Vaayu Infrastructure LLP & Ors. 2020 SCC
      Online NCLAT 532; Dhirendra Kumar vs. Randstand
      India Pvt. Ltd. & Anr. 2019 SCC Online NCLAT 444;
      Neeraj Jhanji vs. Commissioner of Customs & Central

                                                                       H
692        SUPREME COURT REPORTS                      [2021] 2 S.C.R.


A        Excise (2015) 12 SCC 695; G.J. Fernandez vs. State of
         Karnataka & Ors. (1990) 2 SCC 488: [1990] 1 SCR
         229; NTPC Ltd. (Simhadri Project) vs. Rajiv
         Chakraborty] Civil Appeal No. 2798 of 2020; Union
         of India & Ors. vs. West Coast Paper Mills Ltd. & Anr.
         (2004) 3 SCC 458: [2004] 2 SCR 642; Binani
B
         Industries Limited vs.Bank of Baroda & Anr. 2018 SCC
         Online NCLAT 565 – referred to.
                          Case law reference
      [2017] 8 SCR 33            referred to            Para 9
C     [1990] 1 SCR 229           referred to            Para 20
      [2004] 2 SCR 642           referred to            Para 28
      (2015) 7 SCC 58            relied on              Para 46
      [1950] SCR 459             referred to            Para 46
D     [1970] 1 SCR 51            referred to            Para 46
      [1970] 1 SCR 396           referred to            Para 46
      [1977] 1 SCR 996           referred to            Para 46
      [1996] 2 SCR 366           referred to            Para 46
E     [2008] 5 SCR 1108          relied on              Para 46, 51
      [1977] 1 SCR 683           per incuriam           Para 48
      [1970] 2 SCR 10            referred to            Para 50
      [2009] 3 SCR 238           referred to            Para 50
      [1975] 3 SCR 743           held distinguished     Para 53
F
      [1969] 1 SCR 518           referred to            Para 59
      [1998] 2 Suppl. SCR 359 referred to               Para 62
      (2011) 14 SCC 337          referred to            Para 63
      [2001] 3 Suppl. SCR 619    distinguished          Para 66, 73
G
      [2007] 13 SCR 952          distinguished          Para 74
      (2009) 5 SCC 791           distinguished          Para 75
      [2010] 4 SCR 680           distinguished          Para 76

H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                  693


  [2018] 2 SCR 1099            distinguished         Para 77         A
  (2015) 12 SCC 695            distinguished         Para 78
  [2011] 14 SCR 1204           distinguished         Para 81
  [2006] 3 Suppl. SCR 288      relied on             Para 81
  [1986] 2 SCR 278             relied on             Para 95, 97,    B
                                                     100
  (2020) 6 SCC 438             referred to           Para 96
  [2019] 5 SCR 1169            referred to           Para 98
  1957 SCR 575                 referred to           Para 105
                                                                     C
  [2004] 3 Suppl. SCR 833      referred to           Para 108
  [2011] 15 SCR 540            referred to           Para 111
  [2016] 4 SCR 69              referred to           Para 113
  [2018] 5 SCR 516             distinguished         Para 127
  [1984] 3 SCR 118             distinguished         Para 128        D
  [2012] 1 SCR 573             relied on             Para 130
  [2019 ] 3 SCR 845            relied on             Para 136,
                                                     140, 145,
                                                     146, 148,
                                                                     E
                                                     150
  (2020) 11 SCC 467            referred to           Para 136,
                                                     153
  [2018] 12 SCR 362            referred to           Para 141
      CIVIL APPELLATE JURISDICTION: Civil Appeal Nos.2943-           F
2944 of 2020.
      From the Judgment and Order dated 05.08.2020 of the National
Company Law Appellate Tribunal, New Delhi in Company Appeal (AT)
(Insolvency) Nos.344-345 of 2020.
      With                                                           G

      Civil Appeal Nos.3138-3139 of 2020
      Civil Appeal Nos. 2949-2950 of 2020.
      Civil Appeal No. ……../2021 (Diary No.24125 of 2020)
                                                                     H
694            SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A            Mukul Rohatgi, Dr. Abhishek Manu Singhvi, Pinaki Mishra, C.A.
      Sundaram, Gopal Sankar Narayanan, P.P. Chaudary, K.V. Viswanathan,
      Neeraj Kishal Kaul, Shyam Divan, Sr. Advs., Ms. Ruby Singh Ahuja,
      Ms. Kalpana Unadkat, Prateek Kumar, Ms. Tahira Karanjawala, Anupam
      Prakash, Nidhiram Sharma, Ms. Raveena Rai, Utkarsh Maria, Anmol
      Jassal, M/s Karanjawala & Co., David Rao, Sanjeet Purohit, M.S. Vishnu
B     Sankar, Atul Sharma, Sriram Parakkat, Ms. Athira G. Nair, Shrutanjaya
      Bhardwaj, M/s Lawfic, Dheeraj Nair, Vishrutyi Sahni, Varghese Thomas,
      Ms. Aditi Deshpande, Fatema Kachwalla, Jash Shah, Dheeraj Nair,
      Gaurav Agrawal, Ms. Pooja Mahajan, Avinash Amarnath, Ms. Mahima
      Singh, Ms. Avni Shrivastav, Ritesh Kumar, Advs. for the appearing
C     parties.
             The Judgment of the Court was delivered by
             B.R. GAVAI, J.
             1. Leave to file Civil Appeal in Diary No. 24125 of 2020 is granted.
             2. All these appeals, assail the judgment and order of the National
D     Company Law Appellate Tribunal, New Delhi (hereinafter referred to
      as “NCLAT”) dated 5.8.2020, passed in Company Appeal (AT)
      (Insolvency) Nos. 344-345 of 2020.
             3. By the said judgment and order dated 5.8.2020, NCLAT has
      allowed the appeals filed by Kotak Investment Advisors Limited
E     (hereinafter referred to as “KIAL”), respondent No.1 herein, aggrieved
      by two separate orders dated 28.11.2019 passed by National Company
      Law Tribunal, Mumbai Bench (hereinafter referred to as “NCLT” or
      “Adjudicating Authority”) in M.A. No.1039 of 2019 and M.A. No. 691
      of 2019. NCLAT has set aside the said orders passed in the said M.As.
      M.A. No.1039 of 2019 was filed by KIAL objecting to grant of approval
F     to the resolution plan submitted by Kalpraj Dharamshi and Rekha
      Jhunjhunwala, a consortium, (hereinafter referred to as “Kalpraj”), which
      is appellant in Civil Appeal Nos. 2943-2944 of 2020. NCLT has rejected
      the said M.A. Whereas, M.A. No. 691 of 2019 was filed by the Resolution
      Professional of Ricoh India Limited (hereinafter referred to as “the
      Corporate Debtor”) for grant of approval to the Resolution Plan submitted
G     by Kalpraj. NCLT has allowed the said M.A. and approved the resolution
      plan submitted by Kalpraj.
             4. The facts in brief, giving rise to the present appeals are as
      under:
          The Corporate Debtor filed an application on 29.1.2018 before
H     NCLT under Section 10 of the Insolvency and Bankruptcy Code, 2016
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           695
                  [B.R. GAVAI, J. ]

(hereinafter referred to as “I&B Code”) for initiation of Corporate           A
Insolvency Resolution Process (hereinafter referred to as “CIRP”) of
itself vide Company Petition (IB) No. 156/MB/2018. NCLT vide order
dated 14.5.2018, admitted the Petition and directed the moratorium to
commence as prescribed under Section 14 of the I&B Code and directed
certain statutory steps to be taken as a consequence thereof. Vide the
                                                                              B
said order dated 14.5.2018, NCLT also appointed Mr. Krishna Chamadia
as Interim Resolution Professional to carry out the functions as prescribed
under the provisions of the I&B Code. The said Mr. Krishna Chamadia
was subsequently confirmed as Resolution Professional (hereinafter
referred to as ‘RP’) by the Committee of Creditors (hereinafter referred
to as “CoC”) on 15.6.2018.                                                    C
       RP vide notification dated 9.7.2018 invited expression of interest
(hereinafter referred to as “EOI”) to submit a resolution plan from
interested resolution applicants, who fulfilled the minimum conditions
stipulated in the said document (EOI). As per the said EOI, if any
proposed applicant had any queries or clarifications, it was required to      D
write to RP on or before 31.7.2018. The EOI was required to be submitted
via email on the email address of RP or via post at the address mentioned
in the said invitation on or before 8.8.2018.
       On the said date i.e. 9.7.2018, analogously, the first Form ‘G’ also
came to be notified. Vide the said Form ‘G’, the last date prescribed for     E
submission of Resolution Plan was on or before 21.9.2018. The second
Form ‘G’ came to be issued on 24.8.2018, which required the Resolution
Plans to be submitted on or before 28.9.2018. The third Form ‘G’ came
to be issued on 28.9.2018, which required the Resolution Plans to be
submitted on or before 25.10.2018. The fourth Form ‘G’ came to be
issued on 9.11.2018, which required the Resolution Plans to be submitted      F
on or before 13.12.2018. The fifth and the last Form ‘G’ came to be
issued on 11.12.2018, which required the Resolution Plans to be submitted
on or before 8.1.2019.
       KIAL, the appellant before NCLAT (respondent No.1 herein)
and one Karvy Data Management Systems Limited submitted their                 G
Resolution Plans on the last date as stipulated in the last and fifth Form
‘G’ i.e. on 8.1.2019.
      One another applicant i.e. WeP Solutions Ltd. submitted its
Resolution Plan jointly with one Sattva Real Estate Private Limited
(hereinafter referred to as “WeP”) on 13.1.2019.                              H
696            SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A             The appellant in Civil Appeal Nos. 2943-2944 of 2020 i.e. Kalpraj
      submitted its EOI and Resolution Plan to RP on 27.1.2019.
              On 29.1.2019, KIAL sent an email to RP, raising its objection
      permitting Kalpraj to submit Resolution Plan, beyond the prescribed time
      limit. In the meeting of CoC held on 30.1.2019, the Resolution Plan of
      Kalpraj was placed before CoC. In the said meeting, CoC resolved to
B
      direct all the applicants to submit revised plans. Accordingly, an email
      was sent to KIAL directing it to submit its revised plan. Accordingly,
      KIAL submitted its revised plan on 1.2.2019. By another email dated
      10.2.2019, KIAL once again objected to consideration of the plan
      submitted by Kalpraj.
C             It is the case of KIAL, that it had received an email on 11.2.2019
      from RP, justifying the consideration of plan submitted by Kalpraj and
      asking it to submit a second revised plan. However, this is disputed by
      RP. However, it is not in dispute, that on 12.2.2019, revised plans were
      submitted by KIAL as well as Kalpraj. In the meeting of CoC held on
D     13/14.2.2019, plan of Kalpraj came to be approved by a majority.
              After CoC had approved the plan of Kalpraj, RP applied for
      approval of the plan before NCLT on 18.2.2019 vide M.A. No. 691 of
      2019 in Company Petition (IB) No. 156/MB/2018. After coming to know
      about RP applying for approval of the plan of Kalpraj, KIAL filed an
      application on 14.3.2019 being M.A. No.1039 of 2019, objecting to the
E     plan of Kalpraj. The objection was on the ground, that RP was not justified
      in permitting Kalpraj to submit a plan beyond the date prescribed in
      Form ‘G’ and that the decision of CoC to approve the plan submitted by
      Kalpraj was not in accordance with the I&B Code. Vide order dated
      28.11.2019, NCLT allowed M.A. No.691 of 2019 and approved the
F     Resolution Plan of Kalpraj and by a separate order passed on the same
      day, NCLT rejected M.A. No.1039 of 2019, which was filed by KIAL
      objecting to the decision of CoC approving the plan submitted by Kalpraj.
              Contending, that the procedure followed by NCLT was in breach
      of the principles of natural justice, KIAL filed a writ petition before the
      Bombay High Court being Writ Petition (L) No.3621 of 2019, challenging
G     the aforesaid two orders passed by NCLT. The High Court dismissed
      the Writ Petition (L) No.3621 of 2019 filed by KIAL by judgment and
      order dated 28.1.2020, on the ground, that KIAL had an alternate and
      efficacious remedy of filing an appeal before NCLAT.
              KIAL thereafter filed appeals before NCLAT on 18.2.2020. The
H     appeals were opposed by Kalpraj and also by RP on the ground, that the
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                          697
                  [B.R. GAVAI, J. ]

appeals were filed beyond the limitation period prescribed under the         A
I&B Code and as such, ought not to be entertained. However, vide
order dated 5.8.2020, NCLAT did not find favour with the objections
raised by the respondents before it, with regard to limitation and further
found, that the procedure adopted by RP and CoC was in breach of the
provisions of the I&B Code and therefore, allowed the appeals filed by
                                                                             B
KIAL.
       Vide the said order, NCLAT, while setting aside both the orders
dated 28.11.2019, passed by NCLT, also directed CoC to take a decision
afresh, in the light of the directions issued in its order, regarding
consideration of the Resolution Plans, which were submitted prior to the
prescribed date as per last Form ‘G’. This was directed to be done in a      C
period of ten days from the date of the said order. NCLAT further
directed, that if no decision was communicated to the Adjudicating
Authority i.e. NCLT and since the timeline for completion of CIRP had
already expired, the Adjudicating Authority was to pass an order for
liquidation of the corporate debtor.                                         D
       5. Being aggrieved by the aforesaid order passed by NCLAT,
four appeals have been filed before this Court, the details thereof are as
under:
      Case No. &             Cause title            Particulars of the
      Cause title                                       appellant
                                                                             E
    C.A. No.2943-   Kalpraj Dharamshi & anr. Vs. Successful Resolution
    2944/2020       Kotak Investment Advisors Applicant
                    Ltd. & Anr.

    C.A. No.3138-   Deutsche Bank AG vs.      Financial Creditor
    3139 of 2020    Kotak Investment Advisors
                    Ltd. & Ors.                                              F
    C.A. No.2949-   Krishna Chamadia (Erstwhile Erstwhile resolution
    2950 of 2020    Resolution Profession of Ricoh professional
                    India Ltd.)
                    Vs.
                    Kotak Investment Advisors
                    Ltd. & Ors.                                              G
    C.A.            Fourth Dimension Solutions Claiming to be Largest
    D.No.24125 of   Ltd.                       operational creditors
    2020            Vs.
                    Krishna Chamadia & Ors.

                                                                             H
698                SUPREME COURT REPORTS                     [2021] 2 S.C.R.


A             6. We have heard Shri Mukul Rohatgi, Dr. Abhishek Manu Singhvi
      and Shri Pinaki Mishra, learned Senior Counsel appearing for Kalpraj,
      Shri K.V. Viswanathan, learned Senior Counsel appearing for Deutsche
      Bank A.G. and CoC, Shri C.A. Sundaram, Shri Gopal Sankar Narayanan
      and Shri P.P. Chaudary, learned Senior Counsel appearing for Fourth
      Dimension Solutions Limited, Shri Shyam Divan, learned Senior Counsel
B
      appearing for RP and Shri Neeraj Kishan Kaul, learned Senior Counsel
      appearing for KIAL.
              SUBMISSIONS OF SHRI MUKUL ROHATGI, LEARNED
      SENIOR COUNSEL APPEARING ON BEHALF OF KALPRAJ
              7. Shri Mukul Rohatgi, learned Senior Counsel submitted, that
C     though four Form ‘G’ were issued by RP inviting the Resolution Plans
      from the prospective resolution applicants, no plans were received from
      any of the prospective resolution applicants. He submitted, that in
      pursuance to the last and fifth Form ‘G’ published on 11.12.2018, only
      two Resolution Plans were received, that too, on the last date i.e.
D     8.1.2019. He submitted, that in the meantime, Kalpraj submitted its plan
      on 27.1.2019. He submitted, that in the meeting of CoC held on 30.1.2019,
      in order to achieve the object of maximization, all the applicants were
      asked to submit their revised resolution plans. He submitted, that KIAL
      without demur, submitted its revised plans not only once but twice. It is
      therefore submitted, that having submitted its revised plans twice, KIAL
E     is now estopped from challenging the acceptance of the plan of Kalpraj.
      It is submitted, that in the meeting of CoC held on 13/14.2.2019, the
      plans came to be considered by CoC and CoC by the whopping majority
      of 84.36% voting rights approved the plan of Kalpraj. He submitted, that
      only one creditor i.e. Kotak Mahindra Bank Limited (hereinafter referred
F     to as “Kotak Bank”), which is a holding company of KIAL, having voting
      rights of 0.97%, voted in favour of KIAL.
              8. Relying on the judgment of this Court in the case of K.
      Sashidhar vs. Indian Overseas Bank & Ors.1, Shri Rohatgi submitted,
      the opinion on the subject matter expressed by the creditors after due
      deliberation in CoC meeting through voting, which decision is taken as
G
      per the commercial wisdom, is not justiciable before the Adjudicating
      Authority. He also relied on the judgment of this Court in the case of
      Committee of Creditors of Essar Steel India Limited through
      Authorised Signatory vs. Satish Kumar Gupta & Ors.2
      1
          (2019) 12 SCC 150
H     2
          (2019) SCC Online SC 1478
    KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                         699
                      [B.R. GAVAI, J. ]

        9. Shri Rohatgi further submitted, that as held by this Court in        A
Innoventive Industries Ltd. vs. ICICI Bank & Anr.3, I&B Code is a
complete code in itself. He submitted, that Section 61(2) of the I&B
Code provides, that the decision of the Adjudicating Authority (i.e. NCLT)
may be challenged before NCLAT within 30 days. He submitted, that
an appeal would be tenable within a further period of 15 days, only when
                                                                                B
NCLAT comes to a satisfaction, that there was a sufficient cause for
not filing the appeal within a period of 30 days. He submitted, that since
the I&B Code is a complete Code, neither Section 5 nor Section 14 of
the Limitation Act, 1963 (hereinafter referred to as “the Limitation Act”)
would be applicable. He submitted, that the judgment of NCLT was
delivered on 28.11.2019; certified copies of the same were made available       C
to KIAL on 18.12.2019; and appeals came to be filed on 18.2.2020. He
submitted, even if KIAL was given the benefit of the period of 20 days
for obtaining the certified copies, still the appeals ought to have been
filed on 65th day from the order of NCLT. It would be somewhere on 1st/
2nd February, 2020. However, the appeals were filed on 18.2.2020. He            D
submitted, that the litigant like KIAL, which has a team of legal experts
at its disposal cannot be heard to say, that they were not aware of the
alternate remedy and had bona fide filed the writ petition before the
High Court. He submitted, that KIAL is not entitled to the benefit of the
exclusion of period between 11.12.2019 i.e. the date of filing of the writ
petition and 28.1.2020 i.e. the date of dismissal of the writ petition by the   E
High Court. He submitted, that provisions of Section 14 of the Limitation
Act would not at all be applicable and that NCLAT has totally erred in
law, in entertaining the appeals which were ex facie beyond limitation.
        10. Shri Rohatgi further submitted, that NCLT has approved the
plan on 28.11.2019. He submitted, that though appeals were filed by             F
KIAL, there was no stay on the implementation of the resolution plan by
Kalpraj till the impugned order was passed by NCLAT on 5.8.2020,
whereunder, Kalpraj has taken various steps for implementation of the
Resolution Plan submitted by it. He submitted, that Kalpraj has expended
a total amount of Rs.300 crore (approx.) in the following manner:               G
         “i.    On 02.12.2019, a Public Announcement in respect of
                delisting of shares and exit offer to the public shareholders
                of the Corporate Debtor.

3
    (2018) 1 SCC 407                                                            H
700          SUPREME COURT REPORTS                       [2021] 2 S.C.R.


A     ii.      On 13.12.2019, Rs.8,87,01,150/- (Rupees Eight Crores
               Eighty-Seven Lakh One Thousand One Hundred and Fifty
               only) was paid to 668 shareholders in exchange of their
               shares.
      iii.     On 14.12.2019, a Post-offer public announcement was
B              issued by the Appellants recording inter alia that the said
               consideration has been paid to public shareholders.
      iv.      On 20.12.2019, BSE issued a notice in respect of
               discontinuation of trading and delisting of equity shares of
               the Corporate Debtor.
C     v.       On 23.12.2019, debentures worth Rs.21 crores were issued
               by the Corporate Debtor to Appellants.
      vi.      On 27.12.2019, the share capital of the Company increased
               to INR. 100,00,00,000/- (Rupees One Hundred Crores only).

D     vii.     Minosha Digital Solutions Pvt. Ltd. merged with the
               Corporate Debtor with effect from 28.11.2019.
      viii.    On 27.12.2019, the Appellants replaced the Bank Guarantee
               issued by Deutsche Bank for INR 136,66,71,090/- (Rupees
               One Hundred Thirty-Six Crores Sixty-Six Lakh Seventy-
               One Thousand and Ninety Only).
E
      ix.      On 30.12.2019, the CIRP costs amounting to
               INR.2,65,68,000/- (Rupees Two Crores Sixty-Five Lakh
               Sixty-Eight Thousand only) were paid by the Appellants.
      x.       On 01.01.2020, the Appellants have made payment of INR
F              19,54,43,411/- (Rupees Nineteen Crores Fifty-Four Lakh
               Forty-Three Thousand Four Hundred and Eleven) to non-
               related party operational creditors of the Corporate Debtor.
      xi.      From 01.01.2020 to 03.01.2020, the Appellants have made
               Equity infusion of INR 3 crores and an Equity infusion of
G              INR 29 Crores in Company.
      xii.     On 23.01.2020, Appellants made payments to Ricoh
               Company Limited and NRG Group Limited (minority
               shareholder) for the transfer of shares to Appellants.
      xiii.    On 31.01.2020, the Board of directors of the Corporate
H              Debtor was reconstituted and the Appellants became the
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           701
                  [B.R. GAVAI, J. ]

             owners and stepped into the management and control of            A
             corporate debtor. It is no more a subsidiary of Ricoh Japan.
      xiv.   The Appellants are shareholders of the Corporate Debtor
             which is known by its new name Minosha India Limited.
      xv.    On 03.02.2020, the RP (who was the Monitoring Agent of
                                                                              B
             the Monitoring Committee) issued a communication
             recording that the approved Resolution Plan has been
             implemented.
      xvi.   As on 31.07.2020, a total of 21,90,958 no. of shares held by
             809 shareholders have been tendered pursuant to the exit         C
             offer for a sum total of Rs.10,95,47,900/-. The said exit
             offer is subsisting till December 2020, in accordance with
             the applicable SEBI rules and regulations.
      xvii. Registrar of Companies has only noted and issued a
            certificate of the change in name of the Corporate Debtor         D
            from Ricoh India Limited to Minosha India Limited.”
       11. Shri Rohatgi submitted, that NCLAT has grossly erred in holding,
that the order passed by NCLT was in breach of the principles of natural
justice on the premise, that the application of KIAL was heard by a
single Member, whereas the decision was signed by two Members. He             E
submitted, that perusal of the record would reveal, that though M.A.
No.1039 of 2019 i.e. objection of KIAL to the approval of plan of Kalpraj,
was initially listed before the learned single Member, thereafter the
proceedings would itself show, that the said application was listed before
two learned Members on various dates along with main application i.e.
M.A. No.691 of 2019. He submitted, that the counsels for KIAL have            F
participated in the said proceedings before the Bench of two Members
without demur. He submitted, that in any case, both, the application filed
by KIAL as well as the main application filed by RP, were required to be
decided together inasmuch as, the issues were interconnected and
therefore, they are rightly decided by the orders passed on the same          G
day. He therefore submitted, that the finding of NCLAT with regard to
violation of the principles of natural justice is without any merit.
       12. Shri Rohatgi therefore submitted, that the appeals deserve to
be allowed, the order of NCLAT be set aside and that of NCLT be
restored.                                                                     H
702             SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A         SUBMISSIONS BY DR. ABHISHEK MANU SINGHVI,
      LEARNED SENIOR COUNSEL APPEARING FOR KALPRAJ
              13. Dr. Abhishek Manu Singhvi, learned Senior Counsel also
      appeared on behalf of Kalpraj, which is also respondent in the other
      appeals. Dr. Singhvi submitted, that KIAL, in the covering letter along
B     with its Resolution Plan dated 8.1.2019, has unequivocally undertaken to
      waive any and all claims in respect of the Resolution Plan Process. He
      submitted, that the phrase ‘Resolution Plan Process’ is defined in clause
      1.0 of the Process Memorandum which means, “the process set out in
      this Process Memorandum for submission, evaluation and selection of
      Resolution Plan and activities in relation or incidental thereto.” He
C     submitted, that in view of unconditional and irrevocable acceptance of
      the terms of the Process Memorandum and having voluntarily and
      expressly waived all claims with respect to the Resolution Plan Process,
      it is not permissible for KIAL to challenge the decision of CoC approving
      the Resolution Plan of Kalpraj. He submitted, that clause 10.4 of the
D     Process Memorandum itself provides, that RP was at liberty to receive
      any Resolution Plan, at any stage of the Resolution Plan Process and
      examine such Resolution Plan with the approval of CoC. Learned Senior
      Counsel submitted, that having chosen to revise its Resolution Plan and
      submit the same on 12.2.2019 in competition with Kalpraj, KIAL has
      clearly acquiesced to the consideration of the Resolution Plan of Kalpraj
E     by RP and CoC, even after the prescribed date of 8.1.2019 and has
      waived all objections to the consideration of such Resolution Plan. He
      submitted, that even the holding company of KIAL i.e. Kotak Bank of
      which KIAL is a 100% subsidiary also agreed with CoC counsel’s view,
      that the Resolution Plan of Kalpraj can be considered.
F            14. Dr. Singhvi submitted, that the conduct of KIAL is totally
      indefensible. He submitted, that it amounts to taking chances in the process
      and after having failed there, then to challenge the process. He submitted,
      that KIAL had submitted its revised plans after knowing, that it was
      competing with Kalpraj, and only after it was not successful in the process
G     has chosen to challenge the same. He submitted, that the revised
      Resolution Plan submitted by KIAL does not state, that it is without
      prejudice to its contention, that the Resolution Plans submitted after
      8.1.2019 ought not to have been considered by RP and CoC. He
      submitted, that even if such words were used they would not be significant.
      He relied on the judgment of this Court in the case of ITC Ltd. Vs. Blue
H
    KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                        703
                      [B.R. GAVAI, J. ]

Coast Hotels Limited & Ors.4 and Tarapore & Company vs. Cochin                 A
Shipyard Ltd., Cochin & Anr.5, in this regard.
       15. Dr. Singhvi further submitted, that Section 238 of the I&B
Code provides, that the provisions of the Code shall have effect,
notwithstanding anything inconsistent therewith contained in any other
law for the time being in force. He therefore submitted, that the provisions   B
as contained in Section 61(2) of the I&B Code, which provides, that an
appeal has to be filed within 30 days with a further enhanced period of
15 days, when NCLAT is satisfied, that a sufficient cause existed for
not filing the appeal within 30 days, has to be strictly construed. He
relied on the judgment of NCLAT in the case of Kumar Dutta prop.
K.D. Trading vs. Simplex Infrastructure Ltd.6 and Asha Goyal vs.               C
Pharma Traders Pvt. Ltd.7 in that regard.
      16. Dr. Singhvi further submitted, that this Court in a catena of
cases has held, that when under special statutes there is a provision for
appeal and a self-contained provision for limitation, no extension would
be possible beyond the period of time so stipulated. He relied on the          D
following judgments of this Court in this regard.
        (i)     Union of India vs. Popular Construction Co.8,
        (ii)    Singh Enterprises vs. Commissioner of Central Excise,
                Jamshedpur & Ors.9, and                                        E
        (iii)   Chhattisgarh State Electricity Board vs. Central
                Electricity Regulatory Commission & Ors.10
       17. Dr. Singhvi further submitted, that NCLAT in two cases in
Radhika Mehra vs. Vaayu Infrastructure LLP & Ors. 11 and
Dhirendra Kumar vs. Randstand India Pvt. Ltd. & Anr.12 has held,               F
that the provisions of Section 14 of the Limitation Act cannot be made
applicable to the appeal preferred under Section 67 of the I&B Code.

4
  (2018) 15 SCC 99
5
  (1984) 2 SCC 680 (PARA 33)
6
  2019 SCC Online NCLAT 575
                                                                               G
7
  2019 SCC Online NCLAT 150
8
  (2001) 8 SCC 470
9
  (2008) 3 SCC 70
10
   (2010) 5 SCC 23
11
   2020 SCC Online NCLAT 532
12
   2019 SCC Online NCLAT 444                                                   H
704                SUPREME COURT REPORTS                       [2021] 2 S.C.R.


A            18. Dr. Singhvi submitted, that in any case, it cannot be said, that
      filing of the writ petition was a bona fide act of KIAL. He submitted,
      that KIAL, which was armed with a battery of legal counsel, was very
      well aware, that it had an alternate remedy of filing an appeal before
      NCLAT and therefore, was not entitled to take an umbrella of Section
      14 of the Limitation Act. In this regard, he relied on the judgment of this
B
      Court in the case of Neeraj Jhanji vs. Commissioner of Customs &
      Central Excise 13.
            19. Dr. Singhvi also reiterated the submissions made on behalf of
      Kalpraj by Shri Mukul Rohatgi, learned Senior Counsel to the effect,
      that much water has flown after the Resolution Plan was approved by
C     NCLT and also highlighted the various steps taken by Kalpraj for
      implementation of the Resolution Plan.
          SUBMISSION OF SHRI K.V. VISWANATHAN, LEARNED
      SENIOR COUNSEL APPEARING ON BEHALF OF DEUTSCHE
      BANK A.G. AND CoC.
D
             20. Shri K.V. Viswanathan, learned Senior Counsel appearing on
      behalf of Deutsche Bank, which is appellant in one of the appeals and
      CoC, which is respondent in some of the appeals submitted, that the
      order passed by NCLAT was not sustainable inasmuch as, CoC was not
      made a party before NCLAT. He submitted, that CoC had acted bona
E     fide only with a view of achieving maximization, by permitting Kalpraj
      to participate. He submitted, that CoC had approved the Resolution Plan
      submitted by Kalpraj by a thumping majority of 84.36%. He submitted,
      that the commercial wisdom of CoC is not open to judicial scrutiny by
      the Adjudicating Authority, unless it falls within the statutory parameters
      and as such, NCLT has rightly rejected the objection of KIAL and
F     NCLAT has erred in interfering with the same. He submitted, that no
      prejudice is caused to KIAL on account of deviation of the procedure, if
      any. In this regard, he relied on the judgment of this Court in the case of
      G.J. Fernandez vs. State of Karnataka & Ors.14.
           SUBMISSION OF SHRI SHYAM DIVAN, LEARNED
G     SENIOR COUNSEL APPEARING FOR RP
           21. Shri Shyam Divan, learned Senior Counsel appearing on behalf
      of RP submitted, that RP had acted bona fide in order to fetch the
      maximum benefit to the Company. He submitted, that even after the
      13
           (2015) 12 SCC 695
H     14
           (1990) 2 SCC 488
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                             705
                  [B.R. GAVAI, J. ]

prescribed last date, in view of clause 10.4 of the Process Memorandum,         A
RP was entitled to consider the plans received subsequently with the
approval of CoC. He submitted, that RP therefore had bona fide accepted
the plan of Kalpraj and not only that but had also given an opportunity to
KIAL to submit its revised plans, so as to compete with Kalpraj. Shri
Divan also advanced the arguments on similar lines as were advanced
by the other counsel on the grounds of limitation, acquiescence, etc.           B
         SUBMISSION OF SHRI C.A. SUNDARAM, LEARNED
SENIOR COUNSEL APPEARING FOR FOURTH DIMENSION
SOLUTIONS LIMITED
         22. Shri C.A. Sundaram, learned Senior Counsel appearing for
Fourth Dimension Solutions Limited, appellant in Civil Appeal D.No.24125        C
of 2020, which claims to have the highest amount recoverable from the
Corporate Debtor submitted, that the said appellant is not concerned
with the dispute between the parties, which is the subject matter of
consideration in the present appeals. It is further contended, that the
appellants’ dues are subject matter of pending arbitration proceeding           D
between the Corporate Debtor and the appellants and is yet to attain
finality, so as to liquidate the dues. It is aggrieved by the direction given
in paragraph 39 by NCLT in its order dated 28.11.2019 in M.A. No.691
of 2019. The learned Senior Counsel submitted, that by the said direction
it is directed, that the Resolution Applicant who stepped into the shoes of
Corporate Debtor subsequent to the approval of the Resolution Plan by           E
it, shall not be held responsible for any outstanding statutory dues and
other claims for the period before commencement of CIRP. In the
submission of Shri Sundaram, this direction is prejudicial to the appellant,
which is the largest operational creditor entitled to recover an amount of
551 crores (approx..) from the Corporate Debtor. It is also contended,
                                                                                F
that the claim of the appellant – Fourth Dimension, though has been
shown in the information memorandum by RP, it has not been considered
by CoC or any of the applicants in their resolution plan. He relied on the
judgment/order dated 16.11.2020 passed by this Court in Civil Appeal
No. 2798 of 2020 [NTPC Ltd. (Simhadri Project) vs. Rajiv
Chakraborty]                                                                    G
   SUBMISSION OF SHRI NEERAJ KISHAN KAUL,
LEARNED SENIOR COUNSEL APPEARING FOR KIAL
       23. Shri Neeraj Kishan Kaul, learned Senior Counsel appearing
on behalf of KIAL, while replying to the arguments advanced on behalf
of the appellants made manifold submissions.                                    H
706                SUPREME COURT REPORTS                          [2021] 2 S.C.R.


A             24. In reply to the submission on behalf of the appellants, that the
      appeals filed by KIAL before NCLAT being barred by limitation, the
      learned Senior Counsel submitted, that the arguments advanced were
      not correct in law and NCLAT has rightly held the appeals to be within
      limitation. He submitted, that though non-exercise of jurisdiction by the
      High Court under Article 226 of the Constitution, in case of availability
B
      of alternate remedy is the normal practice, the same is a rule of self-
      restraint and not hard and fast rule. It is submitted, that the High Court
      has wide jurisdiction under Article 226 of the Constitution and in a given
      case it can entertain a petition under Article 226 in spite of the availability
      of an alternate and efficacious remedy. He submitted, that this Court
C     itself in a catena of cases has carved out categories wherein, the High
      Court is entitled to exercise its jurisdiction under Article 226 in spite of
      the availability of alternate remedy. He submitted, that one such category
      is where the proceedings challenged before the High Court are proceeded
      in breach of principles of natural justice. The learned Senior Counsel
      has relied on the following judgments of this Court in support of this
D
      proposition.
             (i)     Whirlpool Corporation vs. Registrar of Trade Marks,
                     Mumbai & Ors.15,
             (ii)    Babu Ram Prakash Chandra Maheshwari vs. Antarim
E                    Zilla Parishad Muzaffar Nagar16; and
             (iii)   Nivedita Sharma vs. Cellular Operators Association of
                     India & Ors.17
             25. Shri Kaul submitted, that perusal of the record would reveal,
      that immediately after the filing of application by RP before NCLT for
F     approval of Resolution Plans submitted by Kalpraj, KIAL had filed an
      application objecting thereto being M.A. No.1039 of 2019. He submitted,
      that perusal of the order-sheet of NCLT dated 3.7.2019 would reveal,
      that the application filed by KIAL and one another application being
      M.A. No.2023 of 2019 were heard by the learned single Member and
G     reserved for orders. He submitted, that insofar as M.A. No.691 of 2019
      is concerned, the order dated 3.7.2019 would show, that the said
      application was directed to be kept on 23.7.2019 at 2.30 p.m. along with

      15
         (1998) 8 SCC 1
      16
         (1969) 1 SCR 518
      17
H        (2011) 14 SCC 337
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                         707
                  [B.R. GAVAI, J. ]

other applications for consideration of resolution plan on its commercial   A
aspect. The other matters were directed to be kept for hearing on
15.7.2019. It is further submitted, that when M.A. No.691 of 2019 was
listed on 23.7.2019, it was directed to be heard on 7.8.2019 at 2.30 p.m.
On 7.8.2019, M.A. No. 691 of 2019 was listed, for the first time, before
the Bench consisting of two Members and on that date the matter came
                                                                            B
to be adjourned to 26.8.2019. Again on 26.8.2019, the matter came up
before the Division Bench and the Division Bench directed the same to
be kept on 6.9.2019. On 6.9.2019, the Division Bench adjourned the
matter to 17.9.2019 at 2.30 p.m. Again on 17.9.2019, the matter came
up before the Division Bench which directed it to be adjourned to
19.9.2019. Finally, on 19.9.2019, M.A. No.691 of 2019 was heard on          C
Resolution Plan and reserved for orders. Learned counsel therefore
submitted, that it is clear from the record, that M.A. No.1039 of 2019
filed by KIAL, was heard on 3.7.2019 by the learned single Member
and reserved for orders. However, M.A. No. 691 of 2019 was heard by
the Division Bench on 19.9.2019. Learned counsel therefore submitted,
                                                                            D
that the orders in M.A. No. 1039 of 2019 could have been passed only
by the learned single Member. However, by two orders passed on even
date i.e. 28.11.2019, the Division Bench rejected the application of KIAL
and allowed the application filed by RP thereby, approving the Resolution
Plan submitted by Kalpraj.
       26. Learned Senior Counsel submitted, that in this background        E
KIAL was justified in invoking the jurisdiction of the High Court under
Article 226 of the Constitution inasmuch as, the proceedings conducted
by NCLT were totally in breach of the principles of natural justice, as
the matter was heard by a single Member whereas, the orders were
passed by the Division Bench. Learned counsel submitted, that the High      F
Court while dismissing the writ petition and relegating KIAL to alternate
remedy available in law has passed an elaborate order. Learned Senior
Counsel therefore submitted, that it does not lie in the mouth of the
appellants, that KIAL had not approached the High Court bona fide.
Learned Senior Counsel submitted, that in view of various judgments
delivered by this Court, the High Court could have entertained a petition   G
under Article 226, when the proceedings were conducted in breach of
the principles of natural justice.
    27. Shri Kaul, learned Senior Counsel therefore submitted, that
NCLAT was right in law in giving the benefit of the period for which
                                                                            H
708             SUPREME COURT REPORTS                            [2021] 2 S.C.R.


A     KIAL was bona fide prosecuting its writ petition before the Bombay
      High Court. Learned Senior Counsel submitted, that if that period is
      considered, the appeals filed by KIAL are very well within the limitation.
             28. Learned Senior Counsel submitted, that the purpose behind
      Article 14 of the Limitation Act is to advance justice and not to halt
B     justice. He submitted, that Section 14 enables a party to get the benefit
      of the period for which it was bona fide prosecuting the remedy before
      a wrong forum. Learned counsel submitted, that a liberal approach is
      required to be given to the provisions of Article 14. Learned counsel
      relied on the judgments of this Court in the case of Ketan V. Parekh vs.
      Special Director, Directorate of Enforcement & Anr.18, M.P. Steel
C     Corporation vs. Commissioner of Central Excise19 and Union of India
      & Ors. vs. West Coast Paper Mills Ltd. & Anr.20 in this regard.
              29. Insofar as the arguments of the appellants with regard to
      acquiescence and waiver are concerned, learned Senior Counsel
      submitted, that, at the earliest opportunity, KIAL has objected to Kalpraj
D     submitting its Resolution Plan. He submitted, that on KIAL coming to
      know, that the Resolution Plan of Kalpraj was accepted beyond 8.1.2019,
      KIAL objected to it vide email dated 29.1.2019 addressed to RP. He
      submitted, that RP had replied to its email on 30.1.2019 and requested to
      submit amended Resolution Plan by 3.00 p.m. on 1.2.2019. He submitted,
E     that in the said email it is also mentioned, that “CoC reserves the rights
      to not consider your plan, if received after the said timeline”. He submitted,
      that accordingly, KIAL had no other option but to submit its revised plan.
             30. Learned Senior Counsel submitted, that even after submission
      of the revised plan, KIAL did not hear anything from RP and therefore
F     vide email dated 10.2.2019, addressed to RP, it again raised its objection.
      The said email was replied to by RP on 11.2.2019 wherein, RP stated,
      that the resolution plans submitted after the due date also could be
      considered, in the spirit of value maximisation of assets of the corporate
      debtor. He submitted, that again vide communication dated 11.2.2019,
      KIAL was required to submit a revised bid, which was submitted by it
G     on 12.2.2019. Learned counsel therefore submitted, that it is clear from
      the record, that KIAL had objected to the participation of Kalpraj at the
      earliest possible opportunity i.e. on 29.1.2019. Not only that, thereafter
      18
         (2011) 15 SCC 30
      19
          (2015) 7 SCC 58
      20
H        (2004) 3 SCC 458
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            709
                   [B.R. GAVAI, J. ]

KIAL continued to object to the participation of Kalpraj. Revised plans         A
were submitted by KIAL under compulsion inasmuch as, if it would not
have submitted its revised plans, on that ground alone it had to face the
risk of being ousted from consideration. It is therefore submitted, that
the contention, that KIAL has acquiesced to the participation of Kalpraj
and was therefore estopped from challenging its participation is without
                                                                                B
any substance. Learned counsel submitted, that the contention, that KIAL
was taking chances is also totally incorrect. It had objected to the
participation of Kalpraj at the very first opportunity and continued to
object till CoC approved its plan and also thereafter, by way of an
application before NCLT objecting to the approval of the Resolution
Plan of Kalpraj.                                                                C
       31. Learned counsel further submitted, that the contention, that
KIAL is a subsidiary of Kotak Bank and that Kotak Bank had also not
objected to Kalpraj submitting its Resolution Plan and therefore the same
amounted to acquiescence is also not correct. He submitted, that firstly,
in the reply filed by RP to the application filed by KIAL in NCLT, there        D
is no plea regarding the Kotak Bank’s consensus. He however submitted,
that in any case in view of the judgment of this Court in the case of
Vodafone International Holdings BV vs. Union of India & Anr.21,
both KIAL and Kotak Bank are different corporate entities and any act
of Kotak Bank cannot bind KIAL.
                                                                                E
        32. On merits, Shri Kaul would submit, that the entire process
adopted by RP and CoC was contrary to the statutory provisions, fair
play and transparency. He submitted, that perusal of the definition of
‘applicant’ in the Process Memorandum in clause 1.0 would show, that
for being a resolution applicant, one has to be an applicant who has
applied within the prescribed period either under EOI or Form ‘G’. It is        F
submitted, that since Kalpraj had neither responded within the period
prescribed under EOI or any of the Form ‘G’, it could not have been
considered to be a resolution applicant. He submitted, that the entire
participation of Kalpraj is illegal. He submitted, that after the plan was
submitted by KIAL there was a detailed discussion with RP with regard           G
to the plan submitted by it, wherein entire plan was disclosed, after which
Kalpraj was permitted to step in. He submitted, that perusal of the
Resolution Plan of Kalpraj would reveal, that it is identical with the plans
submitted by KIAL, with a little variation to the extent, that in the plan of
21
     (2012) 6 SCC 613                                                           H
710               SUPREME COURT REPORTS                        [2021] 2 S.C.R.


A     KIAL the provision made for minority shareholder is Rs.1 crore whereas,
      in the plan of Kalpraj it is Rs. 50 crore. He submitted, that the entire
      conduct of RP as well as CoC would reveal, that they had acted in a
      manner that smacks of favouritism to Kalpraj and were determined to
      anyhow approve the plan of Kalpraj. It is submitted, that all these aspects
      have been rightly considered by NCLAT and therefore, the appeals
B     deserve to be dismissed.
             33. With regard to the contention of the appellant/Kalpraj, that it
      has taken several steps in pursuance of the Resolution Plan, which was
      approved by NCLT and any interference at this stage would cause great
      prejudice to many stakeholders, learned counsel submitted, that not much
C     has been done under the Resolution Plan. He submits, in any case,
      whatever steps have been taken are almost identical with the steps that
      KIAL would have taken inasmuch as, the Resolution Plan submitted by
      Kalpraj is almost identical with the Resolution Plan submitted by KIAL.
      He submitted, that in any case, whatever amount has been spent by
      Kalpraj, the same could be reimbursed by KIAL and further steps being
D
      continued to be taken by KIAL, so as to take the Resolution Plan to the
      logical end.
             34. Insofar as the judgment of NCLAT in the case of Binani
      Industries Limited vs. Bank of Baroda & Anr.22 is concerned, learned
      counsel submitted, that the said judgment is totally distinguishable
E     inasmuch as, in the said case both applicants had submitted their plans
      and revised plans within the stipulated period.
             35. In view of the rival submissions, following questions arise for
      our consideration.
             (i)    Whether the appeals filed by KIAL before NCLAT were
F                   within limitation?
             (ii) Whether there was waiver and acquiescence by KIAL, so
                    as to estop it from challenging the participation of Kalpraj?
             (iii) Whether NCLAT was right in law in interfering with the
                    decision of CoC of accepting the resolution plan of Kalpraj?
G            (i) WHETHER THE APPEALS FILED BY KIAL BEFORE
      NCLAT WERE WITHIN LIMITATION?
             36. For appreciating the rival contentions in this regard, it would
      be appropriate to refer to Section 29(2) of the Limitation Act, so also the
      provisions of Section 61 and Section 238A of the I&B Code.
      22
H          2018 SCC Online NCLAT 565
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                    711
                  [B.R. GAVAI, J. ]

    Section 29(2) of the Limitation Act.                               A
    “29. Savings.—(1) …….
    (2) Where any special or local law prescribes for any suit,
    appeal or application a period of limitation different from
    the period prescribed by the Schedule, the provisions of Section
    3 shall apply as if such period were the period prescribed by      B
    the Schedule and for the purpose of determining any period
    of limitation prescribed for any suit, appeal or application
    by any special or local law, the provisions contained in
    Sections 4 to 24 (inclusive) shall apply only insofar as, and
    to the extent to which, they are not expressly excluded by         C
    such special or local law.”
    Section 61 and 238A of the I&B Code
    “61. Appeals and Appellate Authority.—(1) Notwithstanding
    anything to the contrary contained under the Companies Act,
    2013, any person aggrieved by the order of the Adjudicating        D
    Authority under this part may prefer an appeal to the National
    Company Law Appellate Tribunal.
          (2) Every appeal under sub-section (1) shall be filed
    within thirty days before the National Company Law Appellate
    Tribunal:                                                          E
           Provided that the National Company Law Appellate
    Tribunal may allow an appeal to be filed after the expiry of
    the said period of thirty days if it is satisfied that there was
    sufficient cause for not filing the appeal but such period shall
    not exceed fifteen days.                                           F
          (3) An appeal against an order approving a resolution
    plan under Section 31 may be filed on the following grounds,
    namely—
          (i)    the approved resolution plan is in contravention
                 of the provisions of any law for the time being in    G
                 force;
          (ii)   there has been material irregularity in exercise
                 of the powers by the resolution professional
                 during the corporate insolvency resolution
                 period;                                               H
712             SUPREME COURT REPORTS                             [2021] 2 S.C.R.


A                   (iii)   the debts owed to operational creditors of the
                            corporate debtor have not been provided for in
                            the resolution plan in the manner specified by the
                            Board;
                    (iv)    the insolvency resolution process costs have not
B                           been provided for repayment in priority to all
                            other debts; or
                    (v)     the resolution plan does not comply with any other
                            criteria specified by the Board.
                   (4) An appeal against a liquidation order passed under
C            Section 33 may be filed on grounds of material irregularity
             or fraud committed in relation to such a liquidation order.”
             “238-A. Limitation.—The provisions of the Limitation Act,
             1963 (36 of 1963) shall, as far as may be, apply to the
             proceedings or appeals before the Adjudicating Authority,
D            the National Company Law Appellate Tribunal, the Debt
             Recovery Tribunal or the Debt Recovery Appellate Tribunal,
             as the case may be.”
             37. Perusal of the aforesaid would reveal, that though the provisions
      of the Limitation Act, as far as may be, would apply to the proceedings
E     or appeals before the Adjudicating Authority, NCLAT, the Debt Recovery
      Tribunal or the Debt Recovery Appellate Tribunal, where a period of
      limitation for initiation of proceedings is provided under any special or
      local law, different from the period prescribed by the Schedule, the
      provisions of Section 3 shall apply, as if such period were the period
F     prescribed by the Schedule. It would further reveal, that for the purpose
      of determining any period of limitation prescribed for any suit, appeal or
      application by any special or local law, the provisions contained in sections
      4 to 24 (inclusive), shall apply only in so far, and to the extent to which,
      they are not expressly excluded by such special or local law.
             38. An appeal is provided before NCLAT under sub-section (1)
G
      of Section 61 of the I&B Code to any person, who is aggrieved by the
      order of the Adjudicating Authority. Sub-section (2) of Section 61 of the
      I&B Code provides, that every appeal under sub-section (1) shall be
      filed within thirty days before NCLAT. The proviso thereto further
      provides, that NCLAT may allow an appeal to be filed after the expiry
H     of the said period of thirty days if it is satisfied, that there was sufficient
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                              713
                  [B.R. GAVAI, J. ]

cause for not filing the appeal. However, such period shall not exceed           A
fifteen days.
        39. Since there is a period different from the one which is prescribed
by the Schedule to the Limitation Act, the limitation for an appeal would
be governed by Section 61 of the I&B Code, which is a special statute.
As such, an appeal will have to be preferred within a period of thirty           B
days from the date on which the order was passed by NCLT. However,
if NCLAT is satisfied, that there was sufficient cause for not filing the
appeal within a period of thirty days, it may allow an appeal to be filed
within a further period of fifteen days. As such, the normal period of
limitation prescribed under the I&B Code is thirty days, with a provision
for allowing the filing of an appeal within a further period of fifteen days,    C
if NCLAT is satisfied, that there was a sufficient cause for not filing the
appeal within thirty days.
       40. In the present case, the dates are not in dispute. The judgment
of NCLT is dated 28.11.2019. As such, as per Section 61(2) of the I&B
Code, the appeal was required to be filed on or prior to 28.12.2019. The         D
appeal could have been filed within a further period of fifteen days, if
NCLAT was satisfied, that there was sufficient cause for not filing the
appeal within a period of thirty days. As such, the said period would
come to an end on 12.1.2020. The certified copy of the impugned
judgment of NCLT was made available on 18.12.2019. If the allowance              E
for the said period is granted, the appeal should have been preferred on
or prior to 2.2.2020. However, in the present case, the appeal is filed on
18.2.2020. It is also not in dispute, that immediately after the order was
passed on 28.11.2019 by NCLT, KIAL preferred a writ petition being
Writ Petition (L) No. 3621 of 2019 before the Division Bench of the
Bombay High Court on 11.12.2019. The said writ petition came to be               F
dismissed on 28.1.2020 on the ground, that KIAL had an alternate and
efficacious remedy available under Section 61 of the I&B Code and as
such, it was relegated to the alternate remedy available in law.
        41. It is strenuously urged on behalf of all the appellants except
Fourth Dimension Solutions Ltd., that the I&B Code is a complete code            G
in itself, which also provides for a period of limitation and as such, Section
14 of the Limitation Act would not be available to KIAL.
      42. On the contrary, it is urged on behalf of KIAL, that since the
order passed by NCLT was passed in utter breach of the principles of
natural justice, it had bona fide filed a writ petition before the Division      H
714             SUPREME COURT REPORTS                              [2021] 2 S.C.R.


A     Bench of the Bombay High Court. It is urged, that by an elaborate order
      the writ petition came to be dismissed, on the ground of availability of
      alternate remedy. It is therefore urged, that the provisions of Section 14
      or at least the principles laid down therein, would be available to KIAL
      and as such, the appeals, as filed will have to be held to be within limitation.
B             43. Therefore, the crucial question, that arises for consideration,
      is as to whether the provisions of Section 14 of the Limitation Act or the
      principles laid down therein would be available to KIAL for exclusion of
      the period during which it was prosecuting the writ petition before the
      Division Bench of the Bombay High Court.
C            44. It will be relevant to refer to Section 14 of the Limitation Act.
             “14. Exclusion of time of proceeding bona fide in court without
             jurisdiction.—(1) In computing the period of limitation for
             any suit the time during which the plaintiff has been
             prosecuting with due diligence another civil proceeding,
D            whether in a court of first instance or of appeal or revision,
             against the defendant shall be excluded, where the proceeding
             relates to the same matter in issue and is prosecuted in good
             faith in a court which, from defect of jurisdiction or other
             cause of a like nature, is unable to entertain it.

E            (2) In computing the period of limitation for any application,
             the time during which the applicant has been prosecuting with
             due diligence another civil proceeding, whether in a court of
             first instance or of appeal or revision, against the same party
             for the same relief shall be excluded, where such proceeding
             is prosecuted in good faith in a court which, from defect of
F            jurisdiction or other cause of a like nature, is unable to
             entertain it.
             (3) Notwithstanding anything contained in Rule 2 of Order
             XXIII of the Code of Civil Procedure, 1908 (5 of 1908), the
             provisions of sub-section (1) shall apply in relation to a fresh
G            suit instituted on permission granted by the court under Rule
             1 of that Order, where such permission is granted on the
             ground that the first suit must fail by reason of a defect in the
             jurisdiction of the court or other cause of a like nature.
             Explanation.—For the purposes of this section,—
H
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            715
                   [B.R. GAVAI, J. ]

          (a)   in excluding the time during which a former civil               A
                proceeding was pending, the day on which that
                proceeding was instituted and the day on which it ended
                shall both be counted;
          (b)   a plaintiff or an applicant resisting an appeal shall be
                deemed to be prosecuting a proceeding;                          B
          (c)   misjoinder of parties or of causes of action shall be
                deemed to be a cause of a like nature with defect of
                jurisdiction.”
       45. The conditions that are required to be fulfilled for invoking the
provisions of Section 14 of the Limitation Act have been succinctly spelt       C
out in various judgments of this Court including the one in Consolidated
Engineering Enterprises vs. Principal Secretary, Irrigation
Department and others23, which read thus:
          “21. ”Section 14 of the Limitation Act deals with exclusion of
          time of proceeding bona fide in a court without jurisdiction. On      D
          analysis of the said section, it becomes evident that the following
          conditions must be satisfied before Section 14 can be pressed into
          service:
          (1)   Both the prior and subsequent proceedings are civil
                proceedings prosecuted by the same party;                       E
          (2)   The prior proceeding had been prosecuted with due diligence
                and in good faith;
          (3)   The failure of the prior proceeding was due to defect of
                jurisdiction or other cause of like nature;
                                                                                F
          (4)   The earlier proceeding and the latter proceeding must relate
                to the same matter in issue; and
          (5)   Both the proceedings are in a court.”
       46. Perusal of the aforesaid conditions would make it amply clear,
that one of the conditions that is required to be fulfilled is that both the    G
proceedings are in a court. The question as to whether the provisions of
Section 14 of the Limitation Act would also be applicable to the quasi-
judicial forums as against the court, fell for consideration before this
Court in the case of M.P. Steel Corporation (supra). This Court after
23
     (2008) 7 SCC 169                                                           H
716             SUPREME COURT REPORTS                         [2021] 2 S.C.R.


A     an elaborate survey of the various judgments of this Court, including
      judgment in the cases of Bharat Bank Ltd., Delhi vs. Employees of
      the Bharat Bank Ltd., Delhi24, Town Municipal Council, Athani vs.
      Presiding Officer, Labour Courts, Hubli and others etc.25, Nityananda
      M. Joshi and others vs. Life Insurance Corporation of India and
      others26, Commissioner of Sales Tax. U.P., Lucknow vs. Parson Tools
B
      and Plants, Kanpur27, Kerala State Electricity Board, Trivandrum
      vs. T.P. Kunhaliumma28, Officer on Special Duty (Land Acquisition)
      and another vs. Shah Manilal Chandulal and others 29 and
      Consolidated Engineering Enterprises (supra) held, that the word
      “court” in Section 14 takes its colour from the preceding words “civil
C     proceedings”. It was therefore held, that the Limitation Act including
      Section 14 would not apply to appeals filed before a quasi-judicial
      Tribunal. It was held, that since the appeal as mentioned in Section 128
      of the Customs Act is not before a Court, the provisions of Section 14
      would not be applicable.
D            47. All the authorities cited above, including Consolidated
      Engineering Enterprises (supra), have been elaborately discussed in
      the judgment of this Court in the case of M.P. Steel Corporation (supra)
      and therefore, we refrain from burdening the present judgment by
      reproducing the observations made in those judgments.
E            48. This Court in M.P. Steel Corporation (supra) further observed,
      that the judgment of this Court in the case of Commissioner of Sales
      Tax, U.P. vs. Madan Lal Das & Sons, Bareilly30 had not considered
      the law laid down in Parson Tools and Plants (supra) and the other
      judgments nor the aforesaid decisions were pointed out to the Court and
      therefore, the said judgment in the case of Madan Lal Das & Sons
F     (supra) was not an authority for the proposition, that the Limitation Act
      would apply to Tribunals.
            49. After having held, that the Limitation Act, including Section 14
      would not apply to appeals filed before a quasi-judicial Tribunal, this
      Court in M.P. Steel Corporation (supra) observed thus:
G
      24
         AIR 1950 SC 188 = 1950 SCR 459
      25
         (1969) 1 SCC 873
      26
         (1969) 2 SCC 199
      27
         (1975) 4 SCC 22
      28
         (1976) 4 SCC 634
      29
         (1996) 9 SCC 414
H     30
         (1976) 4 SCC 464
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           717
                  [B.R. GAVAI, J. ]

    “….However, this does not conclude the issue. There is authority          A
    for the proposition that even where Section 14 may not apply, the
    principles on which Section 14 is based, being principles which
    advance the cause of justice, would nevertheless apply. We must
    never forget, as stated in Bhudan Singh v. Nabi Bux [(1969) 2
    SCC 481 : (1970) 2 SCR 10] that justice and reason is at the heart
                                                                              B
    of all legislation by Parliament. This was put in very felicitous
    terms by Hegde, J. as follows: (SCC p. 485, para 9)
        ‘9. Before considering the meaning of the word ‘held’ in Section
        9, it is necessary to mention that it is proper to assume that the
        lawmakers who are the representatives of the people enact
        laws which the society considers as honest, fair and equitable.       C
        The object of every legislation is to advance public welfare. In
        other words as observed by Crawford in his book on ‘Statutory
        Constructions’ that the entire legislative process is influenced
        by considerations of justice and reason. Justice and reason
        constitute the great general legislative intent in every piece of     D
        legislation. Consequently where the suggested construction
        operates harshly, ridiculously or in any other manner contrary
        to prevailing conceptions of justice and reason, in most instances,
        it would seem that the apparent or suggested meaning of the
        statute, was not the one intended by the lawmakers. In the
        absence of some other indication that the harsh or ridiculous         E
        effect was actually intended by the legislature, there is little
        reason to believe that it represents the legislative intent.’
    39. This is why the principles of Section 14 were applied in J.
    Kumaradasan Nair v. Iric Sohan [(2009) 12 SCC 175 : (2009)
    4 SCC (Civ) 656] to a revision application filed before the High          F
    Court of Kerala. The Court held: (SCC pp. 180-81, paras 16-18)
        ‘16. The provisions contained in Sections 5 and 14 of the
        Limitation Act are meant for grant of relief where a person
        has committed some mistake. The provisions of Sections 5
        and 14 of the Limitation Act alike should, thus, be applied in a
                                                                              G
        broadbased manner. When sub-section (2) of Section 14 of
        the Limitation Act per se is not applicable, the same would not
        mean that the principles akin thereto would not be applied.
        Otherwise, the provisions of Section 5 of the Limitation Act
        would apply. There cannot be any doubt whatsoever that the
        same would be applicable to a case of this nature.                    H
718     SUPREME COURT REPORTS                             [2021] 2 S.C.R.


A       17. There cannot furthermore be any doubt whatsoever that
        having regard to the definition of ‘suit’ as contained in Section
        2(l) of the Limitation Act, a revision application will not answer
        the said description. But, although the provisions of Section 14
        of the Limitation Act per se are not applicable, in our opinion,
        the principles thereof would be applicable for the purpose of
B
        condonation of delay in filing an appeal or a revision application
        in terms of Section 5 thereof.
        18. It is also now a well-settled principle of law that mentioning
        of a wrong provision or non-mentioning of any provision of
        law would, by itself, be not sufficient to take away the
C       jurisdiction of a court if it is otherwise vested in it in law. While
        exercising its power, the court will merely consider whether it
        has the source to exercise such power or not. The court will
        not apply the beneficent provisions like Sections 5 and 14 of
        the Limitation Act in a pedantic manner. When the provisions
D       are meant to apply and in fact found to be applicable to the
        facts and circumstances of a case, in our opinion, there is no
        reason as to why the court will refuse to apply the same only
        because a wrong provision has been mentioned. In a case of
        this nature, sub-section (2) of Section 14 of the Limitation Act
        per se may not be applicable, but, as indicated hereinbefore,
E       the principles thereof would be applicable for the purpose of
        condonation of delay in terms of Section 5 thereof.’
      40. The Court further quoted from Consolidated Engg.
      Enterprises [(2008) 7 SCC 169] an instructive passage: (Iric
      Sohan case [(2009) 12 SCC 175 : (2009) 4 SCC (Civ) 656], SCC
F     p. 183, para 21)
        ‘21. In Consolidated Engg. Enterprises v. Irrigation
        Deptt. [(2008) 7 SCC 169] this Court held: (SCC p. 181, para
        22)

G       ‘22. The policy of the section is to afford protection to a litigant
        against the bar of limitation when he institutes a proceeding
        which by reason of some technical defect cannot be decided
        on merits and is dismissed. While considering the provisions of
        Section 14 of the Limitation Act, proper approach will have to
        be adopted and the provisions will have to be interpreted so as
H
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                                 719
                   [B.R. GAVAI, J. ]

             to advance the cause of justice rather than abort the                   A
             proceedings. It will be well to bear in mind that an element of
             mistake is inherent in the invocation of Section 14. In fact, the
             section is intended to provide relief against the bar of limitation
             in cases of mistaken remedy or selection of a wrong forum.
             On reading Section 14 of the Act it becomes clear that the
                                                                                     B
             legislature has enacted the said section to exempt a certain
             period covered by a bona fide litigious activity. Upon the words
             used in the section, it is not possible to sustain the interpretation
             that the principle underlying the said section, namely, that the
             bar of limitation should not affect a person honestly doing his
             best to get his case tried on merits but failing because the            C
             court is unable to give him such a trial, would not be applicable
             to an application filed under Section 34 of the 1996 Act. The
             principle is clearly applicable not only to a case in which a
             litigant brings his application in the court, that is, a court having
             no jurisdiction to entertain it but also where he brings the suit
                                                                                     D
             or the application in the wrong court in consequence of bona
             fide mistake or (sic of) law or defect of procedure. Having
             regard to the intention of the legislature this Court is of the
             firm opinion that the equity underlying Section 14 should be
             applied to its fullest extent and time taken diligently pursuing a
             remedy, in a wrong court, should be excluded.’                          E
          See Shakti Tubes Ltd. v. State of Bihar [(2009) 1 SCC 786 :
          (2009) 1 SCC (Civ) 370].’ “
       50. Thus, this Court relying on the earlier judgments in the cases
of Bhudan Singh and another vs. Nabi Bux and another 31, J.
Kumaradasan Nair and another vs. Iric Sohan and others32, and                        F
Consolidated Engineering Enterprises (supra) observed, that the object
of enacting the legislation is to advance public welfare. The entire
legislative process is influenced by considerations of justice and reason.
Justice and reason constitute the great general legislative intent in every
piece of legislation. It has been held by this Court, that in the absence of         G
some other indication that the harsh or ridiculous effect was actually
intended by the legislature, there is little reason to believe, that it represents
the legislative intent. It is further observed, that the provisions contained
31
     (1969) 2 SCC 481
32
     (2009) 12 SCC 175                                                               H
720             SUPREME COURT REPORTS                             [2021] 2 S.C.R.


A     in Sections 5 and 14 of the Limitation Act are meant for grant of relief,
      where a person has committed some mistake. In J. Kumaradasan Nair
      (supra), it has been observed, that when sub-section (2) of Section 14 of
      the Limitation Act per se is not applicable, the same would not mean,
      that the principles akin thereto would not be applicable.
B            51. In Consolidated Engineering Enterprises (supra), it has
      been observed, that while considering the provisions of Section 14 of the
      Limitation Act, proper approach will have to be adopted and the provisions
      will have to be interpreted, so as to advance the cause of justice, rather
      than abort the proceedings. It has been observed, that an element of
      mistake is inherent in the invocation of Section 14. The section, in fact, is
C     intended to provide a relief against the bar of limitation in cases of mistaken
      remedy or selection of a wrong forum. It has been observed, that the
      legislature has enacted Section 14 to exempt a certain period covered
      by a bona fide litigious activity. It has been held, that the equity underlying
      Section 14 should be applied to its fullest extent and time taken diligently
D     pursuing a remedy, in a wrong court, should be excluded. It could thus
      be seen, that this Court has in unequivocal terms held, that when a litigant
      bona fide under a mistake litigates before a wrong forum, he would be
      entitled for exclusion of the period, during which he was bona fide
      prosecuting such a wrong remedy. Though strictly, the provisions of
      Section 14 of the Limitation Act would not be applicable to the proceedings
E     before a quasi-judicial Tribunal, however, the principles underlying the
      same would be applicable i.e. the proper approach will have to be of
      advancing the cause of justice, rather than to abort the proceedings.
              52. An argument similar to the one which is advanced before us,
      that since the Code is a complete Code in itself, the limitation as provided
F     only under the Code would govern the field and would exclude the
      application of provisions of Section 14 of the Limitation Act was made in
      the case of M.P. Steel Corporation (supra). While considering this
      objection, this Court observed thus:
             “42. However, it remains to consider whether Shri Sanghi is right
G            in stating that Section 128 is a complete code by itself which
             necessarily excludes the application of Section 14 of the Limitation
             Act. For this proposition he relied strongly on Parson Tools [(1975)
             4 SCC 22 : 1975 SCC (Tax) 185 : (1975) 3 SCR 743] which has
             been discussed hereinabove. As has already been stated, Parson
             Tools [(1975) 4 SCC 22 : 1975 SCC (Tax) 185 : (1975) 3 SCR
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            721
                  [B.R. GAVAI, J. ]

    743] was a judgment which turned on the three features mentioned           A
    in the said case. Unlike the U.P. Sales Tax Act, there is no provision
    in the Customs Act which enables a party to invoke suo motu the
    appellate power and grant relief to a person who institutes an
    appeal out of time in an appropriate case. Also, Section 10 of the
    U.P. Sales Tax Act dealt with the filing of a revision petition after
                                                                               B
    a first appeal had already been rejected, and not to a case of a
    first appeal as provided under Section 128 of the Customs Act.
    Another feature, which is of direct relevance in this case, is that
    for revision petitions filed under the U.P. Sales Tax Act a sufficiently
    long period of 18 months had been given beyond which it was the
    policy of the legislature not to extend limitation any further. This       C
    aspect of Parson Tools [(1975) 4 SCC 22 : 1975 SCC (Tax) 185
    : (1975) 3 SCR 743] has been explained in Consolidated Engg.
    [(2008) 7 SCC 169] in some detail by both the main judgment as
    well as the concurring judgment. In the latter judgment, it has
    been pointed out that there is a vital distinction between extending
                                                                               D
    time and condoning delay. Like Section 34 of the Arbitration Act,
    Section 128 of the Customs Act is a section which lays down that
    delay cannot be condoned beyond a certain period. Like Section
    34 of the Arbitration Act, Section 128 of the Customs Act does
    not lay down a long period. In these circumstances, to infer
    exclusion of Section 14 or the principles contained in Section 14          E
    would be unduly harsh and would not advance the cause of justice.
    It must not be forgotten as is pointed out in the concurring judgment
    in Consolidated Engg. [(2008) 7 SCC 169] that: (SCC p. 193,
    para 54)
        ‘54. … Even when there is cause to apply Section 14, the               F
        limitation period continues to be three months and not more,
        but in computing the limitation period of three months for the
        application under Section 34(1) of the AC Act, the time during
        which the applicant was prosecuting such application before
        the wrong court is excluded, provided the proceeding in the
        wrong court was prosecuted bona fide, with due                         G
        diligence. Western Builders [State of Goa v. Western
        Builders, (2006) 6 SCC 239] therefore lays down the correct
        legal position.’
    43. Merely because Parson Tools [(1975) 4 SCC 22 : 1975 SCC
    (Tax) 185 : (1975) 3 SCR 743] also dealt with a provision in a tax         H
722             SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A           statute does not make the ratio of the said decision apply to a
            completely differently worded tax statute with a much shorter
            period of limitation— Section 128 of the Customs Act. Also, the
            principle of Section 14 would apply not merely in condoning delay
            within the outer period prescribed for condonation but would apply
            dehors such period for the reason pointed out in Consolidated
B
            Engg. [(2008) 7 SCC 169] above, being the difference between
            exclusion of a certain period altogether under Section 14 principles
            and condoning delay. As has been pointed out in the said judgment,
            when a certain period is excluded by applying the principles
            contained in Section 14, there is no delay to be attributed to the
C           appellant and the limitation period provided by the statute concerned
            continues to be the stated period and not more than the stated
            period. We conclude, therefore, that the principle of Section 14
            which is a principle based on advancing the cause of justice would
            certainly apply to exclude time taken in prosecuting proceedings
            which are bona fide and with due diligence pursued, which
D
            ultimately end without a decision on the merits of the case.”
              53. Perusal of the aforesaid would therefore reveal, that the Court
      has clearly rejected the objection raised by the Revenue in M.P. Steel
      Corporation (supra) which was raised relying on the judgment of this
      Court in the case of Parson Tools and Plants (supra). This Court
E     observed, that the time during which the applicant was prosecuting such
      application before the wrong court can be excluded, provided the
      proceeding in the wrong court was prosecuted bona fide, with due
      diligence. This Court distinguished the judgment in the case of Parson
      Tools and Plants (supra) on the ground, that the period provided for
F     filing a revision under the U.P. Sales Tax Act was sufficiently long period
      of 18 months, beyond which it was the policy of the legislature not to
      extend limitation any further. Relying on the Consolidated Engineering
      Enterprises (supra), it has been observed, that there is a vital distinction
      between extending time and condoning delay. It was further observed,
      that like Section 34 of the Arbitration Act, the period provided in Section
G     128 of the Customs Act did not lay down a long period for preferring an
      appeal. As such, it would be unduly harsh to exclude the principles
      contained in Section 14 of the Limitation Act. Relying on Consolidated
      Engineering Enterprises (supra) it was observed, that there is a
      difference between exclusion of a certain period altogether under
H     principles of Section 14 and condoning the delay. It has been observed,
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           723
                  [B.R. GAVAI, J. ]

that when a certain period is excluded by applying the principles contained   A
in Section 14, there is no delay to be attributed to the appellant and the
limitation period provided by the statute concerned, continues to be the
stated period and not more than the stated period. It was therefore held,
that the principle of section 14, which is a principle based on advancing
the cause of justice would certainly apply to exclude time taken in
                                                                              B
prosecuting proceedings which are bona fide and pursued with due
diligence but which end without a decision on the merits of the case.
       54. Coming to the facts of the present case, immediately after
NCLT pronounced its judgment on 28.11.2019 and even before the
certified copy was made available on 18.12.2019, KIAL had filed writ
petition before the Division Bench of the Bombay High Court on                C
11.12.2019 on the principal ground, that the procedure followed by NCLT
was in breach of principles of natural justice. Such a ground could be
legitimately pursued before a writ court. In that sense, it was not a
proceeding before a wrong court, as such. Perusal of the judgment and
order dated 28.1.2020, passed by the Division Bench of the Bombay             D
High Court, which dismissed the writ petition on the ground of availability
of alternate and equally efficacious remedy would reveal, that the said
writ petition was hotly contested between the parties and by an order
running into 32 pages, the Division Bench of the Bombay High Court
dismissed the petition relegating the petitioner therein (i.e. KIAL) to
avail of an alternate remedy available in law.                                E

       55. Perusal of the memo of the writ petition would reveal, that the
petitioner (i.e. KIAL) has specifically averred thus in the petition:
      “2. By way of present Petition seeks to challenge order dated
      28th November 2019 passed by Hon’ble National Company Law               F
      Tribunal – Bench – II, Mumbai (“NCLT”) on Misc. Application
      No.1039 of 2019 filed by the present Petitioner. The NCLT, in
      gross abuse of process of law and in complete disregard of true
      and actual circumstances has proceeded to pass the impugned
      order. The order impugned is passed by bench of two members,
      Hon’ble M.K. Sharawat (Judicial) and Hon’ble Chandra Bhan               G
      Singh (Technical) on 28th November, 2019. However, the matter
      was heard and reserved for orders on 03rd July, 2019, by Hon’ble
      Member, Shri M.K. Sharawat (Judicial). At the relevant point of
      time, when the matter was heard and argued, Hon’ble Chandra
      Bhan Singh (Technical) was not even appointed as Member of              H
724             SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A           NCLT and never had occasion to hear and adjudicate upon the
            Application filed by the Petitioner. It is not just the Application
            filed by the Petitioner but 3 other Applications which are disposed
            off by the common order were not heard by the bench who has
            passed the order. This is not just contrary to law but demonstrate
            that the entire process of passing the orders was in an absolute
B
            mechanical manner. Annexed hereto and marked as EXHIBIT
            “A” is the copy of the order dated 28th November 2019 passed by
            NCLT on Miscellaneous Application No. 1039 of 2019.”
             56. It could therefore be seen, that the petitioner - KIAL has
      specifically stated, that though the application of the petitioner was heard
C     by a Member (Judicial), the order was passed by a Division Bench
      consisting of Member (Judicial) as well as Member (Technical). Perusal
      of the grounds would further reveal, that a specific ground has been
      taken, that the procedure adopted by NCLT was in breach of principles
      of natural justice.
D            57. It will also be relevant to refer to paragraph 14 of the Memo
      of the writ petition, which reads thus:
            “14. The Petitioner submits that the Petitioner has alternate remedy
            of filing of Appeal before the Hon’ble NCLAT. However, the
            issue involved in present Writ Petition is not just about the merits
E           of the impugned order, but also in respect of functioning of the
            Tribunal and the manner in which Tribunal deals with the matters.
            These Tribunals come under supervisory control of jurisdictional
            High Court i.e. this Hon’ble Court. The issue involved is not in
            respect of this matter but also in respect of day to day functioning
F           of the Tribunal and the manner in which such issues are being
            dealt with by the Tribunal. Therefore, Petitioner is exercising Writ
            Jurisdiction of this Hon’ble Court.”
             58. It could thus clearly be seen, that the petitioner therein i.e.
      KIAL has specifically stated, that though it had an alternate remedy of
G     filing an appeal before NCLAT, since the petition was not just about the
      merits of the impugned order, but also in respect of functioning of the
      Tribunal the petitioner was invoking the writ jurisdiction of the Court.
             59. By now, it is a settled principle of law, that non-exercise of
      jurisdiction by the High Court under Article 226 of the Constitution is not
      a hard and fast rule, but a rule of self-restraint. As early as in 1969, in
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            725
                  [B.R. GAVAI, J. ]

the case of Babu Ram Prakash Chandra Maheshwari (supra), this                  A
Court observed thus:
      “It is a well-established proposition of law that when an alternative
      and equally efficacious remedy is open to a litigant he should be
      required to pursue that remedy and not to invoke the special
      jurisdiction of the High Court to issue a prerogative writ. It is true   B
      that the existence of a statutory remedy does not affect the
      jurisdiction of the High Court to issue a writ. But, as observed by
      this Court in Rashid Ahmed v. The Municipal Board, Kairana
      [(1950) SCR 566], “the existence of an adequate legal remedy is
      a thing to be taken into consideration in the matter of granting
      writs” and where such a remedy exists it will be a sound exercise        C
      of discretion to refuse to interfere in a writ petition unless there
      are good grounds therefore. But it should be remembered that the
      rule of exhaustion of statutory remedies before a writ is granted
      is a rule of self imposed limitation, a rule of policy, and discretion
      rather than a rule of law and the court may therefore in exceptional     D
      cases issue a writ such as a writ of certiorari notwithstanding the
      fact that the statutory remedies have not been exhausted.”
       60. This Court further laid down two well recognized exceptions
to the doctrine with regard to the exhaustion of statutory remedies, which
reads thus:                                                                    E
      “There are at least two well-recognised exceptions to the doctrine
      with regard to the exhaustion of statutory remedies. In the first
      place, it is well-settled that where proceedings are taken before a
      Tribunal under a provision of law, which is ultra vires, it is open to
      a party aggrieved thereby to move the High Court under Art.              F
      226 for issuing appropriate writs for quashing them on the ground
      that they are incompetent, without his being obliged to wait until
      those proceedings run their full course.—(See the decisions of
      this Court in Carl Still G.m.b.H. v. The State of Bihar [A.I.R.
      1961 S.C. 1615] and The Bengal Immunity Co. Ltd. v. The State
      Bihar [(1955) 2 S.C.R. 603]. In the second place, the doctrine           G
      has no application in a case where the impugned order has been
      made in violation of the principles of natural justice (See The State
      of Uttar Pradesh v. Mohammad Nooh [(1958) S.C.R. 595].”
      61. It has been clearly held, that when the proceedings invoked
before a statutory authority are de hors the jurisdiction or when they are     H
726             SUPREME COURT REPORTS                            [2021] 2 S.C.R.


A     in breach of principles of natural justice, the party would be entitled to
      invoke the jurisdiction of the High Court under Article 226 of the
      Constitution.
           62. Referring to earlier judgments, this Court in the case of
      Whirlpool Corporation (supra) observed thus:
B           “15. Under Article 226 of the Constitution, the High Court, having
            regard to the facts of the case, has a discretion to entertain or not
            to entertain a writ petition. But the High Court has imposed upon
            itself certain restrictions one of which is that if an effective and
            efficacious remedy is available, the High Court would not normally
C           exercise its jurisdiction. But the alternative remedy has been
            consistently held by this Court not to operate as a bar in at least
            three contingencies, namely, where the writ petition has been filed
            for the enforcement of any of the Fundamental Rights or where
            there has been a violation of the principle of natural justice or
            where the order or proceedings are wholly without jurisdiction or
D           the vires of an Act is challenged. There is a plethora of case-law
            on this point but to cut down this circle of forensic whirlpool, we
            would rely on some old decisions of the evolutionary era of the
            constitutional law as they still hold the field.”
            63. A similar view has been reiterated in the judgment of this
E     Court in the case of Nivedita Sharma vs. Cellular Operators
      Association of India (supra).
              64. In the present case, perusal of the writ petition would reveal,
      that it was the specific case of KIAL, that its application, objecting to
      the application of RP for approval of the resolution plan was heard by a
F     Member (Judicial), whereas, the final orders were passed by a Bench
      consisting of Member (Judicial) and Member (Technical). It has
      specifically averred, that though an alternate remedy was available to it,
      it was invoking the jurisdiction of the High Court since the question
      involved was also with regard to the manner in which the jurisdiction
      was exercised by NCLT. It could thus be seen, that KIAL was bona
G
      fide prosecuting the proceedings before the High Court in good faith.
      Perusal of the dates referred to herein above would also reveal, that
      KIAL was prosecuting the proceedings before the High Court with due
      diligence. Even before the availability of the certified copy, it had knocked
      the doors of the High Court. The matter before the High Court was
H     hotly contested and ultimately, the petition was dismissed by an elaborate
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            727
                  [B.R. GAVAI, J. ]

judgment relegating KIAL to the alternate remedy available to it in law.       A
As such, the conditions which enable a party to invoke the provisions of
Section 14 of the Limitation Act are very much available to KIAL. If the
period during which KIAL was bona fide prosecuting the writ petition
before the High Court and that too with due diligence, is excluded applying
the principles underlying Section 14 of the Limitation Act, the appeals
                                                                               B
filed before NCLAT would be very much within the limitation. We find,
that KIAL would be entitled to exclusion of the period during which it
was bona fide prosecuting the remedy before the High Court with due
diligence.
       65. That leaves us to consider the judgments referred to by the
appellants on the issue of limitation.                                         C
       66. In the case of Popular Construction Co. (supra) this Court
was considering the question as to whether the provisions of Section 5
of the Limitation Act are applicable to an application challenging an award
under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter
referred to as “the Arbitration Act”). This Court observed thus:               D
       “14. Here the history and scheme of the 1996 Act support the
       conclusion that the time-limit prescribed under Section 34 to
       challenge an award is absolute and unextendible by court under
       Section 5 of the Limitation Act. The Arbitration and Conciliation
       Bill, 1995 which preceded the 1996 Act stated as one of its main        E
       objectives the need “to minimise the supervisory role of courts in
       the arbitral process” [ Para 4(v) of the Statement of Objects and
       Reasons of the Arbitration and Conciliation Act, 1996]. This
       objective has found expression in Section 5 of the Act which
       prescribes the extent of judicial intervention in no uncertain terms:
           ‘5. Extent of judicial intervention.—Notwithstanding                F
           anything contained in any other law for the time being in force,
           in matters governed by this Part, no judicial authority shall
           intervene except where so provided in this Part.’ “
       67. It must be noticed, that the judgment in the case of Popular
Construction Co. (supra) was considered by this Court by a Bench               G
consisting of three Judges in the case of Consolidated Engineering
Enterprises (supra) wherein, the question with regard to applicability of
Section 14 of the Limitation Act to an application under Section 34(3) of
the Arbitration Act fell for consideration. In Consolidated Engineering
Enterprises (supra), the appellant before this Court was an enterprise
                                                                               H
728            SUPREME COURT REPORTS                          [2021] 2 S.C.R.


A     engaged in civil engineering construction as well as development of
      infrastructure. It entered into an agreement with the respondent for
      construction of earthen bund, head sluices and the draft channel of the
      Y.G. Gudda tank. A dispute arose between the parties and therefore, the
      appellant invoked arbitration Clause 51 of the agreement. The dispute
      was referred to the sole arbitrator who passed his award in favour of
B
      the appellant. Feeling aggrieved by the said award, the respondents
      preferred an application to set aside the said award as provided by
      Section 34 of the Arbitration Act in the Court of the Civil Judge (Senior
      Division), Ramanagaram, Bangalore Rural District, Bangalore. However,
      it was realised by the respondents, that an application for setting aside
C     the award should have been filed before the Principal District Judge,
      Bangalore District (Rural). As such, an application was preferred by the
      respondents in the Court of the Civil Judge (Senior Division),
      Ramanagaram with a request to transfer the application made for setting
      aside the award to the Court of the Principal District Judge (Rural),
      Bangalore.
D
            68. The Civil Judge (Senior Division), Ramanagaram passed an
      order directing return of the suit records for presentation before the
      proper court. The respondents therefore collected the papers from the
      Court of the Civil Judge (Senior Division), Ramanagaram and presented
      the same in the Court of the Principal District Judge, Bangalore (Rural).
E     The District Court framed a preliminary issue, as to whether the suit
      was barred by the limitation under Section 34(3) of the Arbitration Act.
      The District Judge held, the application for setting aside the award to be
      time-barred. The respondents invoked the appellate jurisdiction of the
      High Court of Karnataka at Bangalore. The Division Bench of the
F     Karnataka High Court held, that the District Judge, Bangalore had
      committed an error in holding, that Section 14 of the Limitation Act was
      not applicable to an application submitted under Section 34 of the Act. It
      was therefore held, that the time taken during which the respondents
      had been prosecuting in the Court of the Civil Judge (Senior Division),
      Ramanagaram was excludable.
G
            69. Feeling aggrieved, the appellant had approached this Court.
      Panchal, J. speaking for himself and Balakrishna, C.J. (as their Lordships
      then were) observed thus:
            “27. The contention that in view of the decision of the Division
            Bench of this Court in Union of India v. Popular Construction
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                             729
                  [B.R. GAVAI, J. ]

    Co. [(2001) 8 SCC 470] the Court should hold that the provisions            A
    of Section 14 of the Limitation Act would not apply to an application
    filed under Section 34 of the Act, is devoid of substance. In the
    said decision what is held is that Section 5 of the Limitation Act is
    not applicable to an application challenging an award under Section
    34 of the Act. Section 29(2) of the Limitation Act inter alia provides
                                                                                B
    that where any special or local law prescribes, for any application,
    a period of limitation different from the period prescribed by the
    Schedule, the provisions contained in Sections 4 to 24 shall apply
    only insofar as, and to the extent to which, they are not expressly
    excluded by such special or local law. On introspection, the Division
    Bench of this Court held that the provisions of Section 5 of the            C
    Limitation Act are not applicable to an application challenging an
    award. This decision cannot be construed to mean as ruling that
    the provisions of Section 14 of the Limitation Act are also not
    applicable to an application challenging an award under Section
    34 of the Act. As noticed earlier, in the Act of 1996, there is no          D
    express provision excluding application of the provisions of Section
    14 of the Limitation Act to an application filed under Section 34 of
    the Act for challenging an award.
    28. Further, there is fundamental distinction between the discretion
    to be exercised under Section 5 of the Limitation Act and exclusion         E
    of the time provided in Section 14 of the said Act. The power to
    excuse delay and grant an extension of time under Section 5 is
    discretionary whereas under Section 14, exclusion of time is
    mandatory, if the requisite conditions are satisfied. Section 5 is
    broader in its sweep than Section 14 in the sense that a number of
    widely different reasons can be advanced and established to show            F
    that there was sufficient cause in not filing the appeal or the
    application within time. The ingredients in respect of Sections 5
    and 14 are different. The effect of Section 14 is that in order to
    ascertain what is the date of expiration of the “prescribed period”,
    the days excluded from operating by way of limitation, have to be           G
    added to what is primarily the period of limitation prescribed. Having
    regard to all these principles, it is difficult to hold that the decision
    in Popular Construction Co. [(2001) 8 SCC 470] rules that the
    provisions of Section 14 of the Limitation Act would not apply to
    an application challenging an award under Section 34 of the Act.”
                                                                                H
730             SUPREME COURT REPORTS                            [2021] 2 S.C.R.


A            70. This Court clearly held, that the decision in the case of the
      Popular Construction Co. (supra) cannot be construed to mean as a
      ruling, that provisions of Section 14 of the Limitation Act are also not
      applicable to an application challenging an award under Section 34 of
      the Act. It has been held, that in the Arbitration Act, there is no express
      provision excluding application of the provisions of Section 14 of the
B
      Limitation Act to an application filed under Section 34 of the Arbitration
      Act for challenging the award. It has further been found, that there is
      fundamental distinction between the discretion to be exercised under
      Section 5 of the Limitation Act and exclusion of the time provided in
      Section 14 of the said Act. It was held, that the power to excuse delay
C     and grant an extension of time under Section 5 is discretionary, whereas
      under Section 14, exclusion of time is mandatory, if the requisite conditions
      are satisfied. It held, that the effect of Section 14 is that in order to
      ascertain what is the date of expiration of the “prescribed period”, the
      days excluded from operating by way of limitation, have to be added to
      what is primarily the period of limitation prescribed.
D
           71. Raveendran, J. (as His Lordship then was) in his concurring
      judgment observed thus:
            “54. On the other hand, Section 14 contained in Part III of the
            Limitation Act does not relate to extension of the period of limitation,
E           but relates to exclusion of certain period while computing the period
            of limitation. Neither sub-section (3) of Section 34 of the AC Act
            nor any other provision of the AC Act exclude the applicability of
            Section 14 of the Limitation Act to applications under Section
            34(1) of the AC Act. Nor will the proviso to Section 34(3) exclude
            the application of Section 14, as Section 14 is not a provision for
F           extension of period of limitation, but for exclusion of certain period
            while computing the period of limitation. Having regard to Section
            29(2) of the Limitation Act, Section 14 of that Act will be applicable
            to an application under Section 34(1) of the AC Act. Even when
            there is cause to apply Section 14, the limitation period continues
G           to be three months and not more, but in computing the limitation
            period of three months for the application under Section 34(1) of
            the AC Act, the time during which the applicant was prosecuting
            such application before the wrong court is excluded, provided the
            proceeding in the wrong court was prosecuted bona fide, with
            due diligence. Western Builders [(2006) 6 SCC 239] therefore
H           lays down the correct legal position.”
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            731
                   [B.R. GAVAI, J. ]

      72. In paragraph 57, Raveendran, J. also observed, that the decision      A
in Popular Construction Co. (supra) did not consider the applicability
of Section 14 of the Limitation Act to an application under Section 34 of
the Arbitration Act.
       73. As such, in view of the judgment of three Judges Bench of
this Court in the case of Consolidated Engineering Enterprises (supra),         B
the reliance placed by the appellants on the judgment of this Court in
Popular Construction Co. (supra) would not be of any assistance.
       74. Reliance is also placed on the judgment of this Court in the
case of Singh Enterprises (supra) wherein, the question raised was
with regard to applicability of the provisions of Section 5 of the Limitation   C
Act to an appeal filed under Section 35 of the Central Excise Act, 1944.
Again, the said judgment deals with applicability of Section 5 and not of
Section 14 of the Limitation Act and therefore would not support the
case of the appellants.
       75. Similarly, reliance placed by the learned counsel for the
                                                                                D
appellants on the judgment of this Court in the case of Commissioner
of Customs and Central Excise vs. Hongo India Private Limited
and another33, would also not help the appellants inasmuch as, the
question, that fell for consideration there was, with regard to the
applicability of Section 5 of the Limitation Act to a reference application
provided under Section 35-H(1) of the unamended Central Excise Act,             E
1944.
       76. For the same reasons, the judgment of this Court in the case
of Chhattisgarh State Electricity Board (supra) would also not take
the case of the appellants any further inasmuch as, again the question,
that fell for consideration was, with regard to applicability of Section 5      F
of the Limitation Act to an appeal under Section 125 of the Electricity
Act, 2003.
       77. For the same reasons, we find, that the judgment relied on by
the appellants in the case of Bengal Chemists and Druggists
Association vs. Kalyan Chowdhury34 would also not be applicable to
                                                                                G
the facts of the present case inasmuch as, the said judgment also
considered the applicability of Section 5 of the Limitation Act to an appeal
to the Appellate Tribunal provided under Section 421(3) and 433 of the
Companies Act, 2013.
33
     (2009) 5 SCC 791
34
     (2018) 3 SCC 41                                                            H
732             SUPREME COURT REPORTS                             [2021] 2 S.C.R.


A            78. The judgment of this Court in the case of Neeraj Jhanji
      (supra) would not be applicable to the facts of the present case. In the
      said case, the petitioner had initially filed a writ petition before the Delhi
      High Court against the order-in-original passed by the Commissioner of
      Customs, Kanpur. Delhi High Court converted the writ petition into a
      statutory appeal under the Customs Act, 1962 by order dated 9-11-2009.
B
      On 9-9-2010 the Revenue raised an objection about the territorial
      jurisdiction of that Court. On 5-1-2012 the petitioner withdrew the appeal
      with liberty to approach the jurisdictional High Court and then filed a
      statutory appeal before the Allahabad High Court after a delay of 697
      days. It will be relevant to refer to the following observations in Neeraj
C     Jhanji (supra):
             “3. The very filing of writ petition by the petitioner in the Delhi
             High Court against the order-in-original passed by the
             Commissioner of Customs, Kanpur indicates that the petitioner
             took a chance in approaching the High Court at Delhi which had
D            no territorial jurisdiction in the matter. We are satisfied that filing
             of the writ petition or for that matter, appeal before the Delhi
             High Court was not at all bona fide. We are in agreement with the
             observations made by the Allahabad High Court in the impugned
             order [Neeraj Jhanji v. CCE & Customs, Custom Appeal
             Defective 16 of 2012, order dated 6-8-2012 (All)]. The Allahabad
E            High Court has rightly dismissed the petitioner’s application of
             condonation of delay and consequently the appeal as time barred.”
             79. It is thus clear, that this Court found, that the petitioner therein
      had adopted tactics of taking chances by approaching High Court of
      Delhi, which had no territorial jurisdiction. As such, it was found, that
F     neither the writ petition nor the appeal before the Delhi High Court could
      be construed to be a bona fide. It was further noticed, that there was
      an inordinate delay of 697 days. It is thus apparent, that the petitioner
      therein had not satisfied the necessary conditions for applicability of
      Section 14.
G            80. In the present case, as already discussed herein above, the
      petitioner was bona fide prosecuting his remedy before the High Court
      and that too with due diligence. As such, the said judgment also would
      be of no avail to the case of the appellants.
            81. The judgment of this Court in the case of Ketan V. Parekh
H     (supra) is relied upon by both the parties. The question, that arose for
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                             733
                   [B.R. GAVAI, J. ]

consideration in the said case was with regard to applicability of Section       A
14 of the Limitation Act to an Appeal from Order of an Appellate Tribunal
as provided under Section 35 of the Foreign Exchange Management
Act, 1999. This Court relying on the earlier judgment in the case of
Consolidated Engineering Enterprises (supra) and State of
Goa vs. Western Builders35 held, that Section 14 can be invoked in an
                                                                                 B
appropriate case for exclusion of the time, during which the aggrieved
person may have prosecuted with due diligence a remedy before a wrong
forum. However, on facts and on the averments made in the pleadings,
this Court came to the conclusion, that there was not even a whisper in
the applications filed by the appellants, that they had been prosecuting
remedy before a wrong forum i.e. the Delhi High Court with due diligence         C
and in good faith. It will be relevant to refer to the following paragraphs
of the said judgment.
          “32. There is another reason why the benefit of Section 14 of the
          Limitation Act cannot be extended to the appellants. All of them
          are well conversant with various statutory provisions including        D
          FEMA. One of them was declared a notified person under Section
          3(2) of the Special Court (Trial of Offences Relating to
          Transactions in Securities) Act, 1992 and several civil and criminal
          cases are pending against him. The very fact that they had engaged
          a group of eminent advocates to present their cause before the
          Delhi and the Bombay High Courts shows that they have the              E
          assistance of legal experts and this seems to be the reason why
          they invoked the jurisdiction of the Delhi High Court and not of
          the Bombay High Court despite the fact that they are residents of
          Bombay and have been contesting other matters including the
          proceedings pending before the Special Court at Bombay. It also        F
          appears that the appellants were sure that keeping in view their
          past conduct, the Bombay High Court may not interfere with the
          order of the Appellate Tribunal. Therefore, they took a chance
          before the Delhi High Court and succeeded in persuading the
          learned Single Judge of the Court to entertain their prayer for
          stay of further proceedings before the Appellate Tribunal. The         G
          promptness with which the learned Senior Counsel appearing for
          the appellant, Kartik K. Parekh made a statement before the Delhi
          High Court on 7-11-2007 that the writ petition may be converted
          into an appeal and considered on merits is a clear indication of the
35
     (2006) 6 SCC 239                                                            H
734             SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A           appellant’s unwillingness to avail remedy before the High Court
            i.e. the Bombay High Court which had the exclusive jurisdiction
            to entertain an appeal under Section 35 of the Act.
            33. It is not possible to believe that as on 7-11-2007, the appellants
            and their advocates were not aware of the judgment of this Court
B           in Ambica Industries v. CCE [(2007) 6 SCC 769] whereby
            dismissal of the writ petition by the Delhi High Court on the ground
            of lack of territorial jurisdiction was confirmed and it was observed
            that the parties cannot be allowed to indulge in forum shopping. It
            has not at all surprised us that after having made a prayer that the
            writ petitions filed by them be treated as appeals under Section
C           35, two of the appellants filed applications for recall of that order.
            No doubt, the learned Single Judge accepted their prayer and the
            Division Bench confirmed the order of the learned Single Judge
            but the manner in which the appellants prosecuted the writ petitions
            before the Delhi High Court leaves no room for doubt that they
D           had done so with the sole object of delaying compliance with the
            direction given by the Appellate Tribunal and by no stretch of
            imagination it can be said that they were bona fide prosecuting
            remedy before a wrong forum. Rather, there was total absence
            of good faith, which is sine qua non for invoking Section 14 of the
            Limitation Act.”
E
             82. It is thus clear, that the appellants therein were indulging into
      a practice of taking chances. They had approached Delhi High Court,
      which totally lacked territorial jurisdiction and had not approached Bombay
      High Court though they were residents of Bombay and had been
      contesting other matters including the proceedings pending before the
F     Special Court at Bombay. It has been observed, that keeping in view
      their past conduct, Bombay High Court might not have interfered with
      the order of the Appellate Tribunal. Therefore, they took a chance before
      Delhi High Court and succeeded in persuading the learned Single Judge
      of that Court to entertain their prayer for stay of further proceedings
G     before the Appellate Tribunal. This Court further observed, that the
      promptness with which the statement was made on behalf of the
      appellants, that the writ petition may be converted into an appeal was a
      clear indication of the appellant’s unwillingness to avail remedy before
      the High Court of Bombay which had the exclusive jurisdiction to entertain
      an appeal under Section 35 of the Act.
H
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           735
                   [B.R. GAVAI, J. ]

       83. In the present case, the facts are totally contrary. KIAL had       A
approached the High Court of Bombay making a specific grievance,
that NCLT had adopted a procedure which was in breach of the principles
of natural justice. It is specifically mentioned in the writ petition, that
though an alternate remedy was available to it, it was approaching the
High Court since the issue with regard to functioning of NCLT also fell
                                                                               B
for consideration. The proceedings before the High Court were hotly
contested and by an elaborate judgment, the High Court dismissed the
writ petition relegating the petitioner therein i.e. KIAL to an alternate
remedy available in law. It is thus apparently clear, that KIAL was bona
fide prosecuting a remedy before the High Court in good faith and with
due diligence. In a given case, the High Court could have exercised            C
jurisdiction under Article 226 of the Constitution inasmuch as, the
grievance was regarding procedure followed by NCLT to be in breach
of principles of natural justice. That would come within the limited area
earmarked by this Court for exercise of extraordinary jurisdiction under
Article 226 despite availability of an alternate remedy.
                                                                               D
      84. This Court recently in the judgment of Embassy Property
Developments Pvt. Ltd. vs. State of Karnataka and Others36 had an
occasion to consider a similar issue. We find it apposite to refer to the
question framed by this Court, which reads thus:
          “i) Whether the High Court ought to interfere, under Article 226/    E
          227 of the Constitution, with an order passed by the National
          Company Law Tribunal in a proceeding under the Insolvency and
          Bankruptcy Code, 2016, ignoring the availability of a statutory
          remedy of appeal to the National Company Law Appellate Tribunal
          and if so, under what circumstances.”
                                                                               F
          85. It will also be apposite to reproduce the answer given by this
Court.
          “47. Therefore, in fine, our answer to the first question would be
          that NCLT did not have jurisdiction to entertain an application
          against the Government of Karnataka for a direction to execute       G
          Supplemental Lease Deeds for the extension of the mining lease.
          Since NCLT chose to exercise a jurisdiction not vested in it in
          law, the High Court of Karnataka was justified in entertaining the
          writ petition, on the basis that NCLT was coram non judice.”
36
     2019 SCC Online 1542                                                      H
736             SUPREME COURT REPORTS                            [2021] 2 S.C.R.


A            We therefore have no hesitation to hold, that KIAL was entitled
      to extension of the period during which it was bona fide prosecuting a
      remedy before the High Court with due diligence.
         (ii) WHETHER THERE WAS WAIVER AND
      ACQUIESCENCE BY KIAL SO AS TO ESTOP IT FROM
B     CHALLENGING THE PARTICIPATION OF KALPRAJ?
              86. It is strenuously urged on behalf of the appellants, that under
      clause 10.4 of the Process Memorandum, if any Resolution Plan is
      received by RP from any eligible applicant(s) at any stage of the Resolution
      Plan Process, RP is free to examine any resolution plan with the approval
C     of CoC and the applicant will not have any right to object to the submission
      or consideration of such plan. It is further submitted, that even under
      clause 11.2 of the Process Memorandum, RP or CoC, at their sole
      discretion, may request for additional information/documents and/or seek
      clarification from the resolution applicant after the due date for submission
      of the plan. It is further submitted, that delay in submission of additional
D
      information and/or documents sought by RP, CoC or the Process Manager
      would entitle RP, CoC or the Process Manager to reject the resolution
      plan.
              87. It was further submitted by the appellants, that KIAL, in a
      letter submitted along with the resolution plan to RP, had expressly waived
E
      any and all claims with respect to the Resolution Plan Process. Not only
      that, but KIAL had submitted its revised plans twice after Kalpraj was
      permitted to participate in the proceedings. It is therefore submitted, that
      since KIAL had expressly waived all its claims and had also submitted
      its revised plans, after Kalpraj entered into the fray, it was not entitled to
F     raise any grievance. It is submitted, that the principles of waiver and
      acquiescence are squarely applicable in the present case. It was also
      submitted on behalf of the appellants, that the revised plans, submitted
      by KIAL, were submitted without mentioning, that it was without prejudice
      and as such, it was not entitled to make any grievance on that count.
G            88. It is submitted, that the approach adopted by KIAL amounted
      to taking chances, as after having failed in the process, challenging the
      same would not be permissible in law. It is also contended that during
      the 12th meeting of CoC, Kotak Bank, of which KIAL is a 100%
      subsidiary, also agreed with CoC counsel’s view, that Kalpraj’s resolution
      plan can be considered.
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            737
                  [B.R. GAVAI, J. ]

      89. It could thus be seen, that the main thrust of the arguments         A
advanced on behalf of the appellants with regard to waiver and
acquiescence is on two grounds, viz., (i) clause 10.4 of the Process
Memorandum read with paragraph 5(b) of the covering letter for
submission of resolution plan by KIAL, and (ii) participation of KIAL in
the process after Kalpraj was permitted to participate in the process.
                                                                               B
      90. We may refer to clause 10.4 of the Process Memorandum
and paragraph 5(b) of the covering letter for submission of resolution
plan by KIAL, which read thus:
      Clause 10.4 of the Process Memorandum
      “if any Resolution Plan is received by the Resolution professional       C
      from any eligible Applicant(s) at any stage of the Resolution Plan
      Process, the Resolution professional shall be free to examine such
      Resolution Plan with the approval of the Committee of Creditors
      and the Applicant(s) will not have any right to object to submission
      or consideration of such plan.”                                          D
      Paragraph 5(b) of the covering letter for submission of
resolution plan by KIAL.
      “5. We further represent and confirm as follows:
      (a) …..
                                                                               E
      (b) Acceptance
      We hereby unconditionally and irrevocably agree and accept the
      terms of the Process Memorandum and that the decision made
      by the CoC, Resolution professional and/or the Adjudicating
      Authority in respect of any matter with respect to, or arising out       F
      of, the Process Memorandum and the Resolution Plan Process
      shall be binding on us. We hereby expressly waive any and all
      claims in respect of the Resolution Plan Process.”
        91. On the basis of clause 10.4, it is sought to be urged, that even
if the Resolution Plan is received by RP from any eligible applicant(s) at     G
any stage of the Resolution Plan Process, RP was free to examine such
Resolution Plan with the approval of CoC and the applicant(s) will not
have any right to object to submission or consideration of such plan.
     92. On the basis of paragraph 5(b) of the covering letter for
submission of resolution plan by KIAL, it is sought to be urged, that          H
738                SUPREME COURT REPORTS                             [2021] 2 S.C.R.


A     KIAL had unconditionally and irrevocably agreed and accepted the terms
      of the Process Memorandum and the decision made by CoC, RP and/or
      the Adjudicating Authority in respect of any matter with respect to, or
      arising out of, the Process Memorandum and the Resolution Plan
      Process. It is further sought to be urged, that KIAL had agreed to
      surrender all and any of its claim in respect of the Resolution Plan Process.
B
      It is sought to be urged, that this stipulation amounts to a concluded
      contract between the parties and having waived its all claims, KIAL is
      not permitted in law to challenge the participation of Kalpraj in respect
      of Resolution Plan Process.
            93. In this respect, it will be relevant to refer to paragraphs 89 and
C     90 of the judgment of this Court in the case of Central Inland Water
      Transport Corporation Limited and another vs. Brojo Nath Ganguly
      and another37.
                “89. Should then our courts not advance with the times? Should
                they still continue to cling to outmoded concepts and outworn
D               ideologies? Should we not adjust our thinking caps to match the
                fashion of the day? Should all jurisprudential development pass us
                by, leaving us floundering in the sloughs of 19th century theories?
                Should the strong be permitted to push the weak to the wall?
                Should they be allowed to ride roughshod over the weak? Should
E               the courts sit back and watch supinely while the strong trample
                underfoot the rights of the weak? We have a Constitution for our
                country. Our judges are bound by their oath to “uphold the
                Constitution and the laws”. The Constitution was enacted to secure
                to all the citizens of this country social and economic justice. Article
                14 of the Constitution guarantees to all persons equality before
F               the law and the equal protection of the laws. The principle
                deducible from the above discussions on this part of the case is in
                consonance with right and reason, intended to secure social and
                economic justice and conforms to the mandate of the great equality
                clause in Article 14. This principle is that the courts will not enforce
G               and will, when called upon to do so, strike down an unfair and
                unreasonable contract, or an unfair and unreasonable clause in a
                contract, entered into between parties who are not equal in
                bargaining power. It is difficult to give an exhaustive list of all
                bargains of this type. No court can visualize the different situations

H     37
           (1986) 3 SCC 156
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           739
                  [B.R. GAVAI, J. ]

      which can arise in the affairs of men. One can only attempt to          A
      give some illustrations. For instance, the above principle will apply
      where the inequality of bargaining power is the result of the great
      disparity in the economic strength of the contracting parties. It
      will apply where the inequality is the result of circumstances,
      whether of the creation of the parties or not. It will apply to
                                                                              B
      situations in which the weaker party is in a position in which he
      can obtain goods or services or means of livelihood only upon the
      terms imposed by the stronger party or go without them. It will
      also apply where a man has no choice, or rather no
      meaningful choice, but to give his assent to a contract or to
      sign on the dotted line in a prescribed or standard form or to          C
      accept a set of rules as part of the contract, however unfair,
      unreasonable and unconscionable a clause in that contract
      or form or rules may be. This principle, however, will not apply
      where the bargaining power of the contracting parties is equal or
      almost equal. This principle may not apply where both parties are
                                                                              D
      businessmen and the contract is a commercial transaction. In
      today’s complex world of giant corporations with their vast
      infrastructural organizations and with the State through its
      instrumentalities and agencies entering into almost every branch
      of industry and commerce, there can be myriad situations which
      result in unfair and unreasonable bargains between parties              E
      possessing wholly disproportionate and unequal bargaining power.
      These cases can neither be enumerated nor fully illustrated. The
      court must judge each case on its own facts and circumstances.”
                                                    [emphasis supplied]
       94. This Court has held, that the courts will not enforce and will,    F
when called upon to do so, strike down an unfair and unreasonable
contract, or an unfair and unreasonable clause in a contract, entered into
between parties who are not equal in bargaining power. It has been held,
that this principle will apply where a man has no choice, or rather no
meaningful choice, but to give his assent to a contract or to sign on the     G
dotted line in a prescribed or standard form or to accept a set of rules as
part of the contract, however unfair, unreasonable and unconscionable a
clause in that contract or form or rules may be.
     95. Applying the said principles to the facts of the present case,
KIAL had no choice than to accept the terms of the contract. Paragraph        H
740                SUPREME COURT REPORTS                         [2021] 2 S.C.R.


A     5(b) of the letter is a part of a covering letter format, which is provided
      in the Process Memorandum itself. The covering letter is in Format I
      and the party desiring to participate in the Resolution Plan Process has
      no other option, than to sign the dotted lines. Hence, the parties cannot
      be said to have equal bargaining power and the applicants have no other
      choice than to sign on the documents prescribed in the format. Paragraph
B
      5(b) of the covering letter format, requires a party to undertake, that it
      will accept all the decisions made by CoC, RP and/or the Adjudicating
      Authority and that the decisions taken will be binding on it. It also requires
      the applicant, to sign on the document thereby, providing expressly
      waiving any and all claims with respect to the Resolution Plan Process.
C     In turn, it provides for a party to agree to a stipulation, that even if RP or
      CoC acts in any manner, which is not permissible in law, still the resolution
      applicant would be bound by such a decision and shall waive any or all
      its claims in respect of the Resolution Plan Process.
            96. The said principle of law has been subsequently followed in
D     various judgments of this Court including the one in the case of Assistant
      General Manager and others vs. Radhey Shyam Pandey38.
            97. No doubt, that this Court in Central Inland Water Transport
      Corporation Limited (supra) has observed, that the principle laid down
      therein may not apply where both parties are businessmen and the
E     contract is a commercial transaction. In the first place, RP and the
      resolution applicant cannot be said to be the contracting parties having
      equal bargaining power. Secondly, since RP functions under the I&B
      Code for discharging the duties bestowed upon him and assisting the
      process for finalization of resolution plan for survival of the Corporate
      Debtor, it cannot be said that it is a purely commercial transaction between
F     RP and the resolution applicant.
             98. It may be argued, that the judgment in the case of Central
      Inland Water Transport Corporation Limited (supra) arose from a
      case involving a statutory corporation, which was an instrumentality of
      State within the meaning of Article 12 of the Constitution. However,
G     recently, this Court in the case of Pioneer Urban Land and
      Infrastructure Limited vs. Govindan Raghavan39 while construing
      the term of contract between a builder and a flat purchaser observed
      thus:
      38
           (2020) 6 SCC 438
H     39
           (2019) 5 SCC 725
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                             741
                  [B.R. GAVAI, J. ]

      “6.8. A term of a contract will not be final and binding if it is         A
      shown that the flat purchasers had no option but to sign on the
      dotted line, on a contract framed by the builder. The contractual
      terms of the agreement dated 8-5-2012 are ex facie one-sided,
      unfair and unreasonable. The incorporation of such one-sided
      clauses in an agreement constitutes an unfair trade practice as
                                                                                B
      per Section 2(1)(r) of the Consumer Protection Act, 1986 since it
      adopts unfair methods or practices for the purpose of selling the
      flats by the builder.”
      99. We see no reason, as to why the said principle should not be
applicable when RP and CoC are acting under the statutory provisions
under the Code.                                                                 C

      100. We are therefore of the view, in light of the law laid down in
Central Inland Water Transport Corporation Limited (supra), KIAL
cannot be held to be bound by such unconscionable clause in the letter,
which is in a prescribed format.
                                                                                D
      101. The second ground raised, with regard to waiver and
acquiescence, is based upon the participation of KIAL in the Resolution
Plan Process after Kalpraj was permitted to participate in the proceedings.
      102. The word ‘waiver’ has been described in Halsbury’s Laws
of England, 4th Edn., Para 1471, which reads thus:                              E
      “1471. Waiver.—Waiver is the abandonment of a right in such a
      way that the other party is entitled to plead the abandonment by
      way of confession and avoidance if the right is thereafter asserted,
      and is either express or implied from conduct. … A person who is
      entitled to rely on a stipulation, existing for his benefit alone, in a   F
      contract or of a statutory provision, may waive it, and allow the
      contract or transaction to proceed as though the stipulation or
      provision did not exist. Waiver of this kind depends upon consent,
      and the fact that the other party has acted on it is sufficient
      consideration. …
                                                                                G
      It seems that, in general, where one party has, by his words or
      conduct, made to the other a promise or assurance which was
      intended to affect the legal relations between them and to be acted
      on accordingly, then, once the other party has taken him at his
      word and acted on it, so as to alter his position, the party who
      gave the promise or assurance cannot afterwards be allowed to             H
742                SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A               revert to the previous legal relationship as if no such promise or
                assurance had been made by him, but he must accept their legal
                relations subject to the qualification which he has himself so
                introduced, even though it is not supported in point of law by any
                consideration.’
B               (See Halsbury’s Laws of England, 4th Edn., Para 1471.)”
             103. In Halsbury’s Laws of England, Vol. 16(2), 4th Edn., Para
      907, it is stated:
                “The expression ‘waiver’ may, in law, bear different meanings.
                The primary meaning has been said to be the abandonment of a
C               right in such a way that the other party is entitled to plead the
                abandonment by way of confession and avoidance if the right is
                thereafter asserted, and is either express or implied from conduct.
                It may arise from a party making an election, for example whether
                or not to exercise a contractual right… Waiver may also be by
D               virtue of equitable or promissory estoppel; unlike waiver arising
                from an election, no question arises of any particular knowledge
                on the part of the person making the representation, and the
                estoppel may be suspensory only… Where the waiver is not
                express, it may be implied from conduct which is inconsistent
                with the continuance of the right, without the need for writing or
E               for consideration moving from, or detriment to, the party who
                benefits by the waiver, but mere acts of indulgence will not amount
                to waiver; nor may a party benefit from the waiver unless he has
                altered his position in reliance on it.”
              104. For considering, as to whether a party has waived its rights
F     or not, it will be relevant to consider the conduct of a party. For establishing
      waiver, it will have to be established, that a party expressly or by its
      conduct acted in a manner, which is inconsistent with the continuance of
      its rights. However, the mere acts of indulgence will not amount to waiver.
      A party claiming waiver would also not be entitled to claim the benefit of
G     waiver, unless it has altered its position in reliance on the same.
            105. As early as in 1957 in the case of Manak Lal vs. Dr. Prem
      Chand40 an advocate was held guilty for professional misconduct by a
      Tribunal of Three Members. The matter was argued before the High
      Court. An objection was taken before the High Court, that one of the
H     40
           1957 SCR 575 = AIR 1957 SC 425
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                             743
                   [B.R. GAVAI, J. ]

members had appeared on behalf of the complainant and therefore, he              A
was disqualified from acting as a member of the Tribunal. A question
arose before this Court, that since such an objection was not taken before
the Tribunal, whether it amounted to waiver. This Court observed thus:
          “It is true that waiver cannot always and in every case be inferred
          merely from the failure of the party to take the objection. Waiver     B
          can be inferred only if and after it is shown that the party knew
          about the relevant facts and was aware of his right to take the
          objection in question. As Sir John Romilly, M.R., has observed
          in Vyvyan v. Vyvyan [(1861) 30 Beav 65, 74 : 54 ER 813, 817]
          “waiver or acquiescence, like election, presupposes that the person
          to be bound is fully cognizant of his rights, and, that being so, he   C
          neglects to enforce them, or chooses one benefit instead of another,
          either, but not both, of which he might claim”.
       106. It has been held, that a waiver cannot always and in every
case be inferred merely from the failure of the party to take the objection.
Waiver can be inferred, only if and after it is shown that the party knew        D
about the relevant facts and was aware of his right to take the objection
in question. The waiver or acquiescence, like election, presupposes, that
the person to be bound is fully cognizant of his rights, and that being so,
he neglects to enforce them, or chooses one benefit instead of another.
       107. As such, for applying the principle of waiver, it will have to       E
be established, that though a party was aware about the relevant facts
and the right to take an objection, he has neglected to take such an
objection.
       108. In the case of Krishna Bahadur vs. Purna Theatre and
others41, the appellant was appointed in the post of messenger-cum-              F
bearer in the establishment of the respondent. A disciplinary proceeding
was initiated against him wherein, he was found guilty and he was
dismissed from service. The Industrial Tribunal set aside the dismissal
with full back wages and compensation. The appellant was permitted to
join his duties but back wages were not paid. He was again retrenched            G
from services and a sum of Rs.9,030/- was paid as retrenchment
compensation, which the appellant was said to have received under
protest. A trade union took the cause of the appellant, inter alia, on the
ground of contravention of Section 25-G of the Industrial Disputes Act,
41
     (2004) 8 SCC 229                                                            H
744             SUPREME COURT REPORTS                            [2021] 2 S.C.R.


A     1947, so also on the ground of insufficiency of the amount of compensation
      paid to the appellant in terms of Section 25-F(b) thereof. An industrial
      dispute was raised before the Assistant Labour Commissioner, which
      failed, whereupon the Industrial Tribunal was approached by the
      appellant. In the meantime, the appellant had also initiated a proceeding
      under Section 33-C(2) of the Industrial Disputes Act, 1947 which ended
B
      in an amicable settlement, according to which, the appellant agreed to
      receive a sum of Rs.39,000/- as full and final settlement.
             109. However, in the proceedings initiated by the trade union, the
      retrenchment was held to be illegal and he was directed to be deemed to
      be in continuous service with all benefits. A writ petition was filed by the
C
      respondent before the High Court. The said writ petition was dismissed
      by the single judge of the High Court, upholding the findings of the Tribunal.
      In an appeal before the Division bench, a plea was taken for the first
      time, that the workman had accepted the amount paid by the employer
      and as such, it amounted to waiver by the workman. The Division Bench
D     allowed the appeal and set aside the award passed by the Tribunal and
      the judgment and order passed by the single judge. Setting aside the
      judgment of the Division Bench, this Court observed thus:
             “9. The principle of waiver although is akin to the principle of
             estoppel; the difference between the two, however, is that whereas
E            estoppel is not a cause of action; it is a rule of evidence; waiver is
             contractual and may constitute a cause of action; it is an agreement
             between the parties and a party fully knowing of its rights has
             agreed not to assert a right for a consideration.
             10. A right can be waived by the party for whose benefit certain
F            requirements or conditions had been provided for by a statute
             subject to the condition that no public interest is involved therein.
             Whenever waiver is pleaded it is for the party pleading the same
             to show that an agreement waiving the right in consideration of
             some compromise came into being. Statutory right, however, may
             also be waived by his conduct.”
G
             110. This Court has thus held, that the principle of waiver although
      is akin to the principle of estoppel; estoppel is not a cause of action and
      is a rule of evidence, whereas waiver is contractual and may constitute
      a cause of action. It is an agreement between the parties and a party
      fully knowing of its rights has agreed not to assert a right for a
H
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                                745
                   [B.R. GAVAI, J. ]

consideration. It is further held, that whenever waiver is pleaded, it is for       A
the party pleading the same to show that an agreement waiving the right
in consideration of some compromise came into being.
        111. This Court in the case of State of Punjab vs. Davinder Pal
Singh Bhullar and others42 had an occasion to consider an issue, as to
when an issue of bias was not raised by the party at the earliest possible,         B
if it is aware of it and knows its right to raise the said issue, would it
amount to waiver or not. This Court while considering the earlier
judgments observed thus:
          “II. Doctrine of waiver
                                                                                    C
                 37. In Manak Lal [AIR 1957 SC 425] this Court held that
          alleged bias of a Judge/official/Tribunal does not render the
          proceedings invalid if it is shown that the objection in that regard
          and particularly against the presence of the said official in question,
          had not been taken by the party even though the party knew about
          the circumstances giving rise to the allegations about the alleged        D
          bias and was aware of its right to challenge the presence of such
          official. The Court further observed that: (SCC p. 431, para 8)
                    “8. … waiver cannot always and in every case be
             inferred merely from the failure of the party to take the
             objection. Waiver can be inferred only if and after it is shown        E
             that the party knew about the relevant facts and was aware of
             his right to take the objection in question.”
                 38. Thus, in a given case if a party knows the material
          facts and is conscious of his legal rights in that matter, but fails to
          take the plea of bias at the earlier stage of the proceedings, it         F
          creates an effective bar of waiver against him. In such facts and
          circumstances, it would be clear that the party wanted to take a
          chance to secure a favourable order from the official/court and
          when he found that he was confronted with an unfavourable order,
          he adopted the device of raising the issue of bias. The issue of          G
          bias must be raised by the party at the earliest. (See Pannalal
          Binjraj v. Union of India [AIR 1957 SC 397] and P.D.
          Dinakaran (1) v. Judges Enquiry Committee [(2011) 8 SCC
          380].)
42
     (2011) 14 SCC 770                                                              H
746      SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A            39. In Power Control Appliances v. Sumeet Machines (P)
      Ltd. [(1994) 2 SCC 448] this Court held as under: (SCC p. 457,
      para 26)
                “26. Acquiescence is sitting by, when another is invading
         the rights…. It is a course of conduct inconsistent with the
B        claim…. It implies positive acts; not merely silence or inaction
         such as involved in laches. … The acquiescence must be such
         as to lead to the inference of a licence sufficient to create a
         new right in the defendant….”
             40. Inaction in every case does not lead to an inference of
C     implied consent or acquiescence as has been held by this Court
      in P. John Chandy & Co. (P) Ltd. v. John P. Thomas [(2002) 5
      SCC 90]. Thus, the Court has to examine the facts and
      circumstances in an individual case.
             41. Waiver is an intentional relinquishment of a right. It
D     involves conscious abandonment of an existing legal right,
      advantage, benefit, claim or privilege, which except for such a
      waiver, a party could have enjoyed. In fact, it is an agreement not
      to assert a right. There can be no waiver unless the person who is
      said to have waived, is fully informed as to his rights and with full
      knowledge about the same, he intentionally abandons them.
E
      (Vide Dawsons Bank Ltd. v. Nippon Menkwa Kabushiki
      Kaisha [(1934-35) 62 IA 100 : AIR 1935 PC 79], Basheshar
      Nath v. CIT [AIR 1959 SC 149], Mademsetty Satyanarayana
      v. G. Yelloji Rao [AIR 1965 SC 1405], Associated Hotels of
      India Ltd. v. S.B. Sardar Ranjit Singh [AIR 1968 SC
F     933], Jaswantsingh Mathurasingh v. Ahmedabad Municipal
      Corpn. [1992 Supp (1) SCC 5], Sikkim Subba Associates v. State
      of Sikkim [(2001) 5 SCC 629 : AIR 2001 SC 2062] and Krishna
      Bahadur v. Purna Theatre [(2004) 8 SCC 229 : 2004 SCC (L&S)
      1086 : AIR 2004 SC 4282].)
G            42. This Court in Municipal Corpn. of Greater
      Bombay v. Dr Hakimwadi Tenants’ Assn. [1988 Supp SCC 55 :
      AIR 1988 SC 233] considered the issue of waiver/acquiescence
      by the non-parties to the proceedings and held: (SCC p. 65, paras
      14-15)
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                               747
                  [B.R. GAVAI, J. ]

                 “14. In order to constitute waiver, there must be                A
          voluntary and intentional relinquishment of a right. The essence
          of a waiver is an estoppel and where there is no estoppel,
          there is no waiver. Estoppel and waiver are questions of conduct
          and must necessarily be determined on the facts of each case.
          …
                                                                                  B
                 15. There is no question of estoppel, waiver or
          abandonment. There is no specific plea of waiver, acquiescence
          or estoppel, much less a plea of abandonment of right. That
          apart, the question of waiver really does not arise in the case.
          Admittedly, the tenants were not parties to the earlier                 C
          proceedings. There is, therefore, no question of waiver of rights
          by Respondents 4-7 nor would this disentitle the tenants from
          maintaining the writ petition.”
              43. Thus, from the above, it is apparent that the issue of
       bias should be raised by the party at the earliest, if it is aware of it   D
       and knows its right to raise the issue at the earliest, otherwise it
       would be deemed to have been waived. However, it is to be kept
       in mind that acquiescence, being a principle of equity must be
       made applicable where a party knowing all the facts of bias, etc.
       surrenders to the authority of the Court/Tribunal without raising
       any objection. Acquiescence, in fact, is sitting by, when another is       E
       invading the rights. The acquiescence must be such as to lead to
       the inference of a licence sufficient to create rights in other party.”
        112. Thus, for constituting acquiescence or waiver it must be
established, that though a party knows the material facts and is conscious
of his legal rights in a given matter, but fails to assert its rights at the      F
earliest possible opportunity, it creates an effective bar of waiver against
him. Whereas, acquiescence would be a conduct where a party is sitting
by, when another is invading his rights. The acquiescence must be such
as to lead to the inference of a licence sufficient to create a new right in
the defendant. Waiver is an intentional relinquishment of a right. It involves    G
conscious abandonment of an existing legal right, advantage, benefit,
claim or privilege. It is an agreement not to assert a right. There can be
no waiver unless the person who is said to have waived, is fully informed
as to his rights and with full knowledge about the same, he intentionally
abandons them.
                                                                                  H
748                SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A            113. In the case of Galada power and Telecommunication
      limited vs. United India Insurance Company Limited and another 43,
      this Court had an occasion to consider the question, as to whether the
      insurer has waived its right on the basis of claim hit by clause relating to
      duration.
B           114. On the facts, holding, that the case was a case of waiver, this
      Court observed thus:
                “18. In the instant case, the insurer was in custody of the policy.
                It had prescribed the clause relating to duration. It was very much
                aware about the stipulation made in Clauses 5(3) to 5(5), but despite
C               the stipulations therein, it appointed a surveyor. Additionally, as
                has been stated earlier, in the letter of repudiation, it only stated
                that the claim lodged by the insured was not falling under the
                purview of transit loss. Thus, by positive action, the insurer has
                waived its right to advance the plea that the claim was not
                entertainable because conditions enumerated in duration clause
D               were not satisfied. In our considered opinion, the National
                Commission could not have placed reliance on the said terms to
                come to the conclusion that there was no policy cover in existence
                and that the risks stood not covered after delivery of goods to the
                consignee.”
E           115. In the background of this legal position, we will have to
      examine, as to whether the conduct of KIAL can be said to be of such
      a nature, which would amount to acquiescence or waiver.
             116. The dates are not in dispute. As per the invitation of EOI
      published on 9.7.2018, the last date for submission of EOI was 8.8.2018.
F     The first Form ‘G’ was also issued on 9.7.2018, according to which, the
      last date for submission of resolution plan was 21.9.2018. KIAL had
      submitted its EOI on 7.8.2018. First Process Memorandum was issued
      on 17.8.2018. However, since there was no response, four more Form
      ‘G’ were issued on various dates. The last of such Form ‘G’ was issued
G     on 11.12.2018, according to which the last date for submission of
      resolution plan was 8.1.2019. KIAL submitted its resolution plan on
      8.1.2019. Subsequently, Kalpraj submitted its resolution plan on 27.1.2019.
              117. On KIAL coming to know about the same, on 29.1.2019
      itself, it had sent an email protesting to RP against acceptance of belated
H     43
           (2016) 14 SCC 161
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            749
                  [B.R. GAVAI, J. ]

resolution plan of Kalpraj. The said email dated 29.1.2019 sent by KIAL        A
to RP reads thus:
      “As you are aware, that the last date for submission of the bids
      for Ricoh India Limited, under the CIRP was 8th January, 2019.
      Consequently, we duly submitted our bid (along with the requisite
      Bid Bond Guarantee) within the said time. However, we are given          B
      to understand that you have been receiving and accepting the
      bids even after the said date, when no extension of time (filing of
      Form ‘G’) was notified.
      This severely jeopardises our position and is against the spirit of
      the code, especially when our Resolution Plan was opened                 C
      immediately (along with the commercials) and subsequently, even
      discussed at length in the meeting of 15th January, 2019, which
      was attended by various stakeholders.
      In this light, we would request you to share with us the requisite
      notification (Form G) towards extension of time for bid submission       D
      at the earliest. However, in the event, such a notification has not
      been made, it would only be logical that all plans submitted after
      8th January, 2019 should be held invalid, more so when our plan
      has now been opened.
      We look forward to your confirmation on the above.”                      E
        118. It could therefore be seen, that immediately within a day of
the submission of the plan by Kalpraj, KIAL objected to the acceptance
of its plan after 8.1.2019, when no extension of time for the same was
notified. It is specifically stated, that the said severely jeopardized its
position and was against the spirit of the Code, especially when KIAL’s        F
resolution plan was opened immediately and discussed at length with
various stakeholders. KIAL has therefore requested for sharing the
requisite information providing for extension of time for bid submission.
It is further stated, that in the event no such notification was issued, all
plans submitted after 8.1.2019 should be held to be invalid.
                                                                               G
      119. After the said email was addressed by KIAL to RP, it received
an email from RP on 30.1.2019. It is stated in the said email dated
30.1.2019, that subsequent to the resolution plan submitted on 8.1.2019,
CoC’s representative and RP had a detailed discussion with its team on
the changes required to be made in the resolution plan. Vide the said
email dated 30.1.2019, KIAL was requested to submit the amended                H
750              SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A     resolution plan by 3 p.m. on 1.2.2019. On 1.2.2019, left with no choice,
      KIAL submitted its revised resolution plan.
              120. On 10.2.2019, KIAL sent another email to RP, which reads
      thus:
              “It has been quite sometime, since we sought from you on your
B             decision to accept another resolution plan well after the expiry of
              the deadline for submission of the same.
              As pointed out earlier, such an action, after opening of our bid and
              having detailed discussions on the same is not only prejudicial to
              our interests but also against the spirit of the IBC code.
C
              The code provides equal treatment to all potential resolution
              applicants within the framework of law and fixes personal
              responsibilities upon COC members and RPs in the event instances
              of discrimination or departure from the established law are found.

D             We would request a quick response to our query from you on the
              subject.”
              121. In the said email dated 10.2.2019 sent by KIAL, it was stated,
      that it has been quite sometime, that it had sought a response from RP
      on his decision to accept another resolution plan well after the expiry of
      the deadline for submission of the same. It was reiterated, that such an
E
      action, after opening of the bids and having detailed discussions on the
      same was not only prejudicial to its interest but against the spirit of the
      I&B Code. It was reiterated, that the I&B Code, provides equal treatment
      to all potential resolution applicants within the framework of law and
      fixes personal responsibilities upon CoC members and RPs in the event
F     of instances of discrimination or departure from the established law.
             122. Perusal of the record would reveal, that RP had replied to
      KIAL by email dated 11.2.2019. It was stated in the said email, that his
      act of acceptance of resolution plans, submitted after the due date, was
      under the overall supervision of CoC and as per the opinion given by
G     CoC’s legal counsel and RP’s legal counsel. It was also submitted, that
      this was in the spirit of value maximisation of assets of the Corporate
      Debtor.
            123. It is in dispute, as to whether RP had again directed KIAL
      and Kalpraj vide email dated 11.2.2019 to submit revised plan. It is asserted
H     on behalf of the KIAL, that such email was received by it, whereas it is
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                              751
                  [B.R. GAVAI, J. ]

denied by RP. In any event, it is not in dispute, that both KIAL and             A
Kalpraj submitted their revised plans on 12.2.2019.
      124. On 13/14.2.2019, the resolution plan of Kalpraj was accepted
by CoC. On 18.2.2019, RP filed M.A. No.691 of 2019 before NCLT for
approval of the resolution plan of Kalpraj. KIAL filed its M.A. No. 1039
of 2019 on 14.3.2019 before the Adjudicating Authority objecting to the          B
approval of resolution plan of Kalpraj.
        125. It could thus be clearly seen, that KIAL had raised its objection
immediately after the Kalpraj submitted its resolution plan. Not only that,
but, it had also reiterated its objection to the participation of Kalpraj.
Insofar as, submission of amended plans is concerned, it had no other            C
option than to submit its revised plan. This is specifically so in view of
clause 11.2, which reads thus:
       “11.2 No change or supplemental information to the Resolution
       Plan shall be accepted after the Resolution Plan Due Date, unless
       agreed otherwise by the Resolution Professional (in consultation          D
       with the Committee of Creditors). The Resolution Professional or
       the CoC may, at their sole discretion, request for additional
       information/document and/or seek clarifications from a Resolution
       Applicant after the Resolution Plan Due Date. Delay in submission
       of additional information and/or documents sought by the
       Resolution Professional, the CoC or the Process Manager shall             E
       make the Resolution Plan liable for rejection.”
      126. It is thus clear that, had KIAL not responded to the email of
RP and submitted its revised plan, it had to run the risk of being out of
fray.
                                                                                 F
       127. Dr. Singhvi, learned Senior Counsel appearing on behalf of
Kalpraj relied on the judgment of this Court in the case of ITC Limited
vs. Blue Coast Hotels Limited and others (supra), wherein it is held,
that even if a debtor has used the word “without prejudice” it has no
significance. However, in the said case, the debtor had acknowledged
the debt even after action was initiated under the Act and even after            G
payment of a smaller sum. In this background, it was held, that the words
“without prejudice” would have no significance. As such, the said case
would not be applicable to the facts of the present case.
     128. Reliance placed on the judgment of this Court in the case of
Tarapore and Company (supra) would also not be of any assistance to              H
752                SUPREME COURT REPORTS                            [2021] 2 S.C.R.


A     the case of the appellants. It will be relevant to refer to the following
      observations of this Court in the said case.
                “Apart from the technical meaning which the expression “without
                prejudice” carries depending upon the context in which it is used,
                in the present case on a proper reading of the correspondence
B               and in the setting in which the term is used, it only means that the
                respondent reserved to itself the right to contend before the
                arbitrator that a dispute raised or the claim made by the contractor
                was not covered by the arbitration clause. No other meaning can
                be assigned to it. An action taken without prejudice to one’s right
                cannot necessarily mean that the entire action can be ignored by
C               the party taking the same.”
             129. That leaves us with the last submission in this regard made
      on behalf of the appellants. It is submitted, that Kotak Bank had
      participated in the 12th meeting of CoC dated 13.1.2019 and agreed to
      consider resolution plan of Kalpraj in view of clause 10.4 of the Process
D     Memorandum. It is submitted, that KIAL was a 100% subsidiary of
      Kotak Bank and as such, its agreement to consider the resolution plan of
      Kalpraj would amount to waiver and acquiescence by KIAL.
              130. This question has been squarely answered by this Court in
      the case of Vodafone International Holdings BV vs. Union of India
E     and another44. It will be apposite to refer to the following observation
      of this Court:
                “257. The legal relationship between a holding company and WOS
                is that they are two distinct legal persons and the holding company
                does not own the assets of the subsidiary and, in law, the
F               management of the business of the subsidiary also vests in its
                Board of Directors. In Bacha F. Guzdar v. CIT [AIR 1955 SC
                74], this Court held that shareholders’ only right is to get dividend
                if and when the company declares it, to participate in the liquidation
                proceeds and to vote at the shareholders’ meeting. Refer also
G               to Carew and Co. Ltd. v. Union of India [(1975) 2 SCC 791]
                and Carrasco Investments Ltd. v. Directorate of Enforcement
                [(1994) 79 Comp Cas 631 (Del)].”
            131. In view of the aforesaid observation, the objection in this
      regard deserves to be rejected.
      44
H          (2012) 6 SCC 613
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           753
                  [B.R. GAVAI, J. ]

       132. Taking into consideration the fact, that KIAL had objected to     A
participation of any other applicant submitting plan after the due date as
per the last Form ‘G’ and also reiterated its objection, we are of the
considered view, that it cannot be held, that having participated by
submitting the revised plans, KIAL is estopped from challenging the
process on the ground of acquiescence and waiver. Merely because,
                                                                              B
the revised plans are not submitted with the words “without prejudice”,
in our view, would not make any difference. As already discussed
hereinabove, KIAL had no other option than to submit its revised plans
in view of clause 11.2 of the Process Memorandum. Inasmuch as, had it
not responded, it had to run the risk of being out of fray. As already
discussed hereinabove, the conduct of the party is relevant for               C
considering, whether it can be held, that a case is made out of waiver or
acquiescence.
       133. None of the appellants have been in a position to establish,
that KIAL had given up/surrendered its rights to take recourse to the
legal remedies. In any case, the appellants had also not been in a position   D
to establish, that on account of any such waiver or acquiescence any of
the appellants had altered their position to their detriment.
      134. As such, it cannot be held, that KIAL had waived or
acquiesced its rights to challenge the decision of RP or CoC.
                                                                              E
    (iii) WHETHER NCLAT WAS RIGHT IN LAW IN
INTERFERING WITH THE DECISION OF COC OF ACCEPTING
THE RESOLUTION PLAN OF KALPRAJ?
      135. For deciding the said issue, it will be apposite to refer to
Section 30 and 31 of the I&B Code, which read thus:                           F
             “30. Submission of resolution plan.—(1) A resolution
      applicant may submit a resolution plan along with an affidavit
      stating that he is eligible under Section 29-A to the resolution
      professional prepared on the basis of the information memorandum.
                                                                              G
             (2) The resolution professional shall examine each resolution
      plan received by him to confirm that each resolution plan—
      (a)    provides for the payment of insolvency resolution process
             costs in a manner specified by the Board in priority to
             the payment of other debts of the corporate debtor;              H
754     SUPREME COURT REPORTS                             [2021] 2 S.C.R.


A     (b)   provides for the payment of debts of operational creditors
            in such manner as may be specified by the Board which
            shall not be less than—
            (i)     the amount to be paid to such creditors in the event
                    of a liquidation of the corporate debtor under Section
B                   53; or
            (ii)    the amount that would have been paid to such
                    creditors, if the amount to be distributed under the
                    resolution plan had been distributed in accordance
                    with the order of priority in sub-section (1) of Section
C                   53,
                   whichever is higher, and provides for the payment of
            debts of financial creditors, who do not vote in favour of
            the resolution plan, in such manner as may be specified by
            the Board, which shall not be less than the amount to be
            paid to such creditors in accordance with sub-section (1)
D
            of Section 53 in the event of a liquidation of the corporate
            debtor.
                   Explanation 1.—For the removal of doubts, it is
            hereby clarified that a distribution in accordance with the
            provisions of this clause shall be fair and equitable to such
E           creditors.
                   Explanation 2.—For the purposes of this clause, it
            is hereby declared that on and from the date of
            commencement of the Insolvency and Bankruptcy Code
            (Amendment) Act, 2019, the provisions of this clause shall
F           also apply to the corporate insolvency resolution process of
            a corporate debtor—
            (i)     where a resolution plan has not been approved or
                    rejected by the Adjudicating Authority;
            (ii)    where an appeal has been preferred under Section
G                   61 or Section 62 or such an appeal is not time barred
                    under any provision of law for the time being in force;
                    or
            (iii)   where a legal proceeding has been initiated in any
                    court against the decision of the Adjudicating
H                   Authority in respect of a resolution plan;]
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                           755
                  [B.R. GAVAI, J. ]

    (c)    provides for the management of the affairs of the corporate        A
           debtor after approval of the resolution plan;
    (d)    the implementation and supervision of the resolution plan;
    (e)    does not contravene any of the provisions of the law for
           the time being in force;
                                                                              B
    (f)    conforms to such other requirements as may be specified
           by the Board.
          Explanation.—For the purposes of clause (e), if any
    approval of shareholders is required under the Companies Act,
    2013 (18 of 2013) or any other law for the time being in force for        C
    the implementation of actions under the resolution plan, such
    approval shall be deemed to have been given and it shall not be a
    contravention of that Act or law.
           (3) The resolution professional shall present to the committee
    of creditors for its approval such resolution plans which confirm         D
    the conditions referred to in sub-section (2).
           (4) The committee of creditors may approve a resolution
    plan by a vote of not less than sixty-six per cent of voting share of
    the financial creditors, after considering its feasibility and
    viability, the manner of distribution proposed, which may take into
                                                                              E
    account the order of priority amongst creditors as laid down in
    sub-section (1) of Section 53, including the priority and value of
    the security interest of a secured creditor] and such other
    requirements as may be specified by the Board:
          Provided that the committee of creditors shall not approve
                                                                              F
    a resolution plan, submitted before the commencement of the
    Insolvency and Bankruptcy Code (Amendment) Ordinance, 2017,
    where the resolution applicant is ineligible under Section 29-A
    and may require the resolution professional to invite a fresh
    resolution plan where no other resolution plan is available with it:
            Provided further that where the resolution applicant referred     G
    to in the first proviso is ineligible under clause (c) of Section 29-A,
    the resolution applicant shall be allowed by the committee of
    creditors such period, not exceeding thirty days, to make payment
    of overdue amounts in accordance with the proviso to clause (c)
    of Section 29-A:                                                          H
756      SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A            Provided also that nothing in the second proviso shall be
      construed as extension of period for the purposes of the proviso
      to sub-section (3) of Section 12, and the corporate insolvency
      resolution process shall be completed within the period specified
      in that sub-section.]
B            Provided also that the eligibility criteria in Section 29-A as
      amended by the Insolvency and Bankruptcy Code (Amendment)
      Ordinance, 2018 (Ord. 6 of 2018) shall apply to the resolution
      applicant who has not submitted resolution plan as on the date of
      commencement of the Insolvency and Bankruptcy Code
      (Amendment) Ordinance, 2018.
C            (5) The resolution applicant may attend the meeting of the
      committee of creditors in which the resolution plan of the applicant
      is considered:
             Provided that the resolution applicant shall not have a right
      to vote at the meeting of the committee of creditors unless such
D     resolution applicant is also a financial creditor.
             (6) The resolution professional shall submit the resolution
      plan as approved by the committee of creditors to the Adjudicating
      Authority.
             31. Approval of resolution plan.—(1) If the Adjudicating
E     Authority is satisfied that the resolution plan as approved by the
      committee of creditors under sub-section (4) of Section 30 meets
      the requirements as referred to in sub-section (2) of Section 30, it
      shall by order approve the resolution plan which shall be binding
      on the corporate debtor and its employees, members,
      creditors, including the Central Government, any State Government
F
      or any local authority to whom a debt in respect of the payment of
      dues arising under any law for the time being in force, such as
      authorities to whom statutory dues are owed, guarantors and other
      stakeholders involved in the resolution plan:
             Provided that the Adjudicating Authority shall, before passing
G     an order for approval of resolution plan under this sub-section,
      satisfy that the resolution plan has provisions for its effective
      implementation.
             (2) Where the Adjudicating Authority is satisfied that the
      resolution plan does not confirm to the requirements referred to in
H     sub-section (1), it may, by an order, reject the resolution plan.
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                                757
                   [B.R. GAVAI, J. ]

          (3) After the order of approval under sub-section (1),—                   A
          (a)     the moratorium order passed by the Adjudicating Authority
                  under Section 14 shall cease to have effect; and
          (b)     the resolution professional shall forward all records relating
                  to the conduct of the corporate insolvency resolution process
                  and the resolution plan to the Board to be recorded on its        B
                  database.
                 (4) The resolution applicant shall, pursuant to the resolution
          plan approved under sub-section (1), obtain the necessary approval
          required under any law for the time being in force within a period
          of one year from the date of approval of the resolution plan by the       C
          Adjudicating Authority under sub-section (1) or within such period
          as provided for in such law, whichever is later:
                 Provided that where the resolution plan contains a provision
          for combination, as referred to in Section 5 of the Competition
          Act, 2002 (12 of 2003), the resolution applicant shall obtain the         D
          approval of the Competition Commission of India under that Act
          prior to the approval of such resolution plan by the committee of
          creditors.”
       136. The aforesaid provisions have been recently considered in
three judgments of this Court. The first one, being in the case of K.
                                                                                    E
Sashidhar (supra), to which one of us (A.M. Khanwilkar, J.) was a
party, and two other judgments, delivered by three Judges Bench of this
Court, in the cases of Committee of Creditors of Essar Steel India
Limited through Authorised Signatory (supra) and Maharashtra
Seamless Limited vs. Padmanabhan Venkatesh and others45.
       137. This Court in the case of Committee of Creditors of Essar               F
Steel India Limited through Authorised Signatory (supra) has set out
the relevant extracts from the Bankruptcy Law Reforms Committee
(BLRC) Report of 2015, which read thus:
          “56. At this juncture, it is important to set out the relevant extracts
          from the aforementioned Report:                                           G
                “2. Executive Summary         *     *    *
                The key economic question in the bankruptcy process
                ***
45
     (2020) 11 SCC 467                                                              H
758   SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A     The Committee believes that there is only one correct forum
      for evaluating such possibilities, and making a decision:
      a creditors committee, where all financial creditors have
      votes in proportion to the magnitude of debt that they hold.
      In the past, laws in India have brought arms of the Government
      (legislature, executive or judiciary) into this question. This has
B
      been strictly avoided by the Committee. The appropriate
      disposition of a defaulting firm is a business decision, and
      only the creditors should make it.
                                      ***
      5. Process for legal entities * * *
C
      Business decisions by a creditor committee
      All decisions on matters of business will be taken by a committee
      of the financial creditors. This includes evaluating proposals to
      keep the entity as a going concern, including decisions about
      the sale of business or units, retiring or restructuring debt. The
D     debtor will be a non-voting member on the creditors committee,
      and will be invited to all meetings. The voting of the creditors
      committee will be by majority, where the majority requires more
      than 75 per cent of the vote by weight.
                                      ***
E     No prescriptions on solutions to resolve the insolvency
      The choice of the solution to keep the entity as a going
      concern will be voted on by the creditors committee. There
      are no constraints on the proposals that the resolution
      professional can present to the creditors committee. Other
F     than the majority vote of the creditors committee, the resolution
      professional needs to confirm to the Adjudicator that the final
      solution complies with three additional requirements. The first
      is that the solution must explicitly require the repayment of any
      interim finance and costs of the insolvency resolution process
      will be paid in priority to other payments. Secondly, the plan
G
      must explicitly include payment to all creditors not on the
      creditors committee, within a reasonable period after the
      solution is implemented. Lastly, the plan should comply with
      existing laws governing the actions of the entity while
      implementing the solutions.
H                                     ***
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                        759
                  [B.R. GAVAI, J. ]

      5.3.1. Steps at the start of the IRP                                 A
                                     ***
      4. Creation of the creditors committee
      The creditors committee will have the power to decide the
      final solution by majority vote in the negotiations. The majority    B
      vote requires more than or equal to 75 per cent of the creditors
      committee by weight of the total financial liabilities. The
      majority vote will also involve a cram down option on any
      dissenting creditors once the majority vote is obtained. …
      The Committee deliberated on who should be on the creditors          C
      committee, given the power of the creditors committee to
      ultimately keep the entity as a going concern or liquidate it. The
      Committee reasoned that members of the creditors committee
      have to be creditors both with the capability to assess
      viability, as well as to be willing to modify terms of existing
      liabilities in negotiations. Typically, operational creditors        D
      are neither able to decide on matters regarding the
      insolvency of the entity, nor willing to take the risk of
      postponing payments for better future prospects for the
      entity. The Committee concluded that, for the process to be
      rapid and efficient, the Code will provide that the creditors        E
      committee should be restricted to only the financial
      creditors.
      5.3.3. Obtaining the resolution to insolvency in the IRP
      The Committee is of the opinion that there should be freedom
      permitted to the overall market to propose solutions on              F
      keeping the entity as a going concern. Since the manner
      and the type of possible solutions are specific to the time and
      environment in which the insolvency becomes visible, it is
      expected to evolve over time, and with the development of the
      market. The Code will be open to all forms of solutions for
                                                                           G
      keeping the entity going without prejudice, within the rest of
      the constraints of the IRP. Therefore, how the insolvency is
      to be resolved will not be prescribed in the Code. There
      will be no restriction in the Code on possible ways in which the
      business model of the entity, or its financial model, or both,
      can be changed so as to keep the entity as a going concern. The      H
760                 SUPREME COURT REPORTS                        [2021] 2 S.C.R.


A                   Code will not state that the entity is to be revived, or the
                    debt is to be restructured, or the entity is to be liquidated.
                    This decision will come from the deliberations of the
                    creditors committee in response to the solutions proposed
                    by the market.”
B            138. It is thus clear, that the Committee was of the view, that for
      deciding key economic question in the bankruptcy process, the only one
      correct forum for evaluating such possibilities, and making a decision
      was, a creditors committee, wherein all financial creditors have votes in
      proportion to the magnitude of debt that they hold. The BLRC has
      observed, that laws in India in the past have brought arms of the
C     Government (legislature, executive or judiciary) into the question of
      bankruptcy process. This has been strictly avoided by the Committee
      and it has been provided, that the decision with regard to appropriate
      disposition of a defaulting firm, which is a business decision, should only
      be made by the creditors. It has been observed, that the evaluation of
D     proposals to keep the entity as a going concern, including decisions about
      the sale of business or units, restructuring of debt, etc., are required to
      be taken by the Committee of the Financial Creditors. It has been
      provided, that the choice of the solution to keep the entity as a going
      concern will be voted upon by CoC and there are no constraints on the
      proposals that the resolution professional can present to CoC. The
E     requirements, that the resolution professional needs to confirm to the
      Adjudicator, are:
            (i)      that the solution must explicitly require the repayment of any
                     interim finance and costs of the insolvency resolution process
                     will be paid in priority to other payments;
F
            (ii)     that the plan must explicitly include payment to all creditors
                     not on the creditors committee, within a reasonable period
                     after the solution is implemented; and lastly
            (iii)    the plan should comply with existing laws governing the
G                    actions of the entity while implementing the solutions.
             139. The Committee also expressed the opinion, that there should
      be freedom permitted to the overall market, to propose solutions on
      keeping the entity as a going concern. The Committee opined, that the
      details as to how the insolvency is to be resolved or as to how the entity
      is to be revived, or the debt is to be restructured will not be provided in
H
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                                761
                   [B.R. GAVAI, J. ]

the I&B Code but such a decision will come from the deliberations of                A
CoC in response to the solutions proposed by the market.
          140. This Court in the case of K. Sashidhar (supra) observed
thus:
          “32. Having heard the learned counsel for the parties, the moot
          question is about the sequel of the approval of the resolution plan       B
          by CoC of the respective corporate debtor, namely, KS&PIPL
          and IIL, by a vote of less than seventy-five per cent of voting
          share of the financial creditors; and about the correctness of the
          view taken by Nclat that the percentage of voting share of the
          financial creditors specified in Section 30(4) of the I&B Code is         C
          mandatory. Further, is it open to the adjudicating authority/
          appellate authority to reckon any other factor other than
          specified in Sections 30(2) or 61(3) of the I&B Code as the
          case may be which, according to the resolution applicant and
          the stakeholders supporting the resolution plan, may be
          relevant?”                                                                D

                                                           (emphasis supplied)
      141. After considering the judgment of this Court in the case of
Arcelormittal India Private Limited vs. Satish Kumar Gupta and
others46 and the relevant provisions of the I&B Code, this court further            E
observed in K. Sashidhar (supra) thus:
          “52. As aforesaid, upon receipt of a “rejected” resolution plan
          the adjudicating authority (NCLT) is not expected to do anything
          more; but is obligated to initiate liquidation process under Section
          33(1) of the I&B Code. The legislature has not endowed the
                                                                                    F
          adjudicating authority (NCLT) with the jurisdiction or authority to
          analyse or evaluate the commercial decision of CoC much less to
          enquire into the justness of the rejection of the resolution plan by
          the dissenting financial creditors. From the legislative history and
          the background in which the I&B Code has been enacted, it is
          noticed that a completely new approach has been adopted for               G
          speeding up the recovery of the debt due from the defaulting
          companies. In the new approach, there is a calm period followed
          by a swift resolution process to be completed within 270 days
          (outer limit) failing which, initiation of liquidation process has been
46
     (2019) 2 SCC 1                                                                 H
762             SUPREME COURT REPORTS                              [2021] 2 S.C.R.


A             made inevitable and mandatory. In the earlier regime, the corporate
              debtor could indefinitely continue to enjoy the protection given
              under Section 22 of the Sick Industrial Companies Act, 1985 or
              under other such enactments which has now been forsaken.
              Besides, the commercial wisdom of CoC has been given
              paramount status without any judicial intervention, for
B
              ensuring completion of the stated processes within the timelines
              prescribed by the I&B Code. There is an intrinsic assumption
              that financial creditors are fully informed about the viability
              of the corporate debtor and feasibility of the proposed
              resolution plan. They act on the basis of thorough examination
C             of the proposed resolution plan and assessment made by their
              team of experts. The opinion on the subject-matter expressed
              by them after due deliberations in CoC meetings through
              voting, as per voting shares, is a collective business decision.
              The legislature, consciously, has not provided any ground to
              challenge the “commercial wisdom” of the individual financial
D
              creditors or their collective decision before the adjudicating
              authority. That is made non-justiciable.”
                                                               (emphasis supplied)
              142. This Court has held, that it is not open to the Adjudicating
      Authority or Appellate Authority to reckon any other factor other than
E     specified in Sections 30(2) or 61(3) of the I&B Code. It has further
      been held, that the commercial wisdom of CoC has been given paramount
      status without any judicial intervention for ensuring completion of the
      stated processes within the timelines prescribed by the I&B Code. This
      Court thus, in unequivocal terms, held, that there is an intrinsic assumption,
F     that financial creditors are fully informed about the viability of the corporate
      debtor and feasibility of the proposed resolution plan. They act on the
      basis of thorough examination of the proposed resolution plan and
      assessment made by their team of experts. It has been held, that the
      opinion expressed by CoC after due deliberations in the meetings through
      voting, as per voting shares, is a collective business decision. It has been
G     held, that the legislature has consciously not provided any ground to
      challenge the “commercial wisdom” of the individual financial creditors
      or their collective decision before the Adjudicating Authority and that
      the decision of CoC’s ‘commercial wisdom’ is made non-justiciable.
              143. This Court in Committee of Creditors of Essar Steel India
H     Limited through Authorised Signatory (supra) after referring to the
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                              763
                  [B.R. GAVAI, J. ]

judgment of this Court in the case of K. Sashidhar (supra) observed              A
thus:
       “64. Thus, what is left to the majority decision of the Committee
       of Creditors is the “feasibility and viability” of a resolution plan,
       which obviously takes into account all aspects of the plan, including
       the manner of distribution of funds among the various classes of          B
       creditors. As an example, take the case of a resolution plan which
       does not provide for payment of electricity dues. It is certainly
       open to the Committee of Creditors to suggest a modification to
       the prospective resolution applicant to the effect that such dues
       ought to be paid in full, so that the carrying on of the business of
       the corporate debtor does not become impossible for want of a             C
       most basic and essential element for the carrying on of such
       business, namely, electricity. This may, in turn, be accepted by the
       resolution applicant with a consequent modification as to
       distribution of funds, payment being provided to a certain type of
       operational creditor, namely, the electricity distribution company,       D
       out of upfront payment offered by the proposed resolution applicant
       which may also result in a consequent reduction of amounts
       payable to other financial and operational creditors. What is
       important is that it is the commercial wisdom of this majority
       of creditors which is to determine, through negotiation with
       the prospective resolution applicant, as to how and in what               E
       manner the corporate resolution process is to take place.”
                                                         (emphasis supplied)
       144. This Court held, that what is left to the majority decision of
CoC is the “feasibility and viability” of a resolution plan, which is required
to take into account all aspects of the plan, including the manner of            F
distribution of funds among the various classes of creditors. It has further
been held, that CoC is entitled to suggest a modification to the prospective
resolution applicant, so that carrying on the business of the Corporate
Debtor does not become impossible, which suggestion may, in turn, be
accepted by the resolution applicant with a consequent modification as
                                                                                 G
to distribution of funds, etc. It has been held, that what is important is,
the commercial wisdom of the majority of creditors, which is to determine,
through negotiation with the prospective resolution applicant, as to how
and in what manner the corporate resolution process is to take place.
       145. The view taken in the case of K. Sashidhar (supra) and
Committee of Creditors of Essar Steel India Limited through                      H
764            SUPREME COURT REPORTS                             [2021] 2 S.C.R.


A     Authorised Signatory (supra) has been reiterated by another three
      Judges Bench of this Court in the case of Maharashtra Seamless
      Limited (supra).
             146. In all the aforesaid three judgments of this Court, the scope
      of jurisdiction of the Adjudicating Authority (NCLT) and the Appellate
B     Authority (NCLAT) has also been elaborately considered. It will be
      relevant to refer to paragraph 55 of the judgment in the case of K.
      Sashidhar (supra), which reads thus:
            “55. Whereas, the discretion of the adjudicating authority (NCLT)
            is circumscribed by Section 31 limited to scrutiny of the resolution
C           plan “as approved” by the requisite per cent of voting share of
            financial creditors. Even in that enquiry, the grounds on which the
            adjudicating authority can reject the resolution plan is in reference
            to matters specified in Section 30(2), when the resolution plan
            does not conform to the stated requirements. Reverting to Section
            30(2), the enquiry to be done is in respect of whether the resolution
D
            plan provides: (i) the payment of insolvency resolution process
            costs in a specified manner in priority to the repayment of other
            debts of the corporate debtor, (ii) the repayment of the debts of
            operational creditors in prescribed manner, (iii) the management
            of the affairs of the corporate debtor, (iv) the implementation and
E           supervision of the resolution plan, (v) does not contravene any of
            the provisions of the law for the time being in force, (vi) conforms
            to such other requirements as may be specified by the Board.
            The Board referred to is established under Section 188 of the
            I&B Code. The powers and functions of the Board have been
            delineated in Section 196 of the I&B Code. None of the specified
F
            functions of the Board, directly or indirectly, pertain to regulating
            the manner in which the financial creditors ought to or ought not
            to exercise their commercial wisdom during the voting on the
            resolution plan under Section 30(4) of the I&B Code. The
            subjective satisfaction of the financial creditors at the time of voting
G           is bound to be a mixed baggage of variety of factors. To wit, the
            feasibility and viability of the proposed resolution plan and including
            their perceptions about the general capability of the resolution
            applicant to translate the projected plan into a reality. The resolution
            applicant may have given projections backed by normative data
            but still in the opinion of the dissenting financial creditors, it would
H
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                              765
                  [B.R. GAVAI, J. ]

       not be free from being speculative. These aspects are completely          A
       within the domain of the financial creditors who are called upon
       to vote on the resolution plan under Section 30(4) of the I&B
       Code.”
       147. It has been held, that in an enquiry under Section 31, the
limited enquiry that the Adjudicating Authority is permitted is, as to           B
whether the resolution plan provides:
       (i)     the payment of insolvency resolution process costs in a
               specified manner in priority to the repayment of other debts
               of the corporate debtor,
       (ii) the repayment of the debts of operational creditors in               C
               prescribed manner,
       (iii) the management of the affairs of the corporate debtor,
       (iv) the implementation and supervision of the resolution plan,
       (v) the plan does not contravene any of the provisions of the
               law for the time being in force,                                  D
       (vi) conforms to such other requirements as may be specified
               by the Board.
       148. It will be further relevant to refer to the following observations
of this Court in K. Sashidhar (supra):
       57. …Indubitably, the remedy of appeal including the width of             E
       jurisdiction of the appellate authority and the grounds of appeal, is
       a creature of statute. The provisions investing jurisdiction and
       authority in NCLT or Nclat as noticed earlier, have not made
       the commercial decision exercised by CoC of not approving
       the resolution plan or rejecting the same, justiciable. This
                                                                                 F
       position is reinforced from the limited grounds specified for
       instituting an appeal that too against an order “approving a
       resolution plan” under Section 31. First, that the approved
       resolution plan is in contravention of the provisions of any law for
       the time being in force. Second, there has been material irregularity
       in exercise of powers “by the resolution professional” during the         G
       corporate insolvency resolution period. Third, the debts owed to
       operational creditors have not been provided for in the resolution
       plan in the prescribed manner. Fourth, the insolvency resolution
       plan costs have not been provided for repayment in priority to all
       other debts. Fifth, the resolution plan does not comply with any
                                                                                 H
766             SUPREME COURT REPORTS                            [2021] 2 S.C.R.


A            other criteria specified by the Board. Significantly, the matters or
             grounds—be it under Section 30(2) or under Section 61(3) of the
             I&B Code—are regarding testing the validity of the “approved”
             resolution plan by CoC; and not for approving the resolution plan
             which has been disapproved or deemed to have been rejected by
             CoC in exercise of its business decision.”
B
                                                              [emphasis supplied]
             149. It will therefore be clear, that this Court, in unequivocal terms,
      held, that the appeal is a creature of statute and that the statute has not
      invested jurisdiction and authority either with NCLT or NCLAT, to review
C     the commercial decision exercised by CoC of approving the resolution
      plan or rejecting the same.
             150. The position is clarified by the following observations in
      paragraph 59 of the judgment in the case of K. Sashidhar (supra), which
      reads thus:
D            “59. In our view, neither the adjudicating authority (NCLT) nor
             the appellate authority (NCLAT) has been endowed with the
             jurisdiction to reverse the commercial wisdom of the dissenting
             financial creditors and that too on the specious ground that it is
             only an opinion of the minority financial creditors…..”
E           151. This Court in Committee of Creditors of Essar Steel India
      Limited through Authorised Signatory (supra) after reproducing certain
      paragraphs in K. Sashidhar (supra) observed thus:
             “Thus, it is clear that the limited judicial review available, which
             can in no circumstance trespass upon a business decision of the
F            majority of the Committee of Creditors, has to be within the four
             corners of Section 30(2) of the Code, insofar as the Adjudicating
             Authority is concerned, and Section 32 read with Section 61(3) of
             the Code, insofar as the Appellate Tribunal is concerned, the
             parameters of such review having been clearly laid down in K.
             Sashidhar”
G
             152. It can thus be seen, that this Court has clarified, that the
      limited judicial review, which is available, can in no circumstance trespass
      upon a business decision arrived at by the majority of CoC.
          153. In the case of Maharashtra Seamless Limited (supra),
H     NCLT had approved the plan of appellant therein with regard to CIRP
KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                          767
                  [B.R. GAVAI, J. ]

of United Seamless Tubulaar (P) Ltd. In appeal, NCLAT directed, that         A
the appellant therein should increase upfront payment to Rs.597.54 crore
to the “financial creditors”, “operational creditors” and other creditors
by paying an additional amount of Rs.120.54 crore. NCLAT further
directed, that in the event the “resolution applicant” failed to undertake
the payment of additional amount of Rs.120.54 crore in addition to Rs.477
                                                                             B
crore and deposit the said amount in escrow account within 30 days, the
order of approval of the ‘resolution plan’ was to be treated to be set
aside. While allowing the appeal and setting aside the directions of
NCLAT, this Court observed thus:
      “30. The appellate authority has, in our opinion, proceeded on
      equitable perception rather than commercial wisdom. On the face        C
      of it, release of assets at a value 20% below its liquidation value
      arrived at by the valuers seems inequitable. Here, we feel the
      Court ought to cede ground to the commercial wisdom of the
      creditors rather than assess the resolution plan on the basis of
      quantitative analysis. Such is the scheme of the Code. Section         D
      31(1) of the Code lays down in clear terms that for final approval
      of a resolution plan, the adjudicating authority has to be satisfied
      that the requirement of sub-section (2) of Section 30 of the Code
      has been complied with. The proviso to Section 31(1) of the Code
      stipulates the other point on which an adjudicating authority has to
      be satisfied. That factor is that the resolution plan has provisions   E
      for its implementation. The scope of interference by the
      adjudicating authority in limited judicial review has been laid down
      in Essar Steel [Essar Steel India Ltd. Committee of
      Creditors v. Satish Kumar Gupta, (2020) 8 SCC 531], the relevant
      passage (para 54) of which we have reproduced in earlier part of       F
      this judgment. The case of MSL in their appeal is that they want
      to run the company and infuse more funds. In such circumstances,
      we do not think the appellate authority ought to have interfered
      with the order of the adjudicating authority in directing the
      successful resolution applicant to enhance their fund inflow
      upfront.”                                                              G

      154. This Court observed, that the Court ought to cede ground to
the commercial wisdom of the creditors rather than assess the resolution
plan on the basis of quantitative analysis. This Court clearly held, that
the appellate authority ought not to have interfered with the order of the
                                                                             H
768            SUPREME COURT REPORTS                           [2021] 2 S.C.R.


A     adjudicating authority by directing the successful resolution applicant to
      enhance their fund inflow upfront.
             155. It would thus be clear, that the legislative scheme, as
      interpreted by various decisions of this Court, is unambiguous. The
      commercial wisdom of CoC is not to be interfered with, excepting the
B     limited scope as provided under Sections 30 and 31 of the I&B Code.
             156. No doubt, it is sought to be urged, that since there has been
      a material irregularity in exercise of the powers by RP, NCLAT was
      justified in view of the provisions of clause (ii) of sub-section (3) of
      Section 61 of the I&B Code to interfere with the exercise of power by
C     RP. However, it could be seen, that all actions of RP have the seal of
      approval of CoC. No doubt, it was possible for RP to have issued another
      Form ‘G’, in the event he found, that the proposals received by it prior to
      the date specified in last Form ‘G’ could not be accepted. However, it
      has been the consistent stand of RP as well as CoC, that all actions of
      RP, including acceptance of resolution plans of Kalpraj after the due
D     date, albeit before the expiry of timeline specified by the I&B Code for
      completion of the process, have been consciously approved by CoC. It
      is to be noted, that the decision of CoC is taken by a thumping majority
      of 84.36%. The only creditor voted in favour of KIAL is Kotak Bank,
      which is a holding company of KIAL, having voting rights of 0.97%. We
E     are of the considered view, that in view of the paramount importance
      given to the decision of CoC, which is to be taken on the basis of
      ‘commercial wisdom’, NCLAT was not correct in law in interfering
      with the commercial decision taken by CoC by a thumping majority of
      84.36%.

F            157. It is further to be noted, that after the resolution plan of
      Kalpraj was approved by NCLT on 28.11.2019, Kalpraj had begun
      implementing the resolution plan. NCLAT had heard the appeals on
      27.2.2020 and reserved the same for orders. It is not in dispute, that
      there was no stay granted by NCLAT, while reserving the matters for
      orders. After a gap of five months and eight days, NCLAT passed the
G     final order on 5.8.2020. It could thus be seen, that for a long period,
      there was no restraint on implementation of the resolution plan of Kalpraj,
      which was duly approved by NCLT. It is the case of Kalpraj, RP, CoC
      and Deutsche Bank, that during the said period, various steps have been
      taken by Kalpraj by spending a huge amount for implementation of the
H     plan. No doubt, this is sought to be disputed by KIAL. However, we do
 KALPRAJ DHARAMSHI v. KOTAK INVESTMENT ADVISORS LTD.                            769
                   [B.R. GAVAI, J. ]

not find it necessary to go into that aspect of the matter in light of our      A
conclusion, that NCLAT acted in excess of jurisdiction in interfering
with the conscious commercial decision of CoC.
        158. It is also pointed out, that in pursuance of the order dated
5.8.2020 passed by NCLAT, CoC has approved the resolution plan of
KIAL on 13.8.2020. However, since we have already held, that the                B
decision of NCLAT dated 5.8.2020 does not stand the scrutiny of law, it
must follow, that the subsequent approval of the resolution plan of KIAL
by CoC becomes non-est in law. For, it was only to abide by the directions
of NCLAT. We are of the view that nothing would turn on it. The decision
of CoC dated 13/14.2.2019 is a decision, which has been taken in exercise
of its ‘commercial wisdom’. As such, we hold, that the decision taken by        C
CoC dated 13/14.2.2019, which is taken in accordance with its
‘commercial wisdom’ and which is duly approved by NCLT, will prevail.
Further, NCLAT was not justified in interfering with the stated decision
taken by CoC.
      159. In that view of the matter, we find, that Civil Appeal Nos.          D
2943-2944 of 2020 filed by Kalpraj; Civil Appeal Nos. 2949-2950 of
2020 filed by RP and Civil Appeal Nos. 3138-3139 of 2020 filed by
Deutsche Bank deserve to be allowed. It is ordered accordingly. The
order passed by NCLAT dated 5.8.2020 is quashed and set aside and
the orders passed by NCLT dated 28.11.2019 are restored and                     E
maintained.
        160. Insofar as, the Civil Appeals arising out of D.No. 24125 of
2020 filed by Fourth Dimension Solutions Limited are concerned, it is
submitted, that the appeal preferred by it against the order of NCLT is
still pending before NCLAT. Without going into the merits of the rival          F
contentions of the parties, we direct NCLAT to decide the appeal of
Fourth Dimension Solutions Limited in accordance with law, as
expeditiously as possible, and in any case, within a period of two months
from today.
      161. As such, all appeals are disposed of in view of the above and        G
pending applications, if any, shall stand disposed of.

Nidhi Jain                                               Appeals disposed of.



                                                                                H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Insolvency and Bankruptcy Code"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.