Created byFuzzy Cloud

Supreme Court of India

JIYAJEERAO COTTON MILLS LIMITED AND ANOTHERversusMADHYA PRADESH ELECTRICITY BOARD AND OTHERS

Citation
1988 INSC 273
Decided
12 September 1988
Disposal
Dismissed
Bench
A P SEN

Holding

The assessment was valid, the Board was authorized to levy penal rates and enhanced tariffs, and the orders were lawful, so the appeal was dismissed.

Summary

Jiyajeerao Cotton Mills Ltd. entered into a supply agreement with the Madhya Pradesh Electricity Board, but due to electricity scarcity the State issued two orders in 1975: a Regulation Order limiting consumption and imposing penal rates for excess use, and a Generation Order requiring consumers with captive power to generate as much as technically feasible, with provisions for emergency supply. The Board assessed the mill's captive capacity and directed it to generate additional power; the mill later drew extra electricity without prior Board approval and was billed at penal rates. The mill challenged the assessment and the Board's right to levy penal rates, arguing lack of legal sanction and procedural flaws. The Supreme Court examined the validity of the assessment, the statutory powers under Section 22B of the Indian Electricity Act, 1910, and the Board's authority under Sections 49, 42, and 48 of the 1948 Act, concluding that the assessment was proper, the Board was empowered to impose higher tariffs, and the orders were lawful. Consequently, the mill's claims were rejected and the appeal dismissed.

Issues considered

  • Was the assessment of the mill's captive power generation capacity by the Divisional Engineer under the Generation Order valid and lawful?
  • Does Section 22B of the Indian Electricity Act, 1910, together with the Regulation and Generation Orders, empower the Board to levy penal rates for excess electricity consumption?
  • Can the Board impose enhanced tariffs under Sections 49(1) and 49(3) of the 1948 Electricity Act in addition to the orders issued under Section 22B?
  • Should the Regulation Order and the Generation Order be read together, and does this affect the Board's right to charge higher rates?
  • Does the mill's failure to obtain prior permission for emergency supply bar its claim for relief?

Legislation cited

Subjects

electricity supplypenal ratesregulation ordergeneration ordercaptive powerSection 22Btariff enhancementemergency supplyassessment validityboard authority

Judgment

     JIYAJEERAO COTTON MILLS LIMITED AND ANOTHER
A
                          v.
    MADHYA PRADESH ELECTRICITY BOARD AND OTHERS

                           SEPTEMBER 12, 1988

B          [A.P. SEN AND LALIT MOHAN SHARMA, JJ.]

          Indian Electricity Act, 1910--Section 22B-Company entering
    into agreement with Electricity Board for supply of electricity-Board
    supplying additional energy and billing at penal rates-Action of
                                                                              [
    Board-Whether valid and legal.
c       Madhya Pradesh Electricity (Supply and Consumption Regula-
  tion) Order 1975/Madhya Pradesh Electricity (Generation, Control and
  Consumption) Order 1975: Clause 3(i) Regulation Order-Consumers
  to reduce consumption-Board entitled to disconnect supply for breach         ~

  or charge penal rates for excess energy consumed-Generation Order
D provided for assessment of generating capacity of captive power of
    consumer.

         Words and Phrases: 'Regulate'-Meaning of.

       In October 1971 the appellant company entered into an agree-
E ment with the Madhya Pradesh Electricity Board, respondent No. l, for
  supply of electricity. The quantity of electricity to be supplied varied
  from time to time.

         To meet the situation arising out of insufficient generation of
  electricity, the State of Madhya Pradesh issued two orders. By the
F Madhya Pradesh Electricity (Supply and Consumption Regulation)
  Order, 1975 the consumers were asked to reduce their consumption
  failing which they would have to pay charges at penal rates for excess
  consumption,_ without prejudice to the Board's power to disconnect the
  supply. By the Generation Order, the consumers who had alternative
  sources of captive power were required to generate electricity to the
G maximum extent technically feasible, from their own sources of
  electricity.

        After the assessment of their generating capacity, the appellant
  was directed to generate additional electricity of 2,500 K. W. Suh-
                                                                              ;,
  Clause (iii) of Proviso to clause 3 of the Generation Order provided that
H if in certain contingencies tnere was reduction in the generation of
                                     978
                JIYAJEERAO COTTON MILLS '· ELECTRICITY BOARD                979

       electricity by . the consumer; the Board would try to make good thr
       deficit against the appropriate charge for it. Under this provision the
                                                                                   A
       appellant, on pleading emergency, was supplied additional energy from
       time to time. F Jr excess consumption drawn without the Board's prior
       approval, the appellant was sent bills at penal rate.

              The appellant company challenged the demand before the High          B
       Court by filing a writ application under Article 226 of the Constitution,
       which was dismissed by the High Court except for granting some minor
       reliefs.

             Before this Court, it was contended by the appellant:

             (I) There is no sanction in Law for charging at the Penal rate for
                                                                                   c
       the electricity consumed beyond what is permissible under the Genera-
       tion Order.

             (2) That the assessment of their generating capacity was not made
       by the authority empowered to do so. i.e. the Divisional Engineer, and      D
       (3) that the assessment was based on irrelevant and extraneous consi-
       derations.

             Dismissing the appeal, it was,

             HELD: (I) A perusal of the documents on record, including             E
       admissions on the part of the appellant company, furnishes unimpeach-
       able evidence, ·pr-Ol'ing that the assessment of the maximum feasible
       capacity of the appelant's capative power sets was duly made in accord-
       ance with the Generation Order, and that the Divisional Engineer, who
       had been authorised by the Generation Order to assess the appellant's
       generating capacity, reached the conclusion after personally consider-      F
       ing the matter thoroughly.

             (2) In pursuance of the assessment of the generating capacity the
       required direction was issued which was acted upon by the parties for a
       number of years. The Company not only took steps to generate the
       additional energy as was required of it, it also took advantage of the      G
       provisions of proviso (iii) to clause 3 of the Generation Order and
       benefitted by it from time to time. [988A-BI

            (3) The appellant company was fully conscious of the fact that it
' ,.   was consuming electricity beyond its entitlement under the two Orders.
       For several years the Company was particular to obtain the permission       H
    98(1           SUPREME COURT REPORTS              I 1988] Supp. 2 S.C.R.

A   of the Board for drawing electricity itl"'excess of what it<was entitled to
    by the agreement, as modified by the Regulation Order and the Genera-
    tion Order, but later, it not only stopped seeking the advance sanction
    in this regard, it did not even care to inform the Board of the excess
    drawaL [IOOIB-C; t'-G]

B         (4) Section 22B of the Indian Electricity Act, 1910 permits the
    State Government to issue an appropriate order for regulating the
    supply, distribution and consumption of electricity. I IO JOB]

          (5) The expression "regulate" occurs in other statutes also, as for
    example, the Essential Commodities Act, 1955, and it has been found
t   difficult to give the word a precise definition, It has different shades of
    meaning and must take its colour from the context in which it is used
    having regard to the purpose and object of the relevant provisions, and
    as has been repeatedly observed, the Court while interpreting the
    expression must necessarily keep in Yiew the object to be achieved and
    the mischief sought to be remedied. [JOIOC·Dl
D
           ( 6)   There does not appear to be any doubt that either under
    S. 49( I) of the 1948 Act read with the agreement or under s. 49(3)
    or under both the provisions the respondent Board was fully autho-
    rised to levy and to make a demand at a higher rate than the usual
    tariff. I JO 14F..-F]

          (7) The necessity for issuing the two Orders arose out of the
    scarcity of electricity available to the Board for supplying to its custom-
    ers. The situation did not leave any option to the Board but to make
    limited snpply of electricity to its consumers, and it must be held to
    have, in the circumstances, the right to stagger or curtail the supply.
F   The orders were issued in this background and to make the direction
    mentioned therein effective it was considered essential to impose sanc-
    tions which could take any reasonable form; either disconnection in
    case of gross violation or the lesser sanction of enhanced tariff. Hence
    none of the two Orders was illegal or unreasonable.

G         Adoni Cotton Mills v. A.P. State Electricity Board, [1976] 4 SCC
    68; State of U.P. v Hindustan Aluminium Corporation, [1979] 3 SCC
    229 and New Central Jute Mills v U.P. State Electricity Board, [1986]
    Supp.   sec 581.

         CIVIL APPELLATE JURISDICTION: Civil Appeals Nos.
H   3510-3511 of 1982.
       JIYAJEERAO COTION MILLS v. ELECTRICITY BOARD [SHARMA, J.l           981

             From the Judgment and Order dated 23.9.1982 and 18/19.10.1982        A
       of the Madhya Pradesh High Court in Misc. W.P. No .. 888/81 and
       Review M.C.C. No. 352 of 1982.

            D. Gupta, M.C. Bhandare, O.P. Khaitan, Anil Bhatnagar,
       Krishan Kumar, Dhruv Agarwal and Mrs. Kiran Choudhary for the
       Appellants.                                                                B

             S.N. Kacker, M.L. Jaiswal, Vivek Gambhir and S.K. Gambhir
       for the Respondents.

             The Judgment of the Court was delivered by

             SHARMA, J. The dispute in these appeals is. in regard' to the        C
       additional demand of electric charges made by the respondent no. 1 on
       the appellant no. 1 for energy consumed. By a writ application filed
       before the Madhya Pradesh High Court the appellant challenged the
       demand ofRs.1,86,97,880.97 for the period 12.11.1979 to 30.6.1981.
       Except for .granting a minor relief as indicated in paragraph 45 of 'its   D
       judgment, the High Court dismissed the writ application. The writ
       petitioner-appellants have impugned the judgment before this Court
       by special leave.

              2. The appellant no. 1 Jiyajeerao Cotton Mills Ltd. (hereinafter
       referred to as the Company) which runs a textile mill in Gwalior,          E
       entered into an agreement dated 27.10.1971 with the respondent no. 1
       Madhya Pradesh Electricity Board (in short the Board) a licensee
       under the Indian Electricity Act, 1910 (hereinafter referred to as the
       1918 Act) for supply of electricity in accordance with the terms and
       conditions mentioned therein. The quantity of .electricity to be
       supplied varied from time to time under supplementary agreements           F
       and the Board had to supply 2,500 K. W. on A.T. basis with effect from
       1. 11. 1973. Since 1975 the Board is not able to generate sufficient
       electricity to meet the full demand of the consumers and with a view to
       ease the situation. two orders were issued by the State of Madhya
       Pradesh under s. 22B of the 1910 Act on 4.4.1975 called as the Madhya
       Pradesh Electricity (Supply and Consumption Regulation) Order,             G
       1975 and the Madhya Pradesh Electricity (Generation, Control and
       Consumption) Order, 1975. The learned counsel for the parties have
       in their arguments referred to these orders as Regulation Order ancj
•. "   Generation Order respectively. By the Regulation Order, the consum·
       ers were asked to reduce their consumption in accordance with the
       provisions therein. It was further provided ihat without prejudice to      H
                                                                                 --.;
    982          SUPREME COURT REPORTS              [ 198§] Supp. 2 S.C.R.

  the Board's power to disconnect the supply in the event of any viola-
A
  tion thereof, the consumer will have to pay the charges at penal rates
  for the excess energy consumed. The Generation Order said that if a
  consumer had an alternative source of generating power from his own
  generating set (described as captive power by the parties) it may be
  required to generate electricity to the maximum extent technically
B feasible  and the supply by the Board would be reduced to that extent.
  The Order in Clause 3 provided for assessment of the generating
  capacity of the captive power of the consumer. The contract demand
  under the agreement was directed to remain reduced accordingly. Sub-
  clause (iii) of Proviso to Clause 3 said, that if in certain contingencies,
  there was reduction in the generation of electricity by the consumer,
  the Board would try to make good the deficit against an appropriate
c charge   for it. An arbitration clause with respect to any dispute was
  included in the 6th paragraph of the Order as its last term.

         3. Both the Orders came into force with effect from the 7th of
   April, 1975. The Divisional Engineer, Gwalior informed the appellant
 D Company by the letter dated 17.5.1975 (marked as Annexure 'B', page
   121, Vol. II of the paper book) that its additional generation capacity
   technically feasible by its own generating sets had been assessed at
   2,700 K.W. In. view of the contract under which the Board was to
   supply 2,500 K.W. with effect from 1.11.1973, the Company was
   directed to generate-additional electricity to that extent, thus reducing
 E the demand on. the Board to nil. After several letters passed between
   the parties, which will be dealt with at some length later, another letter
   dated 10. 10. 1975 (marked as Annexure 'O', page 136, Vol. II of the
   paper book) was sent to the Company issuing a fresh direction for
   generating additional electricity to the extent of 2,500 K. W. with effect
   from 31.10. 1975.
 F
         4. It appears that the Board did not bill the appellant Company
   for any additional energy supplied at the penafrate for the next several
   years. According to its case the Company invoked the provisions of
   Proviso (iii) to Clause 3 of the Generation Order pleading emergency,
   arising from time to time, covered by the Proviso, and was supplied
 G additional energy accordingly. The Company was under a duty to
   place its difficulties before the Board and obtain permission before
   drawing additional energy under this provision of emergency supply. It
   appears that after 11.11.1979 additional power was drawn, by the
                                                                                .,. f
   appellant without the Board's prior approval and a letter Annexure 'T'
   dated 5.8. 1980 was ultimately sent to the Company explaining the
·H situation and telling it that the supply availed by it with effect from
->       JIYAJEERAO COTION MILLS v. ELECTRICITY llOARD [SHARMA. J .I        983

         12.11.1979 would be billed at the penal rate. In the meantime 1wo
         additional contracts were executed by the parties; the first one on       A
         11.7.1979 (Annexure 'C')"for supplying additional 800K.W., and the
         second one dated 26.2.1980 (Annexure 'D' for additional 190 K.W.
         Thus the total demand under the agreements added to 3,490 K.W. The
         Board by its letter Annexure 'U' dated 13.10.1980 reiterated its stand
         taken under Annexure 'T' intimating the appellant the maximum             B
         amount of electricity it was entitled to consume at the normal rate.
         The letter further added that no additional power would be allowed as
         emergency supply to the Company even during the period of overhaul-
         ing of the generating sets as was done earlier under Proviso (iii) to
         Clause 3 of the Generation Order. The matter was debated for some
         time and ultimately the additional demand for the period 12.11.19'79 to
         30.9.1980 amounting to Rs.94,41,745.60 was served on the appellant        c
         Company by the letter Annexure 'X' dated 15 .1.1981. The further bills
         Were also sent on the same basis.

              5. On 5 .8.1981 the application under Article 226 of_the Consti tu-
         tion was filed before the Madhya Pradesh High Court challenging D
         Annexures 'H', 'O', 'T' and 'U'. The main case of the petitioner-
         appellant was rejected by the High Court, but marginal reliefs with
         respect to the Board's demands for the period 12.11. f979 to 25.2.1980
         and from 26.2.1980 to 31.7.1980 were allowed on the basis of errors in
         cfilculation. The High Court also pointed out that under the terms of
         the Generation Order the Board was under a duty to consider and E
         allow the additional emergency supply when conditions arose making
         the Proviso (iii) to Clause 3 applicable and the Board could not refuse
         to do so as was observed in some of its letters. Subject to these minor
         modifications the writ application was dismissed by the judgment
         dated 23.9.1982. The Company thereafter filed an application for
         review, which was dismissed by a speaking order of 19.10.1982. The F
         present appeals have been filed by special leave against these two
         judgments.

               6. The appeals have been argued at considerable length by Mr
         Dipankar Gupta on behalf of the appellant and Mr. S.N. Kacker
         represeming ihe respondents with great ingenuity and resourceful- G
         ness. Mr. Gupta appearing in support of the appeals, however, did
         not press some of the points urged on behalf of the appellant in the

'    .   High Court and relied upon some new grounds. We, therefore, do not
         consider it necessary to deal with all the points disposed of in the High
         Court judgments except making reference to some of them while deal-
         ing with the points urged before us.                                      H
    984        SUPREME COURT REPORTS                 [1988] Supp. 2 S.C.R.

          7. It will be necessary to examine the relevant portions of the
A   Regulation and Generation Orders (Annexures 'E' and 'G') before
    considering the arguments of the learned counsel. They were both
    issued on 4.4.1975 by the State Government of Madhya Pradesh under
    s. 22B of the 1910 Act, which reads as follows:

B                     "22. B(l) If the State Government is of opinion that
               it is necessary or expedient so to do, for maintaining the
               supply and securing the equitable distribution of energy, it
               may by order provide for regulating the supply, distribu-
               tion, consumption or use thereof.

                    (2) Without prejudice to the generality of the powers
c              conferred by sub-section ( 1) an order made thereunder
               may direct the licensee not to comply, except with the
               permission of the State Government with-

                     \i) The provisions of any contract, agreement or
L                    requisition whether made before or af:er the comm-
                     encement of the Indian Electricity (Amendment)
                     Act, 1959, for the supply (other than the resumption
                     of supply) or an increase in the supply of energy to
                     any person, or

E                    (ii) any requisition for the resumption of supply of
                     energy to a consumer after a period of six months,
                     from the date of its discontinuance, or

                     (iii) any requisition for the resumption of supply of
                     energy made within six months of its continuance,
p                    where the requisitioning consumer was not himself
                     the consumer of the supply at the time of its a1s-
                     continuance."

    Clauses 3 and 4(i) of the Regulation Order (Annexure 'E') have been
    referred to by the learned counsel for the parties repeatedly and they,
G   are quoted below:

               "3.(1). No consumer receiving supply of electrical energy
               from the Board and consuming or using electrical energy
               for any of the categories specified in column (2) of PA RT-
               A of Schedule VII shall consume or use during any month
H              or day electrical energy in excess of that specified in respec-
~       JIYAJEERAO COTION MILLS v. ELECTRICITY BOARD [SHARMA, J.l            985

                   tive entry in column (3) of the said Schedule;
                                                                                    A
                   (2) (a). If at any time during the month, on inspection of
                   the meter reader or any other person authorised by the
                   Divisional EngineerJAssistant Engineer of the Board
                   having jurisdiction, the cunsumer is found to have already
                   -reached or exceeded the quantity of electricity indicated in    B
                   column (3) of Part-A of Schedule VII the Divisional
                   Engineer/Assistant Engineer of the Board, having juris-
                   diction over the area where the consumer's premises is
                   situated, may by an order in writing require the consumer
                   not to utilise electrical energy for the rest of the month and
                   such order shall be complied with by the consumer forth-
                   with. Appeal shall, however, lie with the Deputy Chief
                                                                                    c
                   Engineer of the Board having jurisdiction whose decisions
                   thereon shall be final.

                         (b) Any H .T. consumer who makes default in com-
                   plying with the directions contained in sub-clause (1) and       D
                   item (a) of this sub~clause shall be warned in the first
                   instance in writing by the Divisional Engineer/Assistant
                   Engineer of the Board having jurisdiction over the area
                   where the <:onsumer's premises is situated and if the
                   default continues, the said Divisional Engineer/Assistant
                   Engineer shall after reasonably satisfying himself discon-       E
                   nect power supply altogether to such consumer and supply
                   shall not be resumed without orders of the Deputy Chief
                   Engineer of the Board having jurisdiction."

                   "4. Without prejudice to the Board's powers to disconnect
                   supply in the event of violation of Clause 3 above, the          F
                   Board shall bill the electricity consumed or used in excess
                   of the monthly limit specified in column (3) of the Schedule
                   VII at the penal rates as mentioned below:

                        {i) All H.T. consumers as specified in Schedules I,
                        II, III and IV-Four times of normal tariff (both in         G
                        !"Spec! of demand charges and energy charges) includ-
                        ing fuel cost adjustment charges."
                                                          •.
        The e'xpressions "average monthly consumption"., "average demand"
    •   and "average daily consumption" have been defined in Clause 2 of
        Annexure 'E' by taking January, February and March 1975 as the base         H
    986         SUPREME COURT REPORTS                 [ 1988] Supp. 2 S.C.R.

A period. The VIIth Schedule mentioned in Clause 3 above has not been
  included in the paper books with reference to which arguments have
  been addressed but a copy thereof was filed during the hearing and
  accepted as a correct copy by the both sides.

          8. This Regulation Order was substituted by another Order and
B   later by still a third Order, amending the penal rate and the Schedules
    to the Order. However, the learned counsel for the parties stated that
    except for change in the penal rate and the figures in the Schedules,
    the Order has remained the same all thro11g!i, and it is not necessary,
    therefore, to refer to the other Orders.

           9. So far as the Generation Order is concerned, it requires such
c   consumers, who have their private generating sets, to generate electri-
    city to the maximum extent technically feasible in the following terms:

               "3. Any consumer who is receiving electrical energy from
               the Board and also has an alternative source of generation
D              of power by his own generation set may be required by the
               respective Divisional Engineer of the Board having juris-
               diction to generate electricity from his set (or sets) to the
               maximum extent technically feasible in the opinion of the
               Divisional Engineer and the Board's supply of electrical
               energy to such consumer shall be reduced to the extent of
E              additional generation assessed as feasible by the Divisional
               Engineer;

               Provided that-

                     (i) Before assessing the additional generation feasi-
F                    ble and directing the consumer accordingly, the Divi-
                     sional Engineer shall consult the local Manager or
                     Engineer in charge of the set;

                     (ii) The Board shall, during the period such a direc-
                     tion is in force, reduce the contract demand of the
G                    consumer to a corresponding extent and

                     (iii) if due to an emergency outage, whichjn the opi-
                     nion pf the Divisional Engineer of the Board having
                     jurisdiction is not due to any negligence or failure of
                     those responsible for maintaining and running the
H                    set, there is reduction is additional generation, or if in
    JIYAJEERAO COTION MILLS v. ELECTRICITY BOARD [SHARMA, J.]          987

                     the opinion of the Divisional Engineer, the set has to
                                                                              A
                     be taken out for maintenance during the period of
                     such emergency or maintenance outage the Board
\                    shall try its best to make good the reduction to the
                     consumer, levying an appropriate charge for it."

    Its 6th Clause directed any dispute between the consumer and the          B
    Officer acting under Clauses 3 and 4 to be referred to the Electrical
    Adviser arid Chief Electrical Inspector to the State Government, for
    his decision.

          10. While Regulatioli Order was meant for general application
    to all consumers, the Generation Order was confined only to such
    consumers who were having captive power source. It is also manifest       c
    that such a consumer was under a duty to generate additional electri-
    city orily when the maximum technically feasible capacity of the
    generating set or sets of the consumer was assessed under Proviso (i)
    to Clause 3 and was followed by a direction to that effect. The main
    argument of the learned counsel for the appellant has been that none      D
    of the two assessments and directions contained in Annexures 'H' and
    'O' was sustainable in law on the grounds that-

         (a) in making the assessment of the technically feasible
         maximum capacity, relevant factors were not considered, and
         irrelevant and extraneQus matters were taken into account;           E

         (b) the requisite opinion was not arrived at and the assessment
         was not made by the authority empowered to do so; and

         (c) the participation of the appellate authority in process of
         assessment, corr.pletely vitiated. it in law.                        F

    Mr. Gupta argued that instead of examining the point on its merit, the
    High Court erroneously brushed it aside on the plea of waiver and
    acquiescence. Relying on a number of letters sent by the appellant to
    the respondent Board it was urged that the appellant Company was
    protesting against the impugned directions issued by the Board and it G
    is not right to shut it out on the technical ground of estoppel. Mr.
    Kacker, on the other hand interpreted the High Court's judgment
    differently. According to him, none of the points raised by the
    Company was rejected without examining the merits. He strongly
    relied of! some of the letters referred to in the argument of the
    Company itself as also a few other letters in support of his submission · H
    988         SUPREME COURT REPORTS              [1988] Supp. 2 S.C.R.

A that they furnished unimpeachable evidence including admissions on
  the part of the appellant Company proving that the assessment of the
  maximum feasible capacity of the appellant's captive power sets was
  duly made in accordance with the Generation Order and in pursuance
  thereof the required direction was issued which was acted upon by the
  parties for a number of years. The Company not only took steps to
B generate f!ie additional energy as was required of it, it also took
  advantage of the provisions of Proviso (iii) to Clause 3 of the Genera-
  tion Order and benefitted by it from time to time.

          11. For appreciating the argument of the learned counsel for the
    appellant it is necessary to examine some of the Orders and letters
C   issued in March and April 1975. As has been mentioned earlier, the
    two Government Orders were issued on 4.4.1975. It appears that the
    matter was being discussed by the different authorities of the State
    Government and the Electricity Board since before this date and
    advisability to require the consumers having captive power to generate
    as much energy as was technically feasible was under consideration for
D   some time. The question as to their capacity in this regard, naturally
    assumed importance and some steps for assessing the same were taken
    a few days before the Orders actually came into effect. On 28.3.1975 a
    letter sent from the Board to Sri H.K. Aggarwal, the Electrical
    Adviser and Chief Electrical Inspector to the State Government
    (Annexure 'R-1') referred to a telephonic talk in connection with the
E   assessment of the generating capacity of the captive power set. It was
    mentioned "that it would be necessary to make a realistic assessment
    in respect of each of the consumers" by keeping in mind the suggested
    factors. The letter further said that with that object the Board had
    constituted a Committee consisting of Sri Aggarwal himself, the
    Superintending Engineer of the concerned Circle of the Board and the
F   Divisional Engineer (Generation), Jabalpur of the Board as Members.
    The appellant Company is mentioned as one of the 17 consumers in
    this category. Along with his letter dated the 3rd of May 1975 Sri
    Aggarwal sent the report as desired. It has been contended on behalf
    of the appellant that the Generation Order authorised the Divisional
    Engineer of the Board to assess the additional feasible capacity of the
G   captive power source and any other person or authority or Committee
    could not usurp this jurisdiction. The impugned letter Annexure 'H'
    issued by the Divisional Engineer has been characterised as illegal on
    the ground that it was based upon the assessment by the Committee
    headed by Sri H.K. Aggarwal and not by the Divisional Engineer. The
    learned counsel proceeded to say that immediately after receipt of the
H   intimation by the Board, the Company protested on 21.5.1975. The
J!Y AJEERAO COTION MILLS v. ELECTRICITY BOARD [SHARMA, J. J        989

Board's reply dated 2.6.1975 has been relied upon as showing that the
                                                                       A
direction was issued on the basis of the assessment of the Committee
and not ·of the Divisional Engipeer. It was also pointed out that
_Electrical Adviser and Chief Electrical Inspector to the State
Government (the then incumbent being Sri H.K. Aggarwal) was the
appellate authority under Clause 6 of the Generation Order and could
not, therefore, take part in the original assessment proceeding. The R
reply of the Board is that the Committee no doubt inspected the
generating sets and discussed the matter with the consumers, and thus
collected relevant data for the purpose of assessment of the capacity,
but the Divisional Engineer while relying on the material collected,
did not mechanically accept the conclusion of the Committee. He (the
Divisional Engineer) applied his mind before issuing the Order C
Annexure 'H'. Mr. Kacker further said that the matter did not rest
there. After taking into account the objection raised by the Company
the Divisional Engineer took up the matter afresh and applied his
mind independently. Ultimately he came to a similar conclusion as is
evident by the second direction as contained in Annexure 'O' dated
10.10.1975. The argument of Mr. Kacker appears to be well founded.     D

      12. On receipt of the letter Annexure 'H' dated 17.5.1975
whereby the Divisional Engineer directed the Company io generate
2,500 K.W. of electricity by its own generating sets, the appellant
Company protested by its letter dated 21.5.1975 (at page 195 of the
Paper Book Vol. II). Mr. Gupta strenuously relied on this letter which    E
stated that the Company failed to understand as to how its additional
generating capacity had been assessed at 2,700 K.W. It will be neces-
sary to discuss this letter in some detail later in the judgment while
dealing with another point as Mr. Kacker also has relied on certain
statements made therein. At this stage, however, we should like to
point out that the appellant did not challenge the assessment on the      F
ground that it was not made by the authority mentioned in ihe Genera-
tion Order; and in the last paragraph the request made was for
"review". The next document referred to by the learned counsel for
the appellant is the letter dated 30.5.1975 (page 305 of the Paper Book
 Vol. II), wherein the Company stated _that:
                                                                          G
           "as desired by the Board, we have started generating about
           2,000 K.W. additional power at our generating station ....
           our Coal consumption has, therefore, increased by 70
           tonnes daily for this additional generation."

Finally a request was made in the letter to the Superintending            H
    990         SUPREME COURT REPORTS

A   Engineer of the Board to recommend the appellant's case for allot-
    ment of additional wagons for transport of coal. Instead of advancing
    the appellant's case, the letter shows that the assessment and the direc-
    tion mentioned in Annexure 'H' were accepted by the Company and
    steps were teken to implement the same. Chronologically proceeding,
    the letter dated 2.6.1975 (Annexure 'I' at page 122 of the Paper Book
B   Vol. II) was relied on by Mr. Gupta as proving the fact that the
    assessment of additional generating capacity had been done by the
    Committee mentioned in the letter dated 28.3.1975 (supra) and not by
    the Divisional Engineer as required by the Generation Order. The
    learned counsel for the parties next placed before us the letters dated
    3.6.1975 (document no. 3 at page 302 of the Paper Book Vol. II) and
    dated 4.6.1975 (document no. 1, at page 300 of the Paper Book Vol.
c   II), another letter of the same date (Annexure 'J' at page 123 of the
    Paper Book Vol. II) and then dated 8.8.1975 (Annexure 'K' at p:ige
    132 of the Paper Book Vol. II) and 10.10.1975 (Annexure 'O' at page
    136 of the Paper Book Vol. II).

D          13. The argument of Mr. Kacker has been that the Divisional
    Engineer applied his mind independently to the question of assess-
    ment of the capacity of the appellant's generating sets, and while
    so doing took in consideration the factual data collected by the
    Committee mentioned in the letter of 28.3.1975. It was pointed out
    that all the three persons constituting the Committee were very highly
E   placed officers and there could not be any legitimate objection if the
    Divisional Engineer referred to the data collected by them in presence
    of the Company's Officers after personally verifying them. Evel) a
    judicial tribunal or a regular court is allowed to rely upon evidence
    collected by an enquiry officer or commissioner. The learned counsel
    heavily relied on the letter dated 3.6.1975 from the Divisional
F   Engineer to the Superintending Engineer (document no. 3). On behalf
    of the appellant it was said that the Company had no knowledge of this
    letter in 1975. We do not think that this is a correct stand. The letter
    mentions an inspection of the Company's Power House by the Divi-
    sional Engineer and the materials supplied by the Company to him.
    The details with respect to the boilers of the Company and the other
G   figures mentioned therein, correctness whereof is not challenged by
    the appellant, fully establish that the inspection was made in presence
    of and the figures were collected with the assistance of the officers of
    the appellant Company and the conclusion regarding the assessment
    was reached after taking into account the case of the Company. It has
    been argued on behalf of the Board before us ihat the method adopted
H   by the Divisfonal Engineer as disclosed by this lettter (document
                      /
   JIYAJEERAO COTTON MILLS v. EI.ECTRICITY BOARD [SHARMA, J .]          991

   No. 3) was different from that followed by the Committee, as a result
   of which there was some difference in their final result. On the basis of A
   his independent assessment the Divisional Engineer issued another
   instruction as contained in Annexure 'O' dated 10.10.1975 (at page
    136 of the Paper Book Vol. II), mentioned earlier. This second direc-
   tion which was effective from 31.10.1975 naturally superseded .the
   earlier one under· Annexure 'H'. The Board's impugned demand does · B
   not relate to any period before 31.10.1975 and, therefore, it is immate-
   rial if the direction in Annexure 'H' is completely ignored on account
   of its supersession by Annexure 'O' or on any other ground and it be
   assumed that in absence of a feasible assessment of the capacity, the
   Generation Order was nor applicable to the appellant Company before
   31.10.1975.
                                                                               c
          14. Mr. Gupta relied on the letter dated 4.6.1975 (document
    No. 1), referred to above, for showing that the Company emphatically
    protested against the assumption that it could generate additional 2500
    K.W. It was said that its capability ir, this regard was limited to 1200
    K.W. The learned counsel referred to the other letters also for a          o
    similar purpose. We think that in view of the revised order of the
    Divisional Engineer passed on 10.10.1975, vide Annexure 'O', earlier
   correspondence is not matedal for the purpose for which the appellant
   is trying to use them. The learned counsel for the respondent has
    relied on some of them for his argument on the other poinis and we
   will have to deal with them again when we take up those points. So far      £
   as the question as to whether an assessment of the feasible capacity of
    the generating sets of the appellant Company was made by the Divi-
    sional Engineer as required by the Generation Order is concerned, we
   .have no hesitation in deciding the issue in favour of the respondent.

        15. On behalf of the appellant it was urged that since the Electri-    f'
• cal Adviser-cum-Chief Electrical Inspector of the State Government
  _who has been mentioned as the appellate authority under Clause 6 of
  the Generation Order was associated with the assessment by acting as
  a member of the Committee (vi de Annexure 'R-1' at page 256 of the
  Paper Book Vol. II), the entire process in this regard should be held to
  be completely vitiated. In view of our finding in the preceding              G
  paragraph, the argument has to be rejected. Besides, it is not correct
  to assume that an appeal against the assessment was provided by
  Clause 6 of the Generation Order which reads as follows:

               "6. ln case of any dispute between the consumer and the
               Divisional Engineer acting under Clauses 3, .and 4, it ;shall H
    992         SUPREME COURT REPORTS               [ 1988) Supp. 2 S.C.R.

               be referred to the Electrical Adviser and Chief Electrical
A              Inspector to the Government of Madhya Pradesh whose
               decision sball be final."

    The above is obviously an arbitration clause in case of a dispute and
    since the maintainability of the appellant's writ application before the
B   High Court was decided·in)ts favour, it cannot make a grievance on
    this score. Besides, if the appellant Company had a grievance against
    the assessments which were made in 1975, it ought to have challenged
    the same then and not to have waited for a number of years before
    approaching the High Court.

          16. Mr. Gupta challenged the assessment still on another
c   ground. He contended that while making the assessment, the relevant
    factors were ignored, and irrelevant and extraneous considerations
    were taken into account. The argument which is based on certain
    scientific technical hypothesis proceeded thus: The Company had 3
    Generator Sets described as M.V. Turbo Generator Set, B.B. Turbo
0   Generator Set and AEG Turbo Generator Set; and five Boilers.
    Another Boner was added in 1977. Every generator set has a rated
    capacity which has been described by the learned counsel as the level' at
    which operation can continue satisfactorily for indefinite period. Th,is
    rated capacity is declared by the manufacturer and can be accurately
    ascertained without difficulty. The terms 'overload' and 'overload
E   capacity' have been explained by the learned counsel as "one exceed-
    ing the level •at which operation can continue satisfactorily for an
    indefinite period" and "excess capacity of a generator over that of its
    rating", respectively. It was urgued that overloading may lead to dis-
    tortion or to overheating with risk of damage, depending on the type
    of circuit or device, and so in many cases only temporary overloads are
F   permissible. The overload capacity, it has been said, is referrable
    generally for a specified time. The criticism against the report of the
    Committee is that the Committee took into account the overload
    capacity of the sets and not the rated capacity. Mr. Gupta stressed on
    the point that the AEG Turbo Generator Set was maintained as a
    standby to be operated only when other sets were not available for any
G   reasons. He also said that the feasible generation capacity of a set is
    also dependent on other factors and conditions, namely, age and
    condition of the set, availability of coal of requisite quality and speci-
    fication, adequate and continuous supply of water etcetera. Referring
     to the report of the Divisional Engineer dated 3.6.1975 (document
     No. 3 at page 302 of the Paper Book Vol. II) it was argued that the
H    Divisional E11_gineer picked out a moment of time when the plants
-..
     I   JIYAJEERAO COTTON MILLS v. ELECTRICITY BOARD [SHARMA,J.]                993

         reached the generation of 7500 K.W. and concluded therefrom that
         the appellant was capable of generating 1800 extra K.W. from its               A
         captive plant. It was further suggested that in any view of the matter
         on the basis of the aforesaid opinion of the Divisional Engineer the
         appellant Company ought to have been asked to generate only 1800
         K.W. more and not 2500 K.W. Finally it was argued that the Board
         has to be confined to the reasons in support of the assessment orders          B
         which are mentioned therein and cannot be allowed to travel beyond
         the same.

               17. Mr. Kacker took great pains in going into the reports and
         specially through the aforementioned report of the Divisional
         Engineer dated 3.6.1975, with a view to meet the criticism of the
         appellant and support the report as a correct one on merits. He also           C
         relied on a number of letters sent by the appellant showing that the
         assessment was accepted as binding on it and claiming from time to
         time benefits under Proviso (iii) to Clause 3 of the Generation Order
         which was allowed for a number of years. The learned counsel relied
         on this aspect as furnishing strong circumstantial evidence in support         D
         of the correctness and binding nature of the assessment impugned
         belatedly when the appellant approached the High Court.

                18. It is significant to note that at no point of time either in 1975
     t   or later the appellant chose to get a scientific assessment of its generat-
     I   ing sets made by all" expert, nor even after filing the present writ           E
         petition in the High Court did it file any opinion of a person having
         scientific expert knowledge showing the impugned assessments to be
         erroneous or undependable. It is also important to appreciate that the
         appellant has not either earlier or now made any complaint of ma/a
         fides or bias against any of the members of the Committee or the Divi-
         sional Engineer or for tha·t mattter against any officer of the respon-        F
,.       dent Board or the State. On the other hand, the Officers of the Board
         appear to have taken a very sympathetic attitude towards the appellant
         for more than four years and allowed it the benefit of additional
         energy under Proviso (iii) to Clause 3 of the Generation Order very
         generously. It was only when the Board discovered in 1980 that the
         appellant had stopped even informing the Board and obtaining its               G
          prior approval as envisaged by the Generation Order before consum-
         ing extra energy that the matter was closely examined by the Board's
          Officers. Mr. Kacker is also right in relying upon the conduct of the
          parties for about four or five years after the assessment was made as
          furnishing importa,nt circumstance relevant to the issue. We may,
         therefore, examine a number of letters in this regard some of which            H
          have already been mentioned earlier.
     994         SUPREME COURT REPORTS                 [1988] Supp. 2 S.C.R.

            19. The very first letter of the appellant Company after receiving
     the impugned direction in Annexure 'H' dated 17 .5 .1975 was sent
     within 4 days on 21.5.1975 and is included at page 195 of Vol. II of the
     paper book. It will be seen that the protest against the assessment
     ·referred to by the learned counsel for the appellant was not founded
     on any of the grounds pressed now. The basis was "only due to steam
B    limitation", assuring that "once our boiler under erection starts steam-
     ing, we can enhance our generation to the full installed capacity." The
     prayer in the end of the letter was to "review the whole matter". The
     Divisional Engineer, as mentioned earlier, personally examined the
     entire matter be novo. Although in its letter dated the 21st May 1975
     the Company had stated that it was not advisable to generate more
     than 12 K.W. from its own sets, by the next letter dated 30.5.1975
      (page 305, Vol. II) the appellant informed the Board that they were
     generating about 2000 additional K. W., but were in the need of addi-
     tional coal, for which the Board was requested to make a recommen-
     dation. In Annexure 'J' dated 4.6.1975 (page 123 Vol. II) the protest
     against the assessment was once more reiterated on account of some
D    trouble with the boilers. The first paragraph of this letter indicates that
     the question was under discussion of the Divisional Engineer with the
      Company's representatives who was armed during the conference
      "with all relevant records". In this background the fresh independent
      assessment was made by the Divisional Engineer as per the document
     No. 3 dated 3.6.1975 (page 302, Vol. II). Before the fresh independent
E     direction by the Divisional Engineer as contained in the impugned
     Annexure 'O' dated 10.10.1975 was issued, a suggestion was made on            •
     behalf of the Board to the appellant Company for its satisfaction as to
     the correctness of the assessment by "actually taking the load on the
      set, after running it in parellel with the Board's supply system". The
     learned counsel for the parties before us explained the scientific impli-
H    cations of the test by "parellel running", but we do not consider it
     necessary to go in its technical details. The Board requested the Com-
     pany's consent for such a test, to be communicated positively within a
     week. By its reply dated 25.8.1975 Annexure 'L' (page 133, Vol. II)
     the Company rejected the suggestion on two grounds, namely, that it
     was "not having protection system like power relay etc." and "in case
<1   of tripping of Board's supply we would be doing the parellelling of the
     sets"; which was not safe. In reply thereto the Board satisfactorily met
     the objections by its next letter Annexure 'M' dated 25.10.1975 (page
      134, Vol. II). It was pointed out that the parellel running test will be
      undertaken only for a short period after which the captive sets would
     be separated from the Board's system; and a disturbance free period
H    could be chosen for the same. Besides. the objections to the suggested
JIYAJEERAO COITONMILLS v. ELECTRICITY BOARD [SHARMA, J.]           995

test have to be rejected as frivolous in view of the stand of the Com-
                                                                          A
pany itself as indicated in the letter Annexure 'N' (page 135, Vol. II)
dated 6.11.1975, stating that it had no objection into the suggested
trial, which the appellant claims to have sent to the Board which fact is
however denied. In the meantime the second assessment order under
Annexure 'O' had already been communicated. It was, therefore,
open to the appellant either to accept and act upon this fresh assess-
ment or to go in for a further check as mentioned by the Board. The
appellant did not pursue the matter at all and observed silence on the
suggestion for the parellel running test. Mr. Gupta, however, con-
tended that the offer in the letter dated 25.10.1975 was accepted by the
appellant in its Jetter dated 6.11.1975, Annexure 'N' mentioned above.
Mr. Kacker asked the Court to disbelieve the Company's assertion of
having sent this letter and pointed out that a perusal of all the letters
                                                                          c
sent from the Company to the Board would show that none of them
was ever sent to the Joint Secretary (V) except Annexure 'N'. The
production Manager of the appellant Company under whose signature
the Jetter is claimed to have been sent also does not appear to have
been taking any interest either earlier or later than this letter. Mr. D
Kacker alternatively contended that assuming that such a letter was
actually sent by the Company to .the appropriate authority of the
Board, it does not stand to reason as to why the Company did not send
any reminder, and remained satisfied for more than four years, asking
for benefits from the Board on the basis of the assessment in Annexure
'O' having. been appropriately made. The argument of Mr. Kacker E
appears to be well founded. It is significant to note that the appellant
 had not accepted the offer as wrongly claimed by it, on the basis of the
Jetter Annexure 'N', but at' the same· time the said letter does indicate
that tJle suggested parellel running test was feasible and there was no
justification to reject it on the flimsy grounds mentioned by the appel-
lant on 25.8.1975 (Annexure 'L'). The conclusion is irresistible that F
the appellant Company-Oacked out without adequate reason from the
realistic test proposed by the Board to check the correctness of the
assessment.

      20. Before proceeding to examine the other letters, strongly
relied upon on behalf of the respondent Board, it may be useful to G
recall that the Company had mentioned the inadequate capacity of the ·
boi!er5 in. steam geilera\ion as the ground for not being able to gen-
erate additional electricity as required by the impugned directions. It
was also mentioned that after a sixth boiler became available, the
difficulty would stand resolved. In this background Mr. Kacker placed
before us several letters starting with the letter of the Company dated H
    996         SUPREME 'COURT REPORTS               [1988] Supp. 2 S.C.R.

  14.2.1977 (at pages 4 to 8\of additional paper book prepared and filed
  by the respondent Board, which was referred to by the learned counsel
  as Vol. IV of the Paper Book). The Company, by this letter requested
  the Board to charge at the normal tariff for the additional electricity
  consumed by the Company as emergency supply as per Proviso (iii) to
  Clause 3 of the Generation Order. The statements made in the letter
B appear to be extremely important for the purpose of the Board's case
  and it may be useful to consider them in some detail.

          21. In the first paragraph the Company stated ·that it was again
    placing for the Board's consideration, the reasons why it could not
    generate the additional power according to the direction issued. In the
    second paragraph the main difficulty has been mentioned as steam
    limitation and reason therefor has been. stated in the third paragraph
    as the inferior quality of coal. Later it was stated thus;

               "These problems would not have arisen in case our Sixth
               Boiler recently erected was commissioned and running
D              without any trouble."

    It was said that although the sixth boiler was taken in August, it did
    not work properly for some time. Proceeding further the letter stated:

               "It is only since the beginning of January the Sixth Boiler
               has been in continuous service, as a result of which we were
               in a position to repair our other Boilers also.

                      Since the last week of January, we are generating our
                full requirement .and not even availing the 600 K.W.
                allowed by the Board."
F
    In the penultimate paragraph of the letter, the case for normal tariff on
    the additional electricity already supplied by the Board was argued in
    the fqllowing manners:

                "Considering all the above facts, we sincerely hope, that as
                due to no fault of our own we had to take power from M.P.
                E.B., more than allotted to us, it is requested that the
                charges made to us may be on the usual terms as previously
                granted by the Board for which we will be ever grateful."
                                                          (emphasis added)

H The letter is not only conspicuous by the absence of the objections
    J!Y AJEERAO COITON MILLS v. ELECTRICITY BOARD [SHARMA, J. I          997

    which were taken later in 1980 before filing of this writ case, but it
    positively indicates that the Company accepted the assessment as cor-       A
    rect, and as expected, it was actually able to generate the required
    additional electricity after the addition of the sixth boiler and was
    pleading for normal tariff for the additional electricity already con-
    sumed earlier. This position is re-inforced by several further letters of
    the Company, but before we go to them we would like to point out            B
    another very important fact emerging out of this very letter. At page 7
    of Vol. II of the paper book the letter dealt with another aspect highly
    relevant to the present dispute. Another Limited Company known by
    the name of "Gwalior Rayons" is having a factory near thy appellant
    Company's factory and the appellant was supplying electric energy to
    the other factory illegally and without the permission of the Board. On
    an objection by the Board this matter was dealt with in the following       c
    words:

                "It is not out of place to mention in this appeal that we had
                given now and then some power in the past to the Gwalior
                Rayons, in emergency for their Beam Dyeing Plant                D
                whenever M.P.E.B. power failed. This was due to the fact
                as the Heam dyeing plant is a pressure dyeing plant, with a
                continuous process, there used to be heavy damage to very
                costly Beams. Since this issue was raised by your Divisional
                Engineer, we have completely stopped this type of supply
                to them, though the same was given to them after reducing       E
                our humidity or waste plant load.

                     It is again our request here that the same may be
                allowed in emergency under whatever arragement the
                Board may so decide to avoid costly damage to the cloth."
                                                                                F
    A fervent appeal in the interest of the other factory belonging to a
    different Limited Company altogether was made in the above terms. It
    has to be remembered that in view of the provisions of s. 28(1) of the
    1910·Act, the Company was prohibited from supplying any energy to
    the-other factory. This aspect was stressed in term 2(b) of the agree-
    ment between the appellant and the Board as per Annexure 'A' (page          G
    62 of Vol. II). It was not the appellant's case then or before us now
    that it had obtained the previous sanction of the State Government for
    so doing. Under Cluase 4 of the Generation Order, which reads as
    follows, jurisdiction was vested in the Divisional Engineer of the
/
    Board to direct a consumer having captive source of power to supply
    electricity to the Board or to any other consumer only if the consumer      H
    was having surplus generation:
    998        SUPREME COURT REPORTS                 I1988] Supp. 2 S;C.R.
               "4. If the consumer having own generating set(s) can have,
A
               as a result of additional generation reasonable in the
               opinion of the Divisional Engineer of the Board having
               jurisdiction, energy, surplus to his requirement, the
               Divisional Engineer may direct him to supply the surplus to
               the Board or to another consumer nearby who has been
B              taking supply from the Board and who is willing to take the
               supply from the consumer having generating sets:

                     Provided that

               (i) the contract demand of and the supply to the other
               consumer from the Board shall be reduced correspon-
c              dingly, whether or not the other consumer avails of the
               supply from the consumer having the set,

               (ii) the other consumer shall pay to the consumer having
               generating set(s) for such supply as if it is supplied from the
D              Board,

               (iii) if the payment receivable by the consumer having the
               set under the last preceding clause is less than his incremen-
               tal cost of additional generation, the Board shall make
               good the difference to the consumer having the set(s) and
E
               (iv) the consumer having the set(s) will not be required to
               incur any additional expenditure for laying lines for trans-
               mitting energy to the other consumer; such lines if required
               being laid by and at the cost of the Board."

F How could, in these circumstances, the appellant pass on to a third
  party some of the electricity meant for it, there is no explanation on
  the records. Mr. Gupta the learned counsel for the appellant argued
  that since the other factory was in the neighbourhood it was in the
  interest of the appellant Company for the sake of security to see that
  ot!Jer factory was not plunged in darkness when the supply was inter-
C nipted on account of tripping. Mr. Kacker rightly pointed out that no
  such suggestion was evq made on behalf of the appellant in any of its
  letters. On the other hand, the reason pleaded in the letter quoted
  above was to save the other Company from incurring loss due to costly
  damage to the cloth. In his final reply Mr. Gupta said that the appel-         \
  !ant was passing on some electricity to the Gwalior Rayons only after
H reducing its humidity or waste plant load as stated in the letter. The
J 1Y AJ EE RAO COTTON MILLS v. ELECTRICITY BOARD [SHARMA, J.]         999

explanation is too vague and it cannot be assumed that the appellant         A
was making the contribution to its sister concern by creating artificial
shortage of supply to its mills. The appellant's conduct cannot be
explained except on the premise that it was able to generate adequate
additional electricity for its purpose and was taking for granted the
sympathetic attitude of the Officers of the Board in liberally allowing it
additional emergency supply at normal tariff.                                B

      22. Another letter which calls for a detailed consideration was
sent by the apellant on 30.5.1979 and is included at pages 16 to 20 of
Vol. IV. A fresh request for emergency supply under Proviso (iii) to
Clause 3 of the Generation Order was made in this letter on the
ground that the sixth boiler was out for annual overhaul. It was stated
in the opening sentence that this boiler was giving some trouble earlier
                                                                             c
but later 'stabilised'. The Company was, therefore, self-sufficient
"without drawing any power from the Board so far". The letter
proceeded to state that the sixth boiler would be going for annual
overhaul and after that the annual overhauling of the other boilers
would be carried out; and therefore, 1875 K.W. should be allowed to          D
be drawn for the period mentioned therein. Assurance about the
future was held in the following terms:

            ·'Now when our Sixth Boiler has been stabilised we would
            normally not draw any power from the ~Board after
            15.9. 1977 when overhauling of all the boilers is complete       E
            except in case of emergency due to outage of any of the
            boilers.··

It was further requested thar during the period of breakdown
emergency power as detailed should be supplied and,
                                                                             F
            "we would request you that for the power availed by us
            from the Board for above purpose, say up to a total of 7
            days in a month, we may be charged at the same tariff".

Insisting again that it should be allowed to supply electricity to
Gwalior Rayons, described as its sister concern, the letter read as          G
follows:

                  "Here we may also mention that we have been
            supplying power to our sister concern Mis Gwalior Rayons,
            in accordance with the provisions of sanction granted to
            us under Section 28 of the I.E. Act vide Govt. Order             H
    1000        SUPREME COURT REPORTS              [1988) Supp. 2 S.C.R.

               No. 1313/6061/XIIl/74 dated 8.4.1975. However. it had not
A
               been possible for us to obtain prior permission from S.E.
               Gwalior before switching over power to Gwalior Rayons. It
               may be mentioned here that power has to be supplied to
               Mis Gwalior Rayons during the period the Board's supply
               remained off, and it is not practically possible to obtain
B              prior permission for supply in such cases. We would, there-
               fore, request you that prior permission should be given
               once for all for supplying power to the Gwalior Rayons
               during the period supply from the Board to Mis Gwalior
               Rayons remained off.··

  This letter dated 30.5.1977 confirms the conclusions derived from the
c earlier letter dated 14.2.1977 and clarifies that the first letter was not
  sent by some mistake on the part of the appellant Company. Request
  for emergency supply was, however, made from time to time in 1978
  and for some time in 1979, which was allowed by the Board. The other
  letters including those dated 30.5.1978, 29.6.1978, 7.7.1978 and
D 9. 9. 1978 are all consistent with a correctly made binding assessment of
  the feasible additional capacity from the generating sets belonging to
  the Company.

         23. Mr. Gupta contended that throughout the period 1975 to
    1979 there was never a demand made by the Board for any energy
E   consumed by the appellant at the penal rate and it was only in 1980
    that the Board suddenly decided to press for the additional demand on
    the basis of the Generation Order. The learned counsel emphasised
    that before the provisions of the Generation Order can be relied upon
    by the Board it is essential fer it to make an assessment of the consu-
    mer's capacity to generate electricity from its captive power plant. The
F   fact that no demand was made for many years leads to the conclusion
    that such an assessment as required by the provisions of the Generation
    Order to be made, had not in fact been made, and alternatively assum-
   ing that factually the capacity had been assessed, the same must be
   ignored on account of the conduct of the parties for several years. The
   stand of Mr. Kacker, as has been stated earlier, is that the parties.
G acted on the basis that an assessment had been made in accordance
   with the Generation Order and on that basis the appellant demanded
   the benefit under Proviso (iii) to Clause (3) of the Order. The docu-
   ments relied on by him and discussed in the preceding paragraphs
   support the respondents' stand. They also explain as to why demand
   on the penal rate was not made earlier, but it would be helpful to          \
Hi consider a few more facts relevant to this aspect.
        JIYAJEERAO COTTON MILLS v. ELECTRICITY BOARD [SHARMA . .I.]           1001

              24. The system of supply of power to the consumers is such that
                                                                                      A
        they can go on drawing electricity beyond their entitlement without
        any further positive step by the officers'of the Board. The Board is,
        however, in a position to, by keeping a certain swi.tch known as Air
        Break Switch open, put a restriction on the consumer fro\11 drawing
        excess energy. A letter dated 4.6.1975 (document no. 1, at page 300 of
        Vol. II) sent by the appellant has been strongly relied on by Mr.             B
        Kacker for showing that Air Break Switch was permitted to remain
       ·closed with a view to assure uninterrupted supply to the appellant at its
        request. The result was that the appellant was in a position to draw
        excess electricity without reference to the officers of the Board. That
        letter indicates that the Board was contemplating to keep the switch
        open and the Company by this letter made a request not to do so. The
        appellant Company was fully conscious of the fact that it was consum-         c
        ing electricity beyond its entitlement under the two Orders, by claim-
        ing the benefit of the provisions dealing with emergency supply, and
        was also alive to the fact that this hag to be done only with the prior
        approval of the Board. The relevaq.t portion of the letter is in the
        following terms:                                                              D

                    "Further at no time it m~y kindly be noted that power has
                    been availed from MPJ;rn without prior intimation by
                    phone either to Divisional Engineer or Supdt. Engineer.
                    By keeping the A.B. Switch open at your end, the delay in
                    supply to J.C. Mills will :be considerable which will cause       E
                    very heavy losse~ to the fc. Mills for no fault of their own.
                    This may kindly be revie~ed and .... ".

         The learned counsel for the Board was right in saying that on account
         of this request by the appellant the line was kept open for it unhin-
         dered. This did not mean that the Company was entitled to misuse the         F
       , privilege, draw extra energy without prior permission and thereafter
         refuse to pay higher charges when demanded. It has been conclusively
         established by a large number of letters on the records of the case that
         for several years the Company was particular in obtaining the permis-
         sion of the Board for drawing electricity in excess of what it was
         entitled to, by the agreement as modified by the Regulation Order and        G
         Generation Order, but later, it not only stopped seeking the advance
         sanction in this regard, it di<;! not even care to inform the Board of the
         excess drawal. The Branch of the respondent Board at Gwalior sent
• .}     the bills on the basis of the normal tariff, as the question of grant of
         additional emergency supply was being dealt with by the Head Office
         at Jabalpur. The Gwalior Office. was not at all dealing with the matter      H
     l002        SUPREME COURT REPORTS               11988] Supp. 2 S.C.R

A    relating to the excess emergency supply which aspect was being exclu-
     sively dealt with at Jabalpur, and as soon as the relevant facts came to
     the knowledge of the Head Office of the Board it took up the matter
     with the appellant Company. The entire conduct of the parties furni-
     shes strong circumstantial evidence m support of the Board's case.

B           25. Another argument addressed by Mr. Gupta is based on the
     letters Annex. 'P' series sent by the Board to the .appellant Company
     from time to time. They have been included at pages 137 to 156 of Vol.
     II of the paper book, and according to Mr. Gupta they are inconsistent
     with the Board'; case regarding the appellant's entitlement to receive
     the amount of energy from the Board. He has pointed out that these
     letters do not suggest that the contract demand had been reduced to nil
c    in accordance with Annexures 'H' and 'O'. By way of illustration he
     relied on the letter dated 31.10.1975 (at page 138 of Vol. II) stating
     that the Company's "maximum demand should not exceed 1875 KW".
     We do not find any merit in the submission. The letters marked as 'P'
     series did not deal with the entitlement of the appellant Company as a
D    result of both the Orders-Regulation and Generation. The Regula-
     tion Order was of universal application to all the consumers while the
     Generation Order applied to only such of them who had their own
     generating sets. Under the Regulation Order the contract demand was
     reduced by a certain percentage and provided for payment of charges
     at penal rate in case of excess consumption. The rate of cut and the
E    penal rate for additional consumption did not remain constant, and
     were revised from time to time. It appears that as and when the revi-
     sion in the rates took place the consumers were informed as to the
     effect of the Regulation Order as it stood after modification. Mr.
     hacker was right in saying that since the Regulation Order was appli-
     cable to all the consumers and letters similar to those marked as
F    Annexure 'P' series were being addressed to all of them, there could
     not be any objection in the Board sending similar letters to the appel-
     lant and others having their private generating sets dealing with the
     effect of the Regulation Order alone, without taking into account the
     Generation Order. A perusal of these letters fully supports the
     respondents' stand that they were being issued with reference to the
c;   Regulation Order alone. Further, a close examination of the Genera-
     tion Order would show that the maximum permissible limit available
     under the Regulation Order had not ceased to be relevant even after
     the application of the Generation Order. The entitlement of the appel-
     lant due to emergency outage under Proviso (iii) to Clause 3 of the        '\ <
     Generation Order was limited to the original contract demand as
H    reduced by the Regulation Order." It was, therefore, important for the
JJYAJEERAO COTTON MILLS v. ELECTRICITY HOA RD iSHARMA,J.l            1003

appellant to keep in mind that at no point of time it could be entitled to
                                                                             A
ask for beyond this limit as emergency supply on any ground what-
soever. As this limit fluctuated from time to time on the change in the
percentage of reduction in the Regulation Order, the appellant was
rightly reminded of the latest position in this regard. The learned
counsel for the respondents was also right in saying that these letters
could not have misled the appellant in any manner. The numerous              B
letters discussed earlier clearly indicate that the appellant correctly
appreciated its position and repeatedly made requests for emergency
supply under the Generation Order on the assumption that its entitle-
ment had been rendered to zero. The appellant's letter dated 30.5.1977
(at page 16 of Vol. IV) referred to earlier, fully demonstrates that the.
plea raised by the appellant is devoid of any merit. A portion of the
said letter (not dealt with earlier) is in the following terms:
                                                                             c
            "During the period of break down we would request you to
            agree to the following arrangement:

                 i. Before availing Board's power during the emer-           D
            gency we will intimate the B.E., MPEB, Gwalior as well as
            S.E.MPEB, Gwalior and send a copy of our letter to the
            Director (Com), MPEB, Jabalpur.

                 ii(a) In case 6th boiler is out and other boilers are
            working satisfactorily we may be allowed to draw power           E
            upto 1200 KW.

                  (b) In case 6th boiler is on range and one ofour M. V.
            boilers is out we may be allowed to draw power upto 1200
            KW.
                                                                             F
                  (c) In case 6th boiler is not and one of our M.V.
            boilers is also out, we may be allowed to draw ·power upto
            1875 KW."

If present stand of the appellant be assumed to be correct, there was
no occasion for it to claim varying quantities of power in changing          G
circumstances as mentioned above.

      26. It was also urged on behalf of the appellant that the Board's
letter dated 13.10.1980, Annexure 'U', (at page 182, Vol. II)
impugned by the appellant is also inconsistent with the Board's stand
in the present case. By this letter the appellant was informed that the      H
    1004         SUPREME COURT REPORTS               [1988] Supp. 2 S.C.R.

   contract demand of 3490 KW as per the agreements between the
A  parties was going to be reduced to 1250 KW under the provisions of
   the Generation Order, and on further reduction under the Regulation
   Order it would come down to 875 KW only. The appellant was accor-
   dingly directed to draw power upto 875 KW with effect from 1.8.1980.
   The Board further informed the appellant that no. additional power
B will be supplied during the period of overhauling of the private
   generating sets. This part of Annexure 'U' has been set aside by the
   High Court on the ground that under Proviso (iii) to Clause 3 of the
   Generation Order the Board was under a duty to permit the appellant
   to draw additional electricity on satisfaction of the relevant conditions
  .for emergency supply, which it could not deny. The Board has not
   challenged this part of the High Court's decision, and the same is not
c  relevant for purposes of the present appeal. Reliance on behalf of the
   appellant has been placed on the earlier part of the Jetter directing it to
   limit its drawal to 875 KW. Mr. Gupta explained the situation thus:
   The contract demand as per the original agreement and the subsequent
   agreements by the date on which the letter was issued admittedly was
D  3490  KW. If the Board's case that the appellant's capacity to generate
   electricity from its own sets was assessed at 2500 KW be accepted as
   correct, then the appellant would have been held entitled to draw 990
   KW only and not 1250 KW as mentioned in the Jetter. Mr. Gupta
   invited us to consider this aspect along with the Board's earlier Jetter
   Annexure 'R' dated 28.12.1979 (page 158 of Vol. II), informing the
E appellant that additional power to the extent of 190 KW had been
   sanctioned. The admitted position in regard to different agreements
   between the parties is that initially the parties enterd into a contract
   with respect to 1500 KW only which was later raised to 2500 KW. The
   Regulation and Generation Orders came into existence at that stage.
   In July 1979, a supplementary agreement was executed between the
F parties for supply of additional 800 KW and in December 1979 the
   Board further sanctioned 190 KW. The relevant part of the letter
   relied on by Mr. Gupta is quoted below:

                "The Board has sanctioned 190 KW additional power (over
                and above 3300 KW) at 33 KV subject to the following
G               conditions:



                                                                                     .
                      (I) The Contract Demand shall be reduced in terms
                of Govt. Control Order No. 1254/2048/XIII/75 dated
                4.4.75 after the decision of the Committee headed by the         \
                Electrical Adviser & Chief Electrical Inspector to Govt. of
H               M.P. regarding re-assessment of the capacity of the con-
                sumer's generating set is known."
 JIYAJEERAO COTTON MILLS v. ELECTRICITY BOARD [SHARMA, J. I            1005

 The argument is that the Board could mention about a Committee                A
 proceeding to assess the capacity of the consumer's captive plant only
 if there had not been earlier any assessment. The reduction in the
 contract demand under the Generation Order should have been made
 after the assessment work was completed, but as a matter of fact, no
 such assessment was made and ultimately the letter Annexure 'U'
 dated 13.10.1980 was issued arbitrarily without any basis. In absence         B
 of an assessment of the capacity under the Generation Order, no
 reduction was permissible.

        27. Mr. Kacker's reply is that since the appellant for the period
  of more th.an 4 years was pleading for emergency supply from time to
  time on one ground or the other, an internal Committee of S'!perin-          C
  tending Engineers which had visited the Company's plant on 25.9.1980
  suggested that the appellant Company be granted additional power to
  the extent of 260 KW on regular basis instead of examining the
  grounds relied upon by the appellant every now and then. The latter
  part of the letter informing the appellant that it would not in the future
, be supplied additional power on the ground of emergency has been             D
  referred to in support of this argument. Mr. Kacker further said that
  unfortunately the Board was held liable for the emergency supply if
  the necessary conditions were satisfied and thus the appellant·has
  got double advantage and this cannot be the basis for accepting the
  appellant's case. The learned counsel proceeded to say that the letter
  Annexure 'R' was issued. in connection with the sanction of 190 KW           E
  additional power, subject to the Government Orders, and the reduc-
  tion thereunder was only a matter of arithmetical calculation which
  should have been done without reference to a Committee. The letter
  was not sent in connection with any controversy about the assessment
  of the generating capacity under the Generation Order, and it cannot
  be interpreted in the manner as suggested on behalf of the appellant. It     F
  was further pointed out that admittedly there. was no question of a
  committee headed by the Electrical Adviser and Chief Electrical
  Inspector to the Government of Madhya Pradesh to make a fresh
  assessment under the Generation Order or to undertake the realistic
  assessment of the additional capacity over again. The assessment had
  to be made by the divisional Engineer of the Board. It was lastly said       G
  that this argument addressed by Mr. Gupta before this Court was not
  advanced before the High Court nor was the point taken in the writ
  petition or any affidavit there. On a consideration of the documents
  and the r devant circumstances we agree with Mr. Kacker. The use of
 the word "re-assessment" in the letter guoted above instead of "assess-
 ment" also supports the respondents' case. The term "re-assessment"           H
    1006        SUPREME COURT REPORTS              I 1988] Supp. 2 S.C.R.

A implies that there had· already been an assessment earlier. Even
  interpreting the letter as suggested by Mr. Gupta, the existence of the
  earlier assessment by the Divisional Engineer cannot be ignored. If the
  appellant was not satisfied with it, it should have taken appropnate
  step for getting the same quashed in 1975 itself and should not have
  waited for four or five years before approaching the High Court, and
B in the meantime taking the benefit of the provisions regarding
  emergency supply on its basis.

        28. Now in this background let us come back to the argument of
  Mr. Gupta as mentioned earlier in paragraph 16 above. In reply Mr.
  Kacker asserted that it is not correct to assume that a machine can
C function on a regular basis only according to the rated capacity as
  declared by the manufacturer. By way of illustration he relied upon
  the specifications relating to a machine issued by the Bharat Heavy
  Electricals Ltd. indicating that the "Peaking capacity" of the machine
  with "No time limit" was higher than the "rated output" mentioned.
  The learned counsel also analysed the report of the Divisional En-
o gineer along with the data mentioned by the Committee which in his
  opinion indicated that the maximum capacity of the appellant's sets
  technically feasible was much more than that actually assessed and
  could not be less by any calculation even before the 6th boiler was
  erected. After the sixth boiler became available the capacity rose to at
  least 9700 KW but the Board taking a generous view did not call upon
E the appellant to generate further additional electricity than that
  directed earlier.

          29. We have heard the learned counsel at considerable length on
    this aspect and we think that the question as to what should be
    considered the correct feasible capacity of the appellant's sets is one
F   involving complex technical knowledge and the High Court (or for that
    matter this Court) was well advised not to have attempted to
    determine it. We must reiterate the circumstances which appear to be
    highly relevant, namely, (i) that the Divisional Engineer who has been
    rightly considered by the Generation Order to have sufficient expert
    knowledge in this regard reached the conclusion which is under
G   challenge in the present case after personally considering the matter
    thoroughly along with the Officers of the Company as is apparent by
    many of the letters; (ii) the figures collected by the members of the
    Committee are not challenged as incorrect or inaccurate; (iii) it is not
    suggested that any of the members of the Committee or the Divisional
    Engineer or for that matter any Officer of the respondent Board or of
H   the State Government had any prejudice or bias against the appellant
JIYAJEERAO COTION MILLS v. ELECTRICITY BOARD [SHARMA. J.[            1007

Company; (iv) the appellant did not get an independent assessment of         A
its generating sets made by any person having expert knowledge; (v)
the appellant avoided to get the correctness of the assessment verified
by the parellel running test as suggested by the Board; and (vi) the
conduct of both the appellant and the responuent Board as emerging
from the documents placed by the parties on the records of the case
furnish valuable circumstantial evidence in support of the respondents'      ll
case. The argument of the appellant challenging the assessment as
illegal must, therefore, be rejected.

      30. Mr. Gupta by way of an alternative plea pressed an argu-
ment for granting a limited relief. He urged that even assuming that
the assessment of maximum feasible capacity of the appellant's sets          C
was correctly made in 1975 so as to be binding on the appellant, it is
fully established even by the letters of the Board that the position
stood mater;ally altered by November 1979 which called for a
re-assessment. The Board's letters dated 27.1I.1979 (page 157 Vol. II)
and 28. 12. 1979 (page 158, Vol. II), according to the learned counsel.
indicate that irrespective of whether.the initial assessment was good or     D
not, the Board accepted the position that steps for re-assessment had
to be taken and after taking into account the circumstances, decided to
grant an ad hoc benefit of 260 KW by its letter Annexure 'U' dated
13. 10. 1980 (page 182, Vol. II), discussed earlier. Although the appel-
lant does not agree that the grievance of the appellant was properly
met by the grant of the additional 260 KW but since this was allowed         E
by the Board itself, the relief should have been granted with effect
from November 1979 and not from 1.8. 1980 as mentioned in Annexure
'U'. The plea of the respondent that this additional power was allowed
on account of the recurring demand by the Company for emergency
supply under Proviso (iii) to Clause 3 of the Generation Order has
been challenged as incorrect. It is urged that the letter Annexure 'U'       F
granting additional 260 KW over and above 875 KW the appellant was
held entitled to draw, must be read in the background of Annexure 'Q'
dated 27. 11. 1979 (page 157, Vol. II) and Annexure 'R' dated
28. 12. 1979 (page 158, Vol. II). These letters have been discussed
earlier while dealing with another argument. The argument of the
appellant is that the Board had recognised the need of re-assessment         G
of the capacity and had decided to entrust the work to a committee and
it must be presumed that the team must have submitted some report.
However, no such report has been placed by the Board on the records
of this case and the suggestion is that it is a case of suppression by the
respondent and the Board cannot be heard to say that the team did not
go into the question of re-assessment. Since the matter was raised by        H
    1008        SUPREME COURT REPORTS               [1988] Supp. 2 S.C.R.

A   the appellant in November 1979 which ultimately resulted in the par-
    tial relief up to 260 KW about 11 months later, the benefit ought to
    have been allowed with effect from November 1979 if not earlier. The
    stand of the Board with respect to this additional 260 KW has already
    been mentioned earlier. It is argued by the Board that the Generation
    Order contemplates only a single assessment leading to a single direc-
B   tion and the appellant was not entitled to re-assessment. The word
    "re-assessment" in Annexure 'R' was, according to the respondents,
    mentioned due to inadvertance or under a misconception of tlie exact
    legal position. In any event the additional energy was allowed as the
    result of the repeated demand by the appellant for emergency grant.
    With a view to meet the situation which was arising every now and
    then a generous attitude was taken to allow additional 260 KW. It is
C   contended that no further claim can be legitimately founded on this act
    of generosity. As a result of the High Court's decision the appellant's
    claim for emergency supply was being considered on merits. The ap-
    pellant is thus having the advantage of the double benefit with effect
    from 1.8.1980, because the Board has neither appealed against that
D   part of the High Court judgment, nor has it withdrawn the special
    benefit of 260KW, but a further claim cannot be allowed on account of
    this sympathetic attitude. In view of our finding that a proper and
    binding assessment of the capacity of the appellant's generating sets
    was made in 1975 by the Divisional Engineer in pursuance of which the
    direction in Annexure 'O' was issued and in view of the further fact
E   that on that basis the appellant from time to time asked for and was
    allowed emergency relief under Proviso (iii) to Clause 3 of the Genera-
    tion Order, the argument of Mr. Kacker appears to be correct. The
    appellant has, in our view, failed to establish any right of additional
    relief from an earlier date.

F         31. The next point taken on behalf of the appellant is that there
    is no sanction in law for charging at the penal rate for the electricity
    consumed beyond what is permissible on application of the Generation
    Order. Section 22B of the 1910 Act confers powers of framing subordi-
    nate legislation on the State Government for the purposes and to the
    extent mentioned therein and consequence of contravention of any
G   such Order is provided ins. 42(e) mentioned below:

                "42. Whoever



H                    (~) mak.es default in complying with any order issued
    JIY AJEERAO COTION MILLS v. ELECTRICITY BOARD [SHARMA, J.l             1009

                 to him under section 22B or sub-section (2) of section 34;
                                                                                   A
                 shall be punishable with fine which may extend to one
                 thousand rupees, and, in the case of a continuing offence or
                 default, with a daily fine which may extend to one hundred
                 rupees."
                                                                                   B
     The argument is that s. 22B cannot be so construed as to include a
    delegated power to impose penalty of the delegate's choice for the
    contravention of an order issued under the Section. Since the legisla-
    ture itself exercised its legislative power in that field by including s. 42
    in the statute, the State had or has no authority to take any further step
    for the enforcement of its Order, except by resorting to s. 42. Dealing
     with s. 78-A of the 1948 Act which says that in the discharge of its          c
    functions, the Board shall be guided by such directions on questions of
    policy as may be given to it by the State Government. Mr. Gupta
•   contended that it cannot be interpreted to effectively clothe the State
    to direct the Board to do a thing which it is itself not empowered to do.
    The Board, therefore, should _have either prosecuted the appellant             D
    under s. 42(e) or disconnected the electric supply altogether, but it was
    not entitled to demand penal charges. Mr. Kacker countered by saying
    that s. 42 of the 1910 Act belongs to the group of sections 39 to 50
    dealing with "Criminal Offences and Procedure" as is apparent by the
    heading just aboves. 39, and deals with the criminal liability only. The
    same set of events may.give rise at the same time to civil rights as well      E
    as to a criminal offence, and it is not correct to suggest that merely
    because provisions are specifically included in the Act dealmg with
    criminal liability, the civil liability is deemed to have disappeared. By
    way of illustration, a simple case of theft of movable article may be
    considered: the owner of the property can set the criminal law in
    motion and at the same time may claim the property or compensation             F
    for it under the civil law. Mr. Kacker appears to be right in his stand
    that merely because the appellant became liable to the penalty as
    mentioned ins. 42(e) it cannot on that ground defend an additional
    demand on account of supply of the extra energy, if otherwise main-
    tainable under the law. Besides, s. 48 puts the matter beyond con-
    troversy by expressly stating that the penalty imposed by the aforesaid        G
    section shall be in addition to, and not in derogation of, any liability in
    respect of the payment of compensation which the offender may have
    incurred.

          32 .. While commencing his argument, Mr.. Gupta had indicated
    that one of the points on which the appellant relied upon, related to          H
    1010         SUPREME COURT REPORTS                [1988] Supp. 2 S.C.R.       ·C
   the validity of Clause 3 of the Generation Order mandatorily requiring
A
    a consumer to generate maximum feasible electricity from its own
   generating set. It was suggested that the provisions in the said Clause
   being in excess of the power under s. 22B, were ultra vires. After
   completing his argument on the other points he said that he was not
   pressing this point. Mr. Kacker, therefore, did not address us on this
B aspect. We may not in these circumstances detain ourselves on this
   question except mentioning the decisions in Adoni Cotton Mills v.
   A.P. State Electricity Board, [1976] 4 SCC 68; State of U.P. v.
   Hindustan Aluminium Corporation, [1979] 3 SCC 229; and New
   Central Jute Mills v. U.P. State Electricity Board, [1986] Supp. SCC
   581, showing in unambiguous terms that the power is there. S. 22B
   permits the State Government to issue an appropriate order for
c regulating   the supply, distribution and consumption of electricity. The
   expression "regulate" occurs in other statutes also, as for example, the
   Essential Commodities Act, 1955, and it has been found difficult to
   give the word a precise definition. It has different shades of meaning
   and must take its colour from the context in which it is used having
D regard to the purpose and object of the relevant provisions, and as has
   been repeatedly observed, the Court while interpreting the expression
   must necessarily ·keep in view the object to be achieved and the mis-
   chief sought to be remedied. The necessity for issuing the two Orders
    arose out of the scarcity of electricity available to the Board for supply-
   ing to its customers.- The situation did not leave any option to the
E Board but to make limited supply of electricity to its consumers, and it
    must be held to have, in the circumstances the right to stagger or
    curtail the supply. The Orders were issued in this background and to
    make the direction mentioned therein effective it was considered
    essential to impose sanctions which could take any reasonable form;
    either disconnection in case of gross violation or the lesser sanction of
F enhanced tariff. By the Order issued under s. 22B and quoted in
    paragraph 7 of the judgment in Adoni Cotton Mills' case (supra) the
    State Government directed a reduction in supply of electricity to the
    extent of 75% of the previous average monthly demand and provided
    for payment of the charges for excess consumption at double the tariff
    rates. The Electricity Board thereafter proceeded to impose further
G restrictions. Aggrieved by these measures the Adoni Cotton Mills, an
    aggrieved consumer approached the Court, but its challenge was
    repelled. On behalf of the appellant Mr. Gupta attempted to distin-
    guish the decision on the ground that the fixing of a higher tariff for the
  . excess consumption was against public policy and that this aspect was
    not considered by this Court in Adoni Cotton Mills' case. We do not
H find any merit in this argum@t. The demand of higher charges/tariff
     JIYAJEERAO COTION MILLS ,.'ELECTRICITY BOARD [SHARMA, J.[            1011

     for electricity consumed beyond legally fixed limit is a reasonable          A
     deterrent measure providing an appropriate sanction-not as harsh as
     disconnection of supply of energy altogether-and cannot be opposed
     on the ground of public policy. We. therefore, hold that none of the
     two Orders is illegal or unreasonable.

            33. Mr. Gupta alternatively contended that the provisions fixing      B
     the electric charges at 4 times the normal tariff for the excess con-
     sumption are to be found only in the Regulation Order and since there
     is no corresponding provision in the Generation Order, there is no
     sanction for demanding the penal rate for the electricity consumed
     incontravention of the Generation Order. He proceeded to say that
     there is no language in either of the two Orders to link them with eacn
     other. The different measure taken under the two Orders operate              c
     under different conditions and circumstances, and they cannot, there·
     fore, be lumped together. In reply to the argument of Mr. Kacker that
     since the Schedule to the Regulation Order refers to the 'contract
     demand' which expression denotes the original contract demand as
     reduced by the provisions of both the Regulation Order and the               D
     Generation Order, leading to the conclusion that the provisions
     regarding the payment of penal charges take into account both the
     Orders together, Mr. Gupta contended that although it is true that by
     reason of the Generation Order the contract demand is reduced but it
     cannot be said that a new contract comes into existence for the reduced
     amount to justify the argument of Mr. Kacker, because the reduction          E
     is as a result of operation of law. In other words, the reduced amount
     cannot be termed as 'contract' demand as it is in supersession of the
     contract demand. The contract demand, therefore, remains the same
     as before although there is introduced a statutory bar from drawing it
     in full measure. Applying this logic, it was argued by the learned
     counsel that the Generation Order has to be kept apart while working         F
     out the effect of the Regulation Order. He also referred to the· subse-
     quent Regulation Order of. 1978 in which the relevant Schedule
     prescribes 50 KW as the minimum entitlement which is inconsistent
     with the Board's case. It is urged that the argument on behalf of the
     Board that the two Orders have to be read together must, therefore,
     be rejected.                                                                 G

           24. The reply of Mr. Kacker is three-fold: (i) the point was not
     taken in the writ application before the High Court nor in the grounds
->   before this Court and since it is not a pure question of law it should not
     be allowed to be raised in the argument; (ii) the two Orders were
     issued on the same date with the common object to remedy the same            H
    1012        SUPREME COURT REPORTS              I 1988] Supp. ·2 S.C.R.

  problem as is evident from their preambles and so they cannot be read in
A
  isolation; and (iii) in any event the Electricity Board in levying ancl
  making the impugned demand must be deemed to have exercised its
  power under s. 49 of the 1948 Act which it is certainly entitled to. Mr.
  Gupta said that it was not right to suggest that the point was not raised
  in the High Court. He placed before us the review petition filed in the
B High Court after the disposal of the writ case and relied on the state-
  ment in paragraph 3 of the judgment disposing of the review petition.
  He stated that the written arguments of the Company consisted of
  three parts under the heads 'list of dates', 'notes of argument' and a
  'reply'. Mr. Gupta fairly conceded that the point was not taken in the
  writ petition before the High Court and he was not in a position to
  assert that it was actually argued on behalf of the Company in the first
C argument addressed before the High Court, but he claimed that the
  Company did press the point during the final reply. He could not deny
  that the point was not taken when the present appeals were filed in this
  Court. The judgment of the High Court does not deal with the point.
  In the circumstances, the question arises as to whether the question
D should be allowed to be urged now and if so how should it be
   answered.


        35. Mr. Gupta contended that merely because the two Orders
  are issued under the same provision of law on a particular date, they
  cannot be dovetailed. The similarity in the preamble of the two Orders
E is described as not of great consequence as it merely borrows the
  language from s. 22B. Many Orders are issued under s. 3 of the Essen-
  tial Commodities Act, the argument proceeds, and it cannot, therefore,
  be suggested that the penalty imposed in one has to be applied to the
  other without express language to that effect in either of the two
  Orders. We do not think that in view of the fact that the point was not
F taken on behalf of the Company while instituting the writ application
  in the High Court and filing the present appeals in this Court, it should
  be allowed to be urged at the hearing. Let us assume that the argument
  of Mr. Gupta is correct. Immediately the next question would arise as
  to whether the Board is otherwise authorised in law to levy and
G demand charges for the excess electricity at the higher rate and if so
  whether the Board can be said to have exercised its power in this
  regard. Mr. Kacker contended that apart from the power of the state
  Government to limit the supply of electricity to the consumers by an
  order under s. 22B and to direct payment of penal charges for excess
  consumption, the Board is also empowered to impose sanctions by
H charging enhanced tariff and the authority to do so is derived both
       JIYAJEERAO COTTON MILLS v. ELECTRICITY BOARD [SHARMA, J .]           1013

       under s. 49(3) of the 1948 Act and s. 49(1) read with the original
                                                                                    A
       atgeement. The relevant provisions are quoted below:

                   "49. Provision for the sale of electricity by the Board to
                  ·persons other than licensees.

                         (1) Subject to the provisions of this act and of regula-   B
                   tions, if any, made in this behalf, the Board may supply
                   electricity to any person not being a licensee upon such
                   terms and conditions as the Board thinks fit and may for
                   the purposes of such supply frame uniform tariffs.

                         (2)
                                                                                    c
                         (3) Nothing 'in the foregoing provisions of this
                   section shall derogate from the power of the Board, if it
                   considers it necessary or expedient to fix different tariffs
                   for the supply of electricity to any person not being a
                   licensee, having regard to the geographical position of any      D
                   area, the nature of the supply and purpose for which supply
                   is required and any other relevant factors.

                          (4) In fixing the tariff and terms and conditions for
                   .the supply of electricity, the Board shall not show undue
                   preference to any person."                                       E

        Reliance was placed on several decisions of this Court and of the High
        Courts. It was further contended that it is not essential for the Board
        to frame regulations for the exercise of such power. The learned
        counsel appears to be right. In Adoni Cotton Mills' case (supra) the
        State Government had made an order under s. 22B of the 1910 Act             F
       .limiting the supply to 75% of the previous consumption as was done in
        the present case and directed the payment of punitive rates for excess
        consumption. The Board made supplementary orders for placing
        further onerous conditions on certain groups of consumers. This was
        challenged before the High Court inter alia on the ground that since
        the State Government had already acted under s. 22B, the Board              G
        could not further pass supplementary orders and that in any event
        since the Board had not made regulations laying down the principles
        under s: 79(j) of the 1948 Act, the orders were bad. Both the points
·• }    (alorig with several others) raised by the appellant in that case were
        rejected·by this Court. Referring to s. 49(1) of the 1948 Act, the Court
       observed that the power to enhance the tariff is included in the Section     H
     1014        SUPREME COURT REPORTS               [1988] Supp. 2 S.C.R.

   and the expression that "the Board may supply electricity ..... upon .
A
   such terms and conditions as the Board thinks fit" ins. 49(1) is related
   to the terms and conditions of the agreement between the parties.
   Sub-section (1) confers power on the Board to supply electricity upon
   such terms and conditions as it thinks fit and the terms and conditions
   include the power of the Board to enhance the rates. S. 49(3) permits
B the Board to fix different rates for the supply of electricity having
   regard to certain conditions mentioned therin and "any other relevant
   factors''. It was held that the expression "any other relevant factors"
   could not be considered ejusdem generis because there is no genus of
   the relevant factors. In New Central Jute Mills Co. Ltd. v. V.P. State
   Electricity Board, (supra) the situation again was similar to the present
   case. The argument pressed before the Supreme Court inter alia was
c that the Board had no authority to make the demand in excess of the
   agreed rate under the agreement. Repelling the contention, the Court
   observed in paragraph 4 of the judgment that the agreement itself did
   not envision the supply of electricity in violation of the ban imposed by
   the State Government in exercise of its power under s. 22B of the 1910
D Act; nor did the agreement stipulate the rate at which such supply
   should be charged if notwithstanding the ban against the supply a
   consumer drew electricity in excess of the permissible quantity. In the
   circumstances, the Board was justified in invoking the power under
   s. 49(3) of the 1948 Act which authorised it to supply electricity by
   charging different tariff having regard to certain conditions and "any
E other relevant factors''. S. 49(3) was interpreted to be wide enough to
   cover a situation where electricity in excess of the quantum is drawn in
   disregard of the ban imposed under s. 22B of the 1910 Act. We do not
   consider it necessary to multiply the decisions as there does not appear
   to be any doubt that either under s. 49( 1) of the 1948 Act read with the
   agreement or under s. 49(3) or under both the provisions the respon-
F  dent  Board is fully authorised to levy and to make a demand at a
   higher rate than the usual tariff. It is also clear that it is not essential
   for the Board to make regulations indicating the basis for such levy
   before making the demand. The appellant has not been able to
   successfully show before us that the power by the Board has to be
   exercised in a particular manner and by adopting a particular mode. If
G it is assumed that a particular formality has to be completed before a
    demand can be legitimately raised, the appellant cannot be allowed to
    claim now that the same is lacking in the present case in the absence of
    a proper pleading in the original writ petition before the High Court. If
    the point had been raised in time, the respondent Board could have
    placed relevant materials on the issue. If at the end of the hearing of
 H the case in the High Court the point was mentioned in the appellant's
          JIY AJEERAO COTTON MILLS v. ELECTRICITY BOARD [SHARMA, l .]          10 i5

          final reply and included in the last instalment of its written argument,
          it cannot cure the defect in .the pleading specially when the judgment A
          of the High Court dismissing the writ application does not deal with
          the point. In that view it is not necessary to test the correctness of the.
          argument of Mr. Kacker that the appellant's entitlement to receive the
          quantum of electricity from the Board at the normal tariff can be -
          determined only by a combined reading of the two Orders. We do not, B
          therefore, consider it necessary to decide as to what would have been
          the precisely correct answer if the point had been properly raised
          before the High Court at the appropriate stage.

'               36. We do not find any merit in any of the points urged on behalf
          of the appellant. We were informed by the learned counsel for the
          parties that the appellant does not accept the correctness of the calcu- C
          lations in the letter 'P' series and the question is being examined by the
          High Court in a pending case. The appellant also asserts that even
          during the period commencing from November 1979 the Company had
          pleaded for emergency supply. The High Court has in the present case
          directed the prayer for emergency supply to be considered on merits. D
          Since these questions are not involved in the present appeals, argu~
)         ments relating to these points have not been addressed before us. We,
          in the circumstances, make it clear that any observation made in the
          present case shall not be treated to have decided those points which
          are the subject matter of a pending case in the High Court.
                                                                                       E
                37. It was also pointed out at the Bar that several interim orders
          were issued by this Court during the pendency of the present appeals
          and final direction should be given in regard to them. While granting
          special leave this Court by its order dated 5 .11.1982 directed the appel-
          lant Company as condition for interim relief of restoration of electric
          connection to pay a sum of Rs.50,00,000 within a fortnight and another       F
          sum of Rs.1,50,00,000 within six months with interest from 1. 1.1983 at
          the rate of 12% per annum until payment. The future payment of the
          electricity bills was ordered to be made within four weeks from the
          service of the bills. The Court also said that the applications made by
          the appellants for consideration of emergency supply of the electricity
          should be expeditiously disposed of by the Board on merit, and all           G
          payments by the appellants will be subject to adjustment in the light of
          the decision on the emergency applications. By the order dated
          24.11.1982 the time for payment of Rs.50,00,000 was extended to
    ·•;   6.12.1982. With respect to the payment of Rs.1,50,00,000 the Court by
          its order dated 6.5-1983 permitted the amount to be deposited in two
          equal instalments. The Court also said that if it was ultimately found       H
    lU 16        SUPREME COURT REPORTS                       [1988] Supp. 2 S.C.R.

A  that the appellant had paid any amount in excess of the total liability,
   the Board shall repay such excess amount with interest at the rate of
   12% per annum. By a subsequent order dated 23.4.1984 the appellant
   was required to pay a sum of Rs.1,28,00,000 to the Board by the 10th
   of May, 1984 and to keep the bank guarantee alive till the final dis-
   posal of these appeals as condition for continuance of the interim
B prder. During the hearing of the appeal a grievance was made on
   behalf of the respondent Board that the bank guarantee had not been
   effectively renewed and the learned counsel for the appellant under-
   took on behalf of the Company to correct the defect. Subsequently it
   was stated at the Bar that proper bank guarantee had been furnished in
  accordance with the Court's direction. In view of our present decision
c the respondent Board, besides being entitled to retain the amount
   already paid to it in pursuance of this Court's direction, is further
   entitled to enforce the bank guarantee. The appellant Company,
  ,therefore, must arrange to make the payment withount delay, failing
  1which the Board shall be entitled to take steps for enforcement of the
   bank guarantee. The dispute regarding the appellant's claim to receive
D emergency supply is pending before the High Court. The appellant
   shall be entitled to adjustment in the light of the final decision on this
   point.

         38. In the result, the appeals fail and are dismissed with costs
    payable to the respondent No. 1.

    .R.S.S.                                                      Appeals dismissed .




                                       !   ~ -, -_   ' ..•


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "electricity supply"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.