JASVEER SINGH AND ANR.versusSTATE OF U.P. AND ORS.
- Citation
- 2017 INSC 421
- Decided
- 1 May 2017
- Disposal
- Dismissed
- Bench
- ADARSH KUMAR GOEL
Holding
The challenge to the acquisition proceedings is barred by latches, and the High Court's dismissal is affirmed.
Summary
The appellants' land was acquired under the Land Acquisition Act, 1894 for a railway line, with compensation paid and a reference for higher compensation awarded in 1988. They later filed a writ petition challenging the validity of the acquisition award, alleging it was not a proper award and seeking fresh compensation. The High Court dismissed the petition as barred by latches (delay) and the Supreme Court earlier dismissed the special leave petition, allowing only a fresh challenge under the 2013 Act. On appeal, the Supreme Court affirmed that the challenge is barred by limitation, finding no error in the High Court’s reasoning, and dismissed the appeals. The Court noted that the appellants could pursue relief under the new Land Acquisition Act, 2013, but could not revive the barred claim.
Issues considered
- Whether the writ petition challenging the land acquisition award is barred by limitation/latches.
- Whether an award already finalized can be challenged on the ground of invalidity.
- Whether the appellants are entitled to a fresh challenge under the Land Acquisition Act, 2013.
Legislation cited
- Land Acquisition Act, 1894s. 18, s. 23, s. 4, s. 6
- Land Acquisition Act, 2013
Subjects
Judgment
[2017] 3 S.C.R. 921
JASVEER SINGH AND ANR. A
v.
STATE OF U.P. AND ORS.
(Civil Appeal No. 3790 of 2017)
MAYOl,2017 B
[ADARSH KUMAR GOEL AND R. F. NARIMAN, JJ.)
Land Acquisition Act,. 1894 - Award of compensat.lon -
Challenged - In the instant case, appellants were paid compensation
and possession was duly taken - On reference. higher compensation C
was awarded which decision attained finality - Thereafter appellant
challenged the acquisition proceedings by filing writ petition before
High Court which was held barred by delay and !aches against
which SLP was also dismissed by Supreme ,Court - Writ petition
seeking quashing of acquisition proceedings - High Court dismissed
same - On appeal held: The fact remained that the challenge of the D
appellants was barred by /aches and the said finding did not suffer
from any infirmity - Even if the appellants were permitted to lay a
fresh chc:llenge, they were required to overcome this legal bar which
the appellants were not able to overcome.
Dismissing the appeals, the Court E
HELD: The grievance of the appellants against acquisition
proceedings on the ground that the award was not a valid award
was rejected and SLP was dismissed by this Court but permitting
a fresh challenge. The fact-remains that the challenge of the
appellants is barred by !aches and the said finding does not suffer· F
from any infirmity. There was no J;)rror in the view taken by the
High Court. [Paras 8, 9)[925-F-G; 926-A]
Ajlatoon v. Lt. Governor of Delhi (1975) 1 SCR 802
: (197S) 4 SCC 285; Swaika Properties Pvt. Ltd. v. State
of Rajasthan (2008) 2 SCR 521 : (2008) 4 SCC 695; G
Sc.waran Lata v. State of Haryana (2010) 4 SCR 40 :
(2010) 4 SCC 532; Banda Development Authority,
Banda v. Moti Lal Agarwal [2011) 7 SCR 435 : (2011)
5 SCC 394; Royal Orchid Hotel v. G. Tayarama Reddy
[2011) 11 SCR 701: (2011) 10 SCC 608 - referred to.
H
921
922 SUPREME COURT REPORTS [2017] 3 S.C.R.
A Case Law Reference
[1975] 1 SCR 802 referred to Para3
[2008] 2 SCR 521 referred to Para3
[2010] 4 SCR 40 referred to Para3
B
(2011] 7 SCR 435 referred to Para3
[2011] 11 SCR 701 referred to Para3
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3790
of2017.
c
From the Judgment and Order dated 19.05.2015 of the High Court
ofJucticature at Allahabad in Writ C No. 59918 of2014
WITH
C.A. Nos. 3787 and3786 of2017.
D
Shanti Bhushan, Sr. Adv., Jayant Bhushan, Ashok Kumar Singh,
Kartik Seth, Santwanu Singh, Ad vs. for the Appellant.
P. S. Patwalia, ASG, P. N. Mishra, Sr. Adv., C. D. Singh,
Ms. Shivali Chaudhary, Avi Pandey, Amit Sharma, Dhurv Sheoron,
E Ms. AlkaAggarwal, Raj Bahadur Yadav, Mukesh Kumar Maroria, Rahul
Kaushik, Advs. for the Respondents.
The Judgment of the Court was delivered by
ADARSH KUMAR GOEL, J. l. These appeals have been
prefeued against the Order of the High Court of Allahabad in Writ C.
F No. 59918 of 2014 rejecting the prayer of the appellants for quashing
the land acquisition proceedings initiated vide notification dated 18th
Augu~t 1981 under Sections 4 and 6 of the Land Acquisition Act, 1894.
The acquisition was "for the construction ofNew Broad Gauge Railway
Line between Rampur and Haldwani" in the District ofRampur. Urgency
G clause was invoked. Possession of the land was taken on 19th September,
1986.· The award was made on 22nd September, 1986. The appellants
preferred reference under Section 18 for enhancement of compensation
which was decided vide Award dated 7th December, 1988 by the District
Judge, Rampur. First appeals against the said award were decided by
the High Court on 29th January, 2004. This Court vide order dated 12th
H
JASVEER SINGH AND ANR. v. STATE OF U.P. AND ORS. 923
[ADARSH KUMAR GOEL, J.]
September, 2005 in Civil Appeal Nos. 5714-15 of2005 remanded the A
matters to the High Court having regard to the grievance of the appellant
against denial of statutory benefits. ·
2. On 19th December, 2005 the appellants filed a writ petition
before the High Court seeking quashing of the acquisition proceedings
which was decided by the High Court on 3rd December, 20 l 0 directing B
redetennination of compensation. The said order was set aside by this
Court on 16th October, 2012 in Civil Appeal No.7535 of 2012. It was
observed that :
"After considering the pros and cons, without entering into
serious controversies and making any comment on the merit C
of the case, we are of the considered opinion that in view of
the judgment and order of this Court dated 26th November,
2010, which was passed in presence of the counsel for both
the parties, the High Court ought not to have heard the matter
at all. Thus, the judgment and order impugned before us has
lost its sanctity. Therefore, the same is hereby set aside. D.
However, in order to meet the ends of justice, we remand the
case to the High Court to hear the writ petition afresh
expeditiously preferably within a period of six months from
the date of production of the certified copy of the order before
the Hon 'ble Chief Justice. The matter may be assigned to any E
pc.rticular Bench by the Hon 'ble Chief Justice for /inal
disposal. The parties shall be at liberty to raise all factual
and legal issues involved in the case. The High Court is
requested to deal with the relevant issues in detail.
More so, if the respondents are so aggrieved regarding F
withdrawal of their appeals, which had been remanded by
this Court for determining the entitlement of interest
under Section 23-(JA) of the Land Acquisition Act, 1984 and
an application is made by the respondent to revive the same,
the High Court may consider and decide the said application
in accordance with Law. All the matters shall be heard G
simultaneously by the same Bench if the appeals are
restored. "
3. Thereafter, the High Court considered the contention of the
appellants that the award in respect of compensation was no award in
H
924 SUPREME COURT REPORTS [2017] 3 S.C.R.
A the eye of law and though the possession was taken long back and
railway line had been laid out, the acquisition proceedings were liable to
be set aside and compensation was liable to be awarded at present market
rate. The High Court rejected the said plea vide judgment dated 30th
May, 2014 in Writ-C No.77449 of2005. It was observed that objection
of the appellants against the award had already been considered and
B
remand by the Supreme Court on 12th September, 2005 was only in
respect of statutory benefits. For the first time plea was sought to be
raised in the writ petition against validity of acquisition which was
impermissible in view oflaw laid down by this Court in Aflatoon versus
Lt. Governor of Delhi 1, Swaika Properties Pvt. Ltd. versus State of
C Rajasthan 2, Sawaran Lata versus State of Haryana 3 and Banda
Development Authority, Banda versus Moti La!Agarwal4 • Judgment of
this Court in Royal Orchid Hotel versus G. Tayarama Reddy 5 was
distinguished as that case related to fraudulent exercise of power of
eminent domain. The High Court concluded:
D " 45. Taking into consideration the entire facts and
circumstances of the case, we are of the view that the writ
petition is highly barred by latches and deserves to be
dismissed on the ground of latches alone.
46. As has been observed above, the petitioners' main
E grievance is for enhancement of compensation, for which the
petitioner has already filed First Appeal No.880 of 1993 and
First Appeal No.401of1998 which appeals are being allowed
by order of the date, we see no reason to entertain the writ
petition.
47. Although, various submissions on merits chdlenging the
F
entire acquisition proceedings have been raised by learned
counsel for the petitioners, but we having taken the view that .
the writ petition is highly barred by latches, we do not find it
necessary to enter into the submissions raised by learned
counsel for the petitioners on merits. "
·G 4. The appellant thereafter preferred S.L.P. (Civil) No. 27109 of
2014 which was dismissed. However, it was observed that appellants
I (1975) 4.SCC 285
'(2008) 4 sec 695
'(2010) 4 sec 532
•c2011i 5 sec 394
H '(2011i 10 sec 608
JA~VEER SINGH AND ANR. v. STATE OF U.P. AND ORS. 925
[ADARSH KUMAR GOEL, J.]
are at liberty to work out their grievance based on the new Land A
Acquisition Act (2013) by preferring appropriate proceedings. The
appellant thereafter filed W.P. No.77449 of2005 from which these appeals
have arisen.
5. The High Court dismissed the writ petition with the following
observations: B
" From the facts as noticed herein above, we are of the
considered opinion that not only the Award had been made,
the petitioners had also filed a Rejerence Application which
was rejected and against the Reference Order, they filed First
Appeal, referred to above, which has also been dismissed. c
There is substance in the allegations made. "
6. We have heard learned counsel for the parties.
7. Learned counsel for the appellants submitted that in the present
case the award should be held to have not been validly made and on that
ground the proceedings should be held to have lapsed. D
8. We are unable to accept the above submission. It is seen from
the above resume of the proceedings that the appellants were paid
compensation and possession was duly taken.- The appellants also
preferred reference on which higher compensation was awarded and
matter attained finality upto this Court. The appellants thereafter filed ii E
writ petition challenging the acquisition proceedings which was held to
barred by delay and latches against which SLP was dismissed by this
Court. Of course, an observation was made that the appellants could
prefer appropriate proceedings based on their grievance under the 2013
Act.
F
9. The grievance of the appellants against acquisition proceedings
on the ground that the award was not a valid award was rejectecl and
SLP was dismissed by this Court but permitting a fresh challenge. The
fact remains that the challenge of the appellants is barred by !aches and
the said finding does not suffer from any infirmity. Even ifthe appellants G
were permitted to lay a fresh challenge, they are required to overcome
this legal bar which in our view the appellants have not been able to
overcome.
H
926 SUPREME COURT REPORTS [2017] 3 S.C.R.
A I0. We, thus, do not find any error in the view taken by the High
Court. The appeals are dismissed.
Devika Gujral Appeals dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.