JAGJEET SINGH LYALLPURI (DEAD) THROUGH LRS. & ORS.versusM/S UNITOP APARTMENTS & BUILDERS LTD.
- Citation
- 2019 INSC 1309
- Decided
- 3 December 2019
- Disposal
- Disposed off
- Bench
- R BANUMATHI
Holding
A challenge to an arbitral award on the ground of procedural irregularity, where the parties had mutually agreed to the procedure, does not fall within Section 34(2)(a)(iii) and therefore the award stands.
Summary
The appellants, owners of a 14-kanal land in Ludhiana, entered into a joint‑venture agreement with the respondent builder to construct a residential‑commercial complex, which was abandoned in 1999. After termination of the agreement, the parties attempted arbitration under the Arbitration and Conciliation Act, 1996, where the arbitrator dismissed both the claim and counter‑claim. The respondent challenged the award under Section 34, alleging procedural irregularities such as denial of cross‑examination, and the High Court remanded the matter for fresh consideration. On appeal, the Supreme Court held that the parties had consented to the procedural rules, including the waiver of cross‑examination, and that the challenge did not fall within any ground under Section 34(2)(a)(iii). Consequently, the High Court’s order was set aside, the original award restored, and the appellant was directed to pay Rs.45 lakhs to the respondent and resume possession of the land. The Court exercised its power under Article 142 to fashion a just resolution.
Issues considered
- The applicability of Section 34(2)(a)(iii) of the Arbitration and Conciliation Act, 1996 to a challenge based on alleged denial of opportunity to present evidence.
- Whether the procedural rules agreed by the parties under Section 19 of the Act can be deemed valid and binding despite the lack of cross‑examination.
- Whether the High Court erred in remanding the award for fresh consideration on the ground of procedural irregularity.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 19, s. 34(2)(a)(iii), s. 37
Subjects
Judgment
[2019] 14 S.C.R. 433 433
JAGJEET SINGH LYALLPURI (DEAD) A
THROUGH LRS. & ORS.
v.
M/S UNITOP APARTMENTS & BUILDERS LTD.
(Civil Appeal No. 692 of 2016) B
DECEMBER 03, 2019
[R. BANUMATHI, A.S. BOPANNA AND
HRISHIKESH ROY, JJ.]
Arbitration and Conciliation Act, 1996 :
C
ss. 19 and 34(2) – Agreement between appellants and
respondent-Company – For joint-venture for construction of
residential-cum-commercial complex – On the land owned by the
appellants – Construction not completed by the Company within
the time stipulated in the agreement – Compromise between the parties
– New management of the Company filed application u/s. 9 of the D
Act seeking to restrain the appellants from damaging or demolishing
the construction – Company also sought appointment of Arbitrator
– The Arbitrator, by his Award rejected the claim as well as the
counter-claim of the parties – The Award was affirmed in the appeal
u/s. 37 – High Court remanded the matter to the Arbitrator on the
E
ground that parties were not granted appropriate opportunity to
tender evidence and that the Arbitrator had not considered the
question as to extent of construction on the land and the amount of
expenditure thereon – Appeal to Supreme Court – Held : When the
challenge to arbitral award is on the ground of procedural
irregularity, it would fall u/s. 34(2)(a)(iii) – As per s.19, the rules of F
procedure to be followed by the Arbitrator is flexible and can be as
agreed upon by the parties – In the present case, procedure for the
proceedings was as agreed upon by the parties and no objection
thereto was raised – It is evident from the Award that the Arbitrator
has adverted to the question of extent of construction and the
quantum of expenditure thereon –The challenge to the award does G
not fall under any of the clauses of s.34 – However, in the peculiar
facts of the case, in the interest of justice, in exercise of power u/
Art. 142 of the Constitution, landowner is directed to pay a sum of
Rs. 45 lacs to the Company whereupon they would be entitled to
assume possession of the subject land.
H
433
434 SUPREME COURT REPORTS [2019] 14 S.C.R.
A Disposing of the appeal, the Court
HELD: 1.1 When a challenge is raised on the ground that
the appropriate procedure was not followed and there was denial
of opportunity, it would at best fall under Section 34 (2) (a) (iii) of
Arbitration and Conciliation Act, 1996. [Para 12][443-B-C]
B 1.2 Section 19 of the 1996 Act provides that the Arbitral
Tribunal is not bound by the Code of Civil Procedure or the
Evidence Act. Further, it provides that the parties are free to
agree on the procedure to be followed by the Arbitral Tribunal.
The rules of procedure to be followed by an Arbitral Tribunal is
C flexible and can be agreed upon by the parties as provided under
Section 19 of the 1996 Act. [Para 12 and 11][442-F; 443-H]
1.3 In the present case, in the proceedings dated 28.11.2009
(Annexure P-15) before the Arbitrator, the procedure to be
followed has been discussed and recorded. That apart by the very
D proceedings dated 28.11.2009 the points on which arguments
would be addressed were also treated as the issues for
consideration and has been formulated and recorded in the order
sheet. From a perusal of the proceedings dated 28.11.2009 it
would be clear that both contentions raised by the counsel for
the respondent and which were accepted by the Single Judge of
E the High Court to ultimately remand the matter, would not be
justified. Firstly, in the presence of the parties and their counsel,
it had been recorded that they do not wish to cross-examine any
of the witnesses whose affidavits have been filed by the parties
concerned and one of the witness who was present was discharged
F without being cross examined and no grievance was made either
by the parties or their counsel who were present. It is in that
view, the evidence was taken as closed on 28.11.2009 and the
issues for consideration was settled for arguments on the same
day. In that circumstance having consented to the said procedure,
it would not be open for the respondent to approbate and
G reprobate so as to raise a different contention at this point. Having
accepted the said procedure, the respondent is estopped from
raising such contention before the Single Judge that the arbitrator
misconducted himself by not permitting the parties to cross-
examine the witness and also that the Arbitrator being more than
H
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 435
APARTMENTS & BUILDERS LTD.
70 years of age and suffering from knee problem has pressurized A
the respondent to speed up the matter and the evidence was
closed. [Para 12 and 13][444-A, E-H; 445-A-B]
1.4 Though the respondent was represented by their
counsel and the order dated 28.11.2009 was passed while
recording the proceedings of that day, neither any application B
had been filed before the Arbitrator to recall the said order and
provide opportunity to tender evidence or cross examine, nor
was a challenge raised by initiating any other proceedings, before
the award was passed. It is only subsequent to the award being
passed, such contention is being raised as an afterthought, which
in such event cannot be accepted. [Para 14][445-C-E] C
1.5 That apart, the agreement being entered into on
14.12.1996 and the work not having progressed subsequent to
March,1999 was not seriously in dispute and in that circumstance,
based on the affidavit, the admitted documents have been taken
note by the Arbitrator due to which the non-cross-examination in D
any event has not prejudiced the respondent. [Para 14][445-E]
1.6 Since through the very order dated 28.11.2009, the
issues for consideration on which the arguments would be
addressed was settled and the matter was proceeded on that
understanding without raising any objection, the grievance put E
forth by the respondent and accepted by the Single Judge of the
High Court that the Arbitrator has not answered each of the claims
separately in the award, cannot also be accepted. A perusal of the
award would indicate that the Arbitrator has adverted to all aspects
in a sequential manner and has recorded his conclusion in answer F
to the contentions that were put forth. [Para 15][446-B-C]
2.1 A perusal of the award passed by the Arbitrator would
indicate that after having arrived at the conclusion that the
respondent has committed the breach, the Arbitrator has also
adverted to the contention relating to the cost incurred for the G
extent of construction made, as claimed and has rejected the
same. [Para 16][446-E-F]
2.2 It had been noticed by the Arbitrator relating to the
change of Directors and shareholders of the company in 2007 as
H
436 SUPREME COURT REPORTS [2019] 14 S.C.R.
A against the shareholders who existed as on 30.09.2005 and also
that the erstwhile Directors/shareholders who had personal
knowledge have not been examined by filing their affidavits and
even though an application dated 12.09.2009 for summoning them
as witnesses was filed, the same was not pressed and the evidence
was closed on 28.11.2009 with the consent of the parties. The
B
Arbitrator has in fact recorded that none of them have come
forward to render assistance in the proceedings. In such
circumstance when the respondent, who were themselves the
claimants before the Arbitrator have not conducted the matter in
an appropriate manner by securing affidavit evidence of the
C erstwhile directors/shareholders, they cannot at this stage turn
around and contend that the Arbitrator has misconducted himself.
In any event the challenge to the award does not fall under any of
the clauses of Section 34 of Act, 1996. [Para 17][447-E-H; 448-
A]
D 2.3 Except raising some columns, there is no major
construction that is put up. In so far as the expense as claimed by
the respondent, as indicated by the Arbitrator, there is no
conclusive evidence to that effect. Though such columns are
raised, admittedly construction activity has not taken place beyond
March, 1999 and already two decades have elapsed. In view of
E the breach and the respondent failing in the present lis, there
would be no absolute right in their favour since the inevitable
loss suffered by the appellants by not being able to enjoy the
property for the last more than two decades also cannot be lost
sight. The appellant who is the owner of the property will have to
F enter into a fresh contract and the need and manner of
development may not be the same at this point and in such event
the appellant herein also would be put to some loss to undertake
the demolition process themselves or there would be reduction
that would be made by the alternate developers who would
undertake the project. Further, the actual quantum in any event
G cannot be determined and also when a breach has been committed
through the predecessor directors/shareholders of the respondent
company and when the present directors/shareholders have
entered the scene in the midst of the breach they would have to
bear the loss, if any, to that extent. Therefore, without reference
H to the actual loss suffered by the parties, while putting an end to
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 437
APARTMENTS & BUILDERS LTD.
the litigation between the parties, in the peculiar circumstance A
and in the interest of justice, notwithstanding the fact that the
order of the Single Judge is not sustainable, in exercise of power
under Article 142 of the Constitution of India, the appellant is
directed to pay the sum of Rs. 45,00,000/- (Rupees Forty-Five
Lakhs only) to the respondent whereupon they would be entitled
B
to assume possession of the subject land and proceed to enjoy
the same in accordance with law. [Para 18][448-C-H]
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 692 of
2016.
From the Judgment and Order dated 31.07.2015 of the High Court C
of Punjab and Haryana at Chandigarh in FAO No. 5704 of 2012.
Shyam Divan, Sr. Adv., Ashok K. Mahajan, Advs. for the
Appellants.
Sibo Sankar Mishra, Niranjan Sahu, Advs. for the Respondent.
D
The Judgment of the Court was delivered by
A. S. BOPANNA,J.
1. The appellants are before this Court assailing the order dated
31.07.2015 passed by the High Court of Punjab and Haryana at
Chandigarh in FAO No. 5704 of 2012 (O&M). Through the said order, E
the High Court has remanded the matter to the sole Arbitrator Mr. Justice
Kuldip Singh, retired Judge, Supreme Court of India for providing
opportunity of leading evidence to both the parties and also grant
opportunity to cross-examine the witnesses and thereafter decide each
and every claim and counter claim separately on merits. The said order
F
is passed in an appeal filed by the respondent herein under Section 37 of
the Arbitration and Conciliation Act, 1996 (‘Act 1996’ for short). The
appellant herein who was the respondent in the said appeal is therefore
before this Court claiming to be aggrieved by the said order.
2. The brief facts leading to the present situation is that the
appellants herein are joint owners of the land measuring 14 Kanals and G
3 Marlas (8560 Sq. yards) situate at village Sunet, Tehsil and District
Ludhiana, State of Punjab. The respondent company through its
representatives claiming to be well-versed with construction and
development of properties approached the appellants for joint venture in
H
438 SUPREME COURT REPORTS [2019] 14 S.C.R.
A constructing a residential-cum-commercial complex on the subject land.
Accordingly, an agreement dated 14.12.1996 was entered into and among
other terms agreed therein, the respondent had undertaken to complete
the construction of the building consisting of at least six floors within
three years from the date of obtaining the sanctioned plan from the
Ludhiana Municipal Corporation. The project was required to be funded
B
by the respondent and a sum of Rs. 45,00,000/- (Rupees Forty-Five
Lakhs only) was to be deposited with the appellant as a guarantee for
completion of the project. In that view, the appellants were expected to
retain the same if the building is not completed within the period of three
years. The sale proceeds from the constructed building was to be shared
C in the ratio of 48:52 % between the appellants and the respondent.
3. Pursuant to such agreement the respondent secured the sanction
of the building plan from the Municipal Corporation on 04.07.1997. The
period of three years was to be computed from that point as per the
agreement. Hence the construction ought to have been completed by
D 03.07.2000. According to the appellant, the respondent though commenced
the construction during August, 1997, the activity was undertaken until
31.03.1999 and the project was abandoned by them thereafter. Since
the construction was not completed by 03.07.2000 and no further progress
was made despite the appellant having waited beyond the said period,
the appellants got issued a legal notice dated 01.11.2001 and terminated
E the agreement dated 14.12.1996. The respondent though issued reply
dated 28.11.2001 did not proceed further to make progress in the
construction.
4. The appellants further claim that in such circumstance the
appellant and the respondent entered into a compromise and a cancellation
F agreement dated 26.10.2004 was executed due to which an amount of
Rs. 40,00,000/- (Rupees Forty Lakhs only) from the amount which was
received as security deposit was returned. Notwithstanding the same,
since there was change of guard in the composition of the management,
the respondent filed an application under Section 9 of the Act, 1996
G seeking to restrain the appellants from damaging or demolishing the
construction which had been raised by the respondents. Immediately
thereafter a notice dated 23.11.2004 was issued by the respondent
invoking the arbitration clause for referring the matter to arbitration.
The Arbitration Case No. 124 of 2006 under Section 11 of the Act, 1996
filed by the respondent was allowed on 03.07.2009 and Mr. Justice Kuldip
H
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 439
APARTMENTS & BUILDERS LTD. [A. S. BOPANNA,J.]
Singh, retired Judge, Supreme Court of India was appointed as the sole A
arbitrator to resolve the dispute between the parties.
5. In that view the parties appeared before the learned Arbitrator
and filed their respective claim, counter-claim and objection thereto. The
evidence by way of affidavit and the documents of respective parties
was also filed, where after the learned Arbitrator on hearing the learned B
counsel for the parties passed the award dated 13.01.2010 through which
both the claim as well as the counter claim was dismissed. The respondent
herein claiming to be aggrieved by the same filed a petition under Section
34 of the Act, 1996 in the Court of the Additional District Judge, Ludhiana
which was registered in Arbitration Case No. 3 dated 29.01.2010. The
learned Additional District Judge through the order dated 13.09.2012 C
affirmed the award by dismissing the petition. It is in that view the
respondent herein filed an appeal under Section 37 of the Act, 1996
before the High Court. The learned Single Judge of the High Court has
arrived at the conclusion that the parties have not been granted
appropriate opportunity by the learned arbitrator to tender evidence by D
examining witness and to cross-examine the witnesses, whose affidavits
were filed. It is further held by the High Court that the learned Arbitrator
has not considered the aspect relating to the extent to which the
construction was put up and the amount that was expended by the
respondent herein and no determination, in that regard has been made.
The said observation was made after holding, though the time was not E
the essence of the contract but yet the long delay would not be justified.
It was held, even in that circumstance the other aspects required
consideration. In that background the matter was remanded to the learned
Arbitrator for fresh consideration.
6. Mr. Shyam Divan, learned senior counsel for the appellant while F
assailing such conclusion by the High Court has taken us through the
appeal papers and has referred to the agreement dated 14.12.1996 and
the clauses governing the parties. It is contended that when a dispute is
referred to the learned Arbitrator, Section 19 of the Act, 1996 provides
that the Arbitrator can determine the rules of procedure. In that regard G
it is pointed out that in the hearing held on 28.11.2009 the learned
Arbitrator has in the course of the proceedings finalised the procedure
and recorded the same in the order. It is pointed out that the respondent
was represented by a senior advocate in the arbitration proceedings
wherein it has been agreed that the parties would rely upon the affidavits
H
440 SUPREME COURT REPORTS [2019] 14 S.C.R.
A and documents that were filed and the procedure of cross-examination
could be dispensed. In that background the learned arbitrator has referred
to the materials on record in the background of the claim put forth and
the affidavits filed in support thereof while arriving at the conclusion.
Hence, he contends that the procedural lapse as attempted to be made
out at this stage is not justified.
B
7. It is further contended by Mr. Shyam Divan that in a proceedings
where the consideration ought to be limited to the extent provided under
Section 34 of the Act, 1996 and when the learned Additional District
Judge has in that light examined and confirmed the award, the
consideration ought not to have been expanded by the learned Single
C Judge in a proceedings under Section 37 of the Act, 1996 wherein also
the scope is limited. On the factual aspect it is contended that despite
the terms agreed in the agreement dated 14.12.1996, no progress was
made in the construction even until the point when the proceedings were
initiated before the learned Arbitrator after it was abandoned in March
D 1999. In that circumstance when the learned Arbitrator has taken into
consideration these aspects and arrived at the conclusion, the learned
single judge could not have interfered with the award. The learned senior
counsel in that regard has taken us through the award to point out that a
detailed consideration has been made by the learned Arbitrator on all
aspects including the fact that the cancellation of the agreement was
E agreed between the parties. On the contention urged relating to the
construction incurring an amount of Rs.1,22,00,000/- (Rupees One Crore
Twenty-Two Lakhs only) said to have been made by the respondent
also a consideration has been made. In that circumstance when the
contention was adverted to and a view was taken by the learned
F Arbitrator based on a finding of fact, the learned Single Judge was not
justified in commenting that the said aspect had not been adverted to by
the learned Arbitrator. It is therefore contended that the award is liable
to be sustained and the order passed by the learned Single Judge be set
aside.
G 8. Mr. Shibo Shankar Misra, learned counsel for the respondent
in his attempt to sustain the order passed by the learned Single Judge
contends that the respondent had raised twelve claims before the learned
Arbitrator and each claim should have been decided separately. It is his
case that the learned Arbitrator has proceeded to reject the claim only
on the conclusion that time is the essence of the contract. Though the
H
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 441
APARTMENTS & BUILDERS LTD. [A. S. BOPANNA,J.]
terms as contained in the agreement dated 14.12.1996 is not disputed, A
the learned counsel contends that the delay caused resulting in non-
completion of the project is solely attributable to the appellant. The
appellants had not parted with the title documents relating to the land in
question due to which the respondent was not in a position to raise the
funds from the bank by creating mortgage. Apart from the security
B
amount the respondent has suffered loss to the extent of Rs. 1,22,00,000/
- (Rupees One Crore Twenty-Two Lakhs only) being the cost of
construction which was put up. Specific claim was raised under different
heads before the learned Arbitrator. Despite such contentions and claims
being put forth the learned Arbitrator has not considered the same. In
that regard it is contended that clause 11 of the agreement which provides C
relating to the expenditure incurred has not been properly appreciated.
The learned counsel contended that the learned Additional District Judge
in the proceedings under Section 34 of the Act, 1996 has also not adverted
to these aspects of the matter. However, the learned Single Judge taking
note of these aspects and also keeping in view the decision in the case
D
of Oil and Natural Gas Corporation Ltd. vs. SAW Pipes Limited
2003 (5) SCC 705 has arrived at the conclusion that an award of the
present nature cannot be sustained and has accordingly remanded the
matter to the learned Arbitrator to provide opportunity to the parties and
take a fresh decision. It is contended that in such circumstance when
both parties would have an opportunity, the appellant herein cannot make E
out any grievance. He therefore contends that the above appeal be
dismissed.
9. In the light of the contentions put forth we have perused the
appeal papers and made reference to the material on record. With regard
to the agreement dated 14.12.1996 and the clauses contained therein to F
regulate the parties there is no serious dispute between the parties. The
very fact that a contention has been raised by the respondent seeking to
attribute the delay and the non-completion of the project to the appellant
by contending that the non-furnishing of the title documents had prevented
the respondent from raising loan would by itself indicate that no progress
G
was made except putting up the initial construction and the project was
not completed within the period of three years or thereafter, though the
building plan was sanctioned on 04.07.1997. In that light the appellant
had issued a notice dated 01.11.2001 and terminated the agreement,
which had resulted in a dispute between the parties. In that background
H
442 SUPREME COURT REPORTS [2019] 14 S.C.R.
A the matter was placed before the learned Arbitrator who had been
appointed in a proceeding under Section 11 of the Act, 1996. A perusal
of the award dated 30.01.2010 available at Annexure P-12 to the appeal
papers would indicate that a detailed consideration has been made by
the learned Arbitrator on all aspects of the matter. In that background
B when the petition under Section 34 of the Act, 1996 was filed before the
learned Additional District Judge, the learned Additional District Judge
in fact has also adverted to all aspects of the matter and since no ground
for interference as contemplated under Section 34 of the Act, 1996 was
made out, the learned Additional District Judge through his order dated
13.09.2012 has upheld the award.
C
10. In that backdrop when the learned Arbitrator and the learned
Additional District Judge have arrived at a concurrent opinion, it is
necessary for us to take note as to whether the learned Single Judge in
an appeal filed under Section 37 of the Act, 1996 could have adverted
into the merits of the contention beyond the scope available under Section
D 34 (2) of the Act, 1996 so as to set aside the award and remand the
matter. In that regard whether the contentions which were put forth to
assail the award by picking holes in the procedure adopted by the learned
Arbitrator is to be accepted or not also requires examination, keeping in
view the scope of Section 34 (2) of the Act, 1996 and determine as to
E whether such ground is made out.
11. Since the learned Single Judge has presently accepted the
contention raised on behalf of the respondent herein that the procedure
followed by the learned Arbitrator is contrary to law and has prejudiced
the respondent herein since the witnesses were not cross-examined,
F this aspect of the matter is required to be noticed at the outset. As rightly
pointed out by the learned senior counsel for the appellant, the rules of
procedure to be followed by an Arbitral Tribunal is flexible and can be
agreed upon by the parties as provided under Section 19 of the Act,
1996 which reads as hereunder;
G 19. Determination of rules of procedure – (1) The arbitral
tribunal shall not be bound by the Code of Civil Procedure, 1908
(5 of 1908) or the Indian Evidence Act, 1872 (1 of 1872).
(2) Subject to this Part, the parties are free to agree on the
procedure to be followed by the arbitral tribunal in conducting its
H proceedings.
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 443
APARTMENTS & BUILDERS LTD. [A. S. BOPANNA,J.]
(3) Failing any agreement referred to in sub-section (2), the arbitral A
tribunal may, subject to this Part, conduct the proceedings in the
manner it considers appropriate.
(4) The power of the arbitral tribunal under sub-section (3) includes
the power to determine the admissibility, relevance, materiality
and weight of any evidence. B
12. Further, keeping in view that the contention put forth before
the High Court by the respondent herein to assail the award was in the
manner as noticed above with regard to the appropriate procedure not
being followed and there being denial of opportunity and in that view the
respondent not being able to put forth the case appropriately before the C
learned Arbitrator, the effect of the same is required to be examined.
When a challenge is raised on that ground, in our opinion it would at best
fall under Section 34 (2) (a) (iii) which reads as follows;
“34. Application for setting aside arbitral award – (1)
Recourse to a Court against an arbitral award may be made only D
by an application for setting aside such award in accordance with
sub-section (2) and sub-section (3).
(2) An arbitral award may be set aside by the Court only if—
(a) the party making the application furnishes proof that—
E
(i) xxxxxxxxxxxxxxxx
(ii) xxxxxxxxxxxxxxx
(iii) the party making the application was not given proper
notice of the appointment of an arbitrator or of the arbitral
proceedings or was otherwise unable to present his case; or” F
(emphasis supplied)
Therefore, in order to consider whether the challenge is sustainable
on the ground available in law, at the outset it is necessary to examine
whether the procedural lapse if any is committed by the learned Arbitrator
in unilaterally denying the opportunity to the parties so as to make the G
award invalid and to set aside the same exercising the power under
Section 34 or in an appeal under Section 37 of the Act, 1996. In this
regard as noticed, Section 19 of the Act, 1996 provides that the Arbitral
Tribunal is not bound by the Code of Civil Procedure or the Indian
Evidence Act. Further, it provides that the parties are free to agree on H
444 SUPREME COURT REPORTS [2019] 14 S.C.R.
A the procedure to be followed by the Arbitral Tribunal. In this back drop
it is noticed that in the case on hand, in the proceedings dated 28.11.2009
(Annexure P-15) before the learned Arbitrator, the procedure to be
followed has been discussed and recorded, which reads as hereunder;
“The parties and their learned counsel have been heard. Whatever
B further pleadings, documents and list of witnesses were to be
filed by the parties in terms of the proceedings dated 10.10.2009,
have been done. The evidence of the claimant as well as of the
respondents was to be recorded today. Mr. Ram Lal, whom the
respondents want to cross-examine, is present before the
Arbitrator. The learned counsel for the parties have, however,
C agreed and consented before me they do not wish to cross-
examine any of the witnesses whose affidavits have been filed by
the parties concerned. In view of the consent of the learned
counsel of the parties and parties themselves who are present, I
close the evidence. The parties will rely on the affidavits already
D filed and the documents and other pleadings already placed on
the record.”
(emphasis supplied)
That apart by the very proceedings dated 28.11.2009 the points
on which arguments would be addressed were also treated as the issues
E for consideration and has been formulated and recorded in the order
sheet.
13. From a perusal of the proceedings dated 28.11.2009 it would
be clear that both contentions raised by the learned counsel for the
respondent herein and which were accepted by the learned Single Judge
F to ultimately remand the matter, would not be justified. Firstly, in the
presence of the parties and their learned counsel it has been recorded
that they do not wish to cross-examine any of the witnesses whose
affidavits have been filed by the parties concerned and one of the witness
who was present was discharged without being cross examined and no
G grievance was made either by the parties or their learned counsel who
were present. It is in that view the evidence was taken as closed on
28.11.2009 and the issues for consideration was settled for arguments
on the same day. In that circumstance having consented to the said
procedure, it would not be open for the respondent herein to approbate
and reprobate so as to raise a different contention at this point. Having
H
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 445
APARTMENTS & BUILDERS LTD. [A. S. BOPANNA,J.]
accepted the said procedure the respondent is estopped from raising A
such contention before the learned Single Judge that the arbitrator
misconducted himself by not permitting the parties to cross-examine the
witness and also that the learned Arbitrator being more than 70 years of
age and suffering from knee problem has pressurized the respondent to
speed up the matter and the evidence was closed. It is rather intriguing
B
for us to note that such contention has not only been permitted to be
raised, but also accepted by the learned Single Judge to remand the
matter, which is wholly unjustified.
14. We are of such opinion for the reason that the procedure to be
followed in arbitration proceedings was settled by a separate order dated
28.11.2009 during the course of the proceedings before the learned C
Arbitrator. Thereafter the award was passed only on 13.01.2010. Though
the respondent was represented by their learned counsel and the order
dated 28.11.2009 was passed while recording the proceedings of that
day, neither any application had been filed before the learned Arbitrator
to recall the said order and provide opportunity to tender evidence or D
cross examine, nor was a challenge raised by initiating any other
proceedings, before the award was passed. It is only subsequent to the
award being passed such contention is being raised as an afterthought,
which in such event cannot be accepted. That apart, the agreement
being entered into on 14.12.1996 and the work not having progressed
subsequent to March,1999 was not seriously in dispute and in that E
circumstance based on the affidavit, the admitted documents have been
taken note by the learned Arbitrator due to which the non-cross-
examination in any event has not prejudiced the respondent herein. One
aspect of the matter no doubt was with regard to the claim that was put
forth by the appellant herein that a cancellation agreement dated F
26.10.2004 was entered into and the security deposit of Rs. 40 Lakhs
and the advance of Rs. 23 Lakhs has been re-paid to Mr. S. Surinder
Singh which was disputed by the respondent. On that aspect the learned
Arbitrator in any event has concluded that the said payment if any cannot
be considered as a payment made to the respondent company but has
been received by Mr. Surinder Singh who had made gain unto himself. G
In such event since the respondent has not filed the affidavit of Mr.
Surinder Singh disputing the same, it is an inter-se matter to claim from
Mr. Surinder Singh and therefore, the non-cross-examination on that
aspect also has not resulted in any prejudice. Be that as it may, as already
H
446 SUPREME COURT REPORTS [2019] 14 S.C.R.
A taken note, the procedure to be followed in the arbitral proceedings has
been agreed to by the parties. Hence the respondent cannot be heard to
complain as and when it suits them.
15. Further, since through the very order dated 28.11.2009 the
issues for consideration on which the arguments would be addressed
B was settled and the matter was proceeded on that understanding without
raising any objection, the grievance put forth by the respondent and
accepted by the learned Single Judge that the learned Arbitrator has not
answered each of the claims separately in the award, cannot also be
accepted. A perusal of the award would indicate that the learned
Arbitrator has adverted to all aspects in a sequential manner and has
C recorded his conclusion in answer to the contentions that were put forth.
16. One other aspect which has been recorded by the learned
Single Judge as the reason for which the matter requires reconsideration
by the learned Arbitrator is that the claim put forth by the respondent
that the sum of Rs. 1,22,00,000/- spent by them has not been considered
D by the learned Arbitrator. In that regard the learned Single Judge has
held that though the respondent herein would not be entitled to continue
the project due to lapse of time the learned Arbitrator has not considered
the right of the parties relating to the extent of the cost incurred for the
existing construction and the manner in which it is to be dealt with. On
E this aspect, a perusal of the award passed by the learned Arbitrator
would indicate that after having arrived at the conclusion that the
respondent has committed the breach, the learned Arbitrator has also
adverted to the said contention relating to the cost incurred for the extent
of construction made, as claimed and has rejected the same. The
consideration as made is as hereunder;
F
“I may examine, at this stage the claimant’s contention that
construction worth about Rs. 1 crore 20 lacs has been done on
the project. The claimant has primarily relied on the balance sheet
of the Company for the relevant year in support of this argument.
The balance sheet is Annexure-K at page 118-126 of the statement
G of Claim. In the schedule forming part of the accounts for the
year ending 31 st March, 1999, the balance sheet shows an
expenditure of about 1 crore 20 lacs on the project in process.
This includes Rs. 44 lacs as advance given to the respondents
(land owners) as guarantee money. Expenditure incurred has been
H shown under various headings such as advertisement and publicity,
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 447
APARTMENTS & BUILDERS LTD. [A. S. BOPANNA,J.]
salary, entertainment, iron and steel, cement, GC sheets, stand, A
bricks, marble, crusher, electrical, GI pipes, gate, professional
charges, telephone expenses, electricity expenses, labour and
construction charges. An amount of Rs. 56,58,530/- has been
shown under the heading purchase. It is not indicted so as to what
was purchased. All the items required for the construction of the
B
project have been shown separately but it is not clear on what
purchase/purchase this amount was spent. No explanation is
forthcoming from the claimant in this respect. Mr. Mahajan while
controverting the argument of Mr. Lekhi has stated that Local
Commissioner’s report Annexure-W makes it clear that the
amount which may have been spent on the construction was much C
less. Be that as it may there is no expert evidence on the record
to show as to how much money was spent on the construction.
The claimant company did receive some money as advance against
flats and offices to be constructed. It is in the evidence that Rs.
23 lacs was received by the Company in this respect. The balance
D
sheet as on 31st March, 1999 at page 121 shows that the Company
received Rs. 19,79,488/- as advance against flats and offices. In
the absence of reliable evidence on the record, it is not possible to
accept the argument of the learned counsel for the claimant.”
17. In that circumstance when the learned Arbitrator has noticed
the contention and recorded a finding of fact it cannot be accepted that E
the learned Arbitrator has not adverted to the same so as to require
reconsideration. To be fair to the learned Arbitrator, it has in fact been
noticed by the learned Arbitrator relating to the change of Directors and
shareholders of the company in 2007 as against the shareholders who
existed as on 30.09.2005 and also that the erstwhile Directors/ F
shareholders who had personal knowledge have not been examined by
filing their affidavits and even though an application dated 12.09.2009
for summoning them as witnesses was filed, the same was not pressed
and the evidence was closed on 28.11.2009 with the consent of the
parties. The learned Arbitrator has in fact recorded that none of them
have come forward to render assistance in the proceedings. In such G
circumstance when the respondent herein, who were themselves the
claimants before the learned Arbitrator have not conducted the matter
in an appropriate manner by securing affidavit evidence of the erstwhile
directors/shareholders, they cannot at this stage turn around and contend
that the learned Arbitrator has misconducted himself. In any event the H
448 SUPREME COURT REPORTS [2019] 14 S.C.R.
A challenge to the award does not fall under any of the clauses of Section
34 of Act, 1996. In such circumstance the reliance placed by the learned
Single Judge on a decision in the case of ONGC (supra) is highly
misplaced. Therefore, the order dated 31.07.2015 passed by the learned
Single Judges is not sustainable and the same is liable to be set aside.
B 18. During the course of hearing we had also made an endeavour
to see that the parties amicably settle the matter by enabling the
respondent herein to receive some amount towards the expended portion,
also by not ignoring the loss suffered by the appellants due to delay.
From the photographs produced before us we have noticed that except
raising some columns, there is no major construction that is put up. In so
C far as the expense as claimed by the respondent, as indicated by the
learned Arbitrator as extracted above, there is no conclusive evidence
to that effect. Though such columns are raised, admittedly construction
activity has not taken place beyond March, 1999 and already two decades
have elapsed. In view of the breach and the respondent herein failing in
D the present lis there would be no absolute right in their favour since the
inevitable loss suffered by the appellants by not being able to enjoy the
property for the last more than two decades also cannot be lost sight.
The appellant herein who is the owner of the property will have to enter
into a fresh contract and the need and manner of development may not
be the same at this point and in such event the appellant herein also
E would be put to some loss to undertake the demolition process themselves
or there would be reduction that would be made by the alternate
developers who would undertake the project. Further, the actual quantum
in any event cannot be determined and also when a breach has been
committed through the predecessor directors/shareholders of the
F respondent company and when the present directors/shareholders have
entered the scene in the midst of the breach they would have to bear the
loss, if any, to that extent. Therefore, without reference to the actual
loss suffered by the parties, while putting an end to the litigation between
the parties, in the peculiar circumstance and in the interest of justice,
notwithstanding the fact that we have held the order of the learned Single
G Judge as not sustainable, in exercise of our power under Article 142 of
the Constitution of India the appellant is directed to pay the sum of
Rs. 45,00,000/- (Rupees Forty-Five Lakhs only) to the respondent
whereupon they would be entitled to assume possession of the subject
land and proceed to enjoy the same in accordance with law.
H
JAGJEET SINGH LYALLPURI (DEAD) v. M/S UNITOP 449
APARTMENTS & BUILDERS LTD. [A. S. BOPANNA,J.]
19. In the result the appeal is disposed of with the following order: A
(i) The order dated 31.07.2015 passed by the High Court of Punjab
and Haryana in FAO No. 5704 of 2012 (O&M) is set aside. Consequently,
the award dated 13.01.2010 passed by the learned Arbitrator is restored.
(ii) The appellant is directed to pay the sum of Rs. 45,00,000/-
B
(Rupees Forty-Five Lakhs only) in full quit of all claims, to the respondent
within three months.
(iii) Immediately on payment of the said amount the appellant
shall be entitled to resume possession of the subject land in the status as
it exists and enjoy the same in accordance with law.
C
(iv) Parties to bear their own costs.
Kalpana K. Tripathy Appeal disposed of.
D
E
F
G
H
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.