Created byFuzzy Cloud

Supreme Court of India

J.C. BUDHRAJAversusCHAIRMAN, ORISSA MINING CORPN. LTD. & ANR.

Citation
2008 INSC 64
Decided
18 January 2008
Disposal
Case Partly allowed

Holding

The award is upheld only to the extent of claims that were part of the acknowledged pending liability and not barred by limitation (Rs.13,93,373.50); the balance of the award is set aside.

Summary

The contractor (N.C. Budhraja) completed excavation work for Orissa Mining Corp. Ltd. (OMC) and later claimed extra payment for work beyond the contract. OMC acknowledged pending claims in a letter dated 28‑Oct‑1978 and paid Rs.3,50,000 on 4‑Mar‑1980, after which the contractor invoked arbitration on 4‑Jun‑1980. The legal heir, J.C. Budhraja, filed a claim before the arbitrator that included both the acknowledged pending amount and fresh claims, the latter being time‑barred. The arbitrator awarded an amount exceeding the claim and the time‑barred portion, leading OMC to challenge the award. The Supreme Court held that only the portion of the claim that was part of the acknowledged pending liability (Rs.13,93,373.50) was within the limitation period and within the arbitrator's jurisdiction; the rest was barred by limitation and the award was set aside as legal misconduct. Consequently, the Court upheld that part of the award and set aside the remainder, granting interest on the upheld sum.

Issues considered

  • Whether the claim made before the arbitrator, or any part thereof, was barred by limitation.
  • Whether the award is liable to be set aside on the ground of legal misconduct and error apparent on the face of the award.
  • Whether the arbitrator exceeded his jurisdiction in granting amounts beyond the claim.
  • To what relief the parties are entitled.

Legislation cited

Subjects

ArbitrationLimitation periodAcknowledgement of liabilityLegal heirWork contractAward set asideJurisdictionLegal misconductEscalation of cost

Judgment

                                         I
                                  [2008] 1 S.C.R. 821


     ~                            J.C. BUDHRAJA                             A
         '                                   II.
                CHAIRMAN, ORISSA MINING CORPN. LTD. & ANR.
                       (C.A. Nos. 1971-1973 of 2000)
                                 JANUARY 18, 2008
                                                                            B
              [H.K. SEMA, G.P. MATHUR & R.V. RAVEENDRAN, JJ.]
~

     i             Contract - Work contract - On completion, contractor
             claiming extra payment for the work done beyond the contract
             - Payment for the work under contract received under protest   c
             - Constitution of Committee for consideration of extra payment
             - Statement quantifying the claim, produced before the
             Committee - Committee accepting the same only in part -
             Contractor issuing notice invoking arbitration - Legal heir of
             the contractor, making a claim before the arbitrafor, different
                                                                             D
             from the claim made before the Committee -Arbitrator passing
    ---1     the award for an amount over and above the claimed amount
             - Propriety of- Held: Award in respect of the amount over and
             above the claim made before the Committee was barred by
             limitation -Limitation period in respect the pending claims
             which were made before the Committee having been E
             acknowledged stood extended - It is not permissible for a legal
             heir to make fresh claim before an arbitrator, which was not
             made by his predecessor in interest - Arbitrator committed
             error on the face of the record and a legal misconduct in
    --+      holding that entire claim was within time - Arbitrator also F
             exceeded his jurisdiction in passing award for an amount more
             than what was claimed- Arbitration Act, 1940 -: s. 8(2) -
             Limitation Act, 1963 -s. 18
                  Predecessor in interest of the appellant entered into
             contract with the respondent for removal of over-burden G
     --r     by excavation. After completion of the work by the
             contractor, respondent prepared final bill which was
             further revised in March-April, 1977 amounting to Rs. 1,
             49, 190, 76-74. The contractor accepted the amount under
                                             821                            H
   822      SUPREME COURT REPORTS                [2008) 1 S.C.R.


A protest. Contractor claimed that he executed additional
  work beyond that provided in the contract and thus
  claimed extra payment for the same. He made several
  representations in this regard. As a result, by a letter dated
  28.10.1978, respondent informed that a Committee would
B be constituted to consider the claim. By letter dated
  16.11.1978, contractor sent a statement quantifying the
  claims in respect of the contract in question amounting
  to Rs. 50, 15,820/-. Committee prepared its final report           t
  dated 28.10.1979. The Committee admitted the claim only
c an extent of Rs. 3,50,000/- and rest of the claim was not
  to
  accepted. Information to this effect was given by the
  respondent to the contractor by a letter dated 4.3.1980.
  Contractor sent a notice dated 4.6.1980 invoking
  arbitration in respect of the pending claims. In the
  meantime he also moved application u/s 8 (2) of Arbitration
D
  Act, 1940. During the pendency of the application the
  appellant was substituted as legal heir of the original           ~-
  contractor. In the meantime, after amendment of the
  Arbitration Act, State Government formed Special Arbtiral
  Tribunal to settle the disputes. The appellant filed a claim
E statement before the arbitrator, the nature and quantum
  whereof was different from what was claimed before the
  Committee. Appellant, abandoned the claim to an extent
  of Rs. 21,83, 692/- out of the previous claim of Rs.
  50, 15,820/- and made further new claim. The whole claim
F was totaling to Rs. 95,96,616/-. During the proceedings,         -+ •
  appellant contended that out of Rs. 149,88,566.90 received
  from the respondent and taken into credit towards the
  contract in question, a sum of Rs. 29,86,871/- was
  appropriated towards other contracts and therefore the
G amount paid should be considered as Rs. 120,01,695-99.
  The arbitrator passed the award for an amount more than          i--
  the amount claimed i.e. increasing the liability of the
  respondent by Rs. 29,86,871/- with interest @ 12% per
  annum. The award was for claims in respect of work under
H the  contract, the•work which waS"llot part of the contract
             J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING            823
                        CORPN. LTD. & ANR.

    i     and in respect of escalation in cost of labour and material A
          on account of delay in execution. Appellant filed suit for
          making the award rule of the court. Respondent objected
          to it. The court made the award rule of the court.
          Respondent filed appeal against the order. Appellant also
          challenged the order claiming future interest from. the date B
          of the decree. High Court allowed the appeal of the
~        ·respondent and dismiss~d the case of the appellant.
              In appeal to this court the questions for
         consideration were (1) whether the claim made before the
         arbitrator or any part thereof was barred by limitation; C
         (2) Whether the award was liable to be set aside on the
         ground of legal misconduct and the error apparent on
         the face of the award; (3) whether the arbitrator
         exceeded his jurisdiction; and (4) to what relief the
         parties were entitled.                                   D
              Partly allowing the appeals, the court
                 HELD: 1.1Section18 of the Limitation Act, 1963 deals
           with effect of acknowledgement in writing. Sub-section
           (1) thereof provides that where, before the expiration of E
           the prescribed period for a suit or application in ·respect
           of any right, an acknowledgement of liability in respect of
           such right has been made in writing signed by the party
           against whom such right is claimed, a fresh period of
    .+     limitation shall be computed from the time when the F
         · acknowledgement was so signed. The explanation to the
           section provides that an acknowledge.ment may be
           sufficient though it omits to specify the exact nature of
           the right or avers that the time for payment has. not yet
           come or is accompanied by a refusal to pay, or is coupled G
          with a claim to set off, or is addressed to a person other
           than a person entitled to the right. [Para 14] [841-D-G]
              Shapur Fredoom Mazda v. Durga Prosad Chamaria AIR
         1961 SC 1236 - referred to.
                                                                       H
    824      SUPREME COURT REPORTS                [2008] 1 S.C.R.


A       1.2 A writing to be an acknowledgement of liability
  must involve an admission of a subsisting jural
  relationship between the parties and a conscious
  affirmation of an intention of continuing such relationship
  in regard to an existing liability. The admission need not
B be in regard to any precise amount nor by expressed
  words. A writing, to be treated as an acknowledgement of
  liability should consciously admit his liability to pay or                '
  admit his intention to pay the debt. [Para 15] [843-A-C]          t

          1.3 What can be acknowledged is a present
c subsisting liability. An acknowledgment made with
  reference to a liability, cannot extend limitation for a time
  barred liability or a claim that was not made at the time of
  acknowledgment or some other liability relating to other
  transactions. Any admission of jural relationship in regard
D to the ascertained sum due or a pending claim, cannot be
  an acknowledgement for a new additional claim for                 .,__
  damages. [Para 15] [844-8-D)
         1.4 In the instant case, the cause of action accrued
    when the final bill was signed by the contractor. The
E   respondent informed the contractor that it has been
    decided to constitute a Committee which will go into the
    claims of the contractor so that the dues, if any, could be
    ascertained. It further stated that on the details of the
    claims and payments received being given to the
F   contractor, the respondent will settle up the pending           -+ •
    matters at the earliest. This clearly showed an intention
    on the part of the respondent to admit the jural relationship
    of contractor and employer and an intention to settle the
    pending claims after being satisfied about them.
G   Therefore, the letter dated 28.10.1978 was clearly an
    acknowledgement in writing in so far as the "pending             f- -
    claims" of the contractor. What were the pending claims
    is made clear in the letter dated 16.11.1978 written by the
    contractor enclosing a statement showing that in all, a
H   sum of Rs.50, 15,820/-was due. The Committee constituted
          J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING            825
                    CORPN. LTD. & ANR.

 i    by the respondent examined these claims and admitted A
      the claims only to an extent of Rs.3,52,916/- as per its final
      report dated 7.12.1979. The respondent paid Rs.3,50,000/
      - on 4.3.1980. In view of the acknowledgement in writing
      on 28.10.1978 and payment of Rs.3,50,000/- on 4.3.1980,
      it can be said that in regard to the pending claims of the s
      contractor, the limitation stood extended by three years
      from 4.3.1980 and at all events by three years from
 +    28.10.1978. The contractor issued the notice invoking
      arbitration on 4.6.1980 and immediately filed a petition
      under section 8(2) of the Act for appointment of Arbitrator C
      which was allowed on 6.10.1980. Therefore, whatever
      claims were made before the Arbitrator which was part of
      the claim of Rs.50, 15,820, was within time, having been
      made within three years from 28.10.1978 and
      4.6.1980.(Para 16] (844-D-H; 845-A-E]
                                                                     D
            1.5 In regard to the claims aggregating to
      Rs.95,96,~16/- made in the claim statement filed before the
      Arbitrator, only claims aggregating to Rs.28,32, 138 related
      to and formed part of the said pending claim of
      Rs.50, 15,820. The appellant did not make a claim in regard E
      to the remaining Rs.21,83,692. Therefore, out of the claim
      of Rs.95,96,616 made by the appellant before the
      Arbitrator, the claim for only Rs.28,32, 138/- was not barred
      by limitation. The remaining claims of the appellant
      aggregating to Rs.67,64,488/- out of the total of F
      Rs.95,96,616/- being fresh claims, were not "pending
      claims" in respect of which the acknowledgement was
      made. Therefore the said fresh claims aggregating to
      Rs.67,64,488 made for the first time in the claims statement
      filed on 27.6.1986 were clearly barred by limitation.
      [Para 17] [845-E, F, G]                                        G
--t
            1.6 In the case of arbitration, limitation for the claim
      !s to be calculated on the date on which the arbitration is
      dE:emed to have commenced. Section 37(3) of the
      Arbitration Act provides that for the purpose of Limitation H
    826     SUPREME COURT REPORTS                [2008] 1 S.C.R.


A Act, an arbitration is deemed to have been commenced              ~
  when one party to the arbitration agreement serves on
  the other party thereto, a notice requiring the appointment'
  of an arbitrator. Such a notice having been served on
  4.6.1980, it has to be seen whether the claims were in time
B as on that date. If the claims were barred on 4.6.1980, it
  follows that the claims had to be rejected by the arbitrator
  on the ground that the claims were barred by limitation.                   ....
  The said period has nothing to do with the period of               ~

  limitation for filing a petition under Section 8(2) of the Act.
c Insofar as a petition under Section 8(2), the cause of
  action would arise when the other party fails to comply
  with the notice invoking arbitration. Therefore, the period
  of limitation for filing a petition under section 8(2) seeking
  appointment of an arbitrator cannot be confused with the
D period  of limitation for making a claim.[Para-18) [846-B-F]
       lnder Singh Rekhi vs. Delhi Development Authority -          )>----
  1988 (2) SCC 338; Panchu Gopal Bose vs. Board of Trustees
  for Port of Calcutta - 1993 (4) SCC 338; Utkal Commercial
  Corporation vs. Central Coal Fields 1999 (2)·scc 571 - relied
E on.
        1.7 The contractor was the predecessor in interest
  of the appellant. The original claim (which was the subject
  matter of letter dated 28.10.1978, subjected to examination
  by the Committee as per report dated 7.12.1979, and
F                                                                   + ~
  towards which Rs.3,50,000/- was paid) made by the
  contractor aggregated to Rs.50, 15,820. The Appellant who
  is his legal heir cannot for the first time make a fresh claim
  before the Arbitrator, which was never made by the
  contractor. The Appellant could only pursue the claim
G
  made by the contractor which were pending or subsisting
                                                                    t--
  when the contractor issued the notice dated 4.6.1980.
  [Para 20) [847-C, D, E]
       2. The arbitrator committed an error apparent on the
H face of the record and a legal misconduct in holding that
         J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING            827
                   CORPN. LTD. & ANR.

      the entire claim was within time. His assumption that if A
      the application filed by the contractor in 1980 under
      section 8(2) of Arbitration Act for appointment of an
      Arbitrator was in time, all claims made in the claim
      statement filed before the Arbitrator appointed in such
      proceeding under section 8(2) are also in time, is patently B
      erroneous and is an error apparent on the face of the
      record. The reasoning of the arbitrator that on account of
 +    the formation of the Committee by the respondent to
      scrutinize the pending claims in pursuance of the
      respondent's letter dated 28.10.1978, and the payment of c
      Rs.3,50,000/- on 4.3.1980 in pursuance of the Committee
      giving its final report on 7.12.1979, every claim of the
      contract including new claims which were made for the
      first time in the.claim statement filed in 1986 (as contrasted
      with 'pending claims' considered by the respondent), are D
      not barred by limitation, is also an error apparent in the
~-~
      face of the award. [Para 21] [847-F, G; 848-A]
           3.1 The prayer before the arbitrator in the claim
      statement was for the award of Rs.95,96,616 in regard to
      the work done after giving credit of Rs.1,49,88,566.90. The   E
      categorical stand of the contractor and the appellant all
      along has been that the respondent had paid in all a sum
      of Rs.149,88,566.90. But during the course of the
      arbitration proceedings, the appellant contended that out
~+    of Rs.149,88,566.90 received from the respondent and          F
      taken into credit towards this contract, a sum of
      Rs.29,86,871/- was being appropriated towards other
      contracts and therefore the 'payments made by the
      respondent towards this contract should be taken as
      Rs.120,01,695.90. The arbitrator has mechanically             G
-+    accepted the said altered stand contrary to the claim
      statement and proceeded to determine the amount
      payable by OMC, by taking the amount paid by the
      respondent as Rs.120,01,659.90 towards this contract,
      even though the claim statement showing that the              H
    828      SUPREME COURT REPORTS                [2008] 1 S.C.R.


A respondent had paid Rs.149,88,566.90 remained
  unaltered. The claim statement was not amended to show
  that only Rs.120,01,659.90 had been received from the
  respondent regard to the contract. When the claim made
  in the claim statement is after adjusting Rs.149,88,566.90
B paid by the respondent towards the work, the arbitrator
  cannot proceed on the basis that only Rs.120,01,659.90
  was paid towards the work. By awarding more than what
  was claimed in the claim statement (by showing a lesser
  amount as having been paid by the respondent though
c claim statement showed a higher amount), the Arbitrator
  clearly exceeded his jurisdiction. The Arbitrator thus
  committed a legal misconduct and the award to that extent
  is liable to be set aside. [Para 22] [848-G; 849-A-F]
       3.2 The Arbitrator has exceeded his jurisdiction in
D another respect. The total claim made by the contractor
  before the Arbitration was Rs.95,96,616/- (excluding
  interest). But the amount awarded by the arbitrator
  towards the said claim was Rs.1,02,66,901/36 (excluding
  interest). Making an award in excess of the claim itself by
E Rs.6,70,285 is a clear act of exceeding the jurisdiction and
  amounts to a legal misconduct and to that extent of
  Rs.6,70,285/- the award is invalid. [Para 23] [849-G, H;
  850-A]
F       3.3 In regard to item 35, that is escalation in cost, the
  claim in the claim statement was at the rate of 15% for the
  value of work done in 1972-73, 28.5% in respect of value
  of work done in 1973-74 and 32% in respect of work done
  in 1974-75. But the Arbitrator has awarded escalation at a
  flat rate of 32.6% on the entire cost of work done from
G 1.4.1973 and thereby awarded an escalation in excess of
  what was claimed. This also amounts to exceeding the              +--
  jurisdiction and therefore legal misconduct. The award in
  excess of what was claimed was invalid. [Para 24]
H [850-A-C]
                 JC. BUDHRAJA v. CHAIRMAN, ORISSA MINING            829
                          CORPN. LTD. & ANR.

                   4.1 Awarding amount towards time barred part of the A
              claim of Rs.67 ,64,488, and awarding amounts of
              Rs.29,86,871, Rs.670,285 and escalation in cost at a rate
              more than what is claimed, are all legal misconducts and
·,            the award in regard to those amounts are null and void.
              There is however some overlapping of the aforesaid B
              amounts. [Para 25) [850-D,E]
                    4.2 That part of the award which is valid and separable
        +
              can be upheld. That part relates to the claims which were
              validly before the Arbitrator, which were part of the existing
              or pending claims of Rs.50,15,820 and which were not C
              barred by limitation. They were the claims which were
              existing or pending in 1978, 1979 and 1980 (considered
              by the committee and payment made by the respondent
              which were carried before the Arbitrator to an extent of
              Rs.28,32,128; Only the amounts awarded by the Arbitrator o
              against those claims can be considered as award validly
              made in Arbitration, falling within jurisdiction. They are
              clearly severable from the other portions of the award.
              The total amount awarded by the Arbitrator against claims
              which were not barred by limitation was only E
              Rs.13,93,373.50. The award to this extent is not open to
              challenge. This part of the award does not suffer from any
              legal misconduct. There is also no error apparent on the
              face of the award in respect of the amount. The scope of
        • t   interference with an award is limited. The Award of the
              Arbitrator has to be upheld to an extent of Rs.13,93,373.50 F
              with interest at the rate of 12% P.A. from 1.8.1977 to date
              of award (28.11.1986) and at the rate of 6% P.A. thereafter,
              that is from 29.11.1986 till date of payment. [Paras 26, 27
              and 28) [850-E, F, G; 852-8, C, G, H; 853-A]
    '                                                                      G
I       --t       Hindustan Construction Co. Ltd. vs. Governor of Orissa
~             1995 (3) SCC 8; Hindustan Tea Co. vs. Mis K. Sashikant and
              Co. 1986 (Supp.) sec 506 - relied on.
                  CIVIL APPELLATE JURISDICTION             Civil Appeal
              Nos.1971-1973 of 2000.                                       H
    830       SUPREME COURT REPORTS                [2008] 1 S.C.R.


A        From the final Judgment and Order dated 15.10.1999 of
                                                                     -t-
    the High Court of Orissa at Cuttack in Misc. Appeal Nos. 296 &
    198 of 1998 and Civil Revision No. 109of1998.
        A.K. Panda and T.S. Doabia, Rutwik Panda and Mridul
    Aggarwal for the Appellant.
B
        C.S. Vaidyanathan, K.V. Viswanathan, Rajeev Singh and               ._
    Anup Kumar Singh for the Respondents.
                                                                      +
          The Judgment of the Court was delivered by
c        RAVEENDRAN, J. 1. These appeals are filed against
    the common judgment dated 15.10.1999 passed by the High
    Court of Orissa in Misc. Appeal No.296/1998 filed by the
    respondents and Misc. Appeal No.198/1998 and Civil Revision
    No.109/1998 filed by the appellant.
D       2. The appellant is stated to be legal heir and successor
  in interest of N.C. Budhraja (hereinafter referred to as the
  contractor). M/s. Orissa Mining Corporation Ltd. (for short OMC
                                                                      ~    ,,   -
  or respondent) entered into an agreement dated 16.9.1967
  (Agreement No.30/F-2) for removal of over-burden at Kaliapani
E (Cuttack District) by excavation in all kinds of soil (including
  stoney earth and gravel mixed with boulders), and depositing/
  disposing of the same, as directed. The maximum lift was 6m
  including initial lift of one metre. The order to commence work
  was issued on 23.9.1967. Parties also entered into three
F supplementary agreements in regard to the said contract No.30/     +~
  F-2, on 2.8.1969, 7.3.1970 and 10.2.1972. [Note: OMC had
  also entered into other contracts with the contractor including
  contract dated 22.2.1968 (Contract No.2/F/2) for raising Chrome
  Ore by open excavation from the said mining area. We are not
G concerned with those contracts in these appeals].
                                                                     i--
        3. The main agreement enumerated two items of work                      •
  in its schedule. The first, second, and third supplementary
  agreements enumerated respectively eight items, one item
H and four items in their respective schedules. The work was
                J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                831
                   CORPN. LTD. & ANR. [RAVEENDRAN, J.]
     .:i·   completed by the contractor on 15.6.1975. The final bill in A
            respect of the work was prepared by OMC on 21.10.1976. It
            was revised in March-April 1977 by OMC. The final Bill It
            showed the total value of the work done (under several items
            in the schedule to main and three supplementary agreements)
            as Rs.1,49, 190, 76. 74. The contractor countersigned the B
            said bill on 14.4.1977 under protest, but, however, certified
•           and confirmed that the measurements shown therein were
     -t
            correct.

                  4. According to the contractor, having regard to the zig-
            zag route by which the over burden had to be carried, the actual
                                                                               c
            lead was much longer and actual lift was much higher than what
            were stipulated in the agreement. He contended that the amounts
            shown as due for the work done was as per contract rates which
            was for removing overburden to the extent of lift and lead
            provided in the contract schedules; and at several places, he D
... ~       had to cut and remove the over-burden beyond the extent of lift
            and lead provided in the contract, and he should be paid for
            such extra leads and lifts. He claimed to have executed certain
            additional works not provided in the contract schedules, on the
            directions of OMC. He therefore represented that the matter E
            may be examined and enquired into for determination of proper
            amounts due. In view of the several representations made by
            th.e contractor in respect of the contract no.30/F-2 as also other
            contracts, OMC sent the following letter dated 28.10.1978 to
    .. +                                                                       F
            the contractor:-
                 "Re : Settlement of pending claims.
                 You had called on Chairman, OMC, recently and apprised
                 him of the dues receivable by you in respect of certain
                 long pending matters such as mine benches work and G
    --t
                 raising at Kaliapani Quarry-I. In the matter of Kaliapani it
                 has been decided to constitute a committee which will go
                 separately into your claims and other facts, in which
                 connection you are requested to give all possible help
                                                                              H
    832       SUPREME COURT REPORTS                    [2008] 1 S.C.R.


A         and assistance, so that your dues, if any, will be
                                                                          +--
          ascertainable.
          In regard to other pending matters, you had indicated
          yourself that you will give the details of claims and payment
          received by you. This may be given within a day or two so
B
          as to enable OMC to settle up the above at the earliest."
         5. The contractor sent a reply dated 16.11.1978
                                                                                    ..
  enclosing therewith a statement quantifying his claims relating          t-
  to contract no. 30F-2 (subject matter of these appeals) as
c also another contract (no. 2F-2). A Committee was
  constituted by OMC to scrutinize and recommend on the
  admissibility of the claims made by the contractor in regard
  to Agreement No.30/F-2 and Agreement No.2/F-2. Several
  meetings were held by the said Committee and the claims
  of the contractor aggregating to Rs.50, 15,820 in regard to
D
  contract no.30.F2 were considered. Ultimately the Committee
  submitted a final report dated 7 .12.1979 expressing the view
                                                                           ~    ,
  that the contractor could be paid only a sum of Rs.3,52,916/
  - in regard to his claims in respect of the two contracts. The
  contractor, thereafter, wrote a letter dated 29.2.1980 stating                         ~
E that he had come to know that the Committee had submitted
  its final report and requested for a copy of the report and for
  payments of the amounts due. OMC sent a reply dated
  4.3.1980 stating that the claims were not accepted yet but
  however agreed to release a sum of Rs.3.5 lakhs and
F released the said sum on that day.                                      + ..
        6. The contractor sent a notice dated 4.6.1980 invoking
  the Arbitration Agreement (Clause 23) in respect of pending
  claims relating to Contract No. 30F-2 and two other contracts.
  He suggested a panel of names and requested OMC to appoint
G
  one of them as Arbitrator. Immediately, thereafter, the contractor      t -
  filed Misc. Case No.306/80 in regard to the contract in the Court
  of the Sub-Judge, Bhubaneswar, under section 8(2) of
  Arbitration Act, 1940 ('Act' for short) for appointment of an
  Arbitrator. The court allowed the said petition by order dated
H
               J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                    833
                  CORPN. LTD. & ANR. [RAVEENDRAN, J.]

      -1   6.10.1980 appointing Mr. Justice Balakrishna Patro, a retired A
           Judge of the Orissa High Court as Arbitrator by consent. On
           16.12.1982, an application was made by the present appellant
           under Order 22 Rule 3 CPC claiming to be the son of legatee of
           the contractor and for substituting him in place of the deceased
           N.C. Budhraja, as his legal heir. The said application was. B
           allowed by the court on 15.11.1985. In the meanwhile, Arbitration
..i        Act, 1940 ('Act' for short) was amended by the Arbitration
      -t   (Orissa Amendment) Act, 1984, inserting section 41A providing
           for constitution of and reference to the Arbitration Tribunal. By
           Notification dated 3.5.1986, (amended by Memo dated C
           23.6.1986) the State Government constituted a one Member
           Special Arbitral Tribunal with Justice N. K. Das as Arbitral
           Tribunal to settle the disputes between the contractor and iµMC
           in regard to contract no. 30/F-2.

                 7. The contractor filed a claim statement dated 27 .6.1986 D
           before the arbitrator praying for an award of Rs.3,41,42,040
           with interest from 1.6.1986, as detailed below :

                Value of work done by the contractor      : Rs.2,45,85, 183.89

                Less:     Amounts paid by OMC to the .                            E
                          Contractor                   : Rs.1,49,88.566.90

                Balance due: (Rs.95,96,616.99)
                     rounded off as                        : Rs. 95,96,616.00

                Add: Interest on the said amounts                                 F
                     from the respective dates: Rs.2,40,09,948.00

                Add: Interest on belated
                     Payments : Rs. 5.35.476.00           Rs. 2,45,45,424.00
                                                                                  G
                        Total                             Rs.3,41,42,040.00

                 In the claim statement filed before the arbitrator, the nature
           and quantum of claim made was different from what was claimed
           in the letter dated 16.11.1978 which was considered by the
           Committee. In the claim statement the contractor abandoned             H
    834          SUPREME COURT REPORTS                [2008] 1 S.C.R.


A claims to an extent of Rs.21,83,692 out of the claim of                 -Y-
  Rs.50, 15,820/- made on 16.11.1978 and claimed only
  Rs.26,32, 128 from the original claim. The balance of the claim
  was fresh claims, not made earlier. The claim of Rs.95,96,616
  made before the arbitrator was made up of two parts, first being
B a part of the original claim made in the letter dated 16.11.1978
  and the second being completely fresh claims made for the first
  time in the claim statement, as detailed below :                                    ...
                 Out of the original claim of                                 t
          (i)
                 Rs.50, 15,820 made in the            Rs. 28,32, 128
c                letter dated 16.11.1978 (The
                 claim for balance of Rs.21,83,692
                 not pursued in arbitration)

          (ii)       Fresh claims not made earlier    Rs. 67,64,488
D
          (Note : As per actual calculations, the total of the claims
          made by the appellant was Rs.96,66, 107 and the new                 I- ,
          claims were Rs.68,33,979].

         8. The Arbitrator made a reasoned award dated
E 28.11.1986 holding that the appellant was entitled to a sum
  of Rs.1,02,66,901.36 (which was more than the claim of
  Rs.95,96,616) with interest at 12% per annum from 1.8.1977
  till date of award, and future interest at the rate of 6% P.A.
  from the expiry of one month from the date of the award till
F date of decree. The award is in respect of 35 claims. Out of
  35 claims, Items 1 to 16 related to the schedule items of work
                                                                          ~       .
  under the contract (main agreement and the supplementary
  agreement 1 to 3). Items 17 to 34 were in respect of work
  which did not form part of the contract schedule. Claim 35
G related to escalation in cost of labour and material on account
  of delay in execution.
                                                                          +~

         8.1) The details of the items 1 to 16, (that is description of
    work, total amount claimed, amount admitted, difference in
    dispute and amount awarded) are as under :
H
                 e
     J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                                            835
        CORPN. LTD. & ANR. [RAVEENDRAN, J.]

SI. Description of item                  Claim of        Amount       Amount in     Award by    A
No. Contractor                          admitted by      dispute      Arbitrator
                                                          OMC
1    Removal of overburden in               50802.98      45040.32      5762.66       5762.66
     all kinds of soil etc. within a
-    lead of 100 m.
     (Maximum lift 6M)                                                                          B
2    Removal of overburden etc.            406881.20     406581.20        300.00       300.00
     within alead of one km
     beyond initial lead of 30 m
     (maximum lift-6m)
3    Transportation of excavated           676228.94     616245.60     59983.34     59983.34
     overburdened etc., within a                                                                c
     lead of 1km beyond initial
     leadof6m
4    Transportation of excavated             5361.09        5361.09            0            0
     over burdened etc., within a
     lead of 2km beyond one km.
5    Clearing heavy jungle etc.,             6201.72        3303.72     2898.00             0
                                                                                                D
6    Cutting and uprooting trees            29800.80       14205.60    15595.20             0
     etc., 5' grith
7    Cutting and uprooting trees            11352.00        3360.00     7992.00             0
     etc., 5' to 1O' grith
8    Excavation of overburden             3689850.00    3390979.12    298870.88    298870.88    E
     in all kinds of rocks etc.,
     upto 60m lead
9    Excavation of overburden            10370041.20   10370041.20             0            0
     in all kinds of rock etc., upto
     2km distance and within lifts
     of35m                                                                                      F
10 Lift beyond 15m upto 16m                  5066.85        5054.84        12.01        12.01
   depth
11   Lift beyond 16m upto 17m                9858.70       9785.55         73.15        73.15
12 Lift beyond 17m upto 18m                 12647.79       12373.84       273.95       273.95
13 Lift beyond 18m upto 19m                 13358.54      13037.07       321.47        321.47   G
14 Lift beyond 19m upto 20m                  9812.25       9447.79       364.46        364.46
15 Lift beyond 20 upto 21 m                  5070.33       4882.89        187.44       187.44
16 Lift beyond 21mupto22m                      89.71          76.89        12.82        12.82

                                       1,53,16,507.00 149,19,076/72   397,430/28   365,862/18
                                                                                                H
    836       SUPREME COURT REPORTS                [2008] 1 S.C.R.


A       Though in the claim statement, the appellant had clearly     f'·
  stated that he had in all received Rs.149,88,566/90, and given
  credit for the said sum, during the hearing, the appellant
  contended that instead of Rs.149,88,566/90, he had
  appropriated only Rs.120,01,695/90 towards this contract and
B that the balance of Rs.29,86,871/- had been adjusted towards
  some other contacts. Even though the claim statement was not
  amended, the Arbitrator proceeded on that basis and awarded                   ;..
  Rs.32,83,243 in respect of items 1 to 16 as under:
                                                                      -'\
          A. Total amount claimed for
c            Items 1to16                        Rs. 153, 16,507.00

          B. Total of Items 1 to 16 admitted
             byOMC                              Rs. 149,19,076/72
          C. Total of claims admitted by
D            Arbitrator                           Rs. 3,65,862/18

             (B+C)                      Total   Rs. 152,84,938/90     ~     f


          Amount shown as received by           Rs.1,20,01,695/90
          contractor towards Items 1 to 16
E         (as against Rs.149,88,566/90
          shown as received from OMC in
          the claim statement)

          BALANCE arrived at Arbitrator          Rs.32,83,243.00
F         as due to contractor in respect of
          items 1 to 16                                              -t •
       8.2) Claims of contractor at SI. No. 17 to 34 related to
  items of work not covered in the schedule to the contract, for
  which claim was made on the basis of damages/quantum meruit.
G As against the total of Rs.70,56,573/55 claimed in regard to
  these 18 items (Items 17 to 34), the Arbitrator awarded in all
                                                                     +- •
  Rs.52,56,847/36. The details of the claims made by the
  appellant and the amount awarded in respect of each of them
  are as under :
H
     J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                     837
        CORPN. LTD. & ANR. [RAVEENDRAN, J.]

s.   Description of item                  Amount            Amount      A
N.                                        Claimed          Awarded
17 Extra Head Lead for 90 m             2810144.10        2450042.88
18 Removal of excavated materials         54888.60          50858.60
   from the edge of the quarry
19 Unmeasured quantity of                848372.64         664720.00    B
   excavation
20 Catch Water Drain                     278842.50          27842.50
21 Removal of slipped earth from         143646.00                Nil
   side slopes
22 Restoration of benches to             186761.16         140070.87
   proper shape
                                                                        c
23 Bullah Pilling to prevent              15722.70                Nil
   slipping of benches
24 Dry rubble packing                    202499.00         122856.40
25 Extra lift during construction        262837.73         262837.73
   of Haul Road                                                         D
26 Extra lift for excavated              360690.49         270517.88
   materials dumped at quarry
   edge.
27 Extra lift measured by               1396128.63        1047096.50
   Surveyor but not paid                                                E
28 Idle labour due to non-supply         145577.00                Nil
   of working plan
29 Idle labour due to want of             76850.00                Nil
   working site
30 Idle labour due to stoppage of        389288.00         194644.00
                                                                        F
   work by the respondent and
   restriction of working area
31 Reparing of Haul road                  10640.00                Nil
   damaged by cyclone
32 Reconstruction of Damsala              25370.00          25370.00
   Embankment                                                           G
33 Barbed wire fencing·                   27315.00                Nil
34 Supply of electricity to work          72000.00                Nil
     site and respondent's colony
                                    Rs.70,56,573/55   Rs.52,56,847/36
                                                                        H
    838         SUPREME COURT REPORTS                  [2008] 1 S.C.R.


A      8.3)The last item of claim of the appellant, namely item            'r-
  No.35 was for Rs.22,17,188/34 as escalation in cost between
  1972 and 1975 on account of increase in cost of labour and
  material, based on the General Price Index. The Arbitrator
  determined the value of work executed after 1.4.1973 as
B Rs.52,96,967/-. He awarded an escalation of 32.6% on the said
  value of work and awarded Rs.17,26,811.00 as escalation in
  cost of labour and material.
                                                                                         "
          8.4) Thus the Arbitrator awarded Rs.102,66,901.66 to the             '\
    appellant as detailed below (exclusive of interest), as against
c   the claim of Rs.95,96,616/- (exclusive of interest) made by the
    appellant:
          (i)   Amounts award in respect of          Rs.32,83,243.00
                claims 1 to 16
D         (ii) Amounts awarded in respect of         Rs.52,56,847.36
               claims 17 to 34 (as against
                                                                           •.        f
               claim of Rs.70,56,573/55)
          (iii) Amount awarded in respect of       Rs. 17,26,811.00
                claim 35 as escalation (as against
E
                claim of Rs.22,17,188/34)
                               Total award         Rs.102,66,901.36
       9. The contractor filed OS No.224/1986 for making the
  award rule of the court, on the file of the Civil Judge, Sr. Division,
F Bhubaneswar. The objections to the said award filed by OMC               ~        ..
  were registered as Misc. Case No.5/1987. The said court, by
  common judgment dated 21.3.1998, overruled the objections
  and directed that the award of the arbitrator be made the rule of
  the court and a decree be drawn in terms of the award.
G
       10. Feeling aggrieved, OMC filed Misc. Appeal No.296/
  1998, challenging the decision of the Civil Judge refusing to set
  aside the award, directing a decree in terms of the award. The
                                                                           ...
  contractor filed Misc. Appeal No.198/1998 and Civil Revision
  No.109/1998 claiming future interest from the date of decree
H as the judgment of the Civil Judge was silent on that aspect.
                       J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                    839
                          CORPN. LTD. & ANR. [RAVEENDRAN, J.]

          -1!      The High Court heard and disposed of the said appeals and              A
                   revision petition by common judgment 15.10.1999. It allowed
                   Misc. Appeal No.296/1998 filed by OMC and dismissed M.A.
                   No.198/1998 and C.R. No.109/1998 filed by' the contractor. The
                   High Court held :
                        (i)    The claim of the contractor was barred by limitation 8
                               and therefore the award was liable to be set aside .
.,

          ~
                        (ii)   The arbitrator acted beyond his jurisdiction in
                               awarding huge amounts towards alleged extra work,
                               even though there was nothing to indicate that             c
                               conditions contemplated in proviso to Clause 11
                               (relating to additional work) were satisfied.
                        (iii) Though the award purported to be a reasoned award,
                              the award in regard to Items 17, 18, 19 and 25 to 27
                              was not supported by any reason and therefore, the          D
                              award was liable to be set aside .
 .,.      --.'.i

                        (iv)   The award in respect of escalation in cost (item 35)
                               at the rate of 32.6% of the value of work was without
                               basis, (when the claim itself was for a lesser rate}, in
                                                                                          E
                               the absence of any provision in the contract for
                               escalation, amounted to legal misconduct.
                        (v)    The award being in excess of the claim made by the
                               contractor shocked the judicial conscience of the
                               court.                                                     F
     ..       j
                        (vi)   Interest could have been awarded by the arbitrator
                               only from the date of reference (6.10.1980) and could
                               not be awarded in regard to·any pre-reference period.
                        (vii) Though in the normal course, some of the issues G
                              would have necessitated remitting the matter to the
     ~-~
                              arbitrator for fresh consideration, it was not necessary
                              to remit the matter as the entire award was being set
                              aside on the ground of limitation.
                        The said decision of the High Court is challenged by the          H
    840            SUPREME COURT REPORTS                 (2008] 1 S.C.R.


A appellant in this appeal by special leave.                                 r-
          11. On the contentions urged, the following questions arise
    for consideration :
            (i)    Whether the claim made before the arbitrator or any
B                  part thereof was barred by limitation?
            (ii)   Whether the award is liable to be set aside on the
                   ground of legal misconduct and the error apparent
                   on the face of the award?
c           (iii) Whether the award is liable to be set aside on the
                  ground that the arbitrator exceeded his jurisdiction ?
            (iv) To what relief the parties are entitled?
          .Questions (i) and (ii) :
D           12. The Arbitrator held that the claims were not barred. He
    held:
          "In the case of a suit, the date on which the cause of action
          arises is the date from which the limitation period starts.
          Under section 20, it is the date on which the right to apply
E
          accrues that determines the starting point. That starting
          point does not coincide with the date on which the cause
          of action for filing a suit arises. The same principle would
          apply to an application under section 8 of the Act. ... The
          claimant signed the final bill on 14.4.1977 under protest.
F
          It is not correct to say that the claimant accepted the final
          bill. ... All these factors show that negotiation was going
          on and the matter was in a nebulous and fluid stage. The
          committee gave its report in December, 1979. In March,
          1980 some portion out of the money said to have been
G         found due by the committee was paid on ad hoc basis.
          Notice was given by the contractor on 14.6.80. So, the             +•
          dispute as to final bill still continues. Till the final bill is
          prepared and accepted by the contractor, limitation would
          not accrue. When the matter went to court in 1980, .it was
H
    J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                   841
       CORPN. LTD. & ANR. [RAVEENDRAN, J.]

     not barred by limitation ... "                                  A
       13. The High Court found that the work was completed on
15.6.1975, final measurement was taken on 16.6.1975 and the
final bill was signed by the contractor under protest on 14.4.1977
and therefore held that the cause of action for the contractor to
                                                                      B
make a claim arose on 14.4.1977. According to the High Court,
as the notice invoking arbitration was issued on 4.6.1980 and
the petition under section 8(2) of the Act was filed thereafter,
beyond three years from 14.4.1977, the entire claim was barred
by limitation. The High Court further held that as the final bill was C
signed under protest by the contractor, it could be said that the
cause of action arose on a date subsequent to the date of
signing of the final bill. It further held that the fact that the
Departmental Committee considered the claims in 1979,
subsequent to the signing of the final bill under protest, did not
have the effect of saving/extending limitation in the absence of D
any acknowledgement in writing as required under section 18
of the Act.
      14. Section 18 of the Limitation Act, 1963 deals with
effect of acknowledgement in writing. Sub-section (1) thereof E
provides that where, before the expiration of the prescribed
period for a suit or application in respect of any right, an
acknowledgement of liability in respect of such right has been
made in writing signed by the party against whom such right
is claimed, a fresh period of limitation shall be computed F
from the time when the acknowledgement was so signed.
The explanation to the section provides that· an
acknowledgement may be sufficient though it omits to specify
the exact nature of the right or avers that the time for payment
has not yet come or is accompanied by a refusal to pay, or is G
coupled with a claim to set off, or is addressed to a person
other than a person entitled to the right. Interpreting section
19 of the Limitation Act, 1908 (corresponding to section 18
of the Limitation Act, 1963) this Court in Shapur Fredoom
Mazda v. Durga Prosad Chamaria (AIR 1961 SC 1236), held: H
    842       SUPREME COURT REPORTS                     [2008] 1 S.C.R.


A         "... acknowledgement as prescribed by section 19 merely            r-
          renews debt; it does not create a new right of action. It is
          a mere acknowledgement of the liability in respect of the
          right in question; it need not be accompanied by a promise
          to pay either expressly or even by implication.
B
          The statement on which a plea of acknowledgement is
          based must relate to a present subsisting liability though
          the exact nature or the specific character of the said liability
          may not be indicated in words. Words used in the
          acknowledgement must, however, indicate the existence
c         of jural relationship between the parties such as that of
          debtor and creditor, and it must appear that the statement
          is made with the intention to admit such jural relationship.
          Such intention can be inferred by implication from the nature
          of the admission, and need not be expressed in words. If
D         the statement is fairly clear, then the intention to admitjural
          relationship may be implied from it The admission in
          question need not be express but must be made in
          circumstances and in words from which the court can
          reasonably infer that the person making the admission
E         intended to refer to a subsisting liability as at the date of
          the statement. Stated generally, courts lean in favour of a
          liberal construction of such statements though it does not
          mean that where no admission is made one should be
          inferred, or where a statement was made clearly without·
F         intending to admit the existence of jural relationship such
          intention could be fastened on the maker of the statement
          by an involved or far-fetched process of reasoning."
          In construing words used in the statements made in writing
          on which a plea of acknowledgement rests oral evidence
G
          has been expressly excluded but surrounding
          circumstances can always be considered .... The effect
          of the words used in a particular document must inevitably
          depend upon the context in which the words are used and
          would always be conditioned by the tenor of the said
H
                  J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                    843
                     CORPN. LTD. & ANR. [RAVEENDRAN, J.)
     ~
                   document .....                                                     A
                     15. It is now well settled that a writing to be an
              acknowledgement of liability must involve an admission of a
              subsisting jural relationship between the parties and a conscious
              affirmation of an intention of continuing such relationship in
                                                                                      B
              regard to an existing liability. The admission need not be in
              regard to any precise amount nor by expressed words. If a
      }       defendant writes to the plaintiff requesting him to send his claim
              for verification and payment, it amounts to an acknowledgement.
              But if the defendant merely says, without admitting liability, it
              would like to examine the claim or the accounts, it may not amount      c
              to acknowledgement. In other words, a writing, to be treated as
              an acknowledgement of liability should consciously admit his
              liability to pay or admit his intention to pay the debt. Let us
              illustrate. If a creditor sends a demand notice demanding
              payment of Rs.1 lakh due under a promissory note executed by            D
"~            the debtor and the debtor sends a reply stating that he would
              pay the amount due, without mentioning the amount, it will still
              be an acknowledgement of liability. If a writing is relied on as an
              acknowledgement for extending the period of limitation in
              respect of the amount or right claimed in the suit, the                 E
              acknowledgement should necessarily be in respect of the
              subject matter of the suit. If a person executes a work and issues
              a demand letter making a claim for the amount due as per the
              final bill and the defendant agrees to verify the bill and pay the
          ~
·"            amount, the acknowledgement will save limitation for a suit for         F
              recovery of only such bill amount, but will not extend the limitation
              in regard to any fresh or additional claim for damages made in
              the suit, which was not a part of the bill or the demand letter.
              Again we may illustrate. If a house is constructed under the item
              rate contract and the amount due in regard to work executed is          G
 >-_ __.,
              Rs. two lakhs and certain part payments say aggregating to
              Rs.1,25,0000/- have been made and the contractor demands
              payment of the balance of Rs. 75,000/- due towards the bill and
              the employer acknowledges liability, that acknowledgement will
              be only in regard to the sum of Rs. 75,000/- which is due. If the       H
    844       SUPREME COURT REPORTS                    [2008] 1 S.C.R.


A contractor files a suit for recovery of the said Rs.75,000/- due in
  regard to work done and also for recovery of Rs.50,000/- as
  damages for breach by the employer and the said suit is filed
  beyond three years from completion of work and submission of
  the bill but within three years from the date of acknowledgement,
B the suit will be saved from bar of limitation only in regard to the
  liability that was acknowledged namely Rs.75,000/- and not in
  regard to the fresh or additional claim of Rs.50,000/-which was
                                                                           t
  not the subject matter of acknowledgement. What can be
  acknowledged is a present subsisting liability. An
c acknowledgment made with reference to a liability, cannot
  extend limitation for a time barred liability or a claim that was
  not made at the time of acknowledgment or some other liability
  relating to other transactions. Any admission of jural relationship
  in regard to the ascertained sum due or a pending claim, cannot
D be an acknowledgement for a new additional claim for
  damages.
          16. We will now examine this case with reference to the
    said principles. In this case, the cause of action accrued on
    14.4.1977 when the final bill was signed by the contractor. It is
E   not in dispute that the final bill showed that a sum of
    Rs.17,69,608.73 was payable to the contractor (after giving
    credit to the payments made and after withholding a sum of
    Rs.7,45,953.83 as 5% security deposit). Towards the said sum
    of Rs.17,69,608. 73. Rs.17 lacs was paid on 25.2.1976 and
F   Rs.70,000/- was paid on 6.8.1977. The contractor had made
    some claims and OMC wrote a letter dated 28.10.1978 in
    regard to the pending claims of the contractor. In regard to
    Kaliapani matters, OMC informed the contractor that it has been
    decided to constitute a Committee which will go into the claims
G   of the contractor so that the dues, if any, could be ascertained. It
                                                                           t· •
    further stated that on the details of the claims and payments
    received being given to the contractor, OMC will settle up the
    pending matters at the earliest. This clearly showed an intention
    on the part of OMC to admit the jural relationship of contractor
H   and employer and an intention to settle the pending claims after
                    J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING               845
                       CORPN. LTD. & ANR. [RAVEENDRAN, J.]
    ·-'i         being satisfied about them. Therefore, the letter dated A
                 28.10.1978 was clearly an acknowledgement in writing in so
                 far as the "pending claims" of the contractor. What were the
                 pending claims is made clear in the letter dated 16.11.1978
                 written by the contractor enclosing a statement showing that in
                 all, a sum of Rs.50, 15,820/-was due. The Committee constituted B
                 by the OMC examined these claims and admitted the claims
                 only to an extent of Rs.3,52,916/- as per its final report dated
      ~
                 7.12.1979. OMC paid Rs.3,50,000/- on 4.3.1980. In view of the
                 acknowledgement in writing on 28.10.1978 and payment of the
                 Rs.3,50,000/- on 4.3.1980, it can be said that in regard to the  c
                 pending claims of the contractor, the limitation stood extended
                 by three years from 4.3.1980 and at all events by three years
                 from 28.10.1978. It is not in dispute that the contractor issued
                 the notice invoking arbitration on 4.6.1980 and immediately filed
                 a petition under section 8(2) of the Act for appointment of D
                 Arbitrator which was allowed on 6.10.1980. Therefore, whatever
"     "!
                 claims were made before the Arbitrator which was part of the
                 claim of Rs.50, 15,820, was within time, having been made within
                 three years from 28.10.1978 and 4.6.1980.
                       17. In regard to the claims aggregating to Rs.95,96,616/- E
                 made in the claim statement filed before the Arbitrator, only
                 claims aggregating to Rs.28,32, 138 related to and formed part
                 of the said pending claim of Rs.50, 15,820. The appellant did
                 not make a claim in regard to the remaining Rs.21,83,692.
-..
           ,._
                 Therefore, out of the claim of Rs.95,96,616 made by the F
                 appellant before the Arbitrator, the claim for only Rs.28,32, 138/
                 - was not barred by limitation. The remaining claims of the
                 appellant aggregating to Rs.67,64,488/- out of the total of
                 Rs.95,96,616/- being fresh claims, were not "pending claims"
                 in respect of which the acknowledgement was made. Therefore G
    ·---+        the said fresh claims aggregating to Rs.67,64,488 made for
                 the first time in the claims statement filed on 27 .6.1986 were
                 clearly barred by limitation.
                      18. The learned counsel for the appellant subm.itted that
                                                                                  H
    846       SUPREME COURT REPORTS                   [2008) 1 S.C.R.


A the limitation would begin to run from the date on which a              Y-
  difference arose between the parties, and in this case the
  difference arose only when OMC refused to comply with the
  notice dated 4.6.1980 seeking reference to arbitration. We are
  afraid, the contention is without merit. The appellant is obviously
B confusing the limitation for a petition under section 8(2) of the
  Arbitration Act, 1940 with the limitation for the claim itself. The
  limitation for a suit is calculated as on the date of filing of the
  suit. In the case of arbitration, limitation for the claim is to be          t

  calculated on the date on which the arbitration is deemed to
c have commenced. Section 37(3) of the Act provides that for the
  purpose of Limitation Act, an arbitration is deemed to have been
  commenced when one party to the arbitration agreement serves
  on the other party thereto, a notice requiring the appointment of
  an arbitrator. Such a notice having been served on 4.6.1980, it
D has to be seen whether the claims were in time as on that date.
  If the claims were barred on 4.6.1980, it follows that the claims
                                                                           J<      ~
  had to be rejected by the arbitrator on the ground that the claims
  were barred by limitation. The said period has nothing to do
  with the period of limitation for filing a petition under section
E 8(2) of the Act. Insofar as a petition under section 8(2), the cause
  of action would arise when the other party fails to co.mply with
  the notice invoking arbitration. Therefore, the period of limitation
  for filing a petition under section 8(2) seeking appointment of
  an arbitrator cannot be confused with the period of limitation for
   making a claim. The decisions of this Court in lnder Singh Rekhi      _.,
F                                                                                  ~


   vs. Delhi Development Authority- (1988) 2 SCC 338, Panchu
   Gopal Bose vs. Board of Trustees for Port of Calcutta - (1993)
  4 SCC 338 and Utkal Commercial Corporation vs. Central
   Coal Fields - (1999) 2 SCC 571 also make this position clear.

G       19. The appellant next contended, relying on section 18 of
  Limitation Act, that as there was acknowledgement of liability in        t .
  regard to Contract No.30/F-2 in the letter dated 28.10.1978,                         ,_
  and the notice invoking arbitration was issued on 4.6.1980 within
  3 years from 28.10.1978, he was at liberty to make any claim in
H regard to the contract before the arbitrator, (even though such
    J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING               847
       CORPN. LTD. & ANR. [RAVEENDRAN, J.]

claims had not been earlier made) and all such claims shall A
have to be treated as being within the period of limitation. Such
a contention cannot be countenanced. As noticed above, the
cause of action arose on 14.4.1977. But for the
acknowledgement on 28.10.1978, on the date of invoking
arbitration (4.6.1980), the claims would have been barred by B
time as being beyond the period of limitation. The limitation is
extended only in regard to the liability which was acknowledged
in the letter dated 28.10.1978. It is not in dispute that either on
28.10.1978 or on 4.3.1980, the contractor had not made the
fresh claims aggregating to Rs.67,64,488 and the question of     c
such claims made in future for the first time on 27 .6.1986, being
acknowledged by OMC on 28.10.1998 did not arise.
      20. Another aspect requires to be noticed. The contractor
was N.C.Budhraja. The original claim (which was the subject
matter of letter dated· 28.10.1978, subjected to examination by D
the Committee as per report dated 7.12.1979, and towards
which Rs.3,50,000/- was paid) made by the contractor N.C.
Budhraja aggregated to Rs.50, 15,820. ihe Appellant who is
his LR cannot for the first time make a fresh claim before the
Arbitrator, which was never made by N.C. Budhraja. The E
Appellant could only pursue the claim made by N.C. Budhraja,
which were pending or subsisting when N.C. Budhraja issued
the notice dated 4.6.1980
      21. The arbitrator committed an error apparent on the face F
of the record and a legal misconduct in holding that the entire
claim was within time. His assumption that if the application
filed by the contractor in 1980 under section 8(2) of Arbitration
Act for appointment of an Arbitrator was in time, all claims made
in the claim statement filed before the Arbitrator appointed in G
such proceeding under section 8(2) are also in time, is patently
erroneous and is an error apparent on the face of the record.
The reasoning of the arbitrator that on account of the formation
of the Committee by OMC to scrutinize the pending claims in
pursuance of the OMC's letter dated 28.10.1978, and the
                                                                 H
    848       SUPREME COURT REPORTS                 [2008] 1 S.C.R.

                                                                       t--
A payment of Rs.3,50,000/- on 4.3.1980 in pursuance of the
  Committee giving its final report on 7.12.1979, every claim of
  the contract including new claims which were made for the first
  time in the claim statement filed in 1986 (as contrasted with
  'pending claims' considered by OMC), are not barred by
B limitation, is also an error apparent in the face of the award.
  Under section 18 an acknowledgement in writing extends the
  limitation. Under section 19 a payment made on account of a
  debt, enables a fresh period of limitation being computed.                •
  Therefore, the letter of OMC dated 28.10.1978 and the payment
c of Rs.3,50,000/- by OMC, would result in a fresh period of
  limitation being computed only in regard to the 'existing debt' in
  respect of which acknowledgment and payment was made.
  Admittedly, as at that time, the claim of the contractor was only
  for a sum of Rs.50, 15,820. Therefore, the letter dated
D 28.10.1978 and payment on 4.3.1980 extended the limitation
  only in respect of the claims which were part of the said claim of
  Rs.50, 15,820. Therefore, the fresh claims of Rs.67,64,488/- (out
                                                                           '/i
                                                                                  ~
                                                                                         •
  of the total claim of Rs.95,96,616) is barred by limitation and
  the award made in that behalf is liable to be set aside.
E Consequently, we hold that only that part of the claim before the
  Arbitrator which was part of the claim of Rs.5015,820/- made
  by the contractor, that was existing or pending as on 28.10.1978
  and 4.3.1980, namely Rs.28,32, 128 (out of Rs.95,96,616) could
  have been considered by the Arbitrator.
F                                                                      ~
          Question (iii) & (iv) :                                                ..- '

        22. In the claim statement filed before the arbitrator the
  appellant showed the value of work done as Rs.2,45,85, 183.89
  and the total payments made by OMC as Rs.149,88,566.90.
G Thus he claimed the balance due as Rs.95,96,616. Even while
  calculating the interest on the amount outstanding, the claimant     t·         .
  proceeded on the basis that he has received in all,
  Rs.1,49,88,566.90 from OMC. The prayer before the arbitrator
  in the claim statement was for the award of Rs.95,96,616 in
  regard to the work done after giving credit of Rs.1,49,88,566.90.
H
              J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                   849
                 CORPN. LTD. & ANR. [RAVEENDRAN, J.]

  ~1      The categorical stand of the contractor and the appellant all along   A
          has been that OMC had paid in all a sum of Rs.149,88,566.90.
          But during the course of the arbitration proceedings, the
          appellant contended that out of Rs.149,88,566.90 received from
          OMC and taken into credit towards this contract, a sum of
          Rs.29,86,871 /-was being appropriated towards other contracts         B
          and therefore the payments made by OMC towards this contract
          should be taken as Rs.120,01,695.90. The arbitrator has
   ...    mechanically accepted the said altered stand contrary to the
          claim statement and proceeded to determine the amount
          payable by OMC, by taking the amount paid by OMC as                   c
          Rs.120,01,659.90 towards this contract, even though the claim
          statement showing that OMC had paid Rs.149,88,566.90
          remained unaltered. The claim statement was not amended to
          show that only Rs.120,01,659.90 had been received from OMC
          in regard to the contract. When the claim made in the claim           D
          statement is after adjusting Rs.149,88,566.90 paid by OMC
   ,'/    towards the work, the arbitrator cannot proceed on the basis
          that only Rs.120,01,659.90 was paid towards the work. As a
          result though the Arbitrator found that the amount payable towards
          claims at Items 1 to 16 was only Rs.365,862.18, he awarded            E
          Rs.32,83,243/- to the appellant, thereby increasing the liability
          of OMC by Rs.29,86,871/-. By awarding more than what was
          claimed in the claim statement (by showing a lesser amount as
          having been paid by OMC though claim statement showed a
          higher amount), the Arbitrator clearly exceeded his jurisdiction.
... ...                                                                         F
          The Arbitrator thus committed a legal misconduct and the award
          to that extent is liable to be set aside. Therefore ·the amount
          awarded in respect of claims at items 1 to 16 by the Arbitrator
          is to be reduced by Rs.29,86,871/-.
                23. The Arbitrator has exceeded his jurisdiction in another G
• 1       respect. The total claim made by the contractor before the
          Arbitration was Rs.95,96,616/- (excluding interest). But the
          amount awarded by the arbitrator towards the said claim was
          Rs.1,02,66,901/36 (excluding interest). Making an award in
          excess of the claim itself by Rs.6,70,285 is a clear act of H
   850        SUPREME COURT REPORTS                    [2008] 1 S.C.R.


A exceeding the jurisdiction and amounts to a legal misconduct             t-
  and to that extent of Rs.6,70,285/- the award is invalid.
        23. In regard to item 35, that is escalation in cost, the claim
  in the claim statement was at the rate of 15% for the value of
  work done in 1972-73, 28.5% in respect of value of work done
B
  in 1973-74 and 32% in respect of work done in 1974-75. But
  the Arbitrator has awarded escalation at a flat rate of 32.6% on
  the entire cost of work done from 1.4.1973 and thereby awarded
  an escalation in excess of what was claimed. This also amounts               ~


  to exceeding the jurisdiction and therefore legal misconduct.
c The award in excess of what was claimed was invalid.
       25. The award of the arbitrator in respect of time barred
  claim of Rs.67,64,488 is an error apparent on the face of the
  award. Award of amounts in excess of claim (referred to in paras
D 22, 23 and 24) clearly amount to exceeding the jurisdiction. All
  these, that is awarding amount towards time barred part of the
  claim of Rs.67 ,64,488, and awarding amounts of Rs.29,86,871,            )t

  Rs.670,285 and escalation in cost at a rate more than what is
  claimed, are all legal misconducts and the award in regard to
E those amounts are null and void. There is however some
  overlapping of the aforesaid amounts.
        26. Does it mean that the entire award should be set aside?
  The answer is no. That part of the award which is valid and
  separable can be upheld. That part relates to the claims which
F were validly before the Arbitrator, which were part of the existing
  or pending claims of Rs.50, 15,820 and which were not barred
                                                                          ..       ~




  by limitation. As stated above they were the claims which were
  existing or pending in 1978, 1979 and 1980 (considered by the
  committee and payment made by OMC) which were carried
G before the Arbitrator to an extent of Rs.28,32, 128. Only the
  amounts awarded by the Arbitrator against those claims can
                                                                           t       •
  be considered as award validly made in Arbitration, falling within
  jurisdiction. They are clearly severable from the other portions
  of the award. The particulars of the claims and corresponding
H awards    are as follows:
     J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                                    851
        CORPN. LTD. & ANR. [RAVEENDRAN, J.]

Item Description                 Item No. Contractor's Contractor's      Award by       A
 No.                              in letter   claim      claim before    Arbitrator
                                   dated    originally    Arbitrator
                                  16.11.78 made 16.11.78
7.   Cutting and uprooting          5        20,869.32      11,352.00             Nil
     trees
                                                                                        B
17. Extra head lead for 90 M      7(a)     2,61,926.40 28, 10, 144.00 24,50,042.88
                                                                      (261,926.40)*
18. Removai of excavated            3      3,43,360.58     54,888.60       50,858.60
    material from edge of
    quarry
19. Unmeasured quantity of          4      8,44,360.00    8,48,372.64    6,64,720.00
                                                                                        c
    excavation
20. Catch water drain              12      1,55,400.00     27,842.50      27,842.50
21. Removal of slipped earth       15      3,42,960.00    1,43,646.00             Nil
    from side slopes
26. Extra lift for excavated
                                                                                        D
                                  7(e)       42,370.00    3,60,690.49    270,517.88
    material dumped at                                                  (42,370.00)*
    quarry edge
27. Extra lift measured by         7{b}    1,25,642.00 13,96,128.67 10,47,096.50
    surveyor                                                        (125,642.00)*
28. Idle labour (non supply       9(a)     1,45,575.00    1,45,575.00             Nil
                                                                                        E
     of plans)
29. Idle labour (for want of       9(c)      75,450.00     76,850.00              Ni
     site)
30. Idle labour {due to    9(b) & {d       2,61,205.00    3,89,288.00    194,644.00
     stoppage of work and                                                               F
    restriction of working
    area)
31. Repairing road damaged 10(iii)           10,640.00     10,640.00              Nil
    by cyclone
32. Reconstruction of        10(vii)         25,370.00     25,370.00      25,370.00     G
    Embasskent
33. Wire fencing               13          1,05,000.00     27,315.00              Nil
34. Electricity supply to work    6(b}       72,000.00     72,000.00              Nil
     site and colony
                                          28,32, 128.30                 13,93,373.50    H
    852        SUPREME COURT REPORTS                    [2008] 1 S.C.R.


A         [Note : The figures shown by (*) in the column 'Award by             t'-
          Arbitrator', refer to the maximum that could have been
          awarded by the Arbitrator having regard to claim that was
          not barred by limitation].
        Thus the total amount awarded by the Arbitrator against
B claims which were not barred by limitation was only
  Rs.13,93,373.50. The award to this extent is not open to
  challenge. This part of the award does not suffer from any legal
  misconduct. There is also no error apparent on the face of the
  award in respect of the amount. It is not open to challenge.
c
           27. The scope of interference is limited. In Hindustan
    Construction Co. Ltd. vs. Governor of Orissa - (1995) 3 SCC
    8, this Court held :
          "It is well known that the court while considering the question
D         whether the award should be set aside, does not examine
          that question as an appellant court. While exercising the
          said power, the court cannot reappreciate all the materials
          on the record for the purpose of recording a finding
          whether in the facts and circumstances of a particular case
E         the award in question could have been made. Such award
          can be set aside on any of the grounds specified in section
          30 of the Act."
         In Hindustan Tea Co. vs. Mis K. Sashikant & Co. - 1986
    (Supp.) SCC 506, this Court observed thus :
F                                                                           ..<\
          "The Award is reasoned one. The objections which have                      ~




          been raised against the Award are such that they cannot
          indeed be taken into consideration within the limited ambit
          of challenge admissible under the scheme of the Arbitration
G
          Act. Under the law, the Arbitrator is made the final arbiter
          of the dispute between the parties. The award is not open
          to challenge on the ground that the Arbitrator has reached           t     ..
          a wrong conclusion or has failed to appreciate facts."
       Therefore, the Award of the Arbitrator has to be upheld to
H an extent of Rs.13,93,373.50.
             J.C. BUDHRAJA v. CHAIRMAN, ORISSA MINING                853
                CORPN. LTD. & ANR. [RAVEENDRAN, J.]
    -~         28. In view of the foregoing, we allow these appeals in A
         part, set aside the judgment of the High Court and direct a
         decree in terms of the award for a sum of Rs.13,93,373.50 with
         interest at the rate of 12% P.A. from 1.8.1977 to date of award
         (28.11.1986) and at the rate of 6% P.A. thereafter, that is from
         29 .11.1986 till date of payment. Parties to bear their respective B
         costs.
         K.K.T.                                 Appeals partly allowed.




'   "




.. t


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.