INTERNATIONAL SEAPORT DREDGING PVT LTDversusKAMARAJAR PORT LIMITED
- Citation
- 2024 INSC 827
- Decided
- 24 October 2024
- Disposal
- Appeal(s) allowed
- Bench
- D Y CHANDRACHUD
Holding
The Supreme Court held that the Arbitration Act mandates equal treatment of all parties and that a stay of an arbitral award for payment of money may be conditioned only on security consistent with Order XLI Rule 5 of the CPC, not on the statutory status of the respondent.
Summary
International Seaport Dredging Pvt Ltd entered into a dredging contract with Kamarajar Port Limited, a statutory undertaking, which later gave rise to disputes and arbitration. The arbitral tribunal awarded the appellant approximately Rs 21.07 crore with interest and costs, and the respondent sought correction under s.33 and challenged the award under s.34. The Madras High Court stayed enforcement of the award on the condition that the respondent furnish a bank guarantee for the principal amount, relying on the respondent's status as a statutory body. The Supreme Court held that the Arbitration Act is a self‑contained code that does not differentiate between governmental and private parties, and that the form of security for a stay must be guided by Order XLI Rule 5 of the CPC, not by the party’s status. Accordingly, the Court modified the stay, directing the respondent to deposit 75% of the decretal amount (including interest) by a specified date, with the stay conditioned on that deposit, and allowed the appeal.
Issues considered
- Whether the High Court could condition the stay of execution of an arbitral award on the respondent furnishing a bank guarantee solely because it is a statutory undertaking.
- What form of security, if any, is appropriate under s.36(3) of the Arbitration and Conciliation Act, 1996, in view of the provisions of Order XLI Rule 5 of the CPC.
- Whether the Arbitration Act requires equal treatment of governmental and private parties when granting a stay of a money award.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 18, s. 33, s. 34, s. 36, s. 37
- Arbitration and Conciliation (Amendment) Act, 2015
- Building and other Construction Workers’ Welfare Cess Act 1996
- Code of Civil Procedure, 1908s. Order XLI Rule 5
Headnote
Issue for Consideration Matter pertains to the correctness of the order passed by the High Court granting stay on the execution of the award conditional on the respondent furnishing a bank guarantee. Headnotes† Arbitration and Conciliation Act 1996 Arbitral award – Stay on enforcement – Dispute between parties – Invocation of arbitration agreement – Arbitral award passed directing the respondent to pay the appellant certain sum with 9% interest which would be increased to 12% p.a. if not paid within three months
Subjects
Judgment
[2024] 10 S.C.R. 1503 : 2024 INSC 827
International Seaport Dredging Pvt Ltd
v.
Kamarajar Port Limited
(Civil Appeal No. 12097 of 2024)
24 October 2024
[Dr Dhananjaya Y Chandrachud,* CJI,
J.B. Pardiwala and Manoj Misra, JJ.]
Issue for Consideration
Matter pertains to the correctness of the order passed by the High
Court granting stay on the execution of the award conditional on
the respondent furnishing a bank guarantee.
Headnotes†
Arbitration and Conciliation Act 1996 – ss.36, 34 – Arbitral
award – Stay on enforcement – Dispute between parties –
Invocation of arbitration agreement – Arbitral award passed
directing the respondent to pay the appellant certain sum
with 9% interest which would be increased to 12% p.a. if
not paid within three months and certain amount as costs –
Applications u/s.33 for correction of the award by both the
parties – Arbitral tribunal dismissed the application filed by
the respondent, however allowed the application filed by the
appellant – Respondent challenged the arbitral award u/s.34
and moved an application for stay of execution – High Court
granted a stay on the execution of the award conditional on
the respondent furnishing a bank guarantee – Correctness:
Held: Law qua arbitration proceedings, cannot be any different
merely because of the status of the respondent as a statutory
undertaking – High Court ought not to have based its decision on
the condition for the grant of stay on the status of the respondent
as a statutory authority – Arbitration Act is a self-contained
code, it does not distinguish between governmental and private
entities – Hence, the decision of the Court cannot be influenced
by the position of the party before it and whether it is a fly-by-night
operator – In the absence of any provision of law, it would be
inappropriate for courts to apply this standard while adjudicating
* Author
1504 [2024] 10 S.C.R.
Digital Supreme Court Reports
the conditions upon which a stay of an award may be granted –
Similarly, the form of security required to be furnished should not
depend on whether a party is a statutory or other governmental
body or a private entity – Governmental entities must be treated in
a similar fashion to private parties insofar as proceedings under the
Arbitration Act are concerned, except where otherwise indicated by
law – Parties have entered into commercial transactions with full
awareness of the implications of compliance and non-compliance
with the concerned contracts and the consequences which would
visit them in law – Thus, the submission that the High Court was
correct in directing the respondent to furnish bank guarantees in
relation to the amount awarded because it is a statutory body,
rejected – Under Ord. XLI r.5 CPC, the Court has the power
to direct full or part deposit and/or the furnishing of security in
respect of the decretal amount–Thus, order of the High Court to
be modified – Respondent to deposit an amount quantified at
75% of the decretal amount, inclusive of interest, on or before the
stipulated date before the High Court – Conditional on the deposit
of the said amount, there shall be a stay on the enforcement of
the arbitral award. [Paras 12, 15, 17]
Case Law Cited
Pam Developments Private Limited v. State of West Bengal [2019]
9 SCR 252 : (2019) 8 SCC 112; Toyo Engineering Corpn. v. Indian
Oil Corpn. Ltd., 2021 SCC OnLine SC 3455 – referred to.
List of Acts
Arbitration and Conciliation Act 1996; Arbitration and Conciliation
(Amendment) Act, 2015; Builidng and other Construction Worker’s
Welfare Cess Act 1996; Code of Civil Procedure, 1908.
List of Keywords
Stay on execution of award; Bank guarantee; Arbitral award;
Stay on enforcement; Arbitration agreement; Correction of the
award; Arbitration proceedings; Statutory undertaking; Grant of
stay; Statutory authority; Arbitration Act, a self-contained code;
Fly-by-night operator; Governmental body; Private entity;
Governmental entities; Commercial transactions; Statutory body;
Full or partial deposit; Furnishing of security in respect of decretal
amount.
[2024] 10 S.C.R. 1505
International Seaport Dredging Pvt Ltd v. Kamarajar Port Limited
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 12097 of 2024
From the Judgment and Order dated 09.09.2024 of the High Court
of Judicature at Madras in AN No. 4236 of 2024
Appearances for Parties
Shyam Divan, Sr. Adv., Ms. Shally Bhasin, Chaitanya Safaya,
Prateek Yadav, Adith Deshmukh, S. S. Shroff, Advs. for the Appellant.
C A Sundaram, Sr. Adv., Ms. Rohini Musa, Adv. for the Respondent.
Judgment / Order of the Supreme Court
Judgment
Dr Dhananjaya Y Chandrachud, CJI.
1. Leave granted.
2. The appeal arises from an interim order dated 9 September 2024 of
a Single Judge of the High Court of Judicature at Madras in A No
4236 of 2024 in Arb OP (Com Div) No 335 of 2024.
3. The respondent issued a Letter of Award for executing Capital
Dredging Phase-III at Kamarajar Port to the appellant for an
approximate sum of Rs 274 crores. On 12 August 2015, the parties
entered into a contract for the following work to be conducted by
the appellant:
a. Capital dredging of Container Berth and Multi Cargo Berths
and their approaches;
b. Capital dredging of Coal Berth 3 & Coal Berth 4 and their
approaches;
c. Removal of onshore boulders and transportation to the
designated area;
d. Removal of offshore boulders and transportation to the
designated area;
e. Removal of offshore identified debris/wrecks; and
f. Environmental monitoring.
4. These tasks were to be completed on or before 11 April 2017.
Thereafter, disputes arose between the parties. The appellant invoked
1506 [2024] 10 S.C.R.
Digital Supreme Court Reports
the arbitration agreement. The arbitral proceedings commenced and
the three-member arbitral tribunal made an award on 7 March 2024
directing the respondent to:
a. Pay the appellant a sum of Rs 21,07,66,621 towards the claims
that were allowed in its favour;
b. Pay the appellant interest on the amount awarded at the rate
of nine per cent per annum from 15 November 2017 until the
date of the award if the payment was made within three months,
and, if not, at the rate of twelve per cent per annum from the
date of the award till the date of payment; and
c. Pay the appellant Rs 3,20,86,405 by way of costs.
5. Both parties filed applications under Section 33 of the Arbitration and
Conciliation Act 19961for correction of the award and for additional
arbitral awards. The arbitral tribunal dismissed the application filed by
the respondent. It allowed the application filed by the appellant only
to the extent of increasing the costs awarded to it by Rs 12,00,000 to
reflect the fees paid to the arbitral tribunal subsequent to the parties
filing their memo of costs.
6. The respondent challenged the arbitral award under Section 34 of the
Arbitration Act and moved an application for stay of execution. The
High Court, by its impugned judgment and order dated 9 September
2024, granted a stay on the execution of the award conditional
on the respondent furnishing a bank guarantee in the sum of
Rs 21,07,66,621 within a period of eight weeks.
7. The judgment of the High Court has been assailed by the original
claimant of the arbitral proceeding (i.e., the appellant in this case)
whose contention is that since the award operates as a money
decree under Section 36 of the Arbitration Act, the High Court was
not justified in directing merely the furnishing of a bank guarantee
in relation to the principal amount. The appellant contends that
the respondent ought to have instead been directed to deposit the
amount awarded to it as a condition for the grant of a stay on the
execution of the award.
1 “Arbitration Act”
[2024] 10 S.C.R. 1507
International Seaport Dredging Pvt Ltd v. Kamarajar Port Limited
8. Mr Shyam Divan, senior counsel appearing on behalf of the appellant,
has urged that: (i)A body of precedent has emerged from this Court
in terms of which the sanctity of arbitration must be preserved by
requiring the deposit of the amount awarded as a condition for the
stay on the enforcement of the award; (ii) The amended provisions
of the Arbitration Act require that while considering an application
for stay of an award for the payment of money, due regard has to
be had to the provisions of the Code of Civil Procedure 19082; and
(iii)The award of Rs 21,07,66,621 covered ten claims of which three
were awarded in full and seven in part. The High Courtwhile ordering
a stay, has essentially furnished only two reasons. The first reason
pertains to the question of cess, while the only other reason is that
the respondent is not “a fly by operator”.
9. Mr C A Sundaram, senior counsel appearing on behalf of the
respondent, submits that: (i)The amended provisions of the statute
incorporate provisions of the CPC in regard to ordering a stay of an
award which contains provisions for the payment of money; (ii)Under
Order XLI Rule 5 of the CPC, the requirement is for furnishing of
security and the deposit of money should not, therefore, be regarded
as a default option; (iii)The High Court had due regard to the fact that
the respondent is a statutory body and correctly held that security
should be furnished in the form of a bank guarantee; (iv) As such the
impugned judgment should not be interfered with under Article 136
of the Constitution; and (v) The body of precedents which Mr Divan
relied on pertains to appeals under Section 37 of the Arbitration Act.
10. Section 36(2) of the Arbitration Act indicates that where an application
to set aside an arbitral award has been filed under Section 34, the
filing of such an application shall not, by itself, render that award
unenforceable, unless the Court grants a stay on the enforcement of
the arbitral award in terms of sub-section (3). The provision indicates
that a separate application must be made for this purpose. Sub-
section (3) of Section 36 stipulates that where such an application
has been filed, the Court may, subject to such conditions as it may
deem fit, grant stay of the operation of the award for reasons to be
recorded in writing. Following the amendments brought about by the
Arbitration and Conciliation (Amendment) Act 2015, the first proviso
2 “CPC”
1508 [2024] 10 S.C.R.
Digital Supreme Court Reports
to sub-section (3) stipulates that the Court shall, while considering
an application for grant of stay in the case of an arbitral award for
payment of money, have due regard to the provisions related to the
grant of stay of a money decree under the CPC. The second proviso
provides for a situation in which the Court may grant unconditional
stay. Section 36(3) and its provisos are reproduced below:
“36. Enforcement –
…
(3) Upon filing of an application under sub-section (2) for
stay of the operation of the arbitral award, the Court may,
subject to such conditions as it may deem fit, grant stay
of the operation of such award for reasons to be recorded
in writing:
Provided that the Court shall, while considering the
application for grant of stay in the case of an arbitral
award for payment of money, have due regard to the
provisions for grant of stay of a money decree under
the provisions of the Code of Civil Procedure, 1908
(5 of 1908).
Provided further that where the Court is satisfied that a
Prima facie case is made out that, –
(a) the arbitration agreement or contract which is the
basis of the award; or
(b) the making of the award,
was induced or effected by fraud or corruption, it shall
stay the award unconditionally pending disposal of the
challenge under section 34 to the award.
Explanation.—For the removal of doubts, it is hereby
clarified that the above proviso shall apply to all court
cases arising out of or in relation to arbitral proceedings,
irrespective of whether the arbitral or court proceedings
were commenced prior to or after the commencement of
the Arbitration and Conciliation (Amendment) Act, 2015
(3 of 2016).”
(emphasis supplied)
[2024] 10 S.C.R. 1509
International Seaport Dredging Pvt Ltd v. Kamarajar Port Limited
11. In the present case, there is an arbitral award to the tune of
approximately Rs 21 crores in favour of the appellant. The High
Court, while issuing a direction for furnishing of a bank guarantee,
dealt with only one of the claims which was awarded by the arbitral
tribunal, namely, that which pertained to the refund of the cess
under the Building and Other Construction Workers’ Welfare Cess
Act 1996.3 In this regard, the High Court observed that the Deputy
Chief Labour Commissioner, by its order dated 6 November 2019,
held that the Cess Act was not applicable to the appellant which
was therefore not required to pay cess under that statute. It noted
that the arbitral tribunal had, however, rendered an award in which
it directed the respondent to pay the appellant this amount, which
had already been paid by the respondent to the appellant. It held
thatwhile the substance of the claims of the parties could only be
determined in the proceedings under Section 34 of the Arbitration Act,
it was prima facie satisfied that the arbitral tribunal had erred in not
considering the claim of the respondent. Apart from discussing this
claim, which was in the amount of approximately Rs 3 crores, the
High Court did not address the other claims of the appellant which
were allowed by the arbitral tribunal. The amount awarded in relation
to the remaining claims is approximately Rs 18 crore.
12. The High Court granted a stay on the operation of the award subject
to the respondent furnishing a bank guarantee for the principal
amount awarded to the appellant, i.e. Rs 21,07,66,621. It held that
it was not inclined to issue orders in relation to the interest and
the costs awarded to the appellant because “the petitioner is not a
fly-by operator and is a statutory undertaking.” The law qua arbitration
proceedings, in our view, cannot be any different merely because of
the status of the respondent as a statutory undertaking.
13. In this regard, it is necessary to advert to a decision of a two-Judge
Bench of this Court in Pam Developments Private Limited v State
of West Bengal4 where it was observed:
“20. In our view, in the present context, the phrase used
is “having regard to” the provisions of CPC and not “in
accordance with” the provisions of CPC. In the latter
3 “Cess Act”
4 [2019] 9 SCR 252 : (2019) 8 SCC 112
1510 [2024] 10 S.C.R.
Digital Supreme Court Reports
case, it would have been mandatory, but in the form as
mentioned in Rule 36(3) of the Arbitration Act, it would
only be directory or as a guiding factor. Mere reference to
CPC in the said Section 36 cannot be construed in such a
manner that it takes away the power conferred in the main
statute (i.e. the Arbitration Act) itself. It is to be taken as a
general guideline, which will not make the main provision
of the Arbitration Act inapplicable. The provisions of CPC
are to be followed as a guidance, whereas the provisions of
the Arbitration Act are essentially to be first applied. Since,
the Arbitration Act is a self-contained Act, the provisions of
CPC will apply only insofar as the same are not inconsistent
with the spirit and provisions of the Arbitration Act.”
14. The Court also observed:
“26. Arbitration proceedings are essentially alternate
dispute redressal system meant for early/quick resolution of
disputes and in case a money decree — award as passed
by the arbitrator against the Government is allowed to be
automatically stayed, the very purpose of quick resolution
of dispute through arbitration would be defeated as the
decree-holder would be fully deprived of the fruits of the
award on mere filing of objection under Section 34 of the
Arbitration Act. The Arbitration Act is a special Act which
provides for quick resolution of disputes between the
parties and Section 18 of the Act makes it clear that
the parties shall be treated with equality. Once the Act
mandates so, there cannot be any special treatment
given to the Government as a party. As such, under
the scheme of the Arbitration Act, no distinction is
made nor any differential treatment is to be given to
the Government, while considering an application for
grant of stay of a money decree in proceedings under
Section 34 of the Arbitration Act. As we have already
mentioned above, the reference to CPC in Section 36 of
the Arbitration Act is only to guide the court as to what
conditions can be imposed, and the same have to be
consistent with the provisions of the Arbitration Act.
…
[2024] 10 S.C.R. 1511
International Seaport Dredging Pvt Ltd v. Kamarajar Port Limited
28. Section 36 of the Arbitration Act also does not provide
for any special treatment to the Government while dealing
with grant of stay in an application under proceedings of
Section 34 of the Arbitration Act. Keeping the aforesaid in
consideration and also the provisions of Section 18 providing
for equal treatment of parties, it would, in our view, make it
clear that there is no exceptional treatment to be given
to the Government while considering the application
for stay under Section 36 filed by the Government in
proceedings under Section 34 of the Arbitration Act.”
(emphasis supplied)
15. Bearing in mind the above principles, we are of the view that the
High Court was in error in not even prima facie considering the
fact that apart from the issue of cess, there was an arbitral award
in favour of the appellant in regard to other claims as well. Further,
the High Court ought not to have based its decision on the condition
for the grant of stay on the status of the respondent as a statutory
authority. The Arbitration Act is a self-contained code – it does not
distinguish between governmental and private entities. Hence, the
decision of the Court cannot be influenced by the position of the
party before it and whether it is a fly-by-night operator. Moreover,
an assessment as to whether a party is reliable or trustworthy is
subjective. Many private entities, too, may rely on the size of their
undertaking, its success, public image, or other factors to argue that
they are not fly-by-night operators. In the absence of any provision
of law in this regard, it would be inappropriate for courts to apply
this standard while adjudicating the conditions upon which a stay of
an award may be granted. Similarly, the form of security required to
be furnished should not depend on whether a party is a statutory or
other governmental body or a private entity. Governmental entities
must be treated in a similar fashion to private parties insofar as
proceedings under the Arbitration Act are concerned, except where
otherwise indicated by law. This is because the parties have entered
into commercial transactions with full awareness of the implications
of compliance and non-compliance with the concerned contracts and
the consequences which will visit them in law. Hence, the argument
that the High Court was correct in directing the respondent to furnish
bank guarantees in relation to the amount awarded because it is a
statutory body is rejected.
1512 [2024] 10 S.C.R.
Digital Supreme Court Reports
16. In Toyo Engineering Corpn. v. Indian Oil Corpn. Ltd.,5 this Court
reiterated the same principle in the following terms:
“3. This Court repeatedly having held that Order XLI Rule
5 principles are to be followed in these cases, we find that
largely because public corporations are involved, discretion
continues to be exercised not on principles under Order
XLI Rule 5 but only because large amounts exist and that
Government Corporations have to pay these amounts
under Arbitral Awards. Both these considerations are
irrelevant, as has been pointed out by us earlier.”
17. Under Order XLI Rule 5 of the CPC, the Court has the power to
direct full or part deposit and/or the furnishing of security in respect
of the decretal amount. Bearing in mind the principles which must
guide the Court, we are of the view that the order of the High Court
requires modification. In modification of the direction of the High Court
in the impugned judgment dated 9 September 2024, we direct that:
(i) The respondent shall deposit an amount quantified at 75%
of the decretal amount, inclusive of interest, on or before 30
November 2024 before the High Court; and
(ii) Conditional on the deposit of the aforesaid amount within the
period stipulated above, there shall be a stay on the enforcement
of the arbitral award.
18. The impugned judgment of the High Court shall stand modified in
the above terms. The appeal is allowed accordingly.
19. Pending applications, if any, stand disposed of.
Result of the case: Appeal Allowed.
†
Headnotes prepared by: Nidhi Jain
5 2021 SCC OnLine SC 3455
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.