INDORE VIKAS PRAADHIKARAN (IDA) & ANR.versusSHRI HUMUD JAIN SAMAJ TRUST & ANR.
- Citation
- 2024 INSC 904
- Decided
- 24 November 2024
- Disposal
- Appeal(s) allowed
- Bench
- BELA M TRIVEDI
Holding
A highest bidder does not acquire any vested right or contractual entitlement until the bid is accepted and an allotment letter is issued, and the authority may validly cancel or reject the bid under the terms of the NIT.
Summary
The Indore Vikas Praadhikaran (IDA) issued a notice inviting bids (NIT) to lease a 3,382‑sq‑m plot, fixing a reserve price of Rs 21,120 per sq m. Shri Humud Jain Samaj Trust submitted the highest bid of Rs 25,671.90 per sq m, but the Tender Committee discovered an outstanding property‑tax demand and cancelled the tender, opting to re‑issue a fresh NIT with a higher reserve price of Rs 26,000 per sq m. The Trust, which did not participate in the second NIT, filed a writ petition seeking allotment of the land; the Single Judge dismissed it, holding that the highest bid did not create a vested right. The High Court Division Bench reversed that decision, directing IDA to allot the land if the Trust paid Rs 26,000 per sq m, effectively fixing the price and overruling the authority’s discretion. The Supreme Court held that the highest bidder acquires no vested right absent an allotment letter and that the authority is free to reject or cancel bids under the NIT terms, emphasizing the limited scope of judicial review. Consequently, the Court set aside the High Court order and allowed the appeal, directing IDA to issue a fresh NIT.
Issues considered
- The extent of judicial review over the cancellation of a tender and the authority's power to reject the highest bid.
- Whether a highest bidder acquires any vested right or contractual entitlement before acceptance and issuance of an allotment letter.
- Whether the High Court erred by directing the auctioning authority to fix the price and allot the land.
Legislation cited
Headnote
Issue for Consideration Appellant issued an advertisement inviting bids for leasing out land. Respondent’s bid was found to be the highest. The Tender Committee while finalizing the bids noticed that a property tax demand was outstanding in respect of the land not taken into account while fixing the base price and decided not to accept any of the bids. Respondent No.1 preferred a writ petition, inter alia, challenging resolution rejecting the bid and the issuance of fresh NIT. Single Judge concluded that the Respondent is not entitled to any relief.
Subjects
Judgment
[2024] 11 S.C.R. 925 : 2024 INSC 904
Indore Vikas Praadhikaran (IDA) & Anr.
v.
Shri Humud Jain Samaj Trust & Anr.
(Civil Appeal No. 13089 of 2024)
25 November 2024
[Bela M. Trivedi and Satish Chandra Sharma,* JJ.]
Issue for Consideration
Appellant issued an advertisement inviting bids for leasing out
land. Respondent’s bid was found to be the highest. The Tender
Committee while finalizing the bids noticed that a property tax
demand was outstanding in respect of the land in question,
which was not taken into account while fixing the base price and
decided not to accept any of the bids. Respondent No.1 preferred
a writ petition, inter alia, challenging resolution rejecting the bid
and the issuance of fresh NIT. Single Judge concluded that the
Respondent is not entitled to any relief. In writ appeal, Division
Bench set aside the order of the Single Judge and held that in
case the respondent is willing to pay the amount at the rate of Rs.
26,000/- per square meter, the land in question should be allotted
to the respondent No.1. Whether Division Bench of High Court
was justified in allowing the writ appeal and directing allotment of
land to the Respondent No.1.
Headnotes†
Tender Process – Extent of Judicial Review:
Held: Merely by offering highest bid, the respondent No.1 did not
acquire any vested right for the execution of the contract in its
favour – This Court in the case of CWE-SOMA Consortium has
held that while exercising power of judicial review, the Court does
not sit as an appellate Court over the decision of the government –
The Division Bench should not have interfered in the matter and
could not have gone to the extent of fixing the base price/modifying
the offer made by respondent especially when the respondent
No.1 did not even participate in the fresh NIT – High Court has
virtually passed an order sitting in appeal over the decision of
the government in absence of any mala fide exercise of power
*Author
926 [2024] 11 S.C.R.
Digital Supreme Court Reports
by the Petitioner, the judgment passed by the Division Bench of
the High Court deserves to be set aside and is, accordingly set
aside. [Paras 12, 13, 15]
Right of Bidder in Tender Process:
Held: In the absence of allotment letter and acceptance of highest
bid, no relief could have been granted in favour of respondent No.1
as there was no concluded contract and the decision taken by the
Tender Evaluation Committee to generate more revenues could
not have been interfered with by the High Court – The bidder has
no right in the matter of bid except of fair treatment and cannot
insist for further negotiation. [Paras 13, 14]
Cancellation of auction – Powers of Auctioning Authority:
Held: While we agree with the principle that the auctioning authority
must adhere to the rule of law, the facts of the present case are
entirely distinguishable from Eva Agro – The Appellants were well
within their rights to cancel the auction – Appellant is directed to
issue a fresh NIT for disposal of the land in question enabling
it to generate more revenues in respect of the land in question.
[Paras 15, 16]
Case Law Cited
State of Jharkhand and others v. CWE-SOMA Consortium [2016]
4 SCR 157 : (2016) 4 SCC 172; Haryana Urban Development
Authority and others v. Orchid Infrastructure Developers Private
Limited [2017] 1 SCR 847 : (2017) 4 SC 243; Tata Cellular v. Union
of India [1994] Supp. 2 SCR 122 : (1994) 6 SCC 651 – relied on.
Eva Agro Feeds Private Limited v. Punjab National Bank and Anr.
[2023] 13 SCR 861 : 2023 INSC 809 – distinguished.
List of Acts
Constitution of India.
List of Keywords
Tender; Auction; Advertisement inviting bids; Highest bid;
Cancellation of auction; Fresh tender; Vested right; Judicial review;
Allotment letter; Concluded contract; Terms and conditions of NIT;
Auctioning authority; Right to cancel the auction.
[2024] 11 S.C.R. 927
Indore Vikas Praadhikaran (IDA) & Anr. v.
Shri Humud Jain Samaj Trust & Anr.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 13089 of 2024
From the Judgment and Order dated 08.02.2022 of the High Court
of Madhya Pradesh at Indore in WA No.5 of 2022
Appearances for Parties
Balbir Singh, Sr. Adv., Ms. Vanshaja Shukla, Adv. for the Appellants.
Rakesh Dahiya, Pashupathi Nath Razdan, Advs. for the
Respondents.
Judgment / Order of the Supreme Court
Judgment
Satish Chandra Sharma, J.
1. Leave granted.
2. This present petition is arising out of order dated 08.02.2022 passed
in Writ Appeal No. 5/2022, titled as, “Shri Humad Jain Samaj Trust
Vs. The State of Madhya Pradesh & Ors.”, passed by the High Court
of Madhya Pradesh at Indore. The Division Bench of the High Court
has set aside the order dated 17.12.2021, passed by the learned
Single Judge in Writ Petition No. 26040/2021.
3. The facts of the case reveal that the appellant Indore Vikas
Praadhikaran (IDA), hereinafter referred to as “IDA” issued an
advertisement inviting bids for leasing out land admeasuring 3382
sq. meters situated at Scheme No. 74-C, Sector C, Indore, on
17.07.2020 and the terms and conditions were specified in the Notice
Inviting Tender (NIT). The reserve price was fixed at Rs. 21,120/-
per square meter. The IDA pursuant to the NIT dated 17.07.2020
received three bids and the bid of respondent No. 1-Shri Humud
Jain Samaj Trust was the highest as a bid of Rs. 25,671.90/- per
square meter was offered in the matter. The bids were opened on
09.09.2020. The Tender Committee while it was finalizing the bids
noticed that in respect of the land in question, a property tax demand
to the tune of Rs. 1.25 crores was outstanding and the same was
not taken into account while fixing the base price and, therefore,
the Tender Committee arrived at a conclusion not to accept any
928 [2024] 11 S.C.R.
Digital Supreme Court Reports
of the bids and to issue a fresh tender with a reserve price of Rs.
26,000/- per square meter. The matter was placed before the Board
of IDA and on 27.07.2021, the Board accepted the recommendation
of the Tender Committee. The bid of respondent No. 1 was rejected
and it was resolved to issue a fresh NIT in the matter. Respondent
No. 1 was informed on 23.08.2021 about the rejection of bid of
respondent No.1 and on 01.10.2021, the earnest money was also
refunded. On 18.10.2021, the IDA passed a resolution for issuance
of a fresh NIT with a reserve price of Rs. 26,000/- per square meter
and thereafter, a fresh NIT was issued on 17.11.2021. Respondent
No. 1 after issuance of the fresh NIT preferred a writ petition on
24.11.2021 before the High Court of Madhya Pradesh, inter alia,
challenging resolution dated 27.07.2021 rejecting the bid as well
as being aggrieved by the issuance of fresh NIT dated 17.11.2021.
4. It is pertinent to note that respondent No.1 did not participate in the
subsequent NIT issued on 17.11.2021. Respondent No. 1 before the
High Court stated that by no stretch of imagination, his bid could
have been cancelled as he was the highest bidder. It was further
stated by respondent No.1 before the learned Single Judge that he
is ready to negotiate in the matter and the bid has been cancelled
without assigning any reason.
5. The IDA did file a detailed and exhaustive reply before the learned
Single Judge and reliance was placed upon the terms and conditions
of the NIT. Heavy reliance was placed upon Condition No. 6 which
empowered the IDA to accept or reject any or all bids. Learned Single
Judge after hearing the parties at length arrived at the conclusion
that the petitioner Trust is not entitled to any relief as no contract was
executed at any point of time nor any letter of allotment was issued
in its favour. Learned Single Judge also held that the highest bidder
does not acquire any vested right to have the auction concluded in
his favour and the IDA was justified in issuing fresh NIT in the matter.
6. Respondent aggrieved by the orders passed by the learned Single
Judge preferred a writ appeal and the Division Bench of the High
Court of Madhya Pradesh at Indore Bench allowed the writ appeal
directing the IDA to allot the plot to respondent in case he is ready
to pay the price of the land in question at Rs. 26,000/- per square
meter. Para 6, 7 and 8 of the order passed by the Division Bench
of the High Court reads as under:
[2024] 11 S.C.R. 929
Indore Vikas Praadhikaran (IDA) & Anr. v.
Shri Humud Jain Samaj Trust & Anr.
“6. The dates and events of the case are not in dispute. In
the first NIT, the base price of the land was Rs.21,000/- per
sq. meter as fixed by the Indore Development Authority.
Out of three bidders, the petitioner offered the highest bid.
Rs.25671.90/-. The property tax on land to the Municipal
Corporation is payable by IDA. The resolution has been
passed with the hope that the IDA might fetch higher
prices than the price received in the first round of NIT.
Unfortunately in the second round not, a single bidder had
participated and the tender proceedings have resulted in
an unsuccessful attempt. In all bona fide, the petitioner
has submitted that the petitioner is still ready to match the
base price fixed by the Indore Development Authority in
the second tender by paying the amount of Rs.26,000/-
per sq. meter.
7. Had the Indore Development Authority received an
offer in the second NIT more than Rs.26,000/- per sq.
meter certainly the petitioner would not have any case
before this court. But in the second round of NIT, the
Indore Development Authority has failed to receive any bid
hence the right of the petitioner is still survived to claim
the allotment being a successful bidder. The petitioner
had approached this court by way of the writ petition
before issuance of the second NIT and immediately after
dismissal of the writ petition the writ appeal has been filed
therefore, the cause for the petitioner is still survived. The
Indore Development Authority has wasted public money
by cancelling the first NIT and going for the second NIT.
Learned counsel or the Indore Development Authority
submitted that has the petitioner /appellant participated in
the subsequent tented process the allotment would have
been done on quoting the price of Rs 26000/- it means
the Indore Development Authority has no issue in giving
the land to the petitioner/appellant but same will not be
given through the court as it is beyond judicial review. For
this approach of the Indore Development Authority, a cost
is liable to be imposed.
8. Accordingly, the writ appeal is allowed, and the order
passed by the writ court is set aside. If the petitioner
930 [2024] 11 S.C.R.
Digital Supreme Court Reports
is ready to pay the price of the in question land @
Rs.26,000/- per sq. meter the land in question be allotted
to the appellant.”
7. Hon’ble Division Bench while allowing the writ appeal has held
that the respondent was the highest bidder as in the first round of
the tendering process, the base price of the land was fixed at Rs.
21,120/- per square meter and the respondent No. 1 offered a bid of
Rs. 25,671.90/- per square meter. In the second round while issuing
fresh NIT, the IDA has fixed the base price at Rs. 26,000/- per square
meter and no offer was received by the IDA in the second round of
more than Rs. 26,000/- per square meter and, therefore, the Division
Bench held that in case the respondent is willing to pay the amount
at the rate of Rs. 26,000/- per square meter, the land in question
should be allotted to the respondent No.1.
8. The IDA being aggrieved by the order passed by the Division Bench
of the High Court of Madhya Pradesh at Indore, dated 08.02.2022,
has preferred the present appeal and it has been vehemently argued
by Mr. Balbir Singh, learned Senior Counsel for the appellant that
the order passed by the Division Bench of the High Court deserves
to be set aside as the High Court has in fact decided a suit for
specific performance of contract while deciding the Writ Appeal. He
has vehemently argued before this Court that in the light of Condition
No. 6 of the NIT, dated 17.07.2020, the IDA was having a right to
accept or reject any or all the bids. It was also brought to the notice
of this Court that the bid of respondent No.1 was cancelled only after
it came to the notice of the Tender Committee in its meeting dated
25.09.2020, that there is an outstanding property tax in respect of the
land in question amounting to Rs. 1,25,82,262/- and considering the
location of the plot and after payment of property tax to the Municipal
Corporation and further keeping in view the fact that more revenue is
likely to be generated in future by disposing of the property through
the tendering process, the bid of the respondent No. 1 was rejected.
9. Learned Senior Counsel has placed heavy reliance upon the
judgments delivered in the case of State of Jharkhand and others
Vs. CWE-SOMA Consortium (2016) 4 Supreme Court Cases 172
and Haryana Urban Development Authority and others Vs. Orchid
Infrastructure Developers Private Limited (2017) 4 Supreme
Court Cases 243.
[2024] 11 S.C.R. 931
Indore Vikas Praadhikaran (IDA) & Anr. v.
Shri Humud Jain Samaj Trust & Anr.
10. Learned counsel appearing on behalf of respondent No. 1-Trust has
vehemently argued before this Court that respondent No. 1 was
the highest bidder in respect of NIT dated 17.07.2020 and merely
because the respondent No. 1 has not participated the second
NIT issued on 17.11.2021, the question of setting aside the order
passed by the Division Bench does not arise. It has been vehemently
argued by the learned counsel for respondent No. 1-Trust that once
the respondent No. 1 was declared as the highest bidder amongst
the three bids received in respect of the land in question, his bid of
Rs. 25,671.90/- per square meter should have been accepted and
respondent No.1 should have been declared the successful bidder
and, thence, no case for interference is made out in the present
case. Reliance has been placed on Eva Agro Feeds Private Limited
Vs. Punjab National Bank and Anr., 2023 INSC 809 decided on
06.09.2023 in Civil Appeal No. 7906 of 2021.
11. Heard learned Senior Counsel for the appellant as well as learned
counsel for the respondents at length and perused the entire
documents placed on record in the matter.
12. In the present case, the undisputed facts reveal that first NIT was
issued on 17.07.2020 and respondent No. 1 was certainly the highest
bidder by offering a bid of Rs. 25,671.90/- per square meter. The
Tender Evaluation Committee after examining the bid arrived at
a conclusion to cancel the tender as it came to its notice that an
outstanding property tax demand amounting to Rs. 1,25,82,262/- was
not taken into account while fixing the base price. It was resolved
to issue a fresh NIT and, therefore, a fresh NIT was issued on
17.11.2021 and for the reasons best known to the respondent No. 1,
it did not participate in the second NIT and instead preferred a writ
petition on 24.11.2021 before the High Court of Madhya Pradesh.
Learned Single Judge was justified in dismissing the writ petition on
the ground that merely by offering highest bid, the respondent No.1
did not acquire any vested right for the execution of the contract in its
favour. The Division Bench of the High Court, however, allowed the
writ appeal and has gone to the extent in directing the IDA to accept
the offer of respondent No. 1 which was made before the Court for
an amount of Rs. 26,000/- per square meter in respect of the land
in question, and further directing IDA to allot the land in question to
respondent No.1. This Court in the case of State of Jharkhand and
others Vs. CWE-SOMA Consortium (supra) while dealing with the
932 [2024] 11 S.C.R.
Digital Supreme Court Reports
similar issue of annulment of tender process, in paras 21, 22 and
23 has held as under:
“21 Observing that while exercising power of judicial review,
the Court does not sit as appellate court over the decision
of the Government but merely reviews the manner in which
the decision was made, in Tata Cellular v. Union of India
[Tata Cellular v. Union of India (1994) 6 SCC 651], SCC
in para 70 it was held as under: (SCC p. 675)
“70. It cannot be denied that the principles of
judicial review would apply to the exercise of
contractual powers by government bodies in
order to prevent arbitrariness or favouritism.
However, it must be clearly stated that there are
inherent limitations in exercise of that power of
judicial review. Government is the guardian of
the finances of the State. It is expected to protect
the financial interest of the State. The right to
refuse the lowest or any other tender is always
available to the Government. But, the principles
laid down in Article 14 of the Constitution have
to be kept in view while accepting or refusing a
tender. There can be no question of infringement
of Article 14 if the Government tries to get the
best person or the best quotation. The right to
choose cannot be considered to be an arbitrary
power. Of course, if the said power is exercised
for any collateral purpose the exercise of that
power will be struck down.”
22 The Government must have freedom of contract. In
Master Marine Services (P) Ltd. v. Metcalfe & Hodgkinson
(P) Ltd. [Master Marine Services (P) Ltd. v. Metcalfe &
Hodgkinson (P) Ltd. (2005) 6 SCC 138], SCC in para 12
this Court held as under: (SCC p. 147)
“12. After an exhaustive consideration of a
large number of decisions and standard books
on administrative law, the Court enunciated
the principle that the modern trend points
to judicial restraint in administrative action.
[2024] 11 S.C.R. 933
Indore Vikas Praadhikaran (IDA) & Anr. v.
Shri Humud Jain Samaj Trust & Anr.
The court does not sit as a court of appeal
but merely reviews the manner in which the
decision was made. The court does not have
the expertise to correct the administrative
decision. If a review of the administrative
decision is permitted it will be substituting its
own decision, without the necessary expertise,
which itself may be fallible. The Government
must have freedom of contract. In other words,
fair play in the joints is a necessary concomitant
for an administrative body functioning in an
administrative sphere or quasi-administrative
sphere. However, the decision must not only
be tested by the application of Wednesbury
principles of reasonableness but also must be
free from arbitrariness not affected by bias or
actuated by mala fides. It was also pointed out
that quashing decisions may impose heavy
administrative burden on the administration and
lead to increased and unbudgeted expenditure.
(See para 113 of the Report, SCC para 94.)”
The Court does not have the expertise to correct the
administrative decision as held in Laxmikant v. Satyawan
[Laxmikant v. Satyawan (1996) 4 SCC 208], the Government
must have freedom of contract.
23 The right to refuse the lowest or any other tender is
always available to the Government. In the case in hand,
the respondent has neither pleaded nor established mala
fide exercise of power by the appellant. While so, the
decision of the Tender Committee ought not to have been
interfered with by the High Court. In our considered view,
the High Court erred in sitting in appeal over the decision
of the appellant to cancel the tender and float a fresh
tender. Equally, the High Court was not right in going into
the financial implication of a fresh tender.”
13. This Court in the aforesaid case has held that while exercising power
of judicial review, the Court does not sit as an appellate Court over
the decision of the government but merely reviews the manner in
934 [2024] 11 S.C.R.
Digital Supreme Court Reports
which the decision was made [Tata Cellular v. Union of India (1994)
6 SCC 651]. In the considered opinion of this Court, the Division
Bench should not have interfered in the matter and could not have
gone to the extent of fixing the base price/modifying the offer made
by respondent and, therefore, in light of the aforesaid judgment as
the High Court has virtually passed an order sitting in appeal over
the decision of the government in absence of any mala fide exercise
of power by the IDA, the judgment passed by the Division Bench
of the High Court deserves to be set aside and is, accordingly set
aside. This Court in the case of Haryana Urban Development
Authority Vs. Orchid Infrastructure Developers Pvt. Ltd. (supra)
again dealing with the cancellation of a bid of the highest bidder, in
paragraphs 12,13,14,15, 16 and 30 has held as under:
“12. Firstly, we examine the question whether there being
no concluded contract in the absence of acceptance of
bid and issuance of allotment letter, the suit could be
said to be maintainable for the declaratory relief and
mandatory injunction sought by the plaintiff. The plaintiff
has prayed for a declaration that rejection of the bid was
illegal. Merely by that, the plaintiff could not have become
entitled for consequential mandatory injunction for issuance
of formal letter of allotment. The court while exercising
judicial review could not have accepted the bid. The bid
had never been accepted by the authorities concerned. It
was not a case of cancellation of bid after being accepted.
Thus, even assuming as per the plaintiff’s case that the
Administrator was not equipped with the power and the
Chief Administrator had the power to accept or refuse the
bid, there had been no decision by the Chief Administrator.
Thus, merely by declaration that rejection of the bid by
the Administrator was illegal, the plaintiff could not have
become entitled to consequential relief of issuance of
allotment letter. Thus the suit, in the form it was filed,
was not maintainable for relief sought in view of the fact
that there was no concluded contract in the absence of
allotment letter being issued to the plaintiff, which was a
sine qua non for filing the civil suit.
13. It is a settled law that the highest bidder has no vested
right to have the auction concluded in his favour. The
[2024] 11 S.C.R. 935
Indore Vikas Praadhikaran (IDA) & Anr. v.
Shri Humud Jain Samaj Trust & Anr.
Government or its authority could validly retain power to
accept or reject the highest bid in the interest of public
revenue. We are of the considered opinion that there was
no right acquired and no vested right accrued in favour of
the plaintiff merely because his bid amount was highest and
had deposited 10% of the bid amount. As per Regulation
6(2) of the 1978 Regulations, allotment letter has to be
issued on acceptance of the bid by the Chief Administrator
and within 30 days thereof, the successful bidder has to
deposit another 15% of the bid amount. In the instant case,
allotment letter has never been issued to the petitioner as
per Regulation 6(2) in view of non-acceptance of the bid.
Thus, there was no concluded contract. Regulation 6 of
the 1978 Regulations is extracted hereunder:
“6. Sale of lease of land or building by
auction.—(1) In the case of sale or lease by
auction, the price/premium to be charged shall
be such reserve price/premium as may be
determined taking into consideration the various
factors as indicated in sub-regulation (1) of
Regulation 4 or any higher amount determined
as a result of bidding in open auction.
(2) 10 per cent of the highest bid shall be paid
on the spot by the highest bidder in cash or
by means of a demand draft in the manner
specified in sub-regulation (2) of Regulation 5.
The successful bidder shall be issued allotment
letter in Form CC or C-II by registered post and
another 15 per cent of the bid accepted shall be
payable by the successful bidder, in the manner
indicated, within thirty days of the date of allotment
letter conveying acceptance of the bid by the
Chief Administrator; failing which the 10 per cent
amount already deposited shall stand forfeited
to the authority and the successful bidder shall
have no claim to the land or building auctioned.
(3) The payment of balance of the price/
premium, rate of interest chargeable and the
936 [2024] 11 S.C.R.
Digital Supreme Court Reports
recovery of interest shall be in the same manner
as provided in sub-regulations (6) and (7) of
Regulation 5.
(4) The general terms and conditions of the
auction shall be such as may be framed by
the Chief Administrator from time to time and
announced to the public before auction on the
spot.”
14. We are fortified in our view by a decision of this Court
in U.P. Avas Evam Vikas Parishad v. Om Prakash Sharma
[U.P. Avas Evam Vikas Parishad v. Om Prakash Sharma
(2013) 5 SCC 182 : (2013) 2 SCC (Civ) 737], wherein
the questions arose for its consideration that : whether
there is any vested right upon the plaintiff bidder until the
bid is accepted by the competent authority in relation to
the property in question? Merely because the plaintiff is
the highest bidder by depositing 20% of the bid amount
without there being approval of the same by the competent
authority and it amounts to a concluded contract in relation
to the plot in question; and whether the plaintiff could
have maintained the suit in the absence of a concluded
contract? Considering the aforesaid questions, this Court
has discussed the matter thus : (SCC pp. 195-97, paras
30-31)
“30. In support of the said proposition, the
learned Senior Counsel for the defendant, Mr
Rakesh Dwivedi has also placed reliance upon
another decision of this Court in State of U.P.
v. Vijay Bahadur Singh [State of U.P. v. Vijay
Bahadur Singh (1982) 2 SCC 365]. The learned
Senior Counsel has rightly placed reliance upon
the judgment of this Court in Rajasthan Housing
Board case [Rajasthan Housing Board v. G.S.
Investments (2007) 1 SCC 477] which reads as
under : (SCC p. 483, para 9)
‘9. This being the settled legal position, the
respondent acquired no right to claim that the
auction be concluded in its favour and the
[2024] 11 S.C.R. 937
Indore Vikas Praadhikaran (IDA) & Anr. v.
Shri Humud Jain Samaj Trust & Anr.
High Court clearly erred in entertaining the writ
petition and in not only issuing a direction for
consideration of the representation but also
issuing a further direction to the appellant to
issue a demand note of the balance amount.
The direction relating to issuance of the demand
note for balance amount virtually amounted
to confirmation of the auction in favour of the
respondent which was not the function of the
High Court.’
In State of Orissa v. Harinarayan Jaiswal [State
of Orissa v. Harinarayan Jaiswal (1972) 2 SCC
36] case, relevant paragraph of which reads as
under : (SCC pp. 44-45, para 13)
‘13. … There is no concluded contract till the
bid is accepted. Before there was a concluded
contract, it was open to the bidders to withdraw
their bids (see Union of India v. Bhim Sen Walaiti
Ram [Union of India v. Bhim Sen Walaiti Ram
(1969) 3 SCC 146] ). [Ed.: The matter between
two asterisks has been emphasised in Avam
Evam Vikas Parishad case (2013) 5 SCC 182.] By
merely giving bids, the bidders had not acquired
any vested rights [Ed.: The matter between two
asterisks has been emphasised in Avam Evam
Vikas Parishad case (2013) 5 SCC 182.]’.
31. In view of the law laid down by this Court
in the aforesaid decisions, the learned Senior
Counsel Mr Rakesh Dwivedi has rightly placed
reliance upon the same in support of the case
of the first defendant, which would clearly go
to show that the plaintiff had not acquired any
right and no vested right has been accrued in his
favour in respect of the plot in question merely
because his bid amount is highest and he had
deposited 20% of the highest bid amount along
with the earnest money with the Board. In the
absence of acceptance of bid offered by the
938 [2024] 11 S.C.R.
Digital Supreme Court Reports
plaintiff to the competent authority of the first
defendant, there is no concluded contract in
respect of the plot in question, which is evident
from letters dated 26-5-1977 and 8-7-1977
wherein the third defendant had rejected the
bid amount deposited by the plaintiff and the
same was refunded to him by way of demand
draft, which is an undisputed fact and it is also
not his case that the then Assistant Housing
Commissioner who has conducted the public
auction had accepted the bid of the plaintiff.”
15. This Court in Om Prakash Sharma case [U.P. Avas
Evam Vikas Parishad v. Om Prakash Sharma (2013) 5
SCC 182 : (2013) 2 SCC (Civ) 737] has held that in the
absence of a concluded contract which takes place by
issuance of allotment letter, suit could not be said to be
maintainable as there is no vested right in the plaintiff
without approval of the bid by the competent authority.
Thus, in the wake of the aforesaid decision, in the absence
of a concluded contract, the suit could not have been
decreed for mandatory injunction. It amounted to enforcing
of contract in the absence thereof.
16. In the light of the aforesaid discussion, it is evident
that in the absence of a concluded contract i.e. in the
absence of allotment letter and acceptance of highest
bid, the suit filed by the plaintiff was wholly misconceived.
Even if non-acceptance of the bid was by an incompetent
authority, the court had no power to accept the bid and to
direct the allotment letter to be issued. Merely on granting
the declaration which was sought that rejection was illegal
and arbitrary and by incompetent authority, further relief
of mandatory injunction could not have been granted,
on the basis of findings recorded, to issue the allotment
letter, as it would then become necessary to forward the
bid to competent authority—Chief Administrator—for its
acceptance, if at all it was required.
30. In Meerut Development Authority v. Assn. of
Management Studies [Meerut Development Authority v.
Assn. of Management Studies (2009) 6 SCC 171 : (2009)
[2024] 11 S.C.R. 939
Indore Vikas Praadhikaran (IDA) & Anr. v.
Shri Humud Jain Samaj Trust & Anr.
2 SCC (Civ) 803], this Court has laid down that a bidder
has no right in the matter of bid except of fair treatment
in the matter and cannot insist for further negotiation. The
authority has a right to reject the highest bid. This Court
has laid down thus : (SCC p. 182, paras 27 & 29)
“27. The bidders participating in the tender
process have no other right except the right
to equality and fair treatment in the matter
of evaluation of competitive bids offered by
interested persons in response to notice inviting
tenders in a transparent manner and free from
hidden agenda. One cannot challenge the terms
and conditions of the tender except on the above
stated ground, the reason being the terms of
the invitation to tender are in the realm of the
contract. No bidder is entitled as a matter of
right to insist the authority inviting tenders to
enter into further negotiations unless the terms
and conditions of notice so provided for such
negotiations.
29. The Authority has the right not to accept the
highest bid and even to prefer a tender other
than the highest bidder, if there exist good and
sufficient reasons, such as, the highest bid not
representing the market price but there cannot
be any doubt that the Authority’s action in
accepting or refusing the bid must be free from
arbitrariness or favouritism.”
14. Keeping in view of the aforesaid judgments, this Court is of the
considered opinion that in the absence of allotment letter and
acceptance of highest bid, no relief could have been granted in
favour of respondent No.1 as there was no concluded contract in the
matter and the decision taken by the Tender Evaluation Committee
to generate more revenues could not have been interfered with in
the manner and method as has been done by the Division Bench of
the High Court of Madhya Pradesh at Indore Bench. The bidder has
no right in the matter of bid except of fair treatment and cannot insist
for further negotiation as has been done in the present case. The
terms and conditions of NIT, particularly condition No. 6, empowers
940 [2024] 11 S.C.R.
Digital Supreme Court Reports
the IDA to accept or reject any or all bids. In the present case, the
bid was rejected for valid and cogent reasons and, therefore, the
order passed by the Division Bench of the High Court of Madhya
Pradesh is set aside.
15. Learned Counsels for respondent No. 1 placed heavy reliance on
Eva Agro (supra) stating that the Appellant does not have absolute or
unfettered discretion to cancel the auction. While we agree with the
principle that the auctioning authority must adhere to the rule of law,
the facts of the present case are entirely distinguishable from Eva
Agro (supra). In that case, after the Appellant therein was declared
the highest bidder, the auction was cancelled without providing any
reason. This decision was found to be manifestly arbitrary by this
Court and therefore, the appeal was allowed. However, in the present
case, the decision to cancel the auction was not unfounded, it was
undertaken to remedy the erroneous minimum rate provided in the
NIT dated 07.07.2020, as noted in the report of the Div. Commissioner
of the IDA. Therefore, the Appellants were well within their rights to
cancel the auction. More importantly, in the present case, pursuant
to the cancellation of the first NIT, a second NIT was issued wherein
the respondent No. 1 did not participate. Despite this fact, the
Division Bench of the High Court effectively usurped the powers of
the auctioning authority and fixed the price at Rs. 26,000/- per square
meter. Hence, being entirely distinguishable on facts, the reliance
placed is of no assistance to respondent No. 1.
16. Resultantly, the IDA is directed to issue a fresh NIT for disposal of
the land in question enabling the IDA to generate more revenues in
respect of the land in question. The appellant shall certainly be free
to participate in the fresh NIT as and when issued by the IDA. It is
made clear that the IDA shall not dispose of the land in question
except by way of public auction/by issuing NIT in future.
17. With the aforesaid, the appeal stands allowed.
Result of the case: Appeal allowed.
†
Headnotes prepared by: Adeeba Mujahid, Hony. Associate Editor
(Verified by: Abhinav Mukerji, Sr. Adv.)
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.