Created byFuzzy Cloud

Supreme Court of India

HITECH ELECTROTHERMICS AND HYDROPOWER LTD.versusST ATE OE KERALA AND ORS.

Citation
2002 INSC 524
Decided
7 December 2002
Disposal
Appeal(s) allowed

Holding

The appellant is entitled to a concessional tariff for three years on equitable grounds despite missing the original five‑year deadline.

Summary

Hitech Electrothermics & HydroPower Ltd set up a ferro‑alloy plant in Kerala after the State Government issued an industrial policy (1992) offering a five‑year concessional electricity tariff to new units that commenced commercial production between 1 Jan 1992 and 31 Dec 1996. The Kerala State Electricity Board allocated power to the appellant in 1995 but failed to supply it until October 1998, causing the plant to miss the statutory production deadline. The appellant claimed that, because the delay was due to the Board’s inaction, it should still enjoy the concessional tariff. The Kerala High Court rejected the claim, holding that the production deadline was a condition precedent. On appeal, the Supreme Court examined whether a literal reading of the policy could be set aside in view of the Board’s statutory duty under Section 22 of the Indian Electricity Act, 1910. The Court held that it would be inequitable to deny relief and, on equitable grounds, granted the appellant a reduced concession of three years instead of five. Consequently, the High Court judgment was set aside and the appeals were allowed.

Issues considered

  • Whether an industrial unit that fails to commence commercial production within the policy‑prescribed period due to the electricity board's failure to supply power can still claim the concessional tariff.
  • Whether the policy must be interpreted literally or can be modified on equitable considerations.
  • Whether the board’s duty under Section 22 of the Indian Electricity Act, 1910, obliges it to supply power and precludes it from defeating the incentive.
  • Whether the period of concessional tariff can be reduced in view of the board’s default.

Legislation cited

Subjects

industrial policyconcessional tariffelectricity supplyequitable reliefadministrative lawelectricity boardcommercial productionstatutory dutypolicy interpretation

Judgment

A         HITECH ELECTROTHERMICS AND HYDROPOWER LTD.
                                v.
                    STATE OE KERALA AND ORS.

                               DECEMBER I 7, 2002

B           [G.B. PATTANAIK, CJ., AND K.G. BALAKRISHNAN, J.]


         Administrative Law:

          Government Po/icy-Offering of concessional tariff to new industrial
C unit for period of five years from the date of commercial production, if
    production commenced between specified period-Industrial unit claiming
    incehtive of concessional tariff even though it did not have commercial
    production by the date specified-Held, since industrial unit could not start
    commercial production due to non-supply of power, it would not be equitable
D   to deny relief by giving literal interpretation to the incentive claim of the
    Government-Thus, on equitable consideration concessional tariffto be granted
    for period of three years.

          The question which arose in these appeals was whether an industrial'
    unit could claim the benefit of the policy announced by the State
E   Government offering concessional rate of tariff and electricity duty to new
    industries for a period of five years from the date of commercial
    production, ifthe production commenced between 1.1.1992 and 31.12.1996,
    notwithstanding the fact that there· was delay in production due to inaction
    on the part of the State Electricity Board in providing the necessary
F   electric connection.

           Appellant contended that when the appellant was persuaded to set
    up the industry being lured by incentive of getting the concessional power
    tariff for a period of five years, Board cannot be permitted to prevent such
    a benefit by its own failure to provide power, which prevented appellant
G   from starting commercial production by 31.12.1996.

          Respondent contended that since appellant'.s manufacturing unit did
    not start commercial production within the stipulated period, the benefit
    of the concessional tariff under the policy has rightly been denied; that
H   even if for certain latches on the part of the Board, appellant may be

                                         128
           HITECH ELECTROTHERMICS & HYDROPOWER LTD. v. STATE              129
entitled to an equitable consideration, but in the matter of incentive           A
granted under the policy decision by Government, no manufacturing unit
could claim the benefit, so long as the conditions precedent of the
applicability of policy resolution have not been satisfied; and that appellant
himself was not in a position to start commercial production within the
stipulated time.
                                                                                 B
     Allowing the appeal, the Court

       HELD: I.I. On perusal of the industrial policy of the Government,
unequivocally indicating that concessional tariff rate would be given as
well as the order of the Electricity Board adopting the same, it can be
safely held that such concession could be availed of by the industrial units     C
for a period of five years from the date, they start such production between
1.1.1992 and 31.12.1996. In this context the stand of the Board as well as
the State Government cannot be held to be devoid to any substance when
admittedly the commercial production of the appellant's unit did not start
till 31.12.96. But when the State Government came forward with a policy          D
decision alluring industrial units to set up their industries and under the
provisions of the Electricity Act, every consumer has the right to get the
supply of power and in the instant case when power allocation had been
made in favour of appellant as early as in 1995, and yet the same power
could not be supplied, for such non-supply of power, the commercial
production could not start by 31.12.1996, it would not at all be equitable       E
to deny the relief to appellant by giving a literal interpretation to the
incentive scheme of the Government as adopted by the Board. (134-A-DI

      1.2. The Board denied appellant power supply in appropriate time,
which prevented appellant from starting the commercial production by             F
31.12.1996. This being the position, and having regard to the gamut of
the circumstances, starting from the government policy resolution and
culminating in setting up of the factory by appellant and commenced the
production of ferro alloys, though not by 31.12.1996, granting the
concessional tariff for a period of three years instead of five years, as
indicated in the policy resolution would meet the ends of justice and it is      G
so directed: Be it be stated that appellant has been enjoying the
concessional tariff on the basis of interim orders of the court and,
therefore, that should be taken into account and due adjustment would
be made in computing the period of three years for which grant of
concessional tariff is direct~d. 1134-G-Hl
                                                                                 H
    130                        SUPREME COURT REPORTS [2002) SUPP. 5 S.C.R.

A        Pawan Alloys and Casting Pvt. Ltd., Meerut v. U.P. State Electricity
    Board and Ors., (1997) 7 SCC 251, referred to. '

            CIVIL APPELLATE JURISDICTION : Civil Appeal No. 8322 of
    2001.

B        From the Judgment and Order dated 6.4.2001 of the Kerala High Court
    in Writ Appeal No. 820 of 2001.

                                         WITH

            Civil Appeal Nos. 8323 and 8324 of 200 I.
c         H.N. Salve, L.N. Rao and Dr. A.M. Singhvi, A.T. Patra, Nipun Malhotra,
    Ramesh Singh, Ms. Bina Gupta, Ms. Divya Roy and Ms. Vanita Bhargava
    for the Appellant.

         Mukul Rohtagi, Additional Soliciter General, K.R. Sasiprabhu and M.T.
D   George, for the Respondents.

            The Judgment of the Court was delivered by

         PATT ANAIK, CJ. These appeals by grant of special leave are directed
  against the judgment ofKerala High Court dated 6th April, 2001. The appellant
E approached the High Court of Kera la claiming that it would be entitled to the
  concessional tariff under the policy of the Government and approved by the
  Board even though the actual commercial production of the appellant's factory
  started in 1998. The High Court in the impugned judgment accepted the
  stand of the State Government that in order to be eligible to get the concessional
F tariff under the policy in question, commercial production must have started
  by 31st December, 1996 and since admittedly, the appellant did not have the
  commercial production by that date the incentive of concessional tariff would
  not be available. The question for consideration in these appeals, therefore,
  is whether an industrial unit which has set up the industry being lured by
  policy decision of the Government can still claim the benefit of the
G concessional tariff under the policy notwithstanding the fact that there has
  been delay in production, such delay being attributable to. the inaction on the
  part of the Board in providing the necessary electric connection.

        The Government ofKerala in the Industry Department, issued GO(MS)
  dated 2 J.5.90, indicating therein that the power connection will be given on
H completion of any project irrespective of whether a general power cut is in
        HITECH ELECTROTHERMICS & HYDROPOWER LTD. v. STATE [PATTANAIK, CJ.]         iJ j

       force or not. It had also been stated therein that the new units commencing A
       industrial production will be exempted from power cut for a period of 5 years
       from the date of commercial production. In February, 1992, the government
       came out with industrial policy offering concessional rate of tariff and
       electricity duty to new industries for a period of five years from the date of
       commercial production, if the production commences between 1.1.92 and
       31.12.96. The Kerala State Electricity Board adopted the aforesaid policy B
       decision for implementation and in its order dated 27th of March, 1992,
       reiterated that the concessional tariff, as indicated in industrial policy resolution,
       would be available ifthe commercial production is made between 1.1.92 and
       31.12.96. The appellant industry was issued the registration certificate by the
       District Industries Centre, on 27. I2. I 993. In April, I 994, government issued C
       another GO(MS), confinning that the industries registered prior to 3 I .I2.1993,
       will continue to enjoy the tariff concession and exemption from payment of
  \    electricity duty. The State Electricity Board issued a letter on 7.11.1995 to
       the appellant industry, allocating power in their favour. In its letter dated
        13th March, 1996, the said Kerala State Electricity Board confinned that the
       appellant will be entitled to the tariff concession, as per the policy resolution D
.,..   of the government. The appellant is stated to have invested a huge sum of
       money in setting up factory for production of ferro alloys. On 24th of April,
        1996, the Secretary to the Government of Kerala con finned that the appellant
       will be eligible for concessional tariff, if commercial production starts before
       31.12.1996. In June,1996, the appellant had informed the Board that it is E
       going ahead with the implementation of the project of manufacturing ferro
       alloys and requested for issuance of demand note to enable the appellant to
       pay the charges. On 23rd of August, 1986, the State Electricity Board informed
       the appellant about the estimated amount on the electric connection and
       further stated that the demand note will be intimated to the appellant at the
       earliest. On 3rd of August, 1986, news item was published in Delhi's Times F
       of India, showing the Kerala Government Policy in welcoming the investment
       in Kerala. Between August and October, 1996, the appellant intimated several
       authorities of the government as well as the Board, requesting them to provide
       power for manufacture of ferro alloys in appellant's factory, which was
       otherwise ready for commissioning. But it is only in August, 1997, the Board G
       issued the order, intimating the supply of power to the appellant's factory to
       the extent of I 5 MV A at 110 KV. The Board then took about one year in
       connecting the sub-station in the appellant's factory for supply of power.
       Ultimately, the Board granted power to the appellant's company on 22nd
       October, 1998. In the first week of November, 1998 the appellant got the Bill
       from the Board at the regular rate without the benefit of the concessional H
    132                       SUPREME COURT REPORTS [2002) SUPP. 5 S.C.R.

A tariff as indicated in the Industrial Policy of the Government and also adopted
    by the Board. The appellant, therefore, approached the High Court and the
    High Court by an interim order directed that the appellant would be demanded
    the tariff on the basis of the prevalent rate prior to 1.1.1992. But the power
    connection had been cut off on account of non-payment of the electricity
    charges. The High Court then passed an order that on payment of Rs.50 lacs
B   by the appellant, the electric connection would be given by its order dated
    15.12.1999. The Board filed an application for modification of the aforesaid
    order and finally on 6.4.2000, the High Court of Kerala modified earlier
    order, denying the benefit of concessional tariff. The appeal was carried
    against the order to the division Bench, wherein the division Bench directed
C   t~e Single Judge to dispose of the pending Writ Petition of the appellant and
    till the disposal of the Writ Petition, stayed the order and directed that the
    appellant would pay the electricity charges at pre 1.1.1992 rate by its order
    dated 23.5.2000. The Writ Petition of the appellant was dismissed by the
    learned Single Judge by order dated 21.12.2000 against which the appellant
    carried the appeal to the Division Bench and the Division Bench by the
D   impugned order dated 6.4.2001 having dismissed the appeal, the present
    appeal by grant of special leave has been filed.

            Mr. ·Salve, the learned senior counsel appearing for the appellants
    contended that the Government of Kerala unequivocally in its policy dated
E   6th February, 1992 had indicated that new industrial units will be exempted
    for five years from the payment of enhanced power tariff which came into
    effect on 1.1.92 and this should be available to the units from the date of
    commercial production which start production between 1.1.92 and 31.12.1996.
    This policy was adopted by the Kerala State Electricity Board which issued
    the letter dated 27th of March, 1992, stating therein that the concessional
F   power tariff and electricity duty to industries would be supplied as a measure
    of incentive to all the units who start their commercial production between
    1.1.92 to 31.12.1996, irrespective of the day of permanent electric connection.
    On 7.11.1995, the Kerala State Electricity Board intimated to the appellant
    that in principle sanction of power had been accorded to the extent of 15
G   MVA at 110 KV to the appellant's factory premises at Pudussery Village and
    the power can be availed and will be operational with peak load restrictions
    only after commissioning of 220 KV substation at Kanjikode. But
    notwithstanding the same, the Board having not taken any steps to see that
    the power supply is given to the appellant's premises and it is for such non-
    supply of power, the commercial production being delayed, it will be un-
H   equitable to deny the concessional tariff flowing from the policy resolution
  HITECH ELECTROTHERMICS & HYDRO POWER LTD.'" STATE (PA TT ANAIK, Cl]    J33
 of the government. Mr. Salve contended that under Section 22 of the Indian A
 Electricity Act, 1910, the Board is responsible to supply power on the terms
 and conditions of the licence and the said Board having allocated the power
 in favour of the appellant on 7.11.95 and thereafter their being rio power
 connection until 1998, it cannot deny the benefit flowing from the policy
 resolution of the government which was adopted by the Board in its letter B
 dated 27th of March, 1992. According to Mr. Salve, the Board cannot be
 permitted to prevent the benefit of an incentive policy by its own failure to
 provide power, which prevented the appellant from starting commercial
 production by 31.12.1996. Mr. Salve relying upon the judgment of this court
 in Pawan Alloys and Casting Pvt. Ltd., Meerut v. U.P. State Electricity
 Board and Ors., [1997] 7 SCC 251, contended that when the appellant was C
 persuaded to set up the industry being lured by incentive of getting the
 concessional power tariff for a period of five years, ought not to be denied
 that relief on construing the power policy and literally no such concessional ·
 tariff could be granted unless commercial production starts before 31.12.96.
                                                                               D
           Mr. Rohtagi, the learned Additional Solicitor General, appearing for
  the State of Kerala as well as on behalf of the Board, vehemently argued that
  the language of the policy issued by the Government and adopted by the
  State Electricity Board was unequivocal and such .Policy clearly stipulated
  that only those units which would start commercial production between 1.1.92
  and 31.12.96 would be entitied to the concessional tariff indicated in the E
  policy. Since admittedly the appellant's manufacturing unit did not start
  commercial production within the stipulated period, the benefit of the
  concessional tariff under the policy has rightly been denied and the impugned
  judgment does not suffer from any infinnity. According to Mr. Rohtagi, even
  if for certain latches on the part of the Board, the appellant may be entitled F
  to an equitable consideration, but in the matter of incentive granted under the
  policy decision by the government, no manufacturing unit can claim the
  benefit, so long as the conditions precedent of the applicability of policy
  resolution have not been satisfied. Mr. Rohtagi also contended that there
  might have been some latches on the part of the Board in its failure to G
  provide power connection in time, but the same is not one-sided and even the
  appellant himself was not in a position to start commercial production within
  the stipulated date. Mr. Rohtagi also urged that since there has been no
  finding of the Division Bench of the High Court, as to who was at fault and
· if so, to what extent on which equities could be worked out, the matter could
  be remanded back to the High Court for re-adjudication. Mr. Rohtagi, however H
    134                       SUPREME COURT REPORTS [2002) SUPP. 5 S.C.R.

A to the suggestion from the Court finally agreed that the appeal can be disposed
    of on equitable consideration by this Court by reducing the period for which
    concessional tariff could be given to the appellant.

           On perusal of the industrial policy of the government, unequivocally
    indicating that concessional tariff rate would be given as well as the order of
B   the Electricity Board adopting the same, it can be safely held that such
    concession could be availed of by the industrial units for a period of five
    years from the date, they start such production in between 1.1.92 and
    31.12.1996. In this context the stand of the Board as well as the State
    Government cannot be held to be devoid of any substance when admittedly
C   the commercial production of the appellant's unit did not start till 31.12.96.
    But the question for consideration is when the government has itself come
    forward alluring industrial units to set up their industries and when under the
    provisions of the Electricity Act, every consumer has the right to get the
    supply of power and in the case in hand, when power allocation has been
D   made in favour of the appellant as early as in 1995, and yet the same power
    could not be supplied for such non-supply of power, the commercial production
    could not s!art by 31.12.96, would it at all be equitable to deny the relief to
    the appellant by giving a literal interpretation to the incentive scheme of the
    government as adopted by the Board? Our answer to this question must be
    in the negative. There are several documents on record, which were produced
E   before us to indicate that the appellant has been communicating with the
    Board, seeking power connection at an early date so that it would be able to
    start commercial production by 31.12.96. In making such communication,
    the appellant has been bringing it to the notice of the Board but for supply,
    the appellant has made all other arrangements to set the production, but yet
F   there has been inaction on the part of the Board in providing power to the
    appellant. Mr. Rohtagi, appearing for the Board no doubt brought to our
    notice a letter from the appellant to the Board and contended that it could not
    have been possible for the appellant to start production by 31.12.96 but we
    are unable to accept this submission nor are we making deeper probe into the
    matter. Suffice it to say that the appellant has been denied power supply by
G   the Board in appropriate time, which has prevented the appellant from startin~
    the commercial production by 31.12.96. This being the position, and having
    regard to the gamut of the circumstances, starting from the government policy
    resolution and culminating in setting up of the facto~y by the appellant in
    Kerala and commenced the production of ferro alloys, though not by 31.12.96,
H   we are of the considered opinion that granting the concessional tariff for a
 HITECH ELECTROTHERMICS & HYDROPOWER LTD. v. STATE [PA TT ANAIK, CJ.]        J35

period of three years instead of five years, as indicated in the policy resolution   A
would meet the ends of justice and we, accordingly, so direct. Be it be stated
that the appellant has been enjoying the concessional tariff on the basis of
 interim orders of the court and, therefore, that should be iaken into account
and due adjustment would be made in computing the period of three years,
for which we are directing for grant of concessional tariff. The impugned            B
judgment of the Kerala High Court is set aside and these appeals are allowed
to the extent indicated above.

N.J.                                                           Appeals allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "industrial policy"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.