HINDUSTAN CONSTRUCTION CO. LTD.versusSTATE OF JAMMU AND KASHMIR
- Citation
- 1992 INSC 225
- Decided
- 28 August 1992
- Disposal
- Appeal(s) allowed
- Bench
- S RANGANATHAN
Holding
Arbitrators may award post‑award interest and a court may not set aside a non‑speaking arbitral award on the ground of an alleged error on its face or for interpreting contract terms, except where the arbitrator has exceeded jurisdiction.
Summary
Hindustan Construction Co. Ltd. entered into a bridge‑construction contract with the State of Jammu & Kashmir and, after disputes, the matter was referred to arbitration. The arbitrators awarded the contractor on several items, including full amounts on items 2 and 5 and interest on the total claim, but the Jammu & Kashmir High Court set aside the award on items 2, 5 and the post‑award interest, holding that arbitrators could not award interest after the award and that the award was erroneous on its face. The Supreme Court held that an arbitrator is competent to award interest from the date of the award to the date of payment and that a non‑speaking arbitral award cannot be interfered with on the ground of an alleged error apparent on its face or for interpreting contract clauses, unless the arbitrator has exceeded jurisdiction. Consequently, the Court allowed the contractor's appeals, set aside the High Court orders and directed that the decree be passed in accordance with the arbitral award.
Issues considered
- The competence of arbitrators to award interest for the period from the date of award to the date of payment (post‑award interest).
- The scope of judicial review of a non‑speaking arbitral award, specifically whether a court may set aside such an award on the ground of error apparent on its face.
- The extent to which a court may interfere with an arbitrator's interpretation of contract clauses, i.e., whether the award can be set aside for alleged excess of jurisdiction.
Legislation cited
- Arbitration Act, 1940s. 14, s. 29, s. 30, s. 33
- Code of Civil Procedure, 1908s. 34
Subjects
Judgment
HINDUSTAN CONSTRUCTION CO. LTD. A
v.
STATE OF JAMMU AND KASHMIR
AUGUST 28, 1992
(S. RANGANATHAN, V. RAMASWAMI AND B.P. JEEVAN B
REDDY, JJ.]
Arbitration Act, 1940:
Sections 14, 29, 30 and 33-Award by Arbitrators-lnteiference
with-When arise!l-Whether arbitrators competent to award· interest from the C
date of award till date of payment.
Civil Procedure Code, 1908:
Section 34-Award of interest Pendente lite-Applicability to proceed- D
ings before arbitrator.
The appellant-company entered into a contract with the respondent-
State for the construction of a bridge. Certain disputes which arose
between them were referred to arbitration, in pursuance of a clause there-
for in the contract. There were eight items of claims by the Contractor. E
The two joint arbitrators appointed for the purpose made an award
allowing the entire claim of the appellant on items Nos. 1 and 2 and totally
rejected the claims under items Nos. 3 and 7. Items Nos. 4, 5, 6 and 8 were
allowed in part.
There were further proceedings before the High Court under sec- F
lions 30 and 33 of the Arbitration Act. A Single Judge made the award in
respect of items Nos. 1, 4 and 6 a rule of Court, but set aside the award in
respect of items Nos. 2 and 5. On items No. 8, he held that the arbitrators
could not have awarded future interest upto the date of payment of the
amounts awarded. Rejection of claims under item Nos. 3 and 7 was not G
challenged before the High Court.
The appeal by the contractor and the cross-objections by the State
were dismissed by the Division Bench which, agreeing with the Single
Judge, set aside the award on Items No. 2 and 5 viz., dewatering of piers
by more than one pump and refund of toll tax payment, on the ground that H
297
298 SUPREME COURT REPORTS[l992] SUPP. 1 S.C.R.
A It was in violation of express terms of the clauses of the contract between
the parites. On the issue of interest claim i.e. items No. 8, the Court held
that the power to award future interest (i.e. from the date of the award till
the date of payment) was available only to the Court and not to the
arbitrator.
B Hence the appellant-company filed two 11ppeals b•fore this Court in
respect of item Nos. 2 and S, and also the grant of future interest.
On behalf of the appellant, it was contended that in setting aside the
award on items No. 2 and S the Court had overlooked that it was dealing
C with a non-speaking award and travelled far beyond the scope of permis·
slble grounds of judicial review of such an award; that in dealing with
items No.5, the Division Bench considered itself at liberty to go beyond the
award, take note of such reasons for the award as could proceed to
examine whether those reasons were right or erroneous and, therefore,
proceeded to place its own interpretation on clause 1.'~ and condition 32
D of the contract, and having reached the conclusion that the interpretation
placed by the arbitrators on the said clause was erroneous, proceeded to
set aside that part of the award.
It was contended on behalf of the State that since these were items
E covered by certain terms of the contract, the Court should look at those
terms and interpret them.
Allowing the appeals, this Court,
HELD : 1. The arbitrator is competent to award interest for the
F period commencing with the date of award to the date of decree or date of
realisation, whichever is earlier. This is also quite logical for, while award
of interest for the period prior to an arbitrator entering upon the refer·
ence is a matter of substantive law, the grant of interest for the post
award period is matter of procedure. Section 34 of the Code of Civil
G Procedure, 1908 provides both for awarding of interest pendente lite as wen
as for the post-decree period and the principles of Section 34 "has been
held applicable to proceedings before the arbitrator, though the section as
such may not apply. Therefore, the High Court was not right in setting
aside the award of interest by the arbitrators. [303 8-D]
H Secrermy; Imgation Depaltment of Orissa v. G.C. Roy, 1991 (6) J.T.
HINDUSTAN CONSTRUCTION CO. v. J&K 299
349, followed. A
Union of India v. Bongo Steel Furniture (P) Ltd., (1967] 1 SCR
324/329 and Gujarat Water Supply & Sewage Board v. Unique Erectors,
(1989] 1 SCR 318, relied on.
2.1. The High Court was not correct In setting aside the award on B
items No. 2 and S on the ground that there was an error apparent on the
face of the award. The award is a non-speaking one and contains· no
reasoning which can be declared to be faulty. The scope of the Court's
jurisdiction In Interfering with a non-speaking award on the above ground
In extremely limited. The arbitrators have just awarded amounts to the C
contractor, against Its claim, on Items 2 and S. They made no reference to
the contract or any of Its clauses. Even If, In fact, the arbitrators had
Interpreted the relevant clauses of the contract lo making their award on
the items lo question and even If the Interpretation Is erroneous, the Court
cannot touch the award as It Is within the jurisdiction of the arbitrators
to Interpret the contract. Whether the interpretation Is right or wrong, the D
parties will be boond; only If the arbitrators set oot their line of Inter·
pretatlon In the award and that is found erroneous can the Court Inter-
fere. [304 G·H; 305 A, G, H, 306 A•BJ
Champsey Bhara & Co. v. Jivraj Ba/loo Spinning & Weaving Co. Ltd., E
L.R. 1922-50 I.A, 324, followed.
Sudarsan Trading Co. v. Govt. of Kera/a, (1989] 1 SCR 665, relied on.
Absalom Ltd. v. Great Western (London) Garden, Village society Ltd.,
1933 A.C. 592 and Giacomo Costa Fu Andrea v. British Italian Trading Co. F
Ltd., 1962 (2) A.E.R. 53, referred to.
2.2. A non-speaking award can be considered and If necessary,
interfered with on the ground of excess or jorlsdlctloo also, and Coorts
sometimes rely on this ground to set aside an award, when actually what
they were embarking upon was an interpretation or the contract and a G
criticism of the arbitrator's approach thereto. It is clear that this Is what
bas happened in the instant case. However, the instant case cannot be
brooght within the scope of the "excess of jurisdiction" role .either. The
High Court has not rested Its decision on any qoestloo nf the arbitrator
having exceeded his jurisdiction or travelled beyond the contract; It has H
300 SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R.
A clearly held It to be a case of "error apparent on the face of the award".
[307 G-H; 308-A]
Sudarsan Trading Co. v. Govt. of Kera/a, [1980] 1 SCR 665, relied on.
2.3. The clauses of the contract are not so clear or unambiguous as
B to warrant an inference that the interpretation placed on them by the
arbitrators Is totally unsustainable. Clause 19 does not prohibit the use of
more than one pump for dewaterlng the well. It permits the pneumatic
sinking or well in addtion to sinking of well by dredging methods and it Is
not known whether any dewaterlng would have been necessary in this
C process. This is purely a technical matter and there Is no material to bold
that the arbitrators' interpretation was erroneous. If the arbitrators bad
accepted the plea of the contractor that the dewatering with more than one
pump was authorised by the officials on the spot, the Court cannot
Interfere therewith. Likewise in Clause 1.28 and condition 32, the import
D of the words "tender amount shall exclude" is very ambiguous and the
parties were themselves not clear as to whether they wanted "toll tax" to be
within this clause or outside its purview. Even reading the clauses and the
award side by side, it is difficult to say that the arbitrators' interpretation
Is erroneous on the face of it. [308 B·E J
E CIVILAPPELLATE JURISDICTION: Civil Appeal No. 940 of1978.
From the Judgment dated 31.U.1975 of the Jammu & Kashmir High
Court in Letters Patent Appeal No. 7 of 1973.
F
AND
Civil Appeal No. 2868 Of 1977.
From the Order dated 25.4.1977 of the Jammu & Kashmir High
G Court in Application No. 4 of 1976.
R.F. Nariman and P.H. Parekh for the Appellant.
Ashok Mathur for the Respondent.
H The Judgment of the. Court was delivered by
HINDUSTAN CONSTRUCTION CO. v. J&K [RANGANATHAN, J.] 301
RANGANATHAN, J, The appellant company entered into a contract A
with the Public Works Department of the Jammu & Kashmir Government
for the construction of a bridge on the River Chenab at Baradari. Certain
disputes arose between them which were referred to arbitration in pursuance
of a clause therefor contained in the contract. The two joint arbitrators made
an award on 24th October 1972: There were eight items of claim by the B
contractor which were put up for their consideration. They allowed fully the
entire claim of the appellant on items nos.1 and 2 and totally rejected the
claims under items nos. 3 and 7. The rest ofthe claims were allowed in part.
There were further proceedings before the Jammu & Kashmir High
Court under Sections 30 and 33 of the Arbitration Act. The learned Single C
Judge made the award in respect of items nos. 1, 4, 6 a rule of Court but
set aside the award in respect of items nos. 2 and 5. The rejection of the
claim under items nos. 3 and 7 was not challenged before him. On item 8,
he held that the arbitrators could not have awarded furture interest upto
the date of payment of the amounts awarded. The contractors filed an D
appeal before the Division Bench and the State preferred a memorandum
of cross-objections. Both the appeal and the cross-objections were dis-
missed by the Division Bench. Hence the present two appeals.
The contractors are aggrieved by the High Court's order on three of
the claims made by them : E
Amount
Item Subject Claimed Awarded
No. Rs. Rs.
2 Dewatering of piers 1, 26, 376.62 1, 26, 376.62
by more than one
F
pump
5 Refund of Toll Tax 2, 49, 595.39 2, 39, 204.67
payment
8 Interest on the total 9% p.a. 6% p.a. from date of
amount of claim reference (6.12.68) G
remaining unpaid at to date of payment
or decree, whichever
is earlier.
The High Court as mentioned earlier, set aside the award on items
nos. 2 and 5 and also set aside the grant of future interest. These are the H
302 SUPREME COURT REPORTS[l992] SUPP. 1 S.C.R.
A three issues before us.
In regard to item no. 2 above, the arbitrators had accepted the
contractor's claim in full. The Division Bench, agreeing with the Single
Judge, has set aside the award on this issue on the ground that it is in
violation of an express clause of the contract between the parties which
B read thus:
"19. The foundation wells will be sunk by open dredging
methods only. If the grabs persistently done less than half
full (i.e. not less than half a yd.) dewatering of wells and
c removing the stratum by putting men inside will be resorted
to only if the wells can be dewatered by 1 no. 6" x 6" pump
without blowing. For sinking well in this manner the con-
tractor will be paid extra rupees three per cft. of sinking
done. If complete dewatering by 1 no. 6" x 4" (sic) pump
without blowing of sand is not pQssible, pneumatic sinking
D will be permitted for further sinking of the wells for which
the contractors will be paid extra at rates quoted by them."
Likewise, in regard to item no.5, the Court set aside the award on the
ground that it violated the terms of clause 1.28 and condition 32 of the
contract which were in the following terms :
E
'1.28 Tender amount shall exclude all quarry fees, royalties,
terminal taxes and octroi duty if any payable for materials
to be consumed on the work. No sales tax is payable by the
contractor on constructional works. Any payments made
F by the contractor on this account shall be reimburshed by
the department on production of proper original vouchers.
Condition 32. Tender amount will exclude all quarry fees,
royalties, terminal taxes and octroi duty if any. No sales tax
is payable by the contractor on the constructional works.
G Any payments made by the contractor on such account
shall be reimbursed by the department on production of
proper original vouchers. '1
On the issues of interest (claim no.8) the Court held that the power
H to award furture interest (i.e. from the date of the awa1d to the date of
HINDUSTAN CONSTRUCTION CO. v. J&K [RANGANATHAN, J.] 303
payment) was available only to the Court and not the arbitrator. A
The question of interest can be easily disposed of as it is covered by
recent decisions of this Court. It is sufficient to refer to the latest decision
of. a five-judge Bench of the Court in Secretary, Irrigation Department of
Orissa v. G.C. Roy, (1991) 6 J.T. 349. Though the said decision deals with
the power of the Arbitrator to award interest pendente lite, the principle of B
the decision makes it clear that the arbitrator is competent to award
interest for the period commencing with the date of award to the date of
decree or date of realisation, whichever is earlier. This is also quite logical
for, while award of interest, for the period prior to a arbitrator entering
upon the reference is a matter of substantive law, the grant of interest for C
the post-award period is a matter of procedure. Section 34 of Code of Civil
Procedrue provides both for awarding of interest pendente lite as well as
for the post -decree period and the principle of Section 34 has been held
applicable to proceedings before the arbitrator, though the section as such
1 may not apply. In this connection, the decision in Union of India v. Banoo D
Steel Furniture (P) Ltd., [1967] 1 SCR 324/329 may lie seen as also the
decision in Gujarat Water Supply & Sewage Board v. Unique erectors, [1989]
1 S.C.R. 318 which upholds the said power though on a somewhat different
reasoning. We, therefore, think that the award on item no.8 should have
been upheld.
E
Now coming to the High Court's decision regarding items nos. 2 and
5, Sri Nariman, for the appellant contends that, in setting aside the award
on these items, the Court has overlooked that it was dealing with a
non-speaking award and travelled far beyond the scope of permissible
grounds of judicial review of such an award. He draws our attention to F
certain passages in the judgment of the Division Bench which, he submits,
are contrary to the principles laid down in several decisions of this Court.
In dealing with the award on items no.2, the Court observed :
"The above cited passage from the award clearly shows
that the determination of dispute between the parties by G
the arbitrators was based on consideration of documen-
tary and oral evidence. Although that evidence has not
been specially discussed in the award, yet, that evidence
which has been perused and considered by the learned
arbitrators for giving the award would, in our opinion, H
304 SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R.
A form part of the award and the lamed Judge in Chambers
could, therefore, look into all that evidence. The submis-
sion of the learned counsel therefore deserves to be
repelled, as we do not find that the learned Judge com-
mitted any error in looking into the record accompanying
the award while setting aside the awrd in respect of the
B
claim relating to item no.2."
Again, dealing with item no.5, the Division Bench considered itself
at liberty to go beyond the award, take not of such reasons for the award
as could be deduced from the record accompanying the award and proceed
C to examine whether those reasons were right or erroneous. In this view, it
proceeded to place its own interpretation on clause 1.28 and condition 32
of the contract, and having reached the conclusion that the interpretation
placed by the arbitrators on the said interpretation placed by the ar-
bitrators on the said clause was erroneous, proceeded to set aside that part
of the award. Sri Nariman submits that in adopting this type of approach
D to the issue the Division Bench was influenced by the following observa-
tions of Lord Wright in Absalom Ltd. v. Great Western (London) Garden
Village Society Ltd., (1933) AC. 592 at 612 :
•
"As the action is to set aside the award for matter appearing
E on its face the court is deparred from considering any
matter which does not appear in the award itself or in
documents incorporated in it. The award recited the con-
tract between the parties and referred in terms to certain
conditions of the contract namely clauses 26, 30 and 32;
though these clauses are not set out in full, they must, I
F think, be taken to be incorporated."
which represent a line of approach which has been specifically. deviated
from by our Courts.
In our opinion, there is great force in the contentions urged by
I
G learned counsel. The High Court has set aside the award on the above
items on the ground that there is an error apparent on the face of the
award. This is clearly incorrect. The award is a non-speaking one and
contains no reasoning which can be declared to be faulty. The scope of the
Court's jurisdiction in interfering with non-speaking award on the above
H ground is extremely limited. The rule of limitation in this respect was
HINDUSTAN CONSTRUCTION CO. v. J&K (RANGANATIIAN, J.] 305
enunciated by the Judicial Committee almost seven decades ago in A
Champsey Bhara & Co. v. livraj Ba/loo Spinning & Weaving Co. Ltd., L.R.
1922-50 IA. 324, in words which have been consistently and uniformly
followed and applied in all subsequent decisions. Lord Dunedin said, after
noting with disapproval certain attempts to extend the area of the court's
interference with such an award:
B
"An error in law on the face of the award means, in their
Lordships' view, that you can find in the award or a docu-
ment actually incorporated thereto, as for instance a note
appended by the arbitrator stating the reasons for his
judgment, some legal proposition which is the basis of the c
award and which you can they say is erroneous. It does not
mean that if in a narrative a reference is made to a CO!!len-
. tion of one party, that opens the door to seeing first what
that contention is, and then going to the contract on which
the parties' rights depend to see if that contentiOn is sound.
Here it is impossible to say, from what is shown on the face D
of the award, what mistake the arbitrators made. The only
way that the learned judges have arrived at fmding what
the mistake was is by saying : "inasmuch as the arbitrators
awarded so-and-so, and inasmuch as the letter shows that
the buyer rejected the cotton, the arbitrators can only have E
arrived at that result by totally misinterpreting rule 52." But
they were entitled to give their own interpretation to rule
52 or any other article, and the award will stand unless, on
the face of it, they have tied themselves down to some
special legal proposition which they, when examined, ap-
pears to be unsound."
F
The present case is precisely one of the same type as the one before
the Judicial Committee. The arbitrators have just awarded amounts to the
contractor, against its claims, on items 2 and 5. They make no reference to
the contract or any of its clauses. Yet, the State contends that since these G
are items covered by certain terms of the contract, the Court should look
at those terms and interpret them; if this is done, it is said, the State's
interpretation is bound to be accepted and that apparently accepted by the
arl!itrators will be found to be wrong. It is this contention that has been
accepted. This cannot be done. Even if, in fact, the arbitrators had inter- H
306 SUPREME COURT REPORTS(1992) SUPP. 1 S.C.R.
A preted the relevant clauses of the contract in making their award on the
impugned items and even if the interpretation is erroneous, the Court
cannot touch the award as it is within the jurisdiction of the arbitrators to
interpret the contract. Whether the interpretation is right or wrong, the
parties will be bound; only if they set out their line of interpretation in the
B award and that is found erroneous can the Court interfere.
In going further and proceeding to consider the terms of the contract
and their interpretation, the High Court was influenced by the decision in
Absalom Ltd. v. Great Western (London) Garden Village Society Ltd., (1933)
AC. 592. The ratio of this decision has been discussed and explained by
C the Court of Appeal in Glacoma Costa Fu Andrea v. British Italian Trading
Co. Ltd., (1962) 2 A.E.R. 53 and more recently by this Court (in a derision
to which one of us was a party) in Sudarsan Tarading Co. v. Govt. of Kera/a,
(1989) 1 S.C.R,. 665 at p.687. That decision, therefore, could not have been
taken aid of to fault the award.
D
There is, however, apart from the existence of an "error apparent on
the face of the award", another angle from which a non-speaking award
can be considered by the Court and, if necessary, interfered with. This
ground for impeaching a non-speaking award and its limitations have been
E explained by this Court in the Sudarsan Trading Co, case earlier referred
to. Sabyasachi Mukherjee J. (at p. 685 of (1989] 1 S.C.R.) enunciated the
rule and its limitation thus:
"An award may be remitted or set aside on the ground that
F the arbitrator in making it, had exceeded his jurisdiction
and evidence of matters not appearing on the face of it,
will be admitted in order to establish whether the jurisdic-
tion had been exceeded or not, because the nature of the
dispute in something which has to be determined outside
the award - whatever might be said about it, in the award
G or by the arbitrator. See in this connection, the observations
of Russell on The Law of Aroitration, 20th Edn. 427. Also
see the observations of Christopher Brown Ltd. v. Genos-
senschaft Oestmeichischer etc., (1954) 1 QB 8 at p.10 and
Dalmia Dairy Industries Ltd. v. National Bank of Pakistan,
H (1978] 2 Lloyd's Rep. 223. It has to be reiterated that an
HINDUSTAN CONSTRUCl10N CO. v. J&K [RANGANATHAN, J.] 307
arbitrator acting beyond his jurisdiction - is a different A
ground from the error apparent on the face of the awar.d.
In Halsbury's Laws of England (4th Edn. Vol.2 para 622)
one of the misconducts enumerated, is. tbe decision by the
arbitrators on a matter which is not included in the agree-
ment or reference. But in such a case one has to determine
the distinction between an error within the jurisdiction and
B
an error in excess of the jurisdiction. See the observations
in Anisminic Ltd. v. Foreign· Compensation Commission,
(1969) 2 AC 147 and Regina v. Noseda, Field, Knight &
Fitzpatrick, [1958] 1 SLR 793. But, in the instant case the
court had examined the defferent claims not to find out c
whether these claims were within the disputes referable to
the arbitrator, but to find out whether in arriving at the
decision, the arbitrator had acted correctly or incorrectly.
This, in our opinion, the court had no jurisdiction to do,
namely, substitution of its own evaluation of the conclusion
D
of law or fact to come to the conclusion that the arbitrator
had acted contrary to the bargain between the parties.
Whether a particular amount was liable to be paid on
damges liable to be sustained, was a decision within the
competency of the arbitrator in this case. By purporting to
construe the contract the court could not take upon itself E
the burden of saying that this was contrary to the contract
and, as such, beyond jurisdiciton. It has to be determined
that there is a distinction between disputes as to the juris-
diction of the arbitrator and the disputes as to in what way
that jurisdiction should be exercised ..... " F
The learned Judge further proceeds to point out that Courts are sometime
persuaded to rely on this ground to set aside an award when, actually, what
Ibey were embarking upon was in interpretation of the contract and a
criticism of the arbitrator's approach thereto. It is clear that this is what G
has happened in the present case also. We have already mentioned that
the High Court has not rested its decision on any question of the arbitrator
having exceeded his jurisdiction or travelled beyond the contract; it has
clearly held it to be a case of "error apparent on the face of the award". In
our view, the case cannot be brought within the scope of the 11 excess of
jurisdiction" rule either. H
308 SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R.
A We would like to add th~t we have also heard arguments on the
scope of the relevant clauses of the contract. It seems to us that the clauses
are not so clear or unambiguous as to warrant an inference that the
interpretation placed on them by the arbitrators is totally unsustainable.
Cl.19 does not, as the High Court has said, seem to prohibit the use of
more than one pump for dewatering the well. It permits the pneumatic
B sinking of well in addition to sinking of wells by dredging methods and we
are not aware whether any dewatering would have been necessary in this
process. This is purely a technical matter and we have no material to hold
that the arbitrators' interpretation was erroneous. The contractor has also
contended that the dewatering with more than one pump was authorised
C by the officials on the spot and, if the arbitrators had accepted this plea,
the Court cannot interfere therewith. Likewise in Clause 1.28 and condition
32, the import of the words "tender amount shall exclude" is very ambiguous
and indeed we find that the arguments at various stages indicate that the
parties were themselves not clear as to whether they wanted "toll tax" to be
D within this clause or outside its purview. We do not consider it necessary
to discuss the matter further. We only wish to say that, even reading the
clauses and the award side by side, it is difficult to say that the arbitrator's
interpretation is erroneous on the face of it.
For the reasons discussed above we allow the appeals, set aside the
orders of the learned Single Judge and Division Bench of the High Court
E
and direct the passing of a decree in terms of the award. We, however,
make no order regarding costs.
N.P.V. Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.