Created byFuzzy Cloud

Supreme Court of India

HANUMAN LAXMAN AROOSKARversusUNION OF INDIA & ORS.

Citation
2020 INSC 49
Decided
16 January 2020
Disposal
Disposed off

Holding

The Court held that the minutes of the EAC meeting are to be taken on record and the suspension on the environmental clearance is lifted, subject to cumulative compliance with all stipulated conditions.

Summary

The Union of India sought a direction that the minutes of the 40th meeting of the Expert Appraisal Committee (EAC) dated 23 April 2019 be placed on record so that the Supreme Court's embargo on the environmental clearance (EC) for the Mopa greenfield airport could be lifted. The Court examined whether the EAC had adequately addressed the concerns highlighted in its earlier 2019 judgment, including issues of forests, ecologically sensitive areas, the Western Ghats and flora and fauna, and whether the EAC’s composition and process were valid. Finding that the EAC had revisited its recommendations, imposed additional conditions, and complied with the earlier directives, the Court held that the minutes should be taken on record and the suspension on the EC lifted, subject to cumulative compliance with all conditions. The Court also appointed the National Environmental Engineering Research Institute (NEERI) to oversee compliance and ordered the project proponent to bear the costs. The miscellaneous application was consequently disposed of.

Issues considered

  • Whether the minutes of the Expert Appraisal Committee meeting dated 23 April 2019 should be taken on record.
  • Whether the suspension on the environmental clearance for the Mopa airport should be lifted.
  • Whether the EAC’s composition and its appraisal process satisfy the requirements of expertise and absence of conflict of interest.
  • Whether the additional environmental conditions imposed are sufficient to address the concerns raised by the Court.

Legislation cited

Subjects

environmental clearanceexpert appraisal committeegreenfield airportWestern Ghatsecologically sensitive areaforestmitigation conditionsjudicial reviewzero carbon airportNEERI oversightsuspension lifted

Judgment

1030                       [2020]
                SUPREME COURT     1 S.C.R. 1030
                               REPORTS                       [2020] 1 S.C.R.


 A                    HANUMAN LAXMAN AROOSKAR
                                         v.
                           UNION OF INDIA & ORS.
                             M.A. No.965 of 2019 IN
 B                       (Civil Appeal No. 12251 of 2018)
                                JANUARY 16, 2020
               [DR. DHANANJAYA Y CHANDRACHUD AND
                        HEMANT GUPTA, JJ.]
 C            Environment – Environmental clearance for a greenfield
       airport – The Union of India sought a direction that the minutes of
       the fortieth meeting of the Expert Appraisal Committee (EAC) dated
       23.4.2019 be taken on the record so that the embargo imposed by
       the Supreme Court on the Environmental clearance (EC) for a
       greenfield airport at Mopa Goa can be lifted – Earlier, the Supreme
 D
       Court in its judgment reported as Hanuman Laxman Aroskar v. Union
       of India (2019 SCC Online 441) held that the process leading up to
       the grant of an Environmental clearance on 28.10.2015 was flawed
       – Held: On reading of the process leading upto the instant proceedings,
       it cannot be said that EAC has, it its appraisal process, ignored the
 E     concerns which were highlighted by the Supreme Court – The EAC
       has adequately addressed four areas i.e. (i) Forests; (ii) Ecologically
       sensitive areas; (iii) Western Ghats and (iv) Flora & Fauna and has
       laid down additional conditions to ensure the adequate protection
       of the environment – A comprehensive process has been followed by
       the EAC bearing in mind the requirements of the Airport Guidance
 F
       Manual – The process which has been adopted by the EAC and its
       ultimate conclusions must be scrutinized, in the course of judicial
       review, in the context of the limitations which were attached to the
       Court conducting a merits based review – Earlier, the Court did not
       quash the EC but suspended it until the EAC revisited its
 G     recommendations in the light of the concerns which were expressed
       by the Supreme Court – Having assessed the process which took
       place following the judgment of the Supreme Court and outcome, it
       would be difficult to hold that it fails to meet the standards which
       the Court applies in the course of judicial review in the environmental
       matters – The minutes of the meeting of the EAC dated 23.4.2019
 H
                                        1030
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1031


are taken on record – The additional conditions which have been          A
imposed by the EAC shall, together with the original conditions of
the EC dated 28.10.2015 and the directions issued by the NGT be
cumulatively observed – Also in the earlier judgment, the Supreme
Court noted abject failure of the project proponent to provide
complete information on the existence of reserved forests – In the
                                                                         B
proceedings that followed the judgment, the project proponent sought
to remedy its failure by taking into account additional information
on the significant aspects of the environment – In the process leading
to the grant of the EC as well as the Registry of its suspension by
the Supreme Court, numerous mitigatory conditions have been
imposed on the project proponent – To ensure the oversight of the        C
project by a specialized body to ensure compliance with the
directions cumulatively issued by the Court, the National
Environmental Engineering Research Institute to be appointed to
oversee compliance with directions cumulatively issued by the
Supreme Court – The suspension on the EC accordingly, stand lifted.
                                                                         D
      Disposing of the Miscellaneous Application, the Court
       HELD: 1. During the course of the judgment which was
rendered by this Court on 29 March 2019, certain flaws were
noticed in the process leading up to the grant of an EC on 28
October 2015. The project proponent had not complied with its            E
obligation to make a full disclosure of information on material
aspects of the environment in Form 1 as an intrinsic part of the
EIA process. This Court specifically recorded its concerns on
vital aspects which had not been adequately addressed by the
EAC. Having noticed the flaws in the process and the deficiencies
in the decision making process of the EAC, the Court directed            F
the EAC to revisit the recommendations made by it for the grant
of an EC including the conditions which it had formulated, having
regard to the specific concerns which were highlighted in the
judgment. Thereafter if the EAC were to allow the construction
to proceed, it was directed to impose additional conditions to           G
protect the terrestrial eco-systems. The EAC was under a specific
mandate to lay down conditions pertaining to air, water, noise,
land and the biological and socio-economic environment. During
the course of this judgment, this Court has traced the process as
it evolved before the EAC following the earlier directions of this
                                                                         H
1032            SUPREME COURT REPORTS                      [2020] 1 S.C.R.


 A     Court. The net result of the process is that the concessionaire
       has been subjected to a slew of mitigatory conditions: 53 in the
       original EC, 16 at the behest of NGT and 40 imposed by the EAC
       in the second round. On a reading of the process leading upto
       the present proceeding, it cannot be said that the EAC has, in its
       appraisal process, ignored the concerns which were highlighted
 B
       by this Court. The appellant focused submissions on four areas
       namely (i) Forests; (ii) ESAs; (iii) Western Ghats; and (iv) Flora
       and Fauna. The EAC has adequately addressed these concerns
       and laid down additional conditions to ensure the adequate
       protection of the environment. [Para 42][1069-G-H; 1070-A-D]
 C            2. A comprehensive process has been followed by the EAC
       bearing in mind the requirements of the Airport Guidance
       Manual. The EAC took note of the presence of reserved forests
       and of ESAs in the Western Ghats and deliberated on the impact
       of the construction and operation of the proposed airport on flora
 D     or fauna, hydrological systems and climatic variations. The
       process which has been adopted by the EAC and its ultimate
       conclusions must be scrutinized, in the course of judicial review,
       in the context of the limitations which are attached to the court
       conducting a merits based review. The EAC has accounted for
       the relevant factors outlined by this Court in its previous judgment
 E     in the assessment leading to the grant of the EC. [Para 44]
       [1072-C-F]
             3. The evaluation of merits is a matter which primarily rests
       with an expert authority. The court can certainly supervise
       procedural compliance and ensure that all necessary inputs which
 F     are required to be factored into the decision-making process have
       been duly borne in mind. Once this has been done, the court
       must be circumspect in micro-managing the decision-making
       process by the EAC by substituting its own opinion for that of
       the EAC. Undoubtedly, no process can be perfect or free from
 G     studied criticism. The Appellant has attempted to perform such
       an exercise when it was submitted that the collection of primary
       faunal data from a nearby village and secondary data from ZSI
       sources was not an adequate means of dealing with the concerns
       expressed by this Court. In assessing these criticisms, this Court

 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1033


must equally be cognizant of the fact that by the judgment of this     A
Court dated 29 March 2019, the EAC was required to carry out
the exercise within a period of one month from the receipt of the
order of this Court. The Court did not quash the EC but directed
that it should remain under suspension until the EAC revisited
its recommendations in the light of the concerns which were
                                                                       B
expressed by this Court. Having assessed the process which took
place following the judgment of this Court and the outcome, it
would be difficult for this Court to hold that it fails to meet the
standards which the court applies in the course of judicial review
in environmental matters. [Para 45][1073-B-F]
       4. For the above reasons, the minutes of the meeting of         C
the EAC dated 23 April 2019 are taken on record as prayed for.
The additional conditions which have been imposed by the EAC
shall, together with the original conditions of the EC dated 28
October 2015 and the directions issued by the NGT be
cumulatively observed. [Para 46][1073-G]                               D
       5. The earlier judgment of this Court highlighted numerous
deficiencies by the project proponent leading to the grant of the
EC. This Court highlighted numerous concerns including the
preservation of forests, the existence of ESAs with their attendant
features and the impact of the proposed project on natural water       E
channels. The Court also noted the abject failure of the project
proponent to provide complete information on the existence of
reserved forests. In the proceedings that followed the judgment
of this Court, the project proponent sought to remedy its failure
by taking into account additional information on significant aspects
of the environment. In the process leading to the grant of the EC      F
as well as the lifting of its suspension by this Court, numerous
mitigatory conditions have been imposed on the project
proponent. We deem it appropriate to ensure the oversight of
the project by a specialized body to ensure compliance with the
directions cumulatively issued by this Court. This Court directs       G
the National Environmental Engineering Research Institute to
be appointed to oversee compliance with the directions
cumulatively issued by this Court. The project proponent shall
bear the costs, expenses and fees of NEERI. [Para 48]
[1090-A-D]
                                                                       H
1034            SUPREME COURT REPORTS                       [2020] 1 S.C.R.


 A           Lafarge Umiam Mining Private Limited v. Union of India
       (2011) 7 SCC 338 : [2011] 7 SCR 954 – relied on.
           Hanuman Laxman Aroskar v. Union of India (2019)
       SCCOnline SC 441 – referred to.
                               Case Law Reference
 B
       [2011] 7 SCR 954                  relied on             Para 44
             CIVIL APPELLATE JURISDICTION: Miscellaneous Application
       No. 965 of 2019. In Civil Appeal No. 12251 of 2018.
              From the Judgment and Order dated 21.08.2018 of the National
 C     Green Tribunal, Principal Bench, New Delhi in Appeal No. 6 of 2018
       (earlier Appeal No. 1 of 2016/WZ)
             Ms. Anitha Shenoy, Sr. Adv., Ms. Rashmi Nandakumar, Ritwick
       Dutta, Ms. Kanika Sood, Sanjana Thomas, Ms. Ayushana Awasthi,
       Shankar Narayanan, Advs. for the Appellant.
 D
              K.K. Venugopal, AG, ANS Nadkarni, ASG, Parag P Tripathi,
       Sr. Adv., Pratap Venugopal, Ms. Surekha Raman, Akhil Abaraham Roy,
       Vijay Valson, Ms. Suhasini Sen, S.B. Narayan, S.S. Rebello, Arzu Paul,
       Neeleshwar Pavani, Shivika Agarwal, Niraj Kumar, Ms. Priya Soni,
       Gurmeet Singh Makker, M.S. Ananth, Mahesh Agarwal, Yojit Mehra,
 E     Srinivasan Ramaswamy, Ms. Aashna Agarwal, E. C. Agrawala, Advs.
       for the Respondents.
             The Judgment of the Court was delivered by
             DR. DHANANJAYA Y CHANDRACHUD, J.

 F           INDEX
             A. Introduction
             B. Appraisal by the EAC
                 B.1 Zero-Carbon programme
 G           C. Genesis of the proposed airport
             D. The present challenge
                 D.1 Domain Expertise of the EAC
                 D.2 Conflict of interest
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1035
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

           D.3 Western Ghats and ESAs                                         A
           D.4 Forestland and flora and fauna
      E. Directions
      A. Introduction
       1. The Union of India in the Ministry of Environment, Forests and      B
Climate Change1 moved these proceedings, seeking a direction that the
Minutes of the fortieth meeting of the Expert Appraisal Committee2 dated
23 April 2019 be taken on the record so that the embargo imposed by
this Court on the Environmental Clearance3 for a greenfield airport at
Mopa Goa can be lifted. This follows upon the judgment dated 23 April         C
2019 which was rendered on a challenge addressed to this Court against
a decision of the National Green Tribunal4 upholding the EC, subject to
compliance with certain conditions. By the judgment of this Court, reported
as Hanuman Laxman Aroskar v Union of India5, the process leading
up to the grant of an EC on 28 October 2015 was held to be flawed. The
directions that were imposed by the Court were formulated in the              D
following terms:
      “175. …
      (i) The EAC shall revisit the recommendations made by it for the
      grant of an EC, including the conditions which it has formulated,
                                                                              E
      having regard to the specific concerns which have been highlighted
      in this judgment;
      (ii) The EAC shall carry out the exercise under (i) above within a
      period of one month of the receipt of a certified copy of this order;
      (iii) Until the EAC carries out the fresh exercise as directed above,   F
      the EC granted by the MoEFCC on 28 October 2015 shall remain
      suspended;
      (iv) Upon reconsidering the matter in terms of the present
      directions, the EAC, if it allows the construction to proceed will
      impose such additional conditions which in its expert view will         G
      adequately protect the concerns about the terrestrial eco systems
1
   MoEF-CC
2
  EAC
3
  EC
4
   NGT
5
  (2019) SCCOnline SC 441                                                     H
1036               SUPREME COURT REPORTS                        [2020] 1 S.C.R.


 A           noticed in this judgment. The EAC would be at liberty to lay down
             appropriate conditions concerning air, water, noise, land, biological
             and socio-economic environment;
             (v) The EAC shall have due regard to the assurance furnished by
             the concessionaire to this Court that it is willing to adopt and
 B           implement necessary safeguards bearing in mind international best
             practices governing greenfield airports;
             (vi) We grant liberty to the State of Goa as the project proponent
             and the MoEFCC, as the case may be, to file the report of the
             EAC before this Court in the form of a Miscellaneous Application
 C           so as to facilitate the passing of appropriate orders in the
             proceedings; and
             (vii) No other Court or Tribunal shall entertain any challenge to
             the report that is to be submitted before this Court by the EAC in
             compliance with the present order.”
 D           Pending the completion of the process mandated in the above
       terms, this Court suspended the EC which had been granted on 28
       October 2015.
             The directions issued by this Court required the EAC:
             (i)    To revisit its recommendations for the grant of the EC
 E
                    including the conditions which it had imposed; and
             (ii) To impose, in the event that it allowed the constructionof the
                  airportto proceed additional conditionsto adequatelyprotect
                  the concerns governing the terrestrial eco-systems noticed
                  in the judgment, besides formulating conditions pertaining to
 F
                  air, water, noise, land, biological and socio-economic
                  environment. While doing so, the EAC was under a mandate
                  to take into consideration the specific concerns which were
                  highlighted in the judgment.
             2. The basis of the directions that were issued by this Court
 G     wasformulated in the penultimate paragraphof the judgment which reads
       thus:
             “174. Bearing in view the necessity to maintain a balance between
             the need for an airport and environmental concerns, we are of the
             view that it would be appropriate if the EAC is directed to revisit
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1037
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

         the conditions subject to which it granted its EC on the basis of       A
         the specific concerns which have been highlighted in this
         judgment. Such an exercise primarily is for the EAC to carry out
         in its expert decision making capacity. The EAC is entrusted with
         that function as an expert body. The role of judicial review is to
         ensure that the rule of law is observed. Hence, we propose by the
                                                                                 B
         directions which we will issue under Article 142 of the Constitution,
         to direct the EAC to revisit the conditions for the grant of an EC.
         While doing so, it would be open to the EAC to have due regard
         to the conditions which were incorporated in the order of the NGT
         and to suitably modulate those conditions in pursuance of the liberty
         which we have preserved to it. To facilitate an expeditious decision,   C
         we propose to direct the EAC to carry out this exercise in a
         prescribed time schedule during which period, the EC shall remain
         suspended. We propose to direct that after the EAC has formulated
         its views, they shall be placed before this Court in a Miscellaneous
         Application in the present proceedings, so as to enable the Court
                                                                                 D
         to pass final orders. The Miscellaneous Application may be filed
         either by the State of Goa as the project proponent or by the
         MoEFCC. We clarify that no other Court or Tribunal shall entertain
         any challenge to the ultimate decision of the EAC and final orders
         thereon shall be passed by this Court in the present proceedings.”
        3. Essentially, the concerns which were highlighted in the judgment      E
of this Court related to the need to preservethe biodiversity of the Western
Ghats. These concerns have been the subject of a seminal exercise
carried out in 2013 by a High Level Working Group6 on the Western
Ghats chaired by Dr K Kasturirangan7. The report of the HLWG has
been dwelt upon in the earlier judgment and continues to be a focal point        F
of the continuing debate in the present case. The HLWG was constituted
under the auspices of the MoEF-CC.Its report dated 15 April 2013 is a
valuable contribution to the preservation of biodiversity in the pristine
environment of the Western Ghats.
       4. The judgment of this Court emphasized the failure of the State         G
of Goa, as the project proponent, to provide complete information on the
existence of reserved forests including those which fall within a 15 km
radial distance of the proposed airport at Mopa.Underlying the serious
6
    HLWG
7
    Kasturirangan Committee report                                               H
1038                SUPREME COURT REPORTS                         [2020] 1 S.C.R.


 A     deficiency in the disclosure of information by the project proponent, this
       Court noted its concerns on certain specific aspects. These included
       primarily:
                 (i) Preservation of forests, including reserved forests;
                 (ii) Existence of EcologicallySensitive Areas8 with their attendant
 B                    features such as flora, fauna and environmental quality in
                      terms of water, soil, noise and climatic variations;
                 (iii) Impact of the proposed construction on the flow of water in
                       natural water channels; and

 C               (iv) Socio-economic and environmental concerns which were
                      raised in the course of public consultations.
                 B. Appraisal by the EAC
              5. Following the judgment of this Court, the project proponent
       furnished supplementary information to the EAC which revealed certain
 D     significant environmental features. The disclosure is extracted below:
                 “a) There are seven reserved forests within 15 km. of the proposed
                 Airport in the Goa region (under Section-20) and six proposed
                 reserved forests (under section-4) of Indian Forest Act, 1927.
                 (Survey of India Toposheet and Forest Working Plan of North
 E               Goa)
                 b) There are twenty-nine proposed reserve forests within 15 km.
                 of the proposed Airport in Maharashtra region under Section-4 of
                 Indian Forest Act, 1927 (Survey of India Toposheet & Forest
                 Department, Sawantwadi Division)
 F               c) There are four rivers in Goa viz. Terekhol river, Kalna river,
                 Chapora river, Moide river and one river viz. Tilari river in
                 Maharashtra (source: Survey of India Toposheet).
                 d) There are few patches of mangroves observed near Moide
                 river, Terekhol river, Chapora river.
 G
                 e) Western Ghat Mountain range falls within the study area.
                 f) There are two wetlands, of which one i.e. Anjuna reservoir has
                 been identified inNational Wetland Atlas of Goa.

       8
 H         ESA
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1039
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

          g) There are no coastal areas and declared biospheres in the vicinity   A
          of the proposed airport site.”
       6. The EAC tabulated the details of forest areas which fell within
a radial distance of 15 kmsof the proposed airport and within the territories
of the States of Goa and Maharashtra. The forested areas were found
to be situated in three talukasin the State of Goa (Bicholim, Pernem and          B
Bardez)and in three talukas in the State of Maharashtra (Sawantwadi,
Dodamarg and Vengurla). In Pernem taluka, the information set out in
the minutes of the EAC dated 23 April 2019 demonstrate the existence
of reserved forests inter alia in Mopa.
     7. While reviewing the Environmental Impact Assessment9, the                 C
EAC observed:
          “As per Forest Policy, 1988 of Government of India, required
          forest cover is 33%. Whereas, India average is 21.54%, Goa’s
          forest cover as per India’s state of forest report 2017 is 60.21%.
          There would be impact on forest due to felling of trees but             D
          eventually the forest cover will improve with a 1:10 compensatory
          afforestation program to be undertaken over a period of 5 years
          by the concessionaire, Goa State Biodiversity Board and
          Directorate of Civil Aviation. The enhanced forest cover would
          lead to healthy biodiversity.Further impacts on water, air, soil and
          noise environment will be minimal considering the felling of trees      E
          over a large area and compensatory afforestation plan as approved.
          It is noted that the airport site is not fragmenting the forest area
          thus not restricting and affecting the movement of fauna. The
          Airport plateau has villages on one side and forest cover on the
          other side. The plateau is just an extension of forest cover with       F
          trees, which had 15 houses, some grazing activity and some
          agricultural activity where the animals from the nearby forest may
          have been straying. The proposed airport will be protected from
          all sides with compound wall as per DGCA guidelines and thus
          animals will not able to enter the airport premises.                    G
          The proposed 10 times compensatory plantation needs to be
          monitored by the Government of Goa so that the target of planting
          5.5 lakhs saplings is achieved in a time bound manner, their survival

9
    EIA                                                                           H
1040                 SUPREME COURT REPORTS                            [2020] 1 S.C.R.


 A                rate is monitored and mortality is replenished. As major chunk of
                  2.5 lakh of saplings is proposed to be done by the village level
                  Biodiversity Committees, it is necessary to ensure that people are
                  largely given native species and/or fruit bearing saplings so that
                  they will be able to derive economic benefits from such fruit crops
                  and also such trees will provide better biological environment to
 B
                  birds.”
              8. On the existence of ESAs, the EAC noted that the EIA report
       had only indicated that Pernem taluka, where the project is to come up,
       has not been earmarked as an ESAin the Kasturirangan Committee
       report. The EAC, in its minutes dated 23 April 2019, took note of the
 C     fact that based on the Kasturirangan Committee report, the MoEF-CC
       published a draft notification on 3 October 2018 indicating proposed ESAs
       in the Western Ghats according to which, ten villages in Sawantwadi
       taluka of Sindhudurg district in Maharashtra are comprised in the ESAs
       of the Western Ghats. Apart from the ESAs within the State of
 D     Maharashtra, the EAC noted the existence of an additional eighteen
       species of mammals and fourteen bird species in the study area on the
       basis of data collected from the Zoological Survey of India 10. Reviewing
       the EIA with reference to the existence of ten ESAs within a radial
       distance of 10 Kms in the State of Maharashtra, the EAC noted in its
       minutes dated 23 April 2019:
 E
                  “EAC noted that all the 10 ESA areas within 10 kms in the State
                  of Maharashtra are beyond 4 kilometers from the project boundary,
                  the nearest one being at a distance of 4.1 kms (Village Galel). As
                  per Airport guidance manual maximum impact on the air and noise
                  environment will be there till the aircraft gains a height of 1000 ft.
 F                Emissions from aircraft below 1,000 ft. above the ground will be
                  there typically around 3 km from departure or, for arrivals, around
                  6 km from touchdown. The altitude of 1000 ft in landing and takeoff
                  is achieved within the project site. Considering that all the ESAs
                  are far away from the project, the impact on air and noise
 G                environment is expected to be minimal. With regard to soil
                  environment, impact will be mostly on the airport site self. As
                  regards water environment, as the water flow from the airport
                  site will feed the water bodies in the State of Goa, no impact is
                  envisaged on the ESA areas.”
       10
 H          ZSI
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1041
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      9. The EAC also deliberated on the likely impact of the construction    A
and operation of an airport on the flora, fauna and hydrological systems
in the ESAs as well as in regard to climatic variations. The EAC
categorized them in the following terms:
      “WATER ENVIRONMENT:
      - Changes in the natural flow of storm water, stunted growth,           B
      delayed flowering and fruiting.
      - Fauna migration in search of water to other places.
      - Change their habitat and breeding capacity.
      -Due to eutrophication influence, certain toxic algae production        C
      some animals can suffer symptoms like skin irritation or health
      problems if drinking
      SOIL ENVIRONMENT:
      - Soil impact may lead in to non-germination of seeds & stunted
                                                                              D
      growth, delayed flowering & fruiting, erosion and clearing of topsoil
      (loss of habitat & habitat fragmentation)
      - Affects the quality of the environment or habitat in which they
      live
      - Affects the availability and quality of the food supply               E
      - Soil erosion may increase the turbidity which could impact aquatic
      fauna’s respiration capacity.
      - Loss of local aquatic biodiversity
      - Habitat loss                                                          F
      - Erosion and clearing of topsoil (loss of micro-fauna).
      - Influence the abundance and health of dependent species
      AIR ENVIRONMENT:
      Air impact may lead reduced productivity, changes in water vapor        G
      levels.
      SURROUNDING / NOISE ENVIRONMENT.
       - Migration of birds
      - Breeding capacity reduction
                                                                              H
1042                 SUPREME COURT REPORTS                          [2020] 1 S.C.R.


 A                - Affect life cycle Shy mammals may move away
                  - Bird Aircraft strike
                  - Wild life hazard management
                  Climatic Variations:
 B                - habitats of many species will move pole ward
                  - experience increase in temperature regimes, rainfall
                  - decrease in the moisture regimes and increase in fire incidences.”
             Dealing with these features and the impact upon them of the
 C     proposed project, the EAC observed:
                  “The EAC noted that a total of 385 species of plants, 36 medicinal
                  plant, 86 species of birds, 33 butterfly species, 5 species of
                  amphibians, 18 species of reptiles, 35 fish species, 28 number of
                  mammal species were identified in the study area based on primary
 D                and secondary source of data. The proposed project has minimal
                  intervention and impact on the surrounding ecosystem. There are
                  mitigation measures already prescribed in EC conditions so as to
                  minimize the impact on Biodiversity-Flora & Fauna, Hydrological
                  Systems. This will help enabling the process for sustainable
                  development that benefit both environment and local livelihoods.
 E                With regards to climatic variations, the EAC felt that additional
                  initiatives such as Green Infrastructure Development program,
                  adoption of low emission intensive technologies, renewable energy
                  program, and Airport Carbon Accreditation need to be adopted to
                  reduce the impact on Green House Gas (GHG) emissions and
 F                thereby climate change.”
              10. The next set of concerns that were dealt with by the EAC
       related tothe impact of the proposed project on natural channels for the
       drainage of water. This Court had noted in its earlier judgment that the
       Mopa plateau is at a height of 155 metres above Mean Sea Level 11 and
 G     water from the plateau flows down to the rivers in the State of Goa. The
       laterite plateau is an important source of drainage by providing natural
       channels for water. The deficiency which was seen by this Court was
       that the impact of a greenfield airport on the closing of natural channels

       11
 H          MSL
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1043
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

which feed water bodies had not been scientifically mapped or studied         A
and adequately addressed.
      11. In reviewing the EIA on this aspect, the EAC in its minutes
dated 23 April 2019 observed:
      “If natural water channels that feed the local water bodies are
      not protected then there will be water deficiency in the villages       B
      for agriculture, fishing etc. Further, there will be impact on the
      ground water levels in the villages. EAC while granting EC for
      the project had detailed deliberation on this aspect so as to ensure
      that natural water channels feeding the water bodies are not
      blocked. The EAC reviewed the entire gamut of natural/artificial        C
      drainage and the storm water drainage pattern. As per the
      supplementary information provided now, the airport site, by virtue
      of being located on a plateau and the laterite soil surface, would
      naturally facilitate the flow of storm water and other artificial
      drainage. The proponent has designed for appropriate drainage
      channels in such a manner that the water flow from project site is      D
      channelized suitably into the natural water channels feeding the
      water bodies down slope. All due precautions, however, need to
      be exercised during the construction phase so as to ensure that
      construction material/debris does not, in any manner, block/obstruct
      the natural water channels or springs.                                  E
      The EAC deliberated on the current state of the project
      construction and noted that in the ensuing monsoon season the
      earth piled up at the project site due to excavation may drift to the
      natural water channels which may ultimately reach the water
      bodies in the villages. This is a matter of grave environmental         F
      concern which needs to be addressed by the project proponent
      immediately by development of embankment structures around
      the excavated earth so that piled up earth doesn’t drift to the
      natural water channels and the run-off from the site does not
      pollute or contaminate the water bodies. This shall be maintained
      during construction/operation phase of the project.”                    G
       12. As regards the concerns which were raised in the course of
public consultations, the EAC dealt with environmental concerns which
included:

                                                                              H
1044            SUPREME COURT REPORTS                            [2020] 1 S.C.R.


 A           “rain water harvesting, STP and solid waste management plan,
             impact on flora and fauna, soil quality and its impact, storm water
             management, impact on ground water, socio cultural impact, dust
             pollution during construction activity, employment opportunities to
             the local people, compensation to the affected land owners”
 B           The EAC has opined that these have been adequately addressed.
            13. Finally, after analyzing the responses submitted before it, the
       EAC summed up its analysis thus:
             “1. The EAC observed that the earlier Form-1 did not give proper
             disclosure in respect of the details of forests on the land and nearby
 C           wet land as well as on the water bodies. The EAC took into account
             the supplementary report that has been submitted which takes
             into account the deficiency of disclosure and the same thing has
             been complied with in the supplementary report. In addition, it is
             also noticed that the mitigation measures in respect of the depletion
 D           of forest cover on the project land and water bodies have been
             taken into account. As against 54,176 trees, which have been
             felled on the project site based on earlier approvals given by
             competent authority, the project proponent is proposing to plant
             5,50,000 trees (50,000 trees at the project site, 2,50,000 trees in
             the nearby villages supervised by the Biodiversity Board and
 E           2,50,000 trees under the supervision of DGCA. This is 1:10 times
             the number of trees affected as against the standard requirement
             of 1:3 times number of trees to be planted. The overall supervision
             of this compliance within the time frame of 5 years would be
             vested with DGCA. DGCA, however, needs to constitute a local
 F           monitoring committee for periodic monitoring of this vital exercise.
             2. The EAC noted that neither the project site nor the villages in
             area under study (primary data source) falls in any Eco-Sensitive
             Zone (ESZ). The 10 villages in Maharashtra side fall in ESA not
             ESZ and where the impacts of the project would be minimal. The
 G           EAC also observed that the villages in vicinity of the project in the
             Goa and Maharashtra region are not located in very close
             proximity. The nearest village is about 4.1 km from the boundary
             of the project. The EAC also observed that beyond the runway of
             3.75 km, the flight operation generally found at an altitude of about
             1000 feet and thus there would not be any adverse impact on
 H           flora and fauna in the surrounding area of the airport.
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1045
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

    3. The EAC observed that a certificate from Chief Wildlife Warden        A
    (CWLW) of State through State Government be obtained
    confirming that none of the area of the project falls in the notified
    Eco-sensitive Zone (ESZ) in the State of Goa and no activity
    prohibited in the Ecosensitive zone will be taken up be taken by
    the project proponent.
                                                                             B
    4. The EAC further observed that as per the supplementary report
    and the proposal of the water bodies with respect to observation
    regarding plateau effect of the land and also laterite surface and
    the springs, streams and water courses in the project land have
    been taken into account and appropriate drainage channels have
    been designed to take care of the water flows into the nearest           C
    water courses/rivers, etc.
    5. Appropriate storm water drainage channeling has been taken
    into account not only for the pre-monsoon season but also for
    monsoon and heavy rainfall. The drainage plan should have
    ratification by the concerned water resources department of Goa.         D
    It should be ensured that sustainable water flow in the various
    channels of watershed in the plateau is maintained. For the present,
    base level data on flow of water should be collected and used for
    future monitoring.
    6. The EAC observed that in respect of the fauna, the primary            E
    data has been collected from one of the nearest village and the
    secondary data has been collected from ZSI. In respect of the
    observation of sighting a leopard by villager, the authorities have
    indicated that they do not have any definitive information on the
    same and this need to be verified/authenticated.                         F
    7. It is a well-established fact of silvicultural science and practice
    that no plantation can replace the natural forest. The kind of
    biodiversity in any natural forest is almost impossible to be replaced
    by any kind of plantation activity which at best can be a mix of
    various monocultures. We are still far away in our knowledge of          G
    replicating the creation of natural forest. Therefore, to this extent,
    the EAC does not agree with the assessment of project proponent
    that after cutting of trees and planting of 1:10 trees, richer
    biodiversity the forest would be created. However, 1:10 plantation
    activity under expert guidance can to some extent compensate
    the loss of natural forest.                                              H
1046                SUPREME COURT REPORTS                        [2020] 1 S.C.R.


 A           8. With respect to the various points raised in the public hearing,
             the EAC observed that the supplementary report has made
             available point-wise clarifications on the various concerns on the
             public hearing. However, Hon’ble court shortlisted 14 items of
             concern in the public hearing. Solution/management plan to all
             these need to be clearly spelt out in the EMP and implemented in
 B
             letter and spirit.”
              14. Accordingly, the EAC has recommended the grant of an EC
       to the project with additional environmental safeguards and conditions,
       over and above those which were stipulated in (i) the EC dated 28 October
       2015; and (ii) the order of the NGT dated 21 August 2018.The conditions
 C     which have been imposed by the EAC have been classified under the
       following heads:
             (i)      Statutory compliance;
             (ii)     Air quality monitoring and preservation;
 D           (iii)    Water quality monitoring and preservation;
             (iv)     Noise monitoring and prevention;
             (v)      Energy conservation/ climate change measures;
             (vi)     Waste management;
 E           (vii)    Green Belt; and
             (viii) Public hearing and human health issues.
             15. The EAC has also incorporated as a part of its
       recommendations additional conditions as mandated by the NGT in its
 F     order dated 21 August 2018 under the following heads:
             (i) Air environment;
             (ii) Water environment;
             (iii) Land environment;
 G           (iv) Noise environment;
             (v) Land environment;
             (vi) Biological environment; and
             (vii) Socio-economic environment.
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1047
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      B.1 Zero-Carbon programme                                                A
       16. During the course of the hearing before this Court, a statement
has been made on behalf of the concessionaire GMR Goa International
Airport Limited, that in the event of this Court sustaining the EC for the
project, it stands committed to fulfill the objective of making the proposed
greenfield airport at Mopa Goa, a zero carbon airport operation.               B
Thepurpose of a zero carbon airport operation is to eliminate
anthropogenic carbon emissions reaching the atmosphere completely or
to the minimum extent possible from airport activities performed during
its operation. The statement which has been tendered by the
concessionaire before this Court is in the following terms:
                                                                               C
      “I. Zero carbon programme
      1. The objective of making “Zero Carbon” airport operation is to
         eliminate the anthropogenic carbon emissions reaching to
         atmosphere completely or to the minimum extent possible from
         the activates performed at Airport during its operation.              D
      2. Climate Change and its mitigation in Aviation Industry is
         monitored by International Civil Aviation Organization(ICAO)
         and the emissions from domestic aviation are monitored by the
         respective countries under the United Nations Framework
         Convention on Climate Change (UNFCCC) frameworks.                     E
      3. Carbon emissions management is guided by Airports Council
         International (ACI), through its globally recognized Airport
         Carbon Accreditation (ACA) Program.
      4. In airports, this is addressed by developing infrastructures/
         systems which will generate zero or minimum carbon emissions          F
         during its operations as per UNFCCC approved market
         mechanisms by:
          a. Adopting green building concepts,
          b. Generation and use of renewable energy,
                                                                               G
          c. Use of energy efficient systems,
          d. Developing green landscapes,
          e. Plantations as carbon sink to absorb carbon emission from
             the atmosphere
                                                                               H
1048            SUPREME COURT REPORTS                           [2020] 1 S.C.R.


 A              f. Adopting carbon offset measures for the residual emissions
                   of airport operations
             5. Level 3+ is the highest level of accreditation for carbon emission
                management of airports. As of July 30, 2019, there were 52
                Level 3+ (Neutrality) accredited airports globally (out of 1,957
 B              ACI member airports), including GMR Group’s Delhi and
                Hyderabad Airports (Additional Affidavit of Respondent No.
                5, pp.23-24).
             6. Level 3+ Neutrality is achieved by fulfilling requirements of
                Level 1,2 and 3 accreditation program (R-5 Affidavit, Page
 C              17) and offset of residual emissions under the airport’s control.
                (Sources of emission and measures under the ACA Program
                – Page 18). The Zero Carbon Emission Implementation
                Framework provides for various measures such as:
                a. Internal audit once in two year
 D              b. External audit after every 5 years
                c. Adopt Energy Management System – ISO 50001 and 3rd
                   Party certification
                d. Improve energy efficiency of buildings and equipment &
                   lightings,
 E
                e. Improve ground water availability
                f. Promote energy efficient and alternate fuel vehicles.”
             C. Genesis of the proposed airport

 F            17. Before we deal with the principle challenges addressed before
       the Court on behalf of the original appellantrepresented by Ms Anitha
       Shenoy, learned Senior Counsel, it would be worthwhile to set out briefly
       the genesis of the proposed airport at Mopa Goa.Mr K K Venugopal,
       learned Attorney General for India emphasized the following features of
       the project:
 G
             (i) The construction of an airport at Mopa Goa has been on the
                 drawing board for nearly two decades;
             (ii) The site at Mopawas chosen among three options after due
                  examination by experts;
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1049
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

           (iii) The existing airport at Dabolim is a defence establishment        A
                 which is closed to area traffic between 8:30am to 1:30pm
                 daily;
           (iv) The existing airport at Dabolim was intended to serve four
                million passengers annually while the existing passenger traffic
                is about 7.5 million annually;                                     B
           (v) The passenger traffic at Goa is expected to rise in the upcoming
               financial years to the following extent:
                  FY 21     FY 22        FY 23       FY 24         FY 25
                  12.0      14.1         15.5        16.7          17.9            C

                                                            (million passengers)
           (vi) Due to capacity constraints, international charter flights are
                not granted parking facilities at night at Dabolim; and
           (vii) The proposed greenfield airport will have a capacity to handle    D
                 4.4 million passengers in Phase–I, 13 million passengers in
                 Phase–II and 30 million passengers in Phase–III annually.
       18. The project area ofthe proposed Mopa airport is spread over
2,131 acres. Terms of Reference12 were issued on 1 June 2011 and
were extended on 19 June 2013 and 29 May 2015. The process for land                E
acquisition was initiated around 2008. The Request for Qualification 13
for the Mopa airport was issued on 3 October 2014. The EC was granted
on 28 October 2015. The concession agreement was executed on 8
November 2016. The airport is required by the terms of the agreement
to be operational within thirty-six months from 4 September 2017.                  F
According to the concessionaire, as on 18 January 2019, approximately
14.06 per cent of the project work had been completed. Pursuant to the
orders for the removal of trees, 54,176 trees were felled and 500 trees
were earmarked for transplantation. Ten trees of local species are to be
replanted for every tree which has been felled. 20,000 saplings have
been re-planted. The concessionaire has placed on record the following             G
financial features of the project:


12
     ToR
13
     RFQ                                                                           H
1050              SUPREME COURT REPORTS                       [2020] 1 S.C.R.


 A          “a. The indicative capital cost of the Mopa Airport, Phase I, was
                estimated at INR 1,900 Cr. Total Project Cost was estimated
                at INR 3,000 crores (70% debt and 30% equity).
            b. Total debt commitment incurred by Respondent No.5 for the
               Mopa Airport is approximately INR 1,330 Crs.
 B          c. The annual debt servicing incurred by Respondent No.5 based
               on current disbursement is approximately INR 17 Crs.
            d. Respondent No.5 has also entered into contractual
               commitments for following amounts – INR 1,377 Crs. Towards
               Engineering Contracts, Project Consultant INR 38 Crs.
 C             Independent Engineer INR 11 Crs. totaling – INR 1,426 Crs.
            e. Prior to the order dated 18.01.2019 passed by Hon’ble Supreme
               Court directing status quo be maintained, approximately 1,500
               workforce were gainfully engaged at the Project site along
               with requisite plant and machinery.
 D
            f. The estimated traffic at Goa is (passengers in Million
               Passengers per Annum – MPPA):

                   FY 21    FY 22      FY 23      FY 24      FY 25
                   12.0     14.1       15.5       16.7       17.9
 E

            g. The Scheduled Commencement Date was contemplated as 3
               years from Appointed Date (04.09.2017) – 03.09.2020.
            h. The Concession Period is for 40 years from Appointed Date
 F             with a right of first refusal to Respondent No.5 for an extension
               of 20 years.
            i.    GoG’s share of revenue – 36.99% on Gross Revenue from
                  6th year of Commencement of Appointed Date.”
             According to the concessionaire, the following work was in
 G     progress at the project site when the implementation of the EC was
       suspended:
            “i. Airside Earthworks – these include excavation and filling of
                runways, taxiways, aprons, parking bays, etc.
            ii.   PTB – foundations and column works in progress,
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1051
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

           iii. ATC Building – excavation for foundations are in progress,          A
           iv. Administration Building – foundation and column works in
               progress,
           v.   Precast Compound Wall works – casting of panels and
                columns in progress,
                                                                                    B
           vi. City Side Development Master plan works is in progress.”
           D. The present challenge
       19. The essence of the controversy in the present case is whether
the concerns which were highlighted in the earlier judgment of this Court
dated 29 March 2019, have been adequately addressed and remedied.                   C
       20. Ms Anitha Shenoy, learned Senior Counsel appeared on behalf
of the appellant submitted that by the judgment of this Court dated 29
March 2019, the EAC was directed to revisit the EC granted to the
project and to decide whether or not the project should be approved.
Ms Shenoy prefaced her submissions with two preliminary points:                     D
           (i) The composition of the EAC (Infrastructure-2) which has
               thirteen members does not qualify it as an expert body. None
               of the members had expertise on ornithology or on terrestrial
               eco-system. The EAC is chaired by a former Director of the
               Council for Social Development with retired officers of the          E
               State and Central Pollution Control Boards. One of the
               members has an architectural background, another in chemical
               engineering while one of the members is a Professor of Law.
               The minutes do not disclose whether the EAC sought the
               opinion of a subject specialist or specialized institution; and
                                                                                    F
           (ii) There is a conflict of interest on the part of the EIA consultant
                who had prepared the EIA report. As on the date of EAC
                meeting, Engineers India Limited14 was the EIA consultant
                as well as an independent engineer on the project. The EAC
                minutes recorded that the project proponent and EIL made a
                detailed presentation on the observations of this Court with        G
                comments and responses. EIL was defending its actions as
                an EIA consultant while at the same time being an independent
                engineer for the construction of the airport. This involves a
                conflict of interest.
14
     EIL                                                                            H
1052               SUPREME COURT REPORTS                        [2020] 1 S.C.R.


 A           Apart from addressing the above preliminary points, Ms Shenoy
       has urged submissions focusing upon the following specific areas:
             (i) Forests;
             (ii) Western Ghats;
 B           (iii) Ecologically Sensitive Areas; and
             (iv) Absence of avi-faunal study.
              21. Based on the submissions on the above four facets, Ms Shenoy
       has dwelt upon mitigation measures suggested by the EAC and the need
       to factor in the objections which were addressed during the process of
 C     public consultation. Ms Shenoy urged that the EAC minutes are virtually
       a facsimileof the presentation submitted by the concessionaire and that
       the EAC has failed to fulfill its remit of revisiting the EC as mandated by
       the order of this Court. The submissions which were addressed under
       each of the four heads noted above are catalogued below:
 D           (i)     Forests
                     In the supplementary information contained in updated Form
                     1, the project proponent had disclosed a list of thirty-five
                     proposed reserved forests around the project site. However,
                     there has been no collection of primary data through remote
 E                   sensing or ground truthing as required by the Airport
                     Guidance Manual. No impact study was carried out of the
                     proposed project on the newly disclosed forests. The EAC
                     has merely recorded the fact that the Western Ghats fall
                     within the study area without undertaking a study of the
                     likely impact of the construction of the airport. The MoEF-
 F
                     CC, in its affidavit before this Court, however sought to
                     contend that the Western Ghats are far away from the
                     project and the impact due to the operation of the airport
                     would be minimal. Though there are ten villages in the taluka
                     of Sawantwadi in Sindhudurg district of Maharashtra located
 G                   in the ESAs of the Western Ghats, no study has been
                     conducted of their vulnerability. The HLWG recorded that
                     Tiger and Elephant corridors mostly fall in the ESAs of the
                     Western Ghats. Thus, the EAC has arrived at a conclusion
                     that there will be no impact on the ESAs without knowing
                     why an ESA is proposed to be notified and without carrying
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1053
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

            out an impact assessment. The EAC has equated the issue            A
            of tree felling at the project site with the issue of the impact
            on the 42 forests surrounding the site. However, in its
            summing up, the EAC has acknowledged that compensatory
            forestation can never replace a natural forest.
    (ii)    Impact on Western Ghats                                            B
            The EAC has only adverted to the fact that the Western
            Ghats fall within the study area. While accepting the
            presence of this critical ecological biodiversity hotspot, the
            EAC has not directed any study on the impact nor has it
            adverted to the likely impact of the activity. The critical        C
            significance of the Western Ghats has been emphasized in
            the HLWG report. Absent a study by the EAC, the
            recommendations are flawed.
    (iii)   Ecologically Sensitive Areas
            The EAC has noted that ten villages in the taluka of               D
            Sawantwadi in Sindhudurg district are located in the ESA
            of the Western Ghats. The EAC ought to have determined
            what makes each ESA ecologically sensitive and to study
            the reasons for their vulnerabilities. The EAC has not
            endeavored to find the specific vulnerability of each ESA          E
            and has recorded its satisfaction with a generic explanation.
    (iv)    Flora and Fauna
            The collection of primary and secondary data of flora and
            fauna in the EIA report was perfunctory. Areas which are
            used by protected, important or sensitive species of flora or      F
            fauna for breeding, foraging, nesting, resting, over-wintering
            or migration were not considered by the project proponent.
            The EAC merely included a number of additional species,
            citing a publication of the ZSI as the source, as supplied by
            the project proponent. Species found near the Maharashtra
                                                                               G
            – Goa border as well as those found throughout India in
            forested areas show at least 1172 species. On the other
            hand, the list of species submitted by the project proponent
            does not have a single Scheduled I species despite the fact
            that there are 42 dense forests around the project area.
            Important species such as the Indian elephant, royal Bengal        H
1054             SUPREME COURT REPORTS                            [2020] 1 S.C.R.


 A                   tiger and leopard have been excluded. The EAC did not
                     direct the carrying out of an avi-faunal study, in violation of
                     the directions of this Court, the only reference being to bird
                     strikes.
               22. As regards the mitigation measures proposed by the EAC,
 B     Ms Shenoy submitted that the Airport Guidance Manual requires a
       rigorous study of the impacts of a proposed airport project on the biological
       environment and the measuresrequired to address these impacts.
       Information relating to the state of the environment in the 15 km. radius
       was submitted before the EAC without there being any primary or
       secondary data collection. The EAC however came to the conclusion
 C     that the impact would be minimal. The additional environmental safeguards
       proposed by the EAC have no bearing on the peculiar conditions of the
       proposed airport at Mopa. Ms Shenoy ultimately urged that no effective
       mitigating measures can be implemented unless:
             (i) Authentic information about flora, fauna and natural features
 D               in the study area exists;
             (ii) A scientific objective and independent assessment of the likely
                  impact of the proposed project is made; and
             (iii) A specific finding is arrived at by the EAC on whether the
 E                 damage and impact can be mitigated.
             D.1 Domain Expertise of the EAC
              23. The first aspect which merits scrutiny is the criticism leveled
       by Ms Anitha Shenoy, learned Senior Counsel against the domain
       expertise of the EAC. At the outset, it is necessary to note that the EAC
 F     (Infrastructure–2 Sector) was constituted under an order dated 7 January
       2019 of the MoEF-CC. The composition of the Committee was as follows:
             (i) Prof. T Haque, Retd. Director & CEO, Council for Social
                    Development;
             (ii) Dr N P Shukla, Ex. Chairman, MPPCB, Bhopal;
 G
             (iii) Dr H C Sharatchandra, Ex. Chairman, Karnataka, SPCB;
             (iv) Sh. V Suresh, Former CMD, HUDCO;
             (v) Dr V S Naidu, Member;
             (vi) Sh. B C Nigam, Member;
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1055
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      (vii) Dr Manoranian Hota, Member;                                         A
      (viii) Dr Dipankar Saha, Member;
      (ix) Dr Jayesh Ruparelia, Member;
      (x) Dr (Mrs.) Mayuri H Pandya, Member;
      (xi)    Dr M V Ramana Murthy, Member;                                     B
      (xii)   Representative of School of Architecture and Planning,
              New Delhi, Member (to be nominated);
      (xiii) Addl. Director/Director/Advisor of MoEF& CC, Member
             Secretary.
                                                                                C
         24. The EAC has a vital role in conducting the appraisal of proposed
projects in terms of their environmental impact and consequences. The
EAC is intended to be an expert body. The members of the EAC are
expected to bring to the deliberations of the body their knowledge and
domain expertise. The composition of the EAC as noted above indicates
                                                                                D
that it comprises of experts with a scientific background as well as persons
having domain knowledge on matters pertaining to the environment.
Among the members of the EAC were personswho had a background
of service in the State and Central Pollution Control Boards, the Indian
Forest Service, MoEF-CC and the National Institute of Ocean
Technology. The constitution of the Committee cannot be faulted on the          E
ground that as a body, the EAC lacked domain expertise. As a Committee
which deals with infrastructure projects, the body as constituted also
comprises of persons with relevant background and experience.
Ultimately, the legitimacy of the decision which has been arrived at by
the EAC will be assessed during the course of the judgment. At this
                                                                                F
stage, we are not inclined to accept a generalized challenge on the ground
that the members of the EAC lacked domain expertise.
       25. It is necessary to emphasis two facets:First, under clause
4(vii) of the order dated 7 January 2019 constituting the EAC, the
chairperson is empowered to co-opt an expert as a member for a
particular meeting of the Committee. Infrastructure projects which the          G
EAC is called upon to assess and appraise do not fall into one specific
mould. Hence, the EAC should engage with the enabling provision which
has been made in clause 4(vii) to co-opt experts. The exercise of this
enabling discretion will facilitate the work of the EAC by allowing for
the benefit of the knowledge and expertise of an expert in a particular         H
1056             SUPREME COURT REPORTS                            [2020] 1 S.C.R.


 A     subject area being made available to it. The failure to co-opt an expert
       does not, as a consequence, lead to the invalidation of the exercise
       conducted by the EAC. But the desirability of co-opting experts needs
       to be underscored so as to bring a diversity of experience in the work of
       the EAC. Second, the composition of the EAC is dominated in a large
       measure by retired officials drawn from the Pollution Control Boards in
 B
       the Centre and State and from former officials of the MoEF-CC. In the
       composition of the EAC, the Union Government should travel beyond
       former officials of the Pollution Control Boards and Ministries. Without
       disparaging their credentials or their experience, it is nonetheless desirable
       that the members of the EAC should comprise of a cross section of
 C     persons drawn from different specialties having a bearing on
       environmental protection. Where the EAC has to deal with infrastructure
       projects, it is of course necessary to include persons who are familiar
       with the need for a balanced growth of infrastructureconsistent with
       environmental protection.
 D            26. We strongly commend to the Union Government the need to
       ensure in the composition of the EAC the inclusion of persons with
       specialized knowledge of diverse disciplines in relation to environmental
       protection. Having commended such an exercise to the Union government,
       we would leave the matter there. As we have observed earlier, the
       challenge to the minutes of the 23April 2019 must be addressed on merits,
 E     there being no reasonable basis for this Court to conclude that the EAC
       lacked the expertise to make its recommendations.
              D.2 Conflict of interest
              27. The second preliminary point that was urged by Ms Shenoy
 F     was of a conflict of interest in the role and position of EIL as an EIA
       consultant as well as an independent engineer for the project. The Attorney
       General for India in his written note of submissions on behalf of the
       State of Goa has submitted that EIL was appointed as a consultant for
       preparing the EIA report in 2012. The assignment of EIL concluded
       upon the issuance of an EC by MoEF-CC on 28 October 2015. Thereafter,
 G     the Government of Goa floated a tender for the appointment of an
       independent engineer to supervise the work of construction in 2017. EIL
       secured the bid and came on board as an independent engineer in
       December 2017. After the judgment of this Court dated 29 March 2019
       by which the EAC was directed to revisit the EC conditions, the
 H     Government of Goa sought the assistance of EIL which was the author
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1057
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

of the EIA report in presenting its case before the EAC. Hence, from           A
the facts which have been set-forth before the Court by the learned
Attorney General, it becomes clear that EIL was appointed as an
independent engineer for the project only after the EC had been granted
on 28 October 2015 and in a competitive tendering process. The role of
the independent engineer is to supervise the construction of the airport
                                                                               B
in accordance with the ICAO standards. Certification and licensing of
the airport is in the domain of the Director General of Civil Aviation 15 of
the Government of India. Compliance with environmental conditions
contained in the EC is monitored by the regional office of the MoEF-CC
at Bengaluru. Moreover, there is merit in the submission which was
urged by Ms ANS Nadkarni, learned Additional Solicitor Generalappearing        C
for the MoEF-CC that the decisionin regard to the grant of an EC rests
with MoEF-CC. The fact that EIL whose services were engaged as an
EIA consultant was subsequently appointed as an independent engineer
after the initial grant of an EC will not result in the invalidation of the
EC.
                                                                               D
        D.3 Western Ghats and ESAs
        28. Addressing the concerns of Ms Anitha Shenoy in relation to
the Western Ghats and the ESAs, Mr Nadkarni urged that the scope of
the Kasturirangan Committee reportwas to suggest an all-round and
holistic approach for sustainable and equitable development while keeping      E
in focus measures toconserve, protect and rejuvenate the ecology in the
Western Ghats. The HLWG, with the aid of the National Remote Sensing
Centre16 developed a scientific and objective methodology for identifying
ESAs in the Western Ghats. In doing so, the HLWG bore in mind diverse
parameters including forest and vegetation types, natural and cultural
landscapes, forest fragmentation, biological richness, village boundaries,     F
population density, protected areas, wildlife corridors and world heritage
sites among other considerations. Ten ESAs falling within the study area
have been disclosed in the report along with mitigation measures. It was
urged that upon detailed discussion, it was found that the impact on
these ESAs, as a result of the project, would be minimal. The area where       G
the project site is located, it was urged, has not been identified as an
ESA. The nearest village identified in the State of Maharashtra – Galel
– is at an aerial distance of 4.1 km from the boundary of the project site.
15
     DGCA
16
     NRSC
                                                                               H
1058             SUPREME COURT REPORTS                           [2020] 1 S.C.R.


 A     Mr Nadkarni rebutted the contention that the project would impinge upon
       wildlife corridors. The nearest identified corridor, it was submitted, is on
       the boundary of the States of Goa, Karnataka and Maharashtra which is
       far away from the project site.
              29. Volume-I of the report of the Kasturirangan Committee on
 B     the Western Ghats dated 15 April 2013 contains a summary of the
       recommendations. The report notes that the Western Ghats region
       straddles six states of which 60,000 square kms representing 37 per
       cent of the geographical coverage of the Western Ghats has been identified
       as an ESA. In that context, the report notes:
 C           “About 60,000 km2 of natural landscape (approximately 37% of
             the total geographical area of Western Ghats Region) has been
             identified as Ecologically Sensitive Area (ESA) by HLWG, which
             represents more or less a contiguous band of vegetation extending
             over a distance of 1500 km across 6 States of Western Ghats
             region and includes Protected Areas and World Heritage Sites.
 D           The demarcation unit of ESA is the village. IRS LISS III derived
             spatial layers on vegetation type and landscape level indices (with
             a fine spatial resolution of 24 m) were used as the basis for
             identification of ecologically sensitive areas (ESAs).
             To facilitate sustainable development in the WG region, which is
 E           inhabited by about 50 million people, the non ESA comprising
             mostly cultural landscape is also demarcated. HLWG recommends
             that the Central government should immediately notify the ESA
             area, demarcated by HLWG in public interest. The need for urgent
             action is evident. In this notified area, development restrictions as
 F           recommended in this report will apply.”
              In its recommendations dealing with restrictions on development
       in the proposed ESAs, the report notes:
             “HLWG is recommending a prohibitory and regulatory regime in
             ESA for those activities with maximum interventionist and
 G           destructive impact on the ecosystem. All other infrastructure
             development activities, necessary for the region, will be carefully
             scrutinized and assessed for cumulative impact and development
             needs, before clearance.”
             Among the recommendations of the HLWG are the following:
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1059
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      “All other infrastructure and development projects/schemes should          A
      be subject to environment clearance under Category ‘A’ projects
      under EIA Notification 2006.
      All development projects, located within 10 km of the Western
      Ghats ESA and requiring Environment Clearance (EC), shall be
      regulated as per the provisions of the EIA Notification 2006.”             B
       30. Chapter IV of the Kasturirangan Committee reportexplained
the procedure adopted to define and demarcate the boundaries of the
Western Ghats for identifying ESAs, in the absence of an accepted
definition of Western Ghats. Chapter V dealt with the need for a scientific,
objective and practical strategy for delineating ESAs within the natural         C
landscape with the village as a unit. In that context, the report notes:
      “The results obtained based on the methodology adopted by
      HLWG are analyzed for 188 talukas in terms of the area covered
      under ESAs and number of villages falling under ESA. Maps of
      Western Ghats showing vegetation and land cover classes, natural           D
      and cultural landscapes, biodiversity richness, fragmentation and
      human population density and ESA, and Maps of each of Six
      States showing natural and cultural landscapes and ESAs are also
      provided.”
       Chapter III of the report analyses the impact of climate change           E
on the ecology of the Western Ghats. Explaining the criteria which it had
adopted in demarcating the Western Ghats, the report of the
Kasturirangan Committee reportnotes :
      “HLWG, in the absence of geologically and gemorphologically
      sound criteria in demarcating WG, decided to adopt the criteria            F
      followed by the Western Ghats Development Programme of
      Planning Commission which defined WG in terms of geology
      conceptually, but has taken altitude as the criterion for identification
      of talukas/blocks under Western Ghats Development Programme
      of Planning Commission as recommended by High Level
      Committee, because the Ghats are usually 760-915 m high. All               G
      those talukas/blocks at 600 m and above elevation and those talukas
      having more than 20% of the area at 600 m and above elevation
      that are contiguous to higher altitudes and formed part of the
      administrative boundaries of Western Ghats Development
      Programme are listed under Western Ghats Development
                                                                                 H
1060               SUPREME COURT REPORTS                          [2020] 1 S.C.R.


 A              Programme. This criterion has geological connotation – that at
                600 m on the east the WG springs from Deccan Plateau, on an
                average the mean elevation of WG all along its length from north
                to south is greater than 600 m, and most of the Ghats have height
                of over 600 m.”
 B              31. Adverting to the biodiversity of the Western Ghats, the report
       notes:
                “The Western Ghats has unique taxonomic hierarchies, remnant
                ecosystems and strong endemic associations. The sholas,
                mangroves, kans, dry evergreen forests, swamps, reeds and
 C              riverine belts represent the unique ecosystems. The forests of
                WG are some of the best representatives of non-equatorial
                evergreen forests in the world. The resource value of this mega
                diversity centre spans from timber-non timber category through
                wilderness–ecotourism to gene pools of plants of medicinal-
                aromatic-food-industrial value…
 D
                Floristically the Western Ghats is one of the richest areas in the
                country and harbours as many as 4000-4600 species of flowering
                plants of which 56 generic and 2100 species are endemic.”
             32. The HLWG has catalogued three talukas of Goa as ESAs.
 E     These are tabulated as follows:

       State          District    Taluka      Taluka      ESA          No. of Villages
                                              Area                     with ESA
                                              (km2 )
       Goa            North Goa   Satari      515         406          56

                      South Goa   Kankon      362         284          5
 F
                                  Sanguem     872         771          38

       Goa                                    1,749       1,461        99

       Total



 G
             In the district of Sindhudurg in Maharashtra, five talukas
       namely:Devgad, Kankavli, Kudal, Sawantwadi and Vaibhavvadi have
       been demarcated as ESAs.


 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1061
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      33. Figure 18 in the report of the HLWG which demarcates   A
Elephant and Tiger corridors which is reproduced below:




                                                                 B




                                                                 C




                                                                 D




                                                                 E




                                                                 F




                                                                 G




                                                                 H
1062            SUPREME COURT REPORTS                         [2020] 1 S.C.R.


 A          34. Figure 21 delineates the natural and cultural landscapes in the
       Western Ghats region of Goaand is reproduced below:




 B




 C




 D




 E




 F




 G




 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1063
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      35. The ESAs in the Western Ghats region of Goa are depicted in   A
Figure 22 of the Kasturirangan Committee reportwhich is as follows:




                                                                        B




                                                                        C




                                                                        D




                                                                        E




                                                                        F




                                                                        G




                                                                        H
1064            SUPREME COURT REPORTS                      [2020] 1 S.C.R.


 A           36. Figure 23 provides a depiction of the natural and cultural
       landscapes in the Western Ghats region of Maharashtra, which is as
       follows:



 B




 C




 D




 E




 F




 G




 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1065
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      D.4 Forestland and flora and fauna                                         A
        37. The criticism leveled against the recommendations of the EAC
in its appraisal of the impact of the project on forested areas has been
dealt with in the submissions as follows:
      (i) Details of forested land as marked in working plans were
          obtained by the project proponent from the Governments of              B
          Goa and Maharashtra, details of which have been recorded
          by the EAC in its minutes of 23 April 2019, within a 15 km.
          radial distance from the project site;
      (ii) Concerns about non-disclosure were addressed by the project
           proponent by giving details of forests with impacts and               C
           mitigation measures;
      (iii) Remote sensing has been done by the project proponent as
            mentioned in Annexure IX of the EIA report.Ground truthing
            is usually done on site, performing surface observations and
            measurements of various properties and features of the ground        D
            on the remotely sensed digital image. In this case, the airport
            operation is within the boundaries of the project site and details
            of forest, springs, wetlands etc. were also given and discussed
            in the EAC; and
      (iv) Impact of the airport operations on the air and noise                 E
           environment will generally extend until an aircraft gains a
           height of 1000 feet.According to the Airport Guidance Manual,
           emissions from aircraft at a height upto a 1000 feet above
           ground will extend typically around 3km from departure or, in
           the case of arrivals 6 km from touchdown. Since the airport           F
           site is at a height of 155 metres above MSL, the aircraft will
           gain a height of 1000 feet during departure within the project
           site. Aircraft operations follow a dedicated path called the
           funnel, which in this case has an east-west orientation for
           landing and takeoff. The impact on forests which are primarily
           on the northern and southern sides of the airport site in Goa         G
           and Maharashtra and their ecological features will be minimal.
           The project proponent has relied on a Google image of the
           Mopa region indicating a super imposed flight path for landing
           and takeoff at the airport which is extracted below:
                                                                                 H
1066            SUPREME COURT REPORTS                           [2020] 1 S.C.R.


 A




 B




 C




              Similarly, an image indicating the location of all ESAs within 10km.
 D     radius of Mopa airport has been relied upon by the project proponent:




 E




 F




 G


              38. The criticism that the EAC has conflated the issue of the
       felling of trees with the environmental impact on 42 forests has been
       addressed in the submissions placed before this Court by Mr ANS
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1067
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

Nadkarni, learned Additional Solicitor General appearing for MoEF-CC.          A
It has been submitted that:
      (i)     The forest eco-system comprises mainly of flora and fauna
              in the environmental settings of air, water and land. The
              impacts of all these elements have been assessed and
              mitigation measures have been proposed;                          B
      (ii)    The EAC took due cognizance of the presence of forestland
              and also observed that though a significant number of trees
              were required to be felled, this was a requirement in the
              wake of an identified project site. In that context, it made a
              reference to the compensatoryafforestationprogramme              C
              required in the ratio of 1:10;
      (iii)   The EAC has noted that the airport site does not fragment
              the forest areas and does not restrict the movement of fauna.
              The airport site is predominantly a plateau and the forest
              cover is not contiguous to it. With a boundary wall              D
              surrounding the airport, there is no possibility of animals
              being endangered by entry into the project site;
      (iv)    The impact of airport operations on the soil and water
              environment has also been assessed and necessary
              measures put into place by the EAC for protection and            E
              conservation; and
      (v)     Nearly 3 lakh trees are to be planted: 50,000 at the site and
              2,50,000 in nearby villages within15 km duly supervised by
              the Biodiversity board. Besides this, another 2,50,000
              treesare to be planted and monitored by the DGCA. The            F
              EAC has mandated the plantation of native species and
              fruit bearing saplings to enable residents depending on
              agriculture to derive economic benefits while at the same
              time preserving the biological environment to birds.
      39. MoEF-CC has also responded to the criticism against the
                                                                               G
approach adopted by the EAC in regard to avi-faunal studies and data.
According to the submission, the project proponent presented data drawn
from the ZSI and other sources. It has been submitted that the appellant
while referring to the fauna species from ZSI data has referred to
“external distribution” in most cases. However, ZSI data categorically
mentions the “sighting area/localities” where specific species have been       H
1068              SUPREME COURT REPORTS                          [2020] 1 S.C.R.


 A     actually sighted; all these locations are notably far away from the project
       site. Moreover, as an example, it has been submitted that the appellant in
       adverting to the sighting of leopards in Goa and Maharashtra did not
       limit the submissions to the study area but to the entire territory of the
       States of Maharashtra and Goa. ZSI studies on the fauna of Maharashtra
       records leopard sightings in places like the Melghat Tiger Reserve,
 B
       Tadoba-Andhari Tiger Reserve, Pench National Park, Sanjay Gandhi
       National Park, Bhimashankar Wildlife Sanctuary, and the Phansad Wildlife
       Sanctuary among others. None of these sites fall within the study area.
       Similarly, the ZSI publication on fauna of Goa records sightings of leopards
       in places like Molem National Park, Cotigao Wildlife Sanctuary and
 C     Bondla Wildlife Sanctuary, not of which fall within the study area.
       Moreover, in the Wildlife Institute of India17report (2010), the presence
       of tigers has been recorded in Molem Wildlife Sanctuary and in the
       forests of Ponda and Sanguen Tehsil which are not within a 10 km radius
       of proposed Mopa airport. Relevant data drawn from the WII and the
       Wildlife Trust ofIndia (2017) on the presence of tigers and elephants has
 D
       been relied upon.
               40. The submission which has been urged on behalf of MoEF-CC
       is that the distance of the ESA/ESZ is a prime factor in determining the
       likely impact of the project activities on the environment. On examination
       by the EAC, it has been found that neither the project site nor the villages
 E     under the study area fall in any ESZ. Moreover, of the 10 ESA villages
       in Maharashtra falling within a 10 km. radius of the project site, the
       nearest village (Galel) is about 4.1 kms from the boundary of the project
       and is located in the northern direction. The runway of the proposed
       airport has an east-west orientation. Beyond the runway of 3.75 km.,
 F     flight operations at an altitude of about 1000 feet would have a minimally
       adverse impact on the flora and fauna surrounding the airport. Moreover,
       the common faunal species would primarily be restricted to the forest
       areas. The proposed airport site is not home to any of these species. It
       was, in this context that the EAC has observed that the project site does
       not fragment any forest area. The mitigation measures proposed in the
 G     EC conditions as well as the NGT directions stipulate measures for
       minimizing the impact on biodiversity. The project proponent would be
       bound to follow DGCA and ICAO aircraft strike hazard management
       guidelines including the setting up of an Airfield Environment Management
       Committee. Moreover, it has been submitted that EIL had stated the
 H     17
            WII
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1069
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

migration status of various species of birds in the EIA report. This        A
information was updated with regard to the migratory status of additional
fauna found in the study area in supplementary Form1. However, no set
routes of flyways were observed near the airport site. DGCA has
published the National Aviation Safety Plan 2018-2020 emphasizing avi-
faunal and wildlife management in airports. MoEF-CC has annexed to
                                                                            B
its submissions, DGCA circulars/directions on the following aspects which
would have to be implemented by the concessionaire:
      a) Climate Change Initiatives and Local Air Quality Monitoring
         in Civil Aviation, 2015;
      b) Noise Management of Aircraft Operations at Airports, 2014;         C
      c) Carbon Off-setting and reduction scheme for International
         Aviation;
      d) Guidance on Wildlife Hazard Management;
      e) National Aviation Safety Plan, 2018-2020, 2019.                    D
      41. In regard to the concerns which emerged during the course of
the public consultation, it has been submitted by MoEF-CC that the
updated report submitted by the project proponent took into account
these concerns which primarily are comprised within two categories
(environment and livelihood).The project proponent made a detailed
                                                                            E
presentation before the EAC on these concerns and the action plans
were discussed in the EAC meeting. The EAC has stipulated the
implementation of the environment management plan for addressing the
concerns which were raised during the course of the public hearing.
According to the Airport Guidance Manual, the concerns of the public
which were expressed during public consultation must be addressed by        F
the applicant either through an updated EIA and EMP or through a
supplementary report. The project proponent has done so through updated
information.
       42. During the course of the judgment which was rendered by
this Court on 29 March 2019, certain flaws were noticed in the process      G
leading up to the grant of an EC on 28 October 2015. The project
proponent had not complied with its obligation to make a full disclosure
of information on material aspects of the environment in Form1 as an
intrinsic part of the EIA process. This Court specifically recorded its
concerns on vital aspects which had not been adequately addressed by
                                                                            H
1070            SUPREME COURT REPORTS                            [2020] 1 S.C.R.


 A     the EAC. Having noticed the flaws in the process and the deficiencies
       in the decision making process of the EAC, the Court directed the EAC
       to revisit the recommendations made by it for the grant of an EC including
       the conditions which it had formulated, having regard to the specific
       concerns which were highlighted in the judgment. Thereafter if the EAC
       were to allow the construction to proceed, it was directed to impose
 B
       additional conditions to protect the terrestrial eco-systems. The EAC
       was under a specific mandate to lay down conditions pertaining to air,
       water, noise, land and the biological and socio-economic environment.
       During the course of this judgment, we have traced the process as it
       evolved before the EAC following the earlier directions of this Court.
 C     The net result of the process is that the concessionaire has been subjected
       to a slew of mitigatory conditions: 53 in the original EC, 16 at the behest
       of NGT and 40 imposed by the EAC in the second round. On a reading
       of the process leading upto the present proceeding, it cannot be said that
       the EAC has, in its appraisal process, ignored the concerns which were
       highlighted by this Court. Ms Anitha Shenoy, learned Senior Counsel, as
 D
       we have noted earlier, focursed her submissions on four areas namely
       (i) Forests; (ii) ESAs; (iii) Western Ghats; and (iv) Flora and Fauna. The
       EAC has adequately addressed these concerns and laid down additional
       conditions to ensure the adequate protection of the environment.
             43. The Airport Guidance Manual published by MoEF in February
 E     2010 contains significant points for guidance having a bearing on the
       controversy which has been raised in the present case. In relation to the
       study area, the Manual states:
             “Primary data through measurements and field surveys; and
             secondary data from secondary sources are to be collected in the
 F           study area within 10 km radius from Aerodrome Reference Point
             (ARP). Primary data should cover one season other than monsoon
             and secondary data is to cover one full year. The basis for selection
             of these criteria is that the aircraft gains a height of 1000ft in this
             area below which noise and air pollution are generated maximum
 G           during its take off stage. Secondary data should be collected
             within 15 km aerial distance for the parameters as specifically
             mentioned at column 9 (III) of Form I of EIA Notification, 2006.
             Details of secondary data, the method of collection of secondary
             data, should be furnished. Similarly the proposed locations of
             monitoring stations of water, air, soil and noise etc should be shown
 H           on the study area map.”
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1071
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

       The study area in other words, comprises of a radial distance of           A
10 kms. from the Aerodrome Reference Point.The Manual indicates
that the basis for selection of the criteria is that an aircraft gains a height
of 1000 feet in this area and the maximum impact of noise and air pollution
is generated during the takeoff stage.The Aircraft Guidance Manual
also states that:
                                                                                  B
       “Aircraft engines produce emissions that are similar to other
       emissions resulting from any oil based fuel combustion. These,
       like any exhaust emissions, can affect local air quality at ground
       level. It is emissions from aircraft below 1,000ft, above the ground
       (typically around 3km from departure or, for arrivals, around 6km
       from touchdown) that are chiefly involved in influencing local air         C
       quality.”
This is again emphasized in the following extract:
       “Ambient Air Quality (AAQ) is important for the airport projects.
       The significance of aviation’s impact on air quality will vary             D
       depending on many other factors such as, background pollution
       levels, other sources of pollution, weather and proximity of
       residential areas.
       Aircraft engines produce emissions that are similar to other
       emissions resulting from any oil based fuel combustion. These,             E
       like any exhaust emissions, can affect local air quality at ground
       level. It is emissions from aircraft below 1,000ft, above the ground
       (typically around 3km from departure or, for arrivals, around 6km
       from touchdown that are chiefly involved in influencing local air
       quality. These emissions disperse with the wind and blend with
       emissions from other sources such as domestic heating emissions,           F
       factory emissions and transport pollution.
       The local air quality relevant emissions attributed to aircraft
       operations at airports are oxides of nitrogen (NOx), carbon
       monoxide (CO), Unburnt hydrocarbons (NMHC and VOCs),
       sulphur dioxide(SO2), particulate matter (PM10 and PM2.5).                 G
       Aircraft engines, auxiliary power units, apron vehicles, de- icing,
       and apron spillages of fuel and chemicals emit these pollutants.
       Local factors influence the significance of individual emissions
       for each airport, but often NOx is by far the most abundant and is
                                                                                  H
1072                SUPREME COURT REPORTS                           [2020] 1 S.C.R.


 A              considered the most significant pollutant from an air quality stand
                point.
                Baseline data of these parameters extending over an area of 10km
                radial distance from ARP of the project by observation at a number
                of locations, predominantly in the windward direction duly taking
 B              into account changes in predominant wind direction in the monsoon
                period and changes in humidity in atmosphere. Specific importance
                is to be attached to areas in close proximity of project up to 3km
                is essential, considering the mobile source of emission such as
                aircraft.”
 C            44. A comprehensive process has been followed by the EAC
       bearing in mind the requirements of the Airport Guidance Manual. The
       EAC took note of the presence of reserved forests and of ESAs in the
       Western Ghats and deliberated on the impact of the construction and
       operation of the proposed airport on flora or fauna, hydrological systems
       and climatic variations. The process which has been adopted by the
 D     EAC and its ultimate conclusions must be scrutinized, in the course of
       judicial review, in the context of the limitations which are attached to the
       court conducting amerits based review. In Lafarge Umiam Mining
       Private Limited v Union of India,18 an application was made under
       the 1994 EIA notification for the grant of an EC to a proposed limestone
 E     mining project at Nongtrai Village, East Khasi Hills District Meghalaya.
       EC was granted for the project in 2001. A three judge Bench of this
       Court rejected the challenge and upheld the grant of the EC for the
       proposed project. Chief Justice S H Kapadia, speaking for the Court,
       formulated the standard of judicial review which must be applied in cases
       relating to the environment in the following terms:
 F
                “In the circumstances, barring exceptions, decisions relating to
                utilisation of natural resources have to be tested on the anvil of
                the well-recognised principles of judicial review. Have all the
                relevant factors been taken into account? Have any extraneous
                factors influenced the decision? Is the decision strictly in
 G              accordance with the legislative policy underlying the law (if any)
                that governs the field? Is the decision consistent with the principles
                of sustainable development in the sense that has the decision-
                maker taken into account the said principle and, on the basis of
                relevant considerations, arrived at a balanced decision? Thus, the
       18
 H          (2011) 7 SCC 338
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1073
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

      Court should review the decision-making process to ensure that          A
      the decision of MoEF is fair and fully informed, based on the
      correct principles, and free from any bias or restraint.”
      The EAC has accounted for the relevant factors outlined by this
Court in its previous judgment in the assessment leading to the grant of
the EC.                                                                       B
       45. The evaluation of merits is a matter which primarily rests with
an expert authority. The court can certainly supervise procedural
compliance and ensure that all necessary inputs which are required to
be factored into the decision-making process have been duly borne in
mind. Once this has been done, the court must be circumspect in micro-        C
managing the decision-making process by the EAC by substituting its
own opinion for that of the EAC. Undoubtedly, no process can be perfect
or free from studied criticism. Ms Anitha Shenoy, learned Senior Counsel
has attempted to perform such an exercise when she submitted that the
collection of primary faunal data from a nearby village and secondary
data from ZSI sources was not an adequate means of dealing with the           D
concerns expressed by this Court. In assessing these criticisms, we must
equally be cognizant of the fact that by the judgment of this Court dated
29 March 2019, the EAC was required to carry out the exercise within
a period of one month from the receipt of the order of this Court. The
Court did not quash the EC but directed that it should remain under           E
suspension until the EAC revisited its recommendations in the light of
the concerns which were expressed by this Court. Having assessed the
process which took place following the judgment of this Court and the
outcome, it would be difficult for this Court to hold that it fails to meet
the standards which the court applies in the course of judicial review in
environmental matters.                                                        F

      E. Directions
       46. For the above reasons, the minutes of the meeting of the EAC
dated 23 April 2019 are taken on record as prayed for. The additional
conditions which have been imposed by the EAC shall, together with the        G
original conditions of the EC dated 28 October 2015 and the directions
issued by the NGT be cumulatively observed.The conditions cumulatively
imposed for the grant of an EC, have been set out below:
      I. Conditions imposed by the EC dated 28 October 2015
                                                                              H
1074          SUPREME COURT REPORTS                        [2020] 1 S.C.R.


 A     A. SPECIFIC CONDITIONS:
       (i)      ‘Consent to Establish’ shall be obtained from State Pollution
                Control Board under the Air (Prevention and Control of
                Pollution) Act, 1981 and the Water (Prevention and Control
                of Pollution) Act, 1974.
 B     (ii)     The Project Proponent shall ensure availability of adequate
                land at the junction of the Mopa Airport road and Mumbai/
                Goa NH-17 for traffic circulation/management and to
                provide for all the traffic interchanges and proposed clover.
       (iii)    The approach and exit roads to the Airport shall be approved
 C              from the NHA land should be according to IRC norms.
       (iv)     A perusal of the Topo sheet superimposed on the runway
                area indicates that the extreme end of the runway is covering
                the drainage area partly. The drainage area which is under
                the runway shall be channelized. The area between the
 D              parallel taxiway and runway shall be handled carefully to
                drain the water from the area in the outfall 2.
       (v)      The PP shall submit the site clearance certificate from
                Directorate General of Civil Aviation (DGCA), before
                commencement of work at the project site.
 E
       (vi)     Sewage and other liquid effluent generated from the airport
                including from the existing terminal should be treated
                according to the norms laid down by the State Pollution
                Control Board. The treated sewage shall be recycled for
                flushing/gardening. Proper Dual plumbing shall be provided.
 F
       (vii)    The solid waste generated shall be properly collected,
                segregated and disposed according to the provisions of Solid
                Waste (Management and Handling) Rules, 2000. The
                project proponent shall make provisions for drinking water
                at convenient places for passengers and also at the
 G              cafeterias as to reduce generation of solid wastes including
                PET bottles.
       (viii) Installation and operation of DG sets shall comply with the
              guidelines of CPCB.
       (ix)     Parking provision shall be provided according to the National
 H              Building Code of India, 2005.
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1075
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

    (x)     Water conservation fixtures shall be provided and water         A
            balance shall be maintained through verifiable metering for
            fresh raw water, recycled as well as rain water harvesting.
    (xi)    Necessary permission shall be obtained for drawing of
            ground water from competent authority prior to
            construction/ operation of the project.                         B
    (xii)   The land use around the Airport complex shall be regulated
            through a plan to control unauthorized development which
            may create problems in the operation of the Airport.
    (xiii) The wastewater from hangers shall be tested for presence
           of heavy metals, if any, and shall be treated in STP. The        C
           treated waste water shall be used for gardening/ flushing.
    (xiv) Rain water harvesting shall be provided to recharge the
          ground water.
    (xv) Energy conservation to the extent of at least 20% shall be         D
         incorporated including water conservation (reuse/ recycle,
         rain water harvesting and water efficient fixtures) and other
         green building practices for various buildings proposed within
         the airport complex. The PP shall consider ECBC Guidelines
         2009 to achieve energy efficiency. The energy conservation
         measures shall be subject to periodic verification by the          E
         competent Energy Conservation/Efficiency authority in the
         State.
    (xvi) The project proponent shall prepare a detailed traffic
          management plan to take care of increased vehicular traffic
          which should also cover/clearly delineate widening/               F
          increasing the existing roads and associated road
          infrastructure approving/installation of road safety features/
          pedestrian facility/FOB/under passes etc (that can be done
          by carrying out road safety audits). Measures shall be taken
          to prevent encroachment along/within the ROWs on
                                                                            G
          connecting/main arterial roads.
    (xvii) All the recommendations of the EMP shall be complied with
           in letter and spirit. All the mitigation measures submitted in
           the EIA report shall be prepared in a matrix format and the
           compliance for each mitigation plan shall be submitted to
           RO, MoEF&CC along with half yearly compliance report.            H
1076      SUPREME COURT REPORTS                             [2020] 1 S.C.R.


 A     (xviii)   The responses/commitments made during public hearing
                 shall be complied with in letter and spirit.
       (xix)     Project Proponent shall install noise level display system.
                 Noise level shall be monitored regularly in all seasons
                 (different meteorological conditions) within the compound
 B               as well as nearby habitations and it shall be ensured that
                 the noise level is within the prescribed limits. During night
                 time the noise levels measured at the boundary shall be
                 restricted to the permissible levels to comply with the
                 prevalent regulations.
 C     (xx)      The location of monitoring stations and monitoring of noise
                 level during day and night shall be in accordance with the
                 CPCB guidance document “Requirement and procedure
                 for monitoring Ambient Noise Level due to aircraft”
                 published on 25th June 2008.
 D     (xxi)     Construction spoils, including bituminous material and
                 other hazardous materials, must not be allowed to
                 contaminate watercourses and the dumpsites for such
                 material must be secured so that they should not leach
                 into the ground water.

 E     (xxii)    Any hazardous waste generated during construction phase,
                 should be disposed off as per applicable rules and norms
                 with necessary approval of the SPCB.
       (xxiii)   Under the provision of Environment (Protection) Act,
                 1986, legal action shall be initiated against the project
 F               proponent if it was found that construction of the project
                 has been started without obtaining environmental
                 clearance.
       (xxiv)    The project proponent will set up separate environmental
                 management cell for effective implementation of the
                 stipulated environmental safeguards under the supervision
 G
                 of a Senior Executive.
       (xxv)     Corporate Environment Responsibility:
                 a) The Company shall have a well laid down Environment
                     Policy approved by the Board of Directors.
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1077
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

         b) The Environment Policy shall prescribe for standard           A
             operating Process/procedures to bring into focus any
             infringements/deviation/violation of the environmental
             or forest norms/conditions.
         c) The hierarchical system or Administrative Order of
             the company to deal with environmental issues and            B
             for ensuring compliance with the environmental
             clearance conditions shall be furnished.
         d) To have proper checks and balances, the company
            shall have a well laid down system of reporting of
            non-compliances/violations of environmental norms to          C
            the Board of Directors of the company and/or
            shareholders or stakeholders at large.
        B. GENERAL CONDITIONS:
        (i)     Provision shall be made for the housing of
                construction labour within the site with all necessary    D
                infrastructure and facilities such as fuel for cooking,
                mobile toilets, mobile STP, safe drinking water,
                medical health care, creche etc. The housing may
                be in the form of temporary structures to be
                removed after the completion of the project.              E
        (ii)    A First Aid Room will be provided in the project
                both during construction and operation of the project.
        (iii)   All the topsoil excavated during construction
                activities should be stored for use in horticulture/
                landscape development within the project site.            F
        (iv)    Disposal of muck during construction phase should
                not create any adverse effect on the neighbouring
                communities and be disposed taking the necessary
                precautions for general safety and health aspects
                of people, only in approved sites with the approval       G
                of competent authority.
        (v)     The diesel generator sets to be used during
                construction phase should below Sulphur diesel type
                and should conform to Environment (Protection)
                Rules prescribed for air and noise emission               H
1078   SUPREME COURT REPORTS                          [2020] 1 S.C.R.


 A                standards. The diesel required for operating DG
                  sets shall be stored in underground tanks and if
                  required clearance from Chief Controller of
                  Explosives shall be taken.
         (vi)     Vehicles hired for bringing construction material to
 B                the site should be in good condition and should have
                  a pollution check certificate and should conform to
                  applicable air and noise emission standards and
                  should be operated only during non-peak hours.
         (vii)    Fly ash usage shall be explored as building material
 C                in the construction as per the provisions of Fly Ash
                  Notification of September, 1999 and amended as
                  on 27th August, 2003.
         (viii)   Ready mixed concrete must be used in building
                  construction.
 D       (ix)     Storm water control and its re-use as per CGWB
                  and BIS standards for various applications.
         (x)      Water demand during construction should be
                  reduced by use of pre-mixed concrete, curing
                  agents and other best practices referred.
 E
         (xi)     Separation of grey and black water should be done
                  by the use of dual plumbing line for separation of
                  grey and black water.
         (xii)    Use of glass may be reduced by upto 40% to
                  reduce the electricity consumption and load on air-
 F
                  conditioning. If necessary, use high quality double
                  glass with special reflective coating in windows.
         (xiii)   Roof should meet prescriptive requirement as per
                  Energy Conservation Building Code by using
                  appropriate thermal insulation material to fulfill
 G                requirement.
         (xiv)    Opaque wall should meet prescriptive requirement
                  as per Energy Conservation Building Code which
                  is proposed to be mandatory for all air-conditioned
                  spaces while it is aspirational for non-air-conditioned
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1079
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

                 spaces by use of appropriate thermal insulation         A
                 material to fulfil requirement.
        (xv)     The green belt of the adequate width and density
                 preferably with local species along the periphery
                 of the plot shall be raised as to provide protection
                 against particulars and noise.                          B
        (xvi)    Traffic congestion near the entry and exit points
                 from the roads adjoining the proposed project site
                 must be avoided. Parking should be fully internalized
                 and no public space should be utilized.
        (xvii)   The construction of the structures shall be             C
                 undertaken as per the plans approved by the
                 concerned local authorities/local administration,
                 meticulously conforming to the existing local and
                 central rules and regulations.
        (xviii) The construction material shall be obtained only         D
                from approved quarries. In case new quarries are
                to be opened, specific approvals from the
                competent authority shall be obtained in this regard.
        (xix)    Adequate precautions shall be taken during
                 transportation of the construction material so that     E
                 it does not affect the environment adversely.
        (xx)     Full support shall be extended to the officers of
                 this Ministry/Regional Office by the project
                 proponent during inspection of the project for
                 monitoring purposes by furnishing full details and      F
                 action plan including action taken reports in respect
                 of mitigation measures and other environmental
                 protection activities.
        (xxi)    A six-monthly monitoring report shall need to be
                 submitted by the project proponents to the Regional     G
                 Office of this Ministry regarding the implementation
                 of the stipulated conditions.
        (xxii)   Ministry of Environment, Forest & Climate Change
                 or any other competent authority may stipulate any
                 additional conditions or modify the existing ones, if   H
1080   SUPREME COURT REPORTS                       [2020] 1 S.C.R.


 A               necessary in the interest of environment and the
                 same shall be complied with.
         (xxiii) The Ministry reserves the right to revoke this
                 clearance if any of the conditions stipulated are
                 not complied with the satisfaction of the Ministry.
 B       (xxiv) In the event of a change in project profile or change
                in the implementation agency, a fresh reference
                shall be made to the Ministry of Environment, Forest
                & Climate Change.
         (xxv) The project proponents shall inform the Regional
 C             Office as well as the Ministry, the date of financial
               closure and final approval of the project by the
               concerned authorities and the date of start of land
               development work.
         (xxvi) A copy of the clearance letter shall be marked to
 D              concerned Panchayat local NGO, if any, from whom
                any suggestion/representation has been made
                received while processing the proposal.
         (xxvii) A copy of the environmental clearance letter shall
                 also be displayed on the website of the concerned
 E               State Pollution Control Board. The EC letter shall
                 also be displayed at the Regional office, District
                 Industries centre and Collector’s office/Tehsildar’s
                 office for 30 days.
         (xxviii) The funds earmarked for environmental protection
 F                measures shall be kept in separate account and
                  shall not be diverted for other purpose. Year-wise
                  expenditure shall be reported to this Ministry and
                  its concerned Regional Office.
         5.      These stipulations would be enforced among others
 G               under the provisions of Water (Prevention and
                 Control of Pollution) Act, 1974, the Air (Prevention
                 and Control of Pollution) Act, 1981, the Environment
                 (Protection) Act, 1986, the Public Liability
                 (Insurance) Act, 1991 and EIA Notification 2006,
                 including the amendments and rules made
 H               thereafter.
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1081
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

           6.      All other statutory clearances such as the approvals     A
                   for storage of diesel from Chief Controller of
                   Explosives, Fire Department, Civil Aviation
                   Department, Forest Conservation Act, 1980 and
                   Wildlife (Protection) Act, 1972 etc. shall be
                   obtained, as applicable by project proponents from
                                                                            B
                   the respective competent authorities.
           7.      The project proponent shall advertise in at least
                   two local Newspapers widely circulated in the
                   region, one of which shall be in the vernacular
                   language informing that the project has been
                   accorded Environmental Clearance and copies of           C
                   clearance letters are available with the State
                   Pollution Control Board and may also be seen on
                   the website of the Ministry of Environment, Forest
                   & Climate Change at http://www.envfor.nic.in.
                   The advertisement should be made within seven            D
                   days from the date of receipt of the Clearance letter
                   and a copy of the same should be forwarded to the
                   Regional Office of this Ministry.
                   …
           9.      Status of compliance to the various stipulated           E
                   environmental conditions and environmental
                   safeguards will be uploaded by the project
                   proponent in its website.”
    II. Conditions imposed by the NGT in its order dated 21
August 2018                                                                 F
     A.   AIR ENVIRONMENT
     1.   Total Suspended Particulate Matter (SPM), Respirable
          Particulate Matter (RPM) during construction phase and
          un-burnet and Hydro Carbons (HC), Lead (Pb), CO 2, SO2,
                                                                            G
          CO2, SOOT and Oxides of Nitrogen (NOx) during operation
          phase are going to be major pollutants in this kind of project,
          Besides, fugitive emissions of Volatile Organic Compounds
          (VOC) during fuel handling can be another issue for ambient
          air environment. The provision of only 6 (six) Air Quality
          Monitoring Stations is inadequate as sampling duration has        H
1082        SUPREME COURT REPORTS                          [2020] 1 S.C.R.


 A            been given as ‘twice a week, 4 weeks in a season as per
              CPCB standards for NAAQM, 1994. It would be
              appropriate if the Project Proponent establishes real time
              online continuous Air Quality Monitoring Station also which
              is connected to CPCB server and capable of monitoring all
              relevant and critical parameters and mitigation measures
 B
              taken.
       2.     Although all parameters w.r.t. ambient air parameters have
              been found to be within limits for all 6 (six) locations
              monitored, we feel for the purpose of giving/depicting holistic
              picture with regard to ambient air in the area, at least 3
 C            (three) more locations falling in the State of Maharashtra
              be also monitored and documented.
       B.     WATER ENVIRONMENT
       1.      Only two number of Rain Water Harvesting pits have been
 D            provided which we feel are not adequate and there is a
              need to place other pits at such locations as to capture all
              the excess drainage for water-recharge.
       2.     More frequent Water Quality Monitoring i.e.once every
              month may be carried out by Project Proponent at bore
 E            wells and STP discharge plants instead of 4 (four) times in
              a year as proposed.
       C.     NOISE ENVIRONMENT
       1.      It has been proposed that ambient noise levels shall be
              monitored around the premises of airport, near DG sets
 F            and at main entrance/boundary of airport once a week at 7
              (seven) locations which we feel are inadequate. Besides
              these, continuous monitoring of occupational noise exposure
              limits in such industrial environments would be appropriate
              with audible or visual alarm output capability.
 G     2.     Integrated Noise Model (INM) be more frequently used
              and mitigation undertaken during the operational phase of
              project at regular intervals.
       3.     Although ambient noise levels have been found to be within
              limits at 9 (nine) locations monitored, we feel for the purpose
 H            of giving/depicting holistic picture with regard to ambient
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1083
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

         noise levels in the area, at least 3 (three) more locations      A
         falling in the State of Maharashtra be also monitored and
         documented.
    D.   LAND ENVIRONMENT
    1.   There is a potential for impact on soil quality due to project
         related spills and leaks of fuel and chemicals and               B
         uncontrolled disposal of wastes and waste water. Adequate
         care be taken to avoid spills and leaks of hazardous
         substances and all project related wastes. Littering on sites
         and beyond the sites needs to be adequately prevented and
         controlled.                                                      C
    2.   Debris and Muck Management Plan to be prepared and
         implemented so as to avoid spillage of muck and debris on
         the slopes.
    3.   Soil conservation and stabilization measures needs to be
         undertaken by deploying both mechanical and bio-engineering      D
         methods.
    4.   Remediation, restoration and compensation needs to be
         integral part of policy so as to provide adequate relief for
         any environmental or project related disasters.
                                                                          E
    E.   BIOLOGICAL ENVIRONMENT
    1.   Efforts be made to transplant the trees to other locations in
         the same vicinity by using appropriate mechanical devices
         which are available these days.
    2.   Efforts be made to plant indigenous species which are tall       F
         in size rather than small saplings.
    3.   Concerns have been raised by appellants with regard to
         plant species ‘Dipcadi concanense’ which has been claimed
         to be a threatened plant. This claim of the appellants have
         been negated by the respondent by producing a                    G
         documentation of Botanical Survey of India, Western
         Regional Centre, Pune, Maharashtra titled as ‘A Note on
         Occurrence and Distribution of Dipcadi Concanense”. By
         invoking Precautionary Principle, we direct the Project
         Proponent to draw up a Conservancy by Plan/Scheme for
                                                                          H
1084          SUPREME COURT REPORTS                       [2020] 1 S.C.R.


 A              ‘Dipcadi concanense’ in collaboration with Forest
                Department, State of Goa and Botanical Survey of India
                and ensure its implementation.
       F.       Socio-Economic Environment
       1.       Adequate drills with respect to implementation of Disaster
 B              Management plan needs to be carried out at regular intervals
                so as to ensure preparedness and rapid response to any
                disasters both man made or natural.
       2.       Although ‘Disaster Management Plan’ as Annexure-II is
                part of EIA Report under the sub head 1.2.1-National
 C              Disasters needs further elaboration especially in terms of
                Emergency Response Measures, Rules and Responsibility,
                Mitigation, etc.”
       III.     Conditions imposed in the revised assessment of the
                EAC dated 23 April 2019
 D
       I.       STATUTORY COMPLIANCE:
       (i)      The project proponent shall obtain certificate from Chief
                Wildlife Warden (CWLW) of State through State
                Government that none of the area of the project falls in the
                notified Eco-sensitive Zone (ESZ) and no activity prohibited
 E
                in the Eco-sensitive Zone will be taken up.
       (ii)     The project proponent shall obtain Consent to Establish/
                Operate under the provisions of Air (Prevention & Control
                of Pollution) Act, 1981 and the Water (Prevention & Control
                of Pollution) Act, 1974 from the concerned State Pollution
 F
                Control Board/Committee.
       (iii)    The project proponent shall obtain necessary permission
                from the competent authority for drawing of water from
                Tillari Irrigation Canal.
 G     II.      AIR   QUALITY                MONITORING               AND
                PRESERVATION:
       (i)      The project proponent shall install system to carry out
                Ambient Air Quality monitoring for common/criterion
                parameters relevant to the main pollutants released (e.g.
 H              PM 10 and PM 2.5 in reference to PM emission and SO2,
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1085
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

            and NOx in reference to SO2 and NOx emissions) within           A
            and outside the airport area covering upwind and downwind
            directions.
    (ii)    Notification GSR 94€ dated 25.01.2018 of MoEF&CC
            regarding Mandatory Implementation of Dust Mitigation
            Measures for Construction and Demolition Activities shall       B
            be complied with.
    (iii)   Soil and other construction materials should be sprayed with
            water prior to any loading, unloading or transfer operation
            so as to maintain the dusty material wet.
    (iv)    The excavation working area should be sprayed with water        C
            after operation so as to maintain the entire surface wet.
    (v)     Excavated materials shall be handled and transported in a
            manner that they do not cause any air pollution.
    (vi)    The soil/construction materials carried by the vehicle should   D
            be covered by impervous sheeting to avoid leaking of the
            dusty materials.
    III.    WATER   QUALITY                MONITORING              AND
            PRESERVATION:
    (i)     Appropriate drainage channels need to be designed to take       E
            care of the water flow into the nearest water courses/rivers,
            etc.
    (ii)    It should be ensured that sustainable water flow in the
            various channels of watershed in the plateau is maintained.
    (iii)   Storm water drains are to be built for discharging storm        F
            water from the air-field to avoid flooding/water logging in
            project area. Domestic and industrial waste water shall not
            be allowed to be discharged into the storm water drains
            and directed to STP for treatment.
    (iv)    Proper drainage systems, emergency containment in the           G
            event of a major spill during monsoon season etc. shall be
            provided.
    (v)     The runoff from paved structures like Aprons can be routed
            through drains to oil separation tanks and sedimentation
            basins before being discharged into rainwater harvesting        H
            structures.
1086          SUPREME COURT REPORTS                          [2020] 1 S.C.R.


 A     (vi)     Run off from chemicals and other contaminants from
                aircraft maintenance and other areas within the airport shall
                be suitably contained and treated before disposal. A spillage
                and containment plan shall be drawn up and implemented
                to the satisfaction of the State Pollution Control Board.
 B     (vii)    The project activity shall conform to the General Standards
                for Discharge of Environmental Pollutants notified in the
                Environment (Protection) Rules, 1986, and amended from
                time to time.
       (viii) Rain water harvesting for roof run-off and surface run-off,
 C            as plan submitted should be implemented. Rain water
              harvesting structures shall conform to CGWA guidelines.
              Before recharging the surface run off-pre-treatment must
              be done to remove suspended matter, oil and grease.
       IV.      NOISE MONITORING AND PREVENTION:
 D     (i)      Notification GSR 568(E) dated 18.06.2018 of MoEF & CC
                regarding Ambient Air Quality Standards with respect to
                Noise in Airport Noise Zone shall be complied with.
       (ii)     Noise level survey shall be carried as per the prescribed
                guidelines and report in this regard shall be submitted to
 E              Regional Officer of the Ministry as a part of six-monthly
                compliance report.
       (iii)    Noise from vehicles, power machinery and equipment on-
                site should not exceed the prescribed limit. Equipment
                should be regularly serviced. Attention should also be given
 F              to muffler maintenance and enclosure of noisy equipments.
       (iv)     Acoustic enclosures for DG sets, noise barriers for ground-
                run bays, ear plugs for operating personnel shall be
                implemented as mitigation measures for noise impact due
                to ground sources.
 G     (v)      During airport operation period, noise should be controlled
                to ensure that it does not exceed the prescribed standards.
                During night time the noise levels measured at the boundary
                of the building shall be restricted to the permissible levels to
                comply with the prevalent regulations.
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1087
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

    (vi)    Where construction activity is likely to cause noise nuisance     A
            to nearby residents, restrict it to only during day time i.e.
            between 7 am to 6 pm.
    V.      ENERGY CONSERVATION/CLIMATE CHANGE
            MEASURES:
    (i)     Energy conservation measures like installation of LED should      B
            be integral part of the project design and should be in place
            before project commissioning.
    (ii)    Initiatives such as Green Infrastructure Development
            program, adoption of less emission intensive technologies,
            renewable energy program, electrical vehicles and Airport         C
            Carbon Accreditation need to be adopted to reduce its impact
            on climate change and Green House Gas (GHG) emissions
            as per environmental best practices governing Greenfield
            airports.
    VI.     WASTE MANAGEMENT:                                                 D
    (i)     Soil stockpile shall be managed in such a manner that dust
            emission and sediment runoff are minimized. Ensure that
            soil stockpiles are designed with no slope greater than 2:1
            (horizontal/vertical).
                                                                              E
    (ii)    The project activity shall conform to the Fly Ash notification
            issued under the EP Act of 1986.
    (iii)   The solid wastes shall be segregated as per the norms of
            the Solid Waste Management Rules, 2016. Recycling of
            wastes such as paper, glass (produced from terminals and
                                                                              F
            aircraft caterers), metal (at aircraft maintenance site),
            plastics (from aircrafts, terminals and offices), wood, waste
            oil and solvents (from maintenance and engineering
            operations), kitchen wastes and vegetable oils (from
            caterers) shall be carried out.
    (iv)    Solid inert waste found on construction sites consists of         G
            building rubble, demolition material, concrete; bricks, timber,
            plastic, glass, metals, bitumen etc shall be reused/recycled
            or managed so as to strictly conform to the Solid Waste
            Management Rules, 2016, and Construction and Demolition
            Waste Management Rules, 2016.                                     H
1088          SUPREME COURT REPORTS                          [2020] 1 S.C.R.


 A     (v)      The project proponents shall implement a management plan
                duly approved by the State Pollution Control Board and
                obtain its permissions for the safe handling and disposal of:
                a Trash collected in flight and disposed at the airport
                including segregation, collection and disposed.
 B              b Toilet wastes and sewage collected from aircrafts and
                disposed at the Airport.
                c Wastes arising out of maintenance and workshops.
                d Wastes arising out of eateries and shops situated inside
 C              the airport complex.
                e Hazardous and other wastes.
       VII. GREEN BELT:
       (i)      Green belt shall be developed in area as provided in project
                details, with native tree species in accordance with Forest
 D
                Department. The green belt shall inter alia cover the entire
                periphery of the Airport.
       (ii)     The plantation species in and around Airport site should be
                carefully chosen to avoid bird nesting and to improve pollution
                control and noise control measures. Water intensive and/or
 E              invasive species should not be used for landscaping.
       (iii)    Plantation activity should be taken up under the expert
                guidance for forest department of Goa, care should be taken
                that soil erosion measures should be taken up on priority so
                that the right mineralized soil of forest is not washed away.
 F              The plantation activity should also have an approach of soil
                conservation where planting is done along the contours
                avoiding gully formation. As far as possible monoculture
                plantation should be avoided.
       (iv)     The proposed 10 times compensatory plantation need to be
 G              monitored by the Government of Goa so that the target of
                planting 5.5 lakh saplings is achieved in a a time bound
                manner, their survival rate is monitored and mortality is
                replenished. As major chunk of 2.5 lakh of saplings is
                proposed to be done by the village level Bio Diversity
 H
HANUMAN LAXMAN AROSKAR v. UNION OF INDIA & ORS. 1089
     [DR. DHANANJAYA Y CHANDRACHUD, J.]

              Committees, it is necessary to ensure that people are largely      A
              given native species and/or fruit bearing saplings so that
              they will be able to derive economic benefits from such
              fruit crops and also such trees will provide better biological
              environment to birds.
      (v)     Top soil shall be separately stored and used in the                B
              development of green belt.
      VIII. PUBLIC HEARING AND HUMAN HEALTH
            ISSUES:
      (i)     Solution/management plan regarding redressal of all the
              concerns raised in the public hearing must be clearly spelt        C
              out in the EMP and shall be implemented in letter and spirit.
              Compliance for each mitigation plan shall be submitted to
              Regional Office, MoEF&CC along with half yearly
              compliance report.
      (ii)    Provision of Electro-mechanical doors for toilets meant for        D
              disabled passengers shall be ensured. Children nursing/
              feeding room shall be located conveniently near arrival and
              departure gates.
      (iii)   Emergency preparedness plan based on the Hazard
              identification and Risk Assessment (HIRA) and Disaster             E
              Management Plan shall be implemented.
      (iv)    Provision shall be made for the housing of construction
              labour within the site with all necessary infrastructure and
              facilities such as fuel for cooking, mobile toilets, mobile STP,
              safe drinking water, medical health care, creche etc. The          F
              housing may be in the form of temporary structures to be
              removed after the completion of the project.
      (v)     Occupational health surveillance of the workers shall be
              done on a regular basis.”
      47. We have also taken note of the assurance which has been                G
tendered on behalf of the concessionaire that it will adopt a Zero Carbon
Programme both in the construction and operational phases of the airport.
We accept the undertaking of the concessionaire and issue a direction
for compliance.
                                                                                 H
1090                SUPREME COURT REPORTS                      [2020] 1 S.C.R.


 A            48. The earlier judgment of this Court highlighted numerous
       deficiencies by the project proponent leading to the grant of the EC.
       This Court highlighted numerous concerns including the preservation of
       forests, the existence of ESAs with their attendant features and the
       impact of the proposed project on natural water channels. The Court
       also noted the abject failure of the project proponent to provide complete
 B
       information on the existence of reserved forests. In the proceedings that
       followed the judgment of this Court, the project proponent sought to
       remedy its failure by taking into account additional information on
       significant aspects of the environment. In the process leading to the
       grant of the EC as well as the lifting of its suspension by this Court,
 C     numerous mitigatory conditions have been imposed on the project
       proponent. We deem it appropriate to ensure the oversight of the project
       by a specialized body to ensure compliance with the directions
       cumulatively issued by this Court. We direct the National Environmental
       Engineering Research Institute19 to be appointed to oversee compliance
       with the directions cumulatively issued by this Court. The project
 D
       proponent shall bear the costs, expenses and fees of NEERI.
             49. The suspension on the EC shall accordingly stand lifted.The
       Miscellaneous Application is accordingly disposed of.


 E     Ankit Gyan                                           Application disposed of.




 F




 G




       19
 H          NEERI


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "environmental clearance"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.