GUPTA STEEL INDUSTRIESversusM/S. JOLLY STEEL INDUSTRIES PVT. LTD. AND ANR.
- Citation
- 1996 INSC 1098
- Decided
- 23 September 1996
- Disposal
- Disposed off
Holding
The High Court was incorrect to modify the consent decree without the parties' consent, but the Supreme Court will not interfere with the order due to the lapse of time and directs a trial‑court inquiry into possession, damages, and interest.
Summary
The parties entered into a compromise decree while an appeal was pending, obligating the respondents to deposit specified sums and the appellants to surrender possession of land and machinery. The respondents failed to deposit the amounts by the stipulated deadline; the High Court later accepted the delayed payment and ordered the appellants to pay damages for occupation. The Supreme Court examined whether the High Court could modify a consent decree without the parties' agreement and whether it could extend the time for compliance after the deadline. It held that the High Court was incorrect to modify the decree without consent, but, given the lapse of time, it would not set aside the order and instead directed the trial court to inquire into possession, damages, and the status of the deposited amount, including interest if applicable. The appeals were dismissed with no costs.
Issues considered
- Whether a High Court can modify a consent/compromise decree without the parties' agreement.
- Whether a High Court can extend the time for compliance with a compromise decree after the deadline has passed.
- Determination of damages for use and occupation of the disputed property.
- Whether interest is payable on the deposited amount if not held in an interest‑earning security.
Legislation cited
Subjects
Judgment
GUPTA STEEL INDUSTRIES A
v.
M/S. JOLLY STEEL INDUSTRIES PVT. LTD. AND ANR.
SEPTEMBER 23, 1996
[K. RAMASWAMY AND G.B. PATTANAIK, JJ.] B
Code of Civil Procedure, 1908 :
Compromise decree-Modification of-Pending the first appeal in the
High Court, a compromise decree was passed whereunder respondents were
required to deposit in t1ial cowt ce1tain amounts and the appellants to hand
c
over possession of the la11d and machine1y to the receiver-Respondents did
not deposit the amou11t within time-High Cowt accepted delayed payment
by the respondents and directed the appellant to pay damages for use and
occupation as may be detennined by civil cowt-Held, as a principle of law,
High Court was b1c01Tect in inteifering with and modifying the consent decree D
unless p01ties agree for the same-However, it would not be justified to
inteifere with the order at this distance of tim~irections given to trial court
to .conduct an inquiry whether the appellant was prevented by the respondents
to remain in possession from working out the factory and decide the question
of damages accordingly-If the amount deposited to the credit of the suit had
not been invested in interest eaming secwity, respondents would pay interest E
at the commercial rate from the date of deposit till date of judgment of the
High Court.
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 12995-
13000 of 1996 Etc.
F
From the Judgment and Order dated 18.7.96 of the Bombay High
Court in C.A. Nos. 3588/91, 1686, 3580/92 1415 and 1414 of 1993.
Bhimrao Naik and A.M. Khanwilkar for the Appellant.
Soli J. Sorabjee, J.K. Das and J. Savla for the Respondents. G
The following Order of the Court was delivered :
Leave granted.
We have heard learned counsel on both sides. H
669
670 SUPREME COURT REPORTS (1996) SUPP. 6 S.C.R.
A These appeals by special leave arise from the order of the Division
Bench of the High Court of Bombay made on July 18, 1996 in Civil
Application Nos. 3588-89/91 in FA No. 1 & 2/90.
The admitted position is that pursuant to a compromise entered into
betwe.en the parties, pending the first appeal in the High Court, a com-
B promise decree came ·to be made by the Division Bench on 12.4.1991.
Clause (2) of the Compromise Decree reads as under :
"2. (a) The parties agree that Jolly Steel Industries Pvt. Ltd. and
· Jolly Torsteel Pvt. Ltd., the respondents herein and the Original
C plaintiffs in Suit No. 446 of 1987 and Suit No. 447 of 1987,
respectively, shall between them deposit in the.Trial Court, a sum
of Rs. 15,00,000 (Rupees Fifteen Lakhs only) in the aggregate on
or before 31st May, 1991 and a further sum of Rs. 10,40,000
(Rupees Ten Lakhs and forty thousand only) on or before 29th
June, 1991;
D
(b) These amounts are to be deposited in Suit No. 446 of 1987 in
the Court of Additional Civil Judge, Senior Division, Pune, on
account of over payment by the Appellants (Original defendants)
as the defendants were not liable to pay and the Respondents
(Original plaintiffs) were not entitled to receive the same.
E
(c) The Appellants (Original Defendants) are at liberty to
withdraw the aforesaid amounts."
Admittedly, Rs.12 lakhs was deposited after expiry of the last date,
p namely, June 29, 1991, after one month. In the meanwhile, the respondents
filed an application for extension of time in the trial Court. That was
dismissed on the ground that it had no jurisdiction. Consequently, the
application came to be filed in the High Court. Similarly under Clause 5(a)
the appellants also agreed to hand over possession of the disputed land
and the machinery to the receiver on or before 31st March, 1992. In view
G of the default committed by the respondent, the appellants came to file an
application, on the basis of which the High Court passed an order to
maintain the status quo on March 27, 1992. The appellants have taken out
contempt proceedings against the respondents in which another Division
Bench of the High Court passed an order on July 18, 1996 stating that the
H respondents have prevented the appellants from taking possession due to
GUPTA STEEL INDS. v. JOLLY STEEL INDS. (P) LTD. 671
the factory having been locked by the respondent. Nonetheless, no action A
was taken on the contempt petition. In the impugned order, the Division '
Bench passed an order accepting the delayed payment by the respondents
and directed the appellants to pay damages for use and occupation as may
be determined. by the civil Court. Thus, these appeals by special leave.
As principle of law, the High Court was obviously incorrect in
B
interfering with and modifying the consent decree unless parties agree for
the same. Though it is contended by Shri Bhimrao Naik, learned .senior
counsel for the appellants, that the High Court has no power after the
expiry of the period to extend the time for the compliance on the facts and
circumstances, we do not think that we would be justified to interfere with c
this order at this distance of time. However, as regards the direction to
make payment of compensation, we do not think. that it would he ap-
propriate at this stage to give any finding; however, the trial Court is
directed to conduct an enquiry whether the appellant was prevented by the
acts of the respondents to remain in possession and work out the factory. D
In the event of the finding being recorded that the appellant was prevented
by the acts of the respondent for working out the factory, the appellant will
not be liable to pay damages whatsoever. On the other hand, if it is found
that the appellant had worked out the factory in view of the fact that the
High Court had granted the order of Status quo, we think they are liable
to pay @ Rs. 2,500 p.m. E
It is stated by Mr. Soli J. Sorabjee, learned senior counsel for the
respondents, that Rs. 12,00,000 (Rupees Twelve lakhs only) deposited by
the respondents before the expiry of the period six months by way of a
demand draft, has been encashed by the appellant. The app((llants are F
denying the same. The trial Court is directed to verify whether the amount
was subsisting till the date of the order passed by the High Court and
whether the amount stands deposited in any interest earning security,
within a period of six months from the date of receipt of this order. In case
the amount was deposited to the credit of the suit and it had not been
invested in interest earning security then the respondents are directed to G
. pay interest at the commercial rate from the date of the deposit till date
of the Judgment of the High Court. In case the appellant was found to have
withdrawn it, the need to pay interest does not arise.
Mr. Bhimrao Naik further requests that the amount of Rs. 20,00,000 H
672 SUPREME COURT REPORTS (1996) SUPP. 6 S.C.R.
A (Rupees twenty lakhs only) standing to the credit of the suit, may be
directed to be withdrawn by the appellant. We are not inclined to give any
direction. After the enquiry into mesne profits is conducted by the trial
Court and if there is any amount due to either party, the same may be
worked out accordingly by w_ay of adjustment. ·
B The appeals are accordingly disposed of. No costs.
R.P. Appeals disposed of.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.