GUJARAT MARITIME BOARDversusL&T INFRASTRUCTURE DEVELOPMENT PROJECTS LTD. AND ANOTHER
- Citation
- 2016 INSC 927
- Decided
- 28 September 2016
- Disposal
- Appeal(s) allowed
- Bench
- KURIAN JOSEPH
Holding
A bank guarantee is an independent, unconditional contract, and the decision of the guarantor on breach is binding on the bank; therefore, the High Court cannot restrain its invocation under Article 226.
Summary
The Gujarat Maritime Board (GMB) cancelled a Letter of Intent issued to L&T Infrastructure Development Projects Ltd. (L&T) for port development and invoked a Rs 5 crore performance bank guarantee issued by Yes Bank. L&T challenged the cancellation and the invocation of the guarantee, seeking a writ to restrain GMB from encashing the guarantee. The High Court of Gujarat restrained GMB, but the Supreme Court held that the bank guarantee is an independent, unconditional contract between the bank and GMB, and the decision of GMB on breach is binding on the bank. The Court ruled that the High Court cannot entertain an injunction to restrain the guarantee’s enforcement except in cases of egregious fraud or irretrievable injury, and such matters are beyond the scope of Article 226. Consequently, the Supreme Court set aside the High Court’s order and allowed the appeal.
Issues considered
- Whether the High Court can exercise its discretionary jurisdiction under Article 226 to restrain the invocation of an unconditional bank guarantee.
- Whether a bank guarantee is an independent contract separate from the underlying performance contract.
- Whether an injunction can be granted to prevent enforcement of an unconditional bank guarantee.
- Whether the decision of the guarantor (GMB) on breach is binding on the bank under the terms of the guarantee.
Subjects
Judgment
[2016] 8 S.C.R. 692
A GUJARAT MARITIME BOARD
v.
L&T INFRASTRUCTURE DEVELOPMENT PROJECTS LTD.
AND ANOTHER
B (Civil Appeal No. 9821 of2016)
SEPTEMBER 28, 2016
[KURIAN JOSEPH AND R. F. NARIMAN, JJ.]
Writs:
c Constitution of India - Art.226 - Writ Jurisdiction in
contractual matters -Unconditional performance bank
guarantee - Invocation of - Discretionary jurisdiction of High
Court - Scope of - High Court restrained the appellant-guarantee
from invoking an unconditional bank guarantee executed by the
D first respondent - Held: Bank guarantee is an independent and
separate contract betv"een the guarantor-bank and the appellant-
guarantee - Existence of any dispute between the parties to the
contract not a ground to issue order of injunction to restrain
enforcement of bank guarantee - Between the guarantor-bank and
the appellant-guarantee, there was a written demand for invoking
E the bank guarantee in pursuant to any breach of covenants -
Decision of appellant as to breach was binding on bank to honour
the payment under the guarantee - Justifiability of such decision
is a different matter between the appellant and the first
respondent - High Court not to go in that question u/Art. 226 as
disputed question of facts are involved - Jurisdiction.
F
Allowing the appeal, the Court
HELD: 1. The High Court went wrong both in its analysis
of facts and approach on law. A cursory reading of the Loi issued
by the appellant to the first respondent would clearly show that it
G is not a case of forfeiture of security deposit " ... if the contract
had frustrated on account of impossibility ... " but invocation of
the performance bank guarantee. On law, the High Court ought
to have noticed that the bank guarantee is an independent
contract between the guarantor-bank and the guarantee-appellant.
The guarantee is unconditional. No doubt, the performance
H
692
GUJARAT MARITIME BOARD v. L&T INFRASTRUCTURE 693
DEVELOPMENT PROJECTS LTD.
guarantee is against the breach by the lead promoter, viz., the A
first respondent. But between the bank and the appellant, the
specific condition incorporated in the bank guarantee is that the
decision of the appellant as to the breach is binding on the bank.
The justifiability of the decision is a different matter between the
appellant and the first respondent and it is not for the High Court B
in a proceeding under Article 226 of the Constitution of India to
go into that question since several disputed questions of fact are
involved. [Para 10) [699-E-GJ
2.1 The contention of the first respondent that the
invocation of Bank Guarantee depends on the cancellation of the C
contract and once the cancellation of the contract is not justified,
the invocation of Bank guarantee also is not justified cannot be
appreciated. The bank guarantee is a separate contract and is
not qualified by the contract on performance of the obligations.
No doubt, in terms of the bank guarantee also, the invocation is
only against a breach of the conditions in the Loi. But between D
the appellant and the bank, it has been stipulated that the decision
of the appellant as to the breach shall be absolute and binding on
the bank. [Para 11) [702-E-F]
2.2 An injunction against the invocation of an absolute and
an unconditional bank guarantee cannot be granted except in E
situations of egregious fraud or irretrievable injury to one of the
parties concerned. [Para 12) [702-G]
Himadri Chemicals Industries Limited v. Coal Tar
Refining Company (2007) 8 SCC 110: 2007 (8)
SCR 869 - referred to. F
3. Guarantee given by the bank to the appellant contains
only the condition that in case of breach by the lead promoter,
viz., the first respondent of the conditions of Loi, the appellant is
free to invoke the bank guarantee and the bank should honour it
••• "witliout any demur, merely on a demand from GMB (appellant) G
stating tliat tlie said lead promoter failed to perform tlie
covenants •.. ". It has also been undertaken by the bank that such
written demand from the appellant on the bank shall be ...
"conclusive, absolute and unequivocal as regards tlie amount due
and payable by the bank under this l(Uarantee". Betwe~n the
H
694 SUPREME COURT REPORTS [2016] 8 S.C.R.
A appellant and the first respondent, in the event of failure to
perform the obligations under the Loi, the appellant was entitled
to cancel the Loi and invoke the bank guarantee. On being
satisfied that the first respondent has failed to perform its
obligations as covenanted, the appellant cancelled the Loi and
resultantly invoked the bank guarantee. Whether the cancellation
B
is legal and proper, and whether on such cancellation, the bank
guarantee could have been invoked on the extreme situation of
the first respondent justifying its inability to perform its obligations
under the Loi, etc., are not within the purview of an inquiry under
Article 226 of the Constitution of India. Between the bank and
C the appellant, the moment there is a written demand for invoking
the bank guarantee pursuant to breach of the covenants between
the appellant and the first respondent, as satisfied by the
appellant, the bank is bound to honour the payment under the
guarantee. [Para 13] [703-G-H; 704-A-C]
D Joshi Technologies International Inc. v. Union of India
and others (2015) 7 SCC 728: 2015 (6) SCR 1042 -
referred to.
Case Law Reference
2015 (6) SCR 1042 referred to Para 10
E 2()Q7 (8) SCR 869 referred to Para 12
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 9821
of2016.
From the Judgment and Order dated I 7.02.2016 and 18.02.2016
of the High Court of Gujarat atAhmedabad in Special Civil Application
F No.4870of2015.
Mukul Rohatgi, AG, Tushar Mehta, ASG, Gursharan H. Virk, Nakul
Mohta, Ms. Misha Rohatgi Mohta, Shashibhushan P. Adgaonkar, Advs.
for the Appellant.
Gopal Jain, Sr. Adv., Devashish Bharuka, Chinmayee Chandra,
G Ms. Arpita Bishnoi, Vaibhav Niti, Ravi Bharuka, Advs. for the
Respondents.
The Judgment of the Court was delivered by
KURIAN, J.: 1. Leave granted.
H
2. Whether the High Court is justified in exercising its discretional)'
GUJARAT MARITIME BOARD v. L&T INFRASTRUCTURE 695
DEVELOPMENT PROJECTS LTD. [KURIAN, J.]
jurisdiction under Article 226 of the Constitution oflndia for restraining A
the appellant from invoking an unconditional bank guarantee executed
by the first respondent, is the main issue arising for consideration in this
case.
3. The appellant invited bids for development ofSutrapada Port.
In the process, a Letter oflntent (hereinafter referred to as 'Lol') was B
issued to the first respondent on 06.02.2008. The relevant conditions of
Lol are extracted below:
1. 7 The Lead Promoter shall submit a detailed project report within
12 months of issue of this Letter oflntent (LOI) and present it to
Gujarat Maritime Board for their approval. c
1.8 The Lead Promoter shall obtain all environment clearances
and coastal regulation zone (CRZ) clearances and effective
financial closure and all such other clearances and permissions
within 18 months or issue of this Letter oflntent
1.9 A Performance Guarantee/Bank Guarantee of Rs 5 Crores D
(Rupees Five crores only) shall be submitted to Gujarat Maritime
Board within 4 weeks of issue of this Letter of Intent in the
Performa annexed herewith. (Annexure I). This perfonnance/bank
guarantee is against the submission of Detailed Project Report
within 12 months and obtaining environment clearance, coastal
regulation zone clearance and effecting financial closure within E
18 months as mentioned in para 1.7 and 1.8 above, failing which
Gujarat Maritime Board/Government shall cancel this Letter of
Intent and bank guarantee shall be forfeited."
4. On 07.05.2010, the first respondent requested for change of
location from Sutrapada to Kachchigarh and the bank guarantee was F
extended. At the instance of the first respondent, the Yes Bank Limited
furnished a bank guarantee to the appellant on 26.11.2011 for an amount
ofRs.5 crores. The relevant conditions read as follows:
"
(a) We, YES BANK Ltd. do hereby guarantee and undertake to G
pay to GMB an amount not exceeding Rs 5,00,00,000/- (Rupees
Five Crores only) as against breach by the Lead Promoter for the
development of Kachchigarh Port. The decision of GMB as to
any breach having been committed and loss/damages caused or
suffered shall be absolute and binding on us.
H
696 SUPREME COURT REPORTS [2016] 8 S.C.R.
A (b) We, YES BANK Ltd, do hereby undertake to without any
reference to the Lead Promoter or any other person and
irrespective of the fact whether any dispute is pending between
GMB and the Lead Promoter or any court ofTribunal or arbitrator
relating thereto, pay the amount due and payable under this
guarantee without any demur, merely on demand from GMB stating
B
that the said Lead Promoter's failure to perform the covenants of
the same. Any such written demand made by GMB on the Bank
shall be conclusive, absolute and unequivocal as regards the amount
due and payable by the Bank under this guarantee. However,
Bank's liability under this guarantee shall be restricted to an amount
c not exceeding Rs 5,00,00,0001-(Rupees Five Crores only)."
5. It appears, the first respondent could not proceed with the
work even at Kachchigarh, and on such intimation, the appellant by letter
dated 10.03.2015, cancelled the Loi issued to the first respondent. The
communication dated I 0.03.2015 cancelling the Loi to the extent relevant,
D reads as follows:
"This is with reference to your above mentioned letter informing
GMB about your inability to develop a port at Kachchigarh due to
presence of corals not seeking any further extension of the LOI.
In this regard, it is hereby informed that your admission on failure
E in taking up the Project is in breach of the conditions set out in the
Letter of Intent dated 6.2 .2008. At your request, the proposal for
cancellation of Letter of Intent issued to Mis. L&T Ltd. for
development ofKachchigarh port was laid before the Board and
was further submitted to GOG for its decision in the matter. After
much deliberations, the Government of Gujarat has vide its letter
F dated February 23, 2015 accorded its approval to (a) cancel the
Letter ofintent to Mis L& T Ltd. for development of Kachchigarh
port and (b) forfeit the Bank Guarantee worth Rs.5 crores
submitted by the Company.
In view of the above direction of the Government, the Letter of
G Intent dated 06.02.2008 issued to you for development of
Kachchigarh port (earlier Sutrapada port) is hereby cancelled.
Further, the issuing Bank of the Bank Guarantee has been
informed about GMB's claim on the Bank Guarantee."
xxx xxx xxx xxx"
H
GUJARAT MARITIME BOARD v. L&T INFRASTRUCTURE 697
DEVELOPMENT PROJECTS LTD. [KURIAN, J.]
6. On the same day, the appellant also invoked the bank guarantee A
furnished by the Yes Bank Limited at the instance of the first respondent.
The communication reads as follows:
"This is with reference to the above mentioned Performance Bank
Guarantee issued by your bank on behalf of Mis L&T
Infrastructure Development Projects Ltd.("the Company") B
towards securing the fulfilment of conditions set out in the Letter
oflntent ("LOI") dated 15.07.2010 and having its validity till March
31, 2015 worth Rs.5,00,00,000/-(Rupees Five crore only) submitted
to Gujarat Maritime Board (GMB).
Whereas, in view of breach of the conditions set out in the LOI c
by the Company, the Gujarat Maritime Board/Government intends
to exercise its right in accordance with Clause 1.9 and has decided
to cancel the Letter of Intent and forfeit the above Bank
Guarantee.
I, undersigned hereby put my claim to forfeit the Bank Guarantee D
no. 005GM07113300001 dated November 26, 2011 worth Rs. Five
crores issued by your bank and to reimburse the amount of the
Bank Guarantee in the account of Gujarat Maritime Board,
Gandhinagar.
It is requested to issue Demand Draft in the name of Vice E
Chairman & Chief Executive Officer, Gujarat Maritime Board
payable at Gandhinagar at the earliest."
7. The first respondent filed a writ petition before the High Court
challenging the cancellation of the Lo I and the invocation of the bank
guarantee. The following are the two main reliefs:
F
"
(a) That this Hon'ble Court be pleased to issue an appropriate
writ, order or direction and be pleased to quash and set aside the
decision dated 23.02.2015 of the respondent no. 2 and the
consequential decision of the respondent no. I communicated vide G
letter of 10.03.2015, to approve the request of the petitioner to
cancel the Loi issued to the petitioner, with the condition of
forfeiting the Bank Guarantee worth Rs 5 crores, and further
command the respondent no. 1 to cancel the LoI dated 06.02.2008
and return the Bank Guarantee to the petitioner;
H
698 SUPREME COURT REPORTS [2016] 8 S.C.R.
A (b) That this Hon'ble Court may be pleased to issue appropriate
writ, order or direction directing the respondent no. 1 not to encash
the Bank Guarantee No. 005GM07113300001 dated
26.11.2011 (extended from time to time) and command the
respondent no. I to withdraw the letter dated 10.03.2015 addressed
to Yes Bank invoking the aforesaid Bank Guarantee."
B
8. By the impugned judgment, the writ petition was allowed.
Paragraphs-24, 25 and 26 of the impugned judgment which deal with the
contentions are extracted below:
"24. Learned counsel for the GMB however, would place much
c reliance on the tender conditions in which the tenderer agreed
that the bidder had made a complete and careful examination to
determine the difficulties in matters incidental to the performance
of its obligations under the Concession Agreement and to specify
the nature and extent of all difficulties and hazards. Counsel would
therefore, contend that any difficulty or even impossibility in
D obtaining environmental clearances cannot be a defence of the
petitioner to avoid forfeiture of the security deposit. We are unable
to read such condition in such a rigid manner. If the contract had
frustrated on account of impossibility, we have serious doubt
whether GMB could forfeit security deposit citing the reason that
E whatever be the reason, the petitioner failed to perform its
obligations and, therefore, must be visited with the penalty of
forfeiture. However, there is an additional reason why we must
reject such a contention. We may recall, the initial project was for
construction of port at Sutrapada. On account of the respondents
not being able to make the land available for such project, the
F same had to be shelved. Only as an alternative, the petitioner
suggested Kachchigarh as a site where the port could be
developed. Surely, the petitioner was not expected tn.carry out
complete environmental assessment before coming up with such
an alternative suggestion nor GMB understood the offer of the
G petitioner as to one which will irrespective of environment
concerns, be accepted. When there was a fundamental shift in
the initial project envisaged in the letter of intent, the contention
that whatever be the difficulties in executing the contract, forfeiture
must follow, need to be viewed in the background of such material
changes.
H
GUJARAT MARITIME BOARD v. L&T INFRASTRUCTURE 699
DEVELOPMENT PROJECTS LTD. [KURIAN, J.)
25. The contention that having given unconditional bank guarantee, A
the petitioner cannot avoid encashment thereof, can also not be
accepted. The parameters for avoiding the payment of a bank
guarantee by the bank giving such guarantee cannot be applied in
the present case. The question in the present case is not so much
as to allowing the authorities to encash the bank guarantee as B
much as the authority of the GMB to retain such amount even if
it was so allowed to be encashed. If the decision of GMB to
cancel the contract and to award the penalty of forfeiture ofRs 5
crores on the petitioner itselfis found to be erroneous and therefore,
set aside, the question of allowing GMB to encash the bank
guarantee would simply not arise. C
26. In the result, petition is allowed. Impugned communication
dated l 0.3.2015 is set aside. The respondents shall not encash
the bank guarantee in question."
9. Heard Shri Mukul Rohatgi, learned Attorney General for India,
and Shri Tushar Mehta, learned Additional Solicitor General, appearing D
forthe appellant and Shri Gopal Jain, learned Senior Counsel appearing
for the first respondent.
I 0. Unfortunately, the High Court went wrong both in its analysis
of facts and approach on law. A cursory reading of Loi would clearly
show that it is not a case of forfeiture of security deposit '"... if the E
contract had frustrated on account of impossibility ... " but invocation
of the performance bank guarantee. On law, the High Court ought to
have noticed that the bank guarantee is an independent contract between
the guarantor-bank and the guarantee-appellant. The guarantee is
unconditional. No doubt, the performance guarantee is against the breach F
by the lead promoter, viz., the first respondent. But between the bank
and the appellant, the specific condition incorporated in the bank guarantee
is that the decision of the appellant as to the breach is binding on the
bank. The justifiability of the decision is a different matter between the
appellant and the first respondent and it is not for the High Court in a
proceeding under Article 226 of the Constitution oflndia to go into that G
question since several disputed questions of fact are involved. Recently,
this Court in Joshi Technologies Internationallnc. v. Union oflndia
and others 1, where one of us (R.F. Nariman, J.) is a member, has
surveyed the entire legal position on exercise of writ jurisdiction in
1
(2015)1 sec ns H
700 SUPREME COURT REPORTS [2016] 8 S.C.R.
A contractual matters. The paragraphs which deal with the situation relevant
to the case under appeal, read as follows:
"68. The Court thereafter summarised the legal position in the
following manner: (ABL International Ltd. Case (2004) 3 SCC
553)
B "2 7. From the above discussion of ours, following legal principles
emerge as to the maintainability of a writ petition:
(a) In an appropriate case, a writ petition as against a State
or an instrumentality of a State arising out of a contractual
obligation is maintainable.
(b) Merely because some disputed questions of facts arise
for consideration, same cannot be a ground to refuse to
entertain a writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of
D monetary claim is also maintainable.
28. However, while entertaining an objection as to the
maintainability of a writ petition under Article 226 of the Constitution
of India, the court should bear in mind the fact that the power to
issue prerogative writs under Article 226 of the Constitution is
plenary in nature and is not limited by any other provisions of the
E
Constitution. The High Court having regard to the facts of the
case, has a discretion to entertain or not to entertain a writ petition.
The Court has imposed upon itself certain restrictions in the
exercise of this power. (See Whirlpool Corpn. v. Registrar of
Trade Marks. [(1998) 8 SCC I]) And this plenary right of the
F High Court to issue a prerogative writ will not normally be exercised
by the Court to the exclusion of other available remedies unless
such action of the State or its instrumentality is arbitrary and
unreasonable so as to violate the constitutional mandate of Article
14 or for other valid and legitimate reasons, for which the Court
thinks it necessary to exercise the said jurisdiction."
G
69. The position thus summarised in the aforesaid principles has
to be understood in the context of discussion that preceded which
we have pointed out above. As per this, no doubt, there is no
absolute bar to the maintainability of the writ petition even in
contractual matters or where there are disputed questions of fact
H
GUJARAT MARITIME BOARD v. L&T INFRASTRUCTURE 701
DEVELOPMENT PROJECTS LTD. [KURIAN, J.]
or even when monetary claim is raised. At the same time, A
discretion lies with the High Court which under certain
circumstances, it can refuse to exercise. It also follows that under
the following circumstances, "normally", the Court would not
exercise such a discretion:
69 .1. The Court may not examine the issue unless the action has B
some public law character attached to it.
69.2. Whenever a particular mode of settlement of dispute is
provided in the contract, the High Court would refuse to exercise
its discretion under Article 226 of the Constitution and relegate
the party to the said mode of settlement, particularly when c
settlement of disputes is to be resorted to through the means of
arbitration.
69.3. If there are very serious disputed questions of fact which
are of complex nature and require oral evidence for their
determination. D
69.4. Money claims per se particularly arising out of contractual
obligations are nonnally not to be entertained except in exceptional
circumstances.
70. Further, the legal position which emerges from various
judgments of this Court dealing with different situations/aspects E
relating to contracts entered into by the State/public authority with
private parties, can be summarised as under~
70.1. At the stage of entering into a contract, the State acts purely
in its executive capacity and is bound by the obligations of fairness.
F
70.2. State in its executive capacity, even in the contractual field,
is under obligation to act fairly and cannot practise some
discrimination.
70.3. Even in cases where question is of choice or consideration
of competing claims before entering into the field of contract,
facts have to be investigated and found before the question of a G
violation of Article 14 of the Constitution could arise. If those
, facts are disputed and require assessment of evidence the
correctness of which can only be tested satisfactorily by taking
detailed evidence, involving examination and cross-examination
of witnesses, the case could not be conveniently or satisfactorily H
702 SUPREME COURT REPORTS [2016] 8 S.C.R.
A decided in proceedings under Article 226 of the Constitution. In
such cases the Court can direct the aggrieved party to resort to
alternate remedy of civil suit, etc.
70.4. Writ jurisdiction of the High Court under Article 226 of the
Constitution was not intended to facilitate avoidance of obligation
B voluntarily incurred.
70.5. Writ petition was not maintainable to avoid contractual
obligation. Occurrence of commercial difficulty, inconvenience
or hardship in performance of the conditions agreed to in the
contract can provide no justification in not complying with the
C terms of contract which the parties had accepted with open eyes.
It cannot ever be that a licensee can work out the licence if he
finds it profitable to do so: and he can challenge the conditions
under which he agreed to take the licence, if he finds it
commer~ially inexpedient to conduct his business.
D 70.6. Ordinarily, where a breach of contract is complained of, the
party complaining of such breach may sue for specific
performance of the contract, if contract is capable of being
specifically performed. Otherwise, the party may sue for
damages."
E 11. It is contended on behalf of the first respondent that the
invocation of Bank Guarantee depends on the cancellation of the contract
and once the cancellation of the contract is not justified, the invocation
of Bank Guarantee also is not justified. Weare afraid that the contention
cannot be appreciated. The bank guarantee is a separate contact and is
not qualified by the contract on performance of the obligations. No doubt,
F in terms of the bank guarantee also, the invocation is only against a
breach of the conditions in the Loi. But between the appellant and the
bank, it has been stipulated that the decision of the appellant as to the
breach shall be absolute and binding on the bank.
12. An injunction against the invocation of an absolute and an
G unconditianal bank guarantee cannot be granted except in situations of
egregious fraud or irretrievable injury to one of the parties concerned.
This position also is no more res integra. In Himadri Chemicals
Industries Limited v. Coal Tar Refining Company2 , at paragraph -14:
H '(2007J s sec 110
GUJARAT MARITIME BOARD v. L&T INFRASTRUCTURE 703
DEVELOPMENT PROJECTS LTD. [KURIAN, J.]
"14. From the discussions made hereinabove relating to the A
principles for grant or refusal to grant of injunction to restrain
enforcement of a bank guarantee or a letter of credit, we find that
the following principles should be noted in the matter ofinjunction
to restrain the encashment of a bank guarantee or a letter of
credit:
B
(i) While deaiing with an application for injunction in the course
of commercial dealings, and when an unconditional bank
guarantee or letter of credit is given or accepted, the beneficiary
is entitled to realise such a bank guarantee or a letter of credit
in terms thereof irrespective of any pending disputes relating
to the terms of the contract.
c
(ii) The bank giving such guarantee is bound to honour it as
per its terms irrespective of any dispute raised by its customer.
(iii) The courts should be slow in granting an order of injunction
to restrain the realisation of a bank guarantee or a letter of o
credit.
(iv) Since a bank guarantee or a letter of credit is an
independent and a separate contract and is absolute in nature,
the existence of any dispute between the parties to the contract
is not a ground for issuing an order of injunction to restrain E
enforcement of bank guarantees or letters of credit.
(v) Fraud of an egregious nature which would vitiate the very
foundation of such a bank guarantee or letter of credit and the
beneficiary seeks to take advantage of the situation.
(vi) Al lowing encashment of an unconditional bank guarantee F
or a letter of credit would result in irretrievable harn1 or injustice
to one of the parties concerned."
13. Guarantee given by the bank to the appellant contains only
the condition that in case of breach by the lead promoter, viz., the first
respondent of the conditions of Loi, the appellant is free to invoke the G
bank guarantee and the bank should honour it ... "ll'ithout any de11n11;
merely on a demand from GMB (appellant) stating that the said
lead promoter failed to pe1for111 the covenants ... ". It has also been
undertaken by the bank that such written demand from the appellant on
the bank shall be ... "conclusive, abs(l/ute and unequivocal as regards
H
704 SUPREME COURT REPORTS [2016] 8 S.C.R.
A the amount due and payable by the bank under this guarantee".·
Between the appellant and the first respondent, in the event of failure to
perform the obligations under the Loi dated 06.02.2008, the appellant
was entitled to cancel the LoI and invoke the bank guarantee. On being
satisfied that the first respondent has failed to perform its obligations as
covenanted, the appellant cancelled the Lo I and resultantly invoked the
B
bank guarantee. Whether the cancellation is legal and proper, and whether
on such cancellation, the ba.nk guarantee could have been invoked on
the extreme situation of the first respondent justifying its inability to
perform its obligations under the Loi, etc., are not within the purview of
an inquiry under Article 226 of the Constitution of India. Between the
c bank and the appellant, the moment there is a written demand for invoking
the bank guarantee pursuant to breach of the covenants between the
appellant and the first respondent, as satisfied by the appellant, the bank
is bound to honour the payment under the guarantee.
14. Therefore, the appeal is allowed and the impugned judgment
D is set aside. However, we make it clear that this judgment will not stand
in the way of the first respondent working out its grievances in appropriate
proceedings as permitted under law.
Ankit Gyan Appeal allowed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.