Created byFuzzy Cloud

Supreme Court of India

G H M/S TREATY CONSTRUCTION & ANR.versusM/S RUBY TOWER CO-OP. HSG. SOCIETY LTD.

Citation
2019 INSC 780
Decided
19 July 2019
Disposal
Case Partly allowed

Holding

The Supreme Court affirmed the builder's obligation to pay the agreed Rs 25 lakh but dismissed the compensation and daily penalty, directing completion of statutory requisites and execution of the conveyance deed after the Occupancy Certificate is obtained.

Summary

Treaty Construction built a residential‑commercial project whose flats were purchased by members who formed the Ruby Tower Co‑op Housing Society. The society alleged that the builder failed to complete interior works, did not obtain a Completion or Occupancy Certificate, and collected excess possession charges, seeking repayment and compensation. The State Consumer Commission ordered the builder to pay Rs 26.25 lakh, obtain the certificates, execute a deed of conveyance and pay Rs 3 lakh compensation plus a daily penalty of Rs 1,000 for delay. The National Consumer Commission modified the order, confirming a payment of Rs 25 lakh (as agreed in 2003 meetings) but also imposing the compensation and daily penalty. The Supreme Court upheld the Rs 25 lakh payment, set aside the compensation and daily penalty, directed both parties to complete their respective requisites and the builder to execute the deed after obtaining the Occupancy Certificate, and waived costs. The appeal was therefore partly allowed.

Issues considered

  • The builder's liability to pay Rs 25 lakh as per the 2003 settlement meeting.
  • Whether the builder is liable to pay Rs 3 lakh compensation for failure to obtain an Occupancy Certificate.
  • Whether a daily penalty of Rs 1,000 for delay in obtaining the Occupancy Certificate is justified.
  • Whether the National Consumer Commission had jurisdiction to modify the State Commission's order on pecuniary grounds.
  • Whether the builder must execute a deed of conveyance within a specified period after obtaining the Occupancy Certificate.

Legislation cited

Subjects

Consumer Protection Actdeficiency of serviceoccupancy certificateMOFAco‑operative housing societypecuniary jurisdictioncompensationdaily penaltydeed of conveyance

Judgment

606                       [2019]
               SUPREME COURT     9 S.C.R. 606
                              REPORTS                       [2019] 9 S.C.R.


A                  M/S TREATY CONSTRUCTION & ANR.
                                        v.
              M/S RUBY TOWER CO-OP. HSG. SOCIETY LTD.
                         (Civil Appeal No. 5699 of 2019)
B                                JULY 19, 2019
                     [ABHAY MANOHAR SAPRE AND
                        DINESH MAHESHWARI, JJ.]
             Consumer Protection – Deficiency of service – Appellants
C     evolved a scheme of constructing a building consisting of flats and
      shops – Purchasers of those flats and shops formed a co-operative
      housing society – In relation to the project in question, dispute arose
      between the members of the respondent-society and appellants-
      builders – Respondent-society contended that appellants failed to
      complete the interior works and failed to obtain the completion
D
      certification as also the occupancy certificate – It was also alleged
      that appellants borrowed varied sums of money from the respondent-
      society on pretext of completing the unfinished work – On the other
      hand, appellants contended that delay was due to the obstruction
      caused and created by the respondent, who had made illegal
E     construction/alterations – State Commission, inter alia, directed
      appellants to execute Deed of conveyance of the property in question
      after obtaining the completion certificate and occupancy certificate
      and entitled the respondent for refund of amount of Rs.26,25,000/
      -, which was given to obtain possession of the flat – Before, National
      Commission, appellants denied the receipt of the loan amount of
F
      Rs.26,25,000/- – The said submission was accepted by the National
      Commission, however, it held that appellants had agreed to pay a
      sum of Rs.25,00,000/- to the respondent-society in the meeting dated
      17.12.2003, therefore, the appellants were bound by the admission
      so made by them and were liable to that extent – National Commission
G     also directed appellants to pay compensation of Rs.3,00,000/- for
      not obtaining occupancy certificate and directed appellants to pay
      Rs.1000/- per day after 60 days of the order and until obtaining
      full occupancy certificate – On appeal, held: Direction by the
      National Commission as regards payment of sum of Rs.25,00,000/-
H
                                       606
M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                           607
               HSG. SOCIETY LTD.

by the appellants to the respondent requires no interference –             A
Insofar other directions are concerned, there was no record to hold
the appellants liable for compensation – In other words, there was
no material on record to find if respondent-society or its members
suffered any loss – Therefore, part of order directing appellants to
pay compensation of Rs.3,00,000/- set aside – Also, Municipal
                                                                           B
Corporation had issued notices regarding alterations by the
members of the respondent-society and dispute regarding the same
has not settled as the High Court has directed for inspection of the
building and necessary follow up steps – Thus, in the circumstances,
part of the impugned order requiring the appellants to pay Rs.1000/
- per day after 60 days of the order, also set aside – Appellants and      C
respondent directed to complete all requisites on their part – After
completion of all the requisites by the parties, the appellants directed
to execute the Deed of conveyance in favour of the respondent-
society after obtaining necessary occupancy certificate –
Maharashtra Ownership Flats (Regulation of Promotion,
                                                                           D
Construction, Sale, Management and Transfer) Act, 1963 – ss.4
and 11.
      Partly allowing the appeal, the Court
       HELD : 1. Indisputably, in the application dated
21.03.2013 as moved before the State Commission, the                       E
respondent-society restricted its prayer for money recovery to a
sum of Rs.25,00,000/- with reference to the minutes of meetings
dated 17.12.2003 and 14.12.2003. It is at once clear that the
aforesaid sum of Rs. 25,00,000/- was agreed to be paid by the
appellants in full and final settlement of the claim of the
respondent-society. The appellants having agreed to make such              F
payment, the National Commission has rightly put them to the
terms of honouring their unequivocal commitment/promise. In
the given set of facts and circumstance, this Court is unable to
accept the contention that a particular part of order of the State
Commission having not been challenged by the respondent-                   G
society, the National Commission could not have granted the
relief otherwise available on the face of record. In an overall view
of the matter, when such a relief emanates from the very
commitment made by the appellants in the meetings aforesaid,

                                                                           H
608            SUPREME COURT REPORTS                      [2019] 9 S.C.R.


A     the National Commission had been fully justified in granting the
      same to the respondent-society. Therefore, there is no reason to
      consider any interference in this part of direction by the National
      Commission. [Para 10] [624-G-H; 625-A-B]
             2. Even when this Court finds no reason to interfere with
B     the above-mentioned parts of the order impugned, it appears
      difficult to approve the directions in the remaining parts thereof,
      particularly those relating to other pecuniary reliefs. The National
      Commission has saddled the appellants with a liability to pay
      compensation to the tune of Rs. 3,00,000/- for not obtaining
      Occupancy Certificate and has issued further directions to the
C     appellants to obtain such certificate as also to execute the
      requisite Deed and to pay Rs. 1,000/- per day for every day of
      delay. True it is that Occupancy Certificate was not obtained by
      the appellants but then, fact of the matter remains that the
      members of respondent-society chose to take over possession
D     without such certificate; and then, several questions have arisen
      as regards the alteration allegedly carried out by them for which,
      the Municipal Corporation has the objections to raise. In any
      case, there appears nothing on record to find the basis for holding
      the appellants liable for compensation and then, for assessing
      the quantum of compensation, if at all there be any liability of the
E     appellants. In other words, there is no material on record to find
      if the respondent-society or its members suffered any loss; and if
      so, the extent thereof. Therefore, this part of the order impugned,
      directing the appellants to pay compensation to the tune of Rs.
      3,00,000/-, cannot be approved. [Para 11] [625-C-F]
F           3. As regards direction to appellants to convey the title of
      the property in question by executing a registered Deed within a
      period of four months after obtaining Occupancy Certificate,
      though the appellants cannot avoid their legal obligation to
      execute the requisite Deed but then, having regard to the facts
G     and circumstances of the case and more particularly the facts
      relating to the issuance of notices by the Municipal Corporation;
      and the dispute/objection regarding alterations by the members
      of the respondent-society having not been settled as yet with the
      High Court having issued directions for inspection of the building
      and for necessary follow-up steps, awarding of Rs. 1,000/- per
H
M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                        609
               HSG. SOCIETY LTD.

day for every day of delay seems rather unwarranted. In the given       A
situation, where the Municipal Corporation had been of the view
that there were visible illegal constructions made by the members
of respondent-society because of which the Certificate cannot be
issued; and in view of the orders dated 12.06.2017 and 07.01.2019
passed by the High Court in W.P. No. 970 of 2015, the penalty of
                                                                        B
Rs. 1,000/- per day deserves to be waived at present but with the
requirements on the parties to complete the respective
requisites, while leaving it open for them to take recourse to
appropriate remedies, in case of any grievance arising in future.
[Para 12] [625-G-H; 626-A-B]
      4. In the result:                                                 C

       (i) The impugned order dated 07.03.2018 is not interfered
with, to the extent it relates to the payment of Rs. 25,00,000/- by
the appellants to the respondent-society. The appellants shall
make payment of this amount of Rs. 25,00,000/- within 45 days
from today failing which, this amount shall carry interest @ 8%         D
p.a. from today until payment; (ii) The other part of the order
impugned, saddling the appellants with liability to pay
compensation to the tune of Rs. 3,00,000/- is set aside; (iii) Yet
another part of the order impugned, requiring the appellants to
pay Rs. 1,000/- per day after 60 days of the order and until            E
obtaining full Occupancy Certificate, is also set aside; (iv) As
regards obtaining of Occupancy Certificate and execution of the
Deed of Conveyance by the appellants, it is provided that: (a) the
appellants shall complete all the requisites on their part for
obtaining Occupancy Certificate within three months from today;
and (b) the respondent-society and its members shall also ensure        F
compliance of the requisites on their part (with reference to the
orders passed by the High Court in W.P. No. 970 of 2015) within
three months from today and for that matter, they may seek
necessary directions from the High Court, if so required. Within
two months of completion of all the requisites by the parties, the      G
appellants shall execute the Deed of Conveyance in favour of the
respondent-society after obtaining the necessary Occupancy
Certificate. As regards this part of the matter, it is also left open
for the parties to take recourse to appropriate remedies in

                                                                        H
610            SUPREME COURT REPORTS                           [2019] 9 S.C.R.


A     accordance with law, in case of any grievance arising in future;
      (v) The cost imposed on the appellants is waived and parties are
      left to bear their own costs of this litigation. [Para 14] [626-D-H;
      627-A-B]
            CIVIL APPELLATE JURISDICTION : Civil Appeal No. 5699
B     of 2019.
            From the Judgment and Order dated 07.03.2018 of the National
      Consumer Disputes Redressal Commission at New Delhi in First Appeal
      No. 109 of 2015.
             Vinay Navare, Ms. Gwen Kartika, Ms. Abha R. Sharma, Advs.
C     for the Appellants.
           Sukumar Pattjoshi, Sr. Adv., Nitin S.Tambwekar, Seshatalpa Sai
      Bandaru, Vikas Nautiyal, Advs. for the Respondent.
            The Judgment of the Court was delivered by
D           DINESH MAHESHWARI, J. 1. Leave granted.
             2. This appeal by special leave is directed against the judgment
      and order dated 07.03.2018, as passed by the National Consumer
      Disputes Redressal Commission (‘the National Commission’ hereafter)
      in First Appeal No. 109 of 2015, whereby the National Commission has
E     modified the order dated 17.12.2014, as passed by the State Consumer
      Disputes Redressal Commission, Maharashtra, Mumbai (‘the State
      Commission’ hereafter) in Complaint Case No. 120 of 2005; and has
      issued directions to the effect that: (i) the appellants shall pay a sum of
      Rs. 28,00,000/- to the respondent-society (the complainant) within a period
      of 45 days, failing which the amount shall carry interest @ 8% per annum
F
      from the date of passing of the order till the date of payment; (ii) a sum
      of Rs. 1,000/- per day shall further be paid by the appellants after 60
      days from the date of order till the time full Occupancy Certificate is
      obtained; (iii) the appellants shall convey the title of the property in
      question by executing a registered Deed in terms of the order passed by
G     the State Commission within a period of 4 months after obtaining the
      Occupancy Certificate. The National Commission has also upheld costs
      of Rs. 50,000/-, payable by the appellant No.1 herein.
            3. The background aspects of the matter, so far relevant for the
      present purpose, may be noticed, in brief, as follows:
H
 M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                                           611
      HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

      3.1. The appellants had evolved the scheme of constructing a                          A
building consisting of 64 flats and 13 shops on a plot bearing Survey No.
22, Hissa No. 7 [C.T.S. Nos. 99, 99 (1 to 16) and 114] at Sahakar Road,
Off. S.V.Road, Jogeshwari (West) Mumbai. The persons who agreed
to purchase respective flats and shops in the said project eventually
formed a Co-operative Housing Society, who is the respondent in this
                                                                                            B
appeal (‘the respondent-society’ hereafter). In relation to the project in
question, several disputes ensued between the members of respondent-
society on one hand and appellants-builders on the other, leading to a
complaint before the State Commission, being Complaint No. 120 of
2005 by the respondent-society1.
       3.2. The respondent-society submitted before the State                               C
Commission, inter alia, that several sale deeds were executed between
the period 1994 to 2002 whereby, its members purchased certain
apartment units as also commercial units of varied sizes but, despite
making payment over and above the agreed sale consideration, the
appellants failed to discharge their part of the contract inasmuch as the                   D
interior works remained incomplete; and the appellants also failed to
obtain the Completion Certification as also the Occupancy Certificate.
It was also alleged that pending completion of the building works, the
appellants borrowed and collected varied sums of money from the
members of the respondent-society, on the pretext that the money would
be used towards finishing the incomplete works; and this aspect was                         E
recorded in the minutes of the meeting held on 12.07.1998.
       3.2.1.It was further alleged that after some time, the respondent-
society demanded reimbursement of the amount given by its members;
and though the appellants agreed to reimburse a lump sum of
Rs. 25,00,000/- on 17.12.2003 but, even after a lapse of about a decade,                    F
the appellants had failed to reimburse the amount; failed to obtain the
Occupancy Certificate; and also failed to complete the pending works
to the satisfaction of respondent. It was yet further alleged that as an
added burden, upon taking possession of their individual units, the members
of respondent-society had to spend additional sums of money to complete                     G
the interior works in their respective flats and the building; and had also
to pay excess of taxes under various heads. Thus, according to the
respondent, there was a clear deficiency of services on the part of
1
  Apart from the present appellants, several other persons were also joined as opposite
parties in the said complaint case who have since been deleted from the array of parties.   H
612            SUPREME COURT REPORTS                          [2019] 9 S.C.R.


A     appellants and there was a clear violation of Sections 4 and 11 of The
      Maharashtra Ownership Flats (Regulation of the Promotion,
      Construction, Sale, Management and Transfer) Act, 1963. (‘MOFA’).
            3.2.2. With the submissions aforesaid, the respondent-society
      sought the following reliefs before the State Commission in the complaint:
B           “a) To hold and declare the Opposite Parties guilty of
             deficiency in service as well as unfair trade practice under
             the provision of the said Act.
            b) To direct the Opposite Parties to convey the said land/
             property in favour of the Complainant’s Society by
C            completing all requisites formalities at their own expenses.
            c) To direct the Opposite Parties to handover the Completion
              Certificate, Occupation Certificate, to the Complainants’
              realization of the same.

D           d) To refund the amount collected towards temporary loan to
             the tune of Rs. 35,16,820/- to the Complainants’ Society along
             with the interest @ 21% from the date of payment till the
             realization of the same.
            e) To refund the amount collected toward possession Charges
              to the tune of Rs. 26,25,000/- to the Complainants’ Society
E
              along with the interest 21% from the date of payment till the
              realization of the same.
            f) To direct the opposite parties to reimburse the expenses
              incurred by the Complainant’s Society ‘to the tune of Rs.
              46,40,000/- towards the completion of interior civil work
F
              along with the interest 21% from the date of payment till the
              realization of the same.
            g) To direct the Opposite Parties to develop the garden on the
             plot reserved for the same.
G           g) (sic) That the Hon’ble Forum may be pleased to direct the
             Opposite Party to pay an amount of Rs. 2,00,000/- towards
             compensation mental agony and cost of the above numbered
             Complaint and further an amount of Rs. 1,00,000/- towards
             incidental expenses incurred by the Complainant.

H
 M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                                613
      HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

      h) For such other and further reliefs as the nature and                    A
       circumstances of the case may deem fit and proper.”
       3.3. The appellants filed their separate counter versions to the
complaint aforesaid. Apart from stating that the claim of the respondent
was exaggerated, they also contended that there was a clear admission
of the fact that the appellants had undertaken to reimburse a sum of Rs.         B
25,00,000/- towards full and final settlement of the grievances raised by
the respondent, and the said amount was to be realized by consuming
the unconsumed FSI available on the said plot of land, as per the stipulations
incorporated in the registered agreement for sale, which fact had been
concealed by respondent. The appellants further submitted that the delay
was not on their part but had been due to the obstruction caused and             C
created by the respondent and its members who, after purchasing their
respective flats, had made illegal constructions/alterations, which had
clearly been brought out in the show-cause notices issued by the
Municipal Corporation. The appellants also denied the contention of the
respondent that the members completed their respective interior civil            D
works.
       3.4. During the course of hearing of the matter and pending disposal
of the complaint, the respondent-society filed an application dated
21.03.2013 before the State Commission with the submissions that the
prayer (d) of the complaint was not pressed; the amount claimed in               E
prayer (f) was restricted to Rs. 25,00,000/-; and that although there was
no illegal alteration by the flat purchasers, yet the complainant was
agreeable to remove the same as required by the Municipal Corporation.
The respondent-society stated in this application as under:
      “1) That the complainant is not pressing the prayer of Rs.                 F
       35,16820/- [claimed in prayer (d) i.e. temporary loan]
       alongwith interest 21% interest.
      2) That the complainant is restricting the prayer 10(f) to
       amount of Rs. 25,00,000/- as per the minutes of meeting dtd
       17/12/03 & 14/12/03 which was signed by both the parties.                 G
      3) That the complainant says that there is no illegal alteration
       made by the flat purchasers. However, the complainant
       consent to remove the same (if any) as required by BMC.”

                                                                                 H
614            SUPREME COURT REPORTS                          [2019] 9 S.C.R.


A            3.4.1. At this juncture, for their relevance, we may also take note
      of the minutes of the aforesaid meetings dated 14.12.2003 and 17.12.2003
      as under:-
            “Minutes of meeting held with Ruby Tower Members on 14/
            12/03
B           1. It was discussed that BMC expenses upto procuring of Occ.
            Certificate will be that of the Builders which the Builders have
            agreed.
            2. Regarding the settlement of accounts for which the Builders
            had offered Rs. 15,00,000/- in the last meeting held, the
C           members offered Rs. 25,00,000/-, subject to the above
            condition as full and final settlement towards all loans,
            liabilities, etc of the Builder.
            3. It was finalized that another meeting would be held on
            Wednesday i.e. 17/12/03 after Namaz-e-Isha at 9:00 p.m.
D
            4. It is agreed that henceforth transfer charges of Ruby Tower
            will be of the Ruby Tower Soc. (Prop).
            5. The meeting held was concluded in a cordial atmosphere
            and all present Society members have happily agreed to this
            proposal.”
E
            “Date: 17.12.2003
            Minutes of the meeting held with members of Ruby Tower
            01. As decided on 14.12.03, the meeting for finalizing the
            settlement of all pending dues/liabilities of the Builder was
F           conducted at 9.30 p.m. at the Builder’s office.
            2. The Builders agreed to the demand of Rs. 25,00,000.00
            raised by the members in the last meeting. However, it was
            clarified that the first priority would be that of regularizing
            ‘Ruby Tower’ with respect to BMC.
G
            3.Regarding payment of the agreed amount of Rs 25,00,000/
            -, it was proposed by the Builder that he would arrange for
            the same within six to nine months, which the members agreed.
            4. It was clarified by the present members that their decision
            was binding on all the members and all had authorized the
H
M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                             615
     HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

      members present to finalize the matter in the meeting held             A
      among themselves on 16.12.03.
      5. The meeting concluded in a cordial atmosphere. “
       3.5. On consideration of the material on record, the State
Commission observed that the Municipal Corporation had raised the
alleged objections by their letter/notice dated 09.07.1993 whereas the       B
flat owners were put in possession somewhere between 1995 to 2002;
that the Society was established in the year 2005; and the frantic efforts
made by the owners/members of respondent-society for execution of
the Deed of Conveyance and for obtaining Occupancy Certificate was
just and legitimate. The State Commission further observed that the          C
respondent had produced certain sample receipts to show that charges
amounting to Rs. 26,25,000/- were collected for handing over possession
of the flats and such charges were collected beyond the stipulated agreed
consideration. The State Commission, however, found that there
was no documentary evidence to show that the additional amount of
Rs. 46,40,000/- was spent to complete the interior civil works.              D

       3.6. In view of its findings, the State Commission partly allowed
the complaint while directing the appellants to execute the Deed of
Conveyance of the property in question after obtaining the Completion
Certificate and Occupancy Certificate within 90 days and else, to pay
Rs. 1,000/- per day until the date of compliance. The State Commission       E
also observed that the complainants had not pressed for refund of the
loan amount of Rs. 35,16,820/- and, therefore, the respondent-society
was held entitled only for the refund of the amount of Rs. 26,25,000/-,
which was given to obtain possession of the flat, together with interest
@ 9% p.a. from the date of filing of the complaint and payable within 90     F
days, failing which the said amount shall bear an interest @ 12% p.a.
      3.7. The State Commission, inter alia, observed and directed as
under:-
      “[8]. On going through the record and documentary evidence
      relied upon by parties, we find that the prayer for refund of          G
      Rs. 26,25,000/- which was extended as loan by the
      complainant society members is justified as few sample receipts
      showing the charges collected for handing over the possession
      of flats. On carefully going through the terms and conditions
      of the registered agreement, it appears that the opponents
                                                                             H
616      SUPREME COURT REPORTS                         [2019] 9 S.C.R.


A     have collected these charges under the guys (sic) of possession
      of the flats beyond the stipulated agreed consideration.
      Therefore, we find that complainants are entitled to get refund
      of an amount of Rs. 26,25,000/- since it was illegally collected
      by the opponents from the flat buyers of the complainant
      society. Complainants have not pressed refund of Rs.
B
      35,16,820/- allegedly extended as temporary loan to the
      opponents for completion of balance work. Therefore, we do
      not want to comment further. There is not documentary
      evidence to demonstrate that Rs. 46,40,000/- were incurred
      by the complainant society to complete the interior civil works.
C     Therefore, we are not inclined to consider this monetary claim.
      The registered agreement does not provide for development
      of garden. Therefore, prayer beyond the stipulations of
      agreement cannot be considered as pleaded by the learned
      counsel of the opponents.
D     [9] . Considering facts and circumstances of the case,
      opponents have failed to comply their statutory obligations
      u/s. 11 of the MOFA Act to execute the deed of conveyance
      and obtain Completion Certificate and Occupation Certificate.
      Therefore, the complainant’s prayer seeking directions to the
      opponents to fulfill statutory obligations are just and proper.
E     Complainant society has discharged initial burden to prove
      deficient service rendered by the opponents. Therefore,
      complaint must succeed for issue of directions to the opponents
      to fulfill the statutory obligations and refund of illegally
      collected excess amount from the members of the complainant
F     society.
                                  ORDER
      (1) Complaint is partly allowed.
      (2) Opponents, jointly and severally, are directed execute Deed
G     of Conveyance, by obtaining completion certificate and
      occupation certificate for transferring rights, interest and title
      of building and piece of land bearing Survey No. 22, Hissa
      No. 7, and bearing C.T.S. Nos. 99, 99(1 to 16) and assessed
      by Municipal Corporation of Greater Bombay in Ward No.
      KN 150512-00 No. K-5125 (1-2) 89A, 90, K-5125 (3) 898,
H
M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                            617
     HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

      K-5126 (1), 88 and K-5126 (3) 8890, in favour of complainant          A
      society within period of 90 days from date of the this order,
      failing which opponent shall pay Rs. 1,000/- per day to the
      complainant society from the date of this order till compliance.
      (3) Opponents, jointly and severally, are directed to pay
      Rs. 26,25,000/- [amount illegally collected for hading over           B
      the possession of the flats] along with interest @ 9% p.a.
      effective from the date of filing of complaint i.e. 04/10/2005
      within period of 90 days from the date of this order, failing
      which the rate of interest shall be payable @ 12% p.a. from
      04/10/2005 till its realization.
                                                                            C
      (4) Opponents shall bear their own costs and pay costs of
      Rs. 50,000/- to the complainant society within period of 90
      days from the date of this order.
      (5) Certified copies of this order be furnished to the parties”.
       3.8. In appeal against the order of the State Commission before      D
the National Commission, the appellants denied the receipt of loan amount
of Rs. 26,25,000/- and argued that the deletion of the name of the then
President of the respondent-society, who was a signatory to all the
receipts, was not warranted, as his presence would have clarified all the
issues which formed the subject-matter of the complaint; and that due to    E
the failure on the part of the respondent-society to remove the changes/
alterations made to the building, the Municipal Corporation refused to
issue the Occupancy Certificate. It was also argued that the State
Commission had no pecuniary jurisdiction in relation to the complaint in
this matter.
                                                                            F
      3.9. The National Commission rejected the contention that the
State Commission had no pecuniary jurisdiction for the reason that the
same was not urged before the State Commission and the matter was
decided on merits. The National Commission examined the record and
found that there was absolutely no evidence on record to show that the
alleged money was taken by the appellants for the purpose of completing     G
the pending works in the building. The National Commission, however,
observed that having agreed to pay a sum of Rs. 25,00,000/- to the
respondent-society, the appellants were bound by the admission so made
by them and were liable to that extent. As regards the arguments relating
                                                                            H
618            SUPREME COURT REPORTS                           [2019] 9 S.C.R.


A     to Occupancy Certificate, the National Commission was of the view
      that the appellants were negligent and there had been deficiency in service
      inasmuch as the appellants should not have handed over possession of
      the flats without obtaining the Occupancy Certificate. However, for the
      purpose of regularizing and legalizing the title of the members of
      respondent-society, it was preferred that a time bound order be made
B
      and, accordingly, the National Commission upheld the order passed by
      the State Commission with certain modifications.
             3.10. The National Commission, inter alia, observed, held and
      directed as under:-
C           “10. I have carefully considered the arguments of both the
            learned counsel and have examined the material on record.
            Basically I agree with the contention of the learned counsel
            for the appellant that all the receipts were issued by the
            President of the Society and he has been deleted from the
            array of the parties on the request of the complainant and
D           therefore, there is no proof that the money has been paid to
            the appellant. The State Commission has ordered only on
            presumption. Thus, the OP/appellant herein cannot be saddled
            with the responsibility to refund the amount of Rs. 26,25,000/
            - to the complainant as loan repayment. However, this is also
E           true that the appellant has admitted that he had agreed in the
            meeting dated 17.03.2003 to pay Rs. 25 lakhs to the
            complainant for the deficiency in service. Clearly this amount
            has not been paid by the OP to the complainant and therefore,
            the appellant No. 1 is liable to pay Rs. 25 lakhs to the
            complainant as per his own admission in the list of dates filed
F           along with the present appeal.
            11. So far as the question of obtaining the Occupancy
            Certificate is concerned, as per the provisions of MOFA the
            possession should not have been handed over to the members
            of the complainant society without obtaining occupancy
G           certificate and this is a clear unfair trade practice. It is being
            argued on behalf of the OP that there are additions and
            modifications in the building and therefore, it is difficult to
            obtain the certificate and the matter is getting delayed. This
            argument is not tenable as the situation has been created by
H
M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                        619
     HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

   the OPs themselves as they offered possession without the            A
   occupancy certificate. Clearly, not obtaining occupancy
   certificate is the deficiency on the part of the OP/appellant.
   12. Coming to the question of FSI, though there is a provision
   in the agreement in condition no. 42 that the allottees/
   purchasers shall not object to OP utilizing additional FSI,          B
   which may be available at the time of agreement or being
   made available even in a future date. However, this provision
   goes against the spirit of MOFA as this Commission in Vaibhav
   Development Corporation and others (supra) has held that it
   is obligatory upon the builder to obtain a full Occupancy
   Certificate, without which a Conveyance Deed in favour of            C
   the complainant society cannot be executed. However, there
   has to be a reasonable time for execution of conveyance deed
   in favour of the Society and this according to the said Rule
   has to be within four months if no period of conveying the
   title to the Society is mentioned in the Sale Agreement.             D
   13. As the OP has given possession to the members of the
   Society without obtaining Occupancy Certificate, the
   possession of allottees has become illegal. As the purchasers
   have paid full consideration of the flats, they are entitled to
   have legal possession and legal right and title. It is also seen     E
   from the observation of the State Commission that the
   appellants/opposite parties have not replied to the queries
   raised by the Municipal Corporation and therefore, they
   themselves were negligent and deficient in taking steps for
   getting the Occupancy Certificate. As complaint has been filed
   by the society, it is essential that the possession of its members   F
   is regularized and title of the members as well as of the Society
   is legalized. This can only be legalized if OP obtains
   Occupancy Certificate.
   Therefore, it is necessary to direct the OP to obtain the
   Occupancy Certificate in a time bound manner. In this respect,       G
   the order of the State Commission is perfectly valid so far as
   it relates to directing the OP to obtain Occupancy Certificate
   within 90 days. Once the Occupancy Certificate is obtained
   the title has to be conveyed to the Society within four months.
                                                                        H
620     SUPREME COURT REPORTS                        [2019] 9 S.C.R.


A     From this point of view, the condition No. 42 is against the
      provisions of MOFA. Hence, this condition will not be a binding
      on the other party. Therefore, the existence of this condition
      in the agreement shall only be seen as unfair trade practice.
      As the OP has not obtained the occupancy certificate and
      thereby the OP is not able to register the conveyance deed in
B
      favour of the complainant Society, the continuing deficiency
      on the part of the appellant/OP is evident. Therefore, I do not
      find any error in the order of the State Commission in respect
      of the OP obtaining occupancy certificate and then executing
      the conveyance deed in favour of the Society. The penalty of
C     Rs. 1,000/- per day was effective from 17.03.2015, however,
      looking at the difficulties of the appellant in getting the
      occupancy certificate due to some modifications, additions
      and alterations in the building, I deem it appropriate to put a
      lump sum compensation of Rs. 3 lakhs to be paid to the
      Complainant Society by the appellant for not obtaining
D
      occupancy certificate till today. It is further ordered that the
      order of the State Commission for paying Rs. 1,000/- per day
      shall be applicable now from the expiry of 60 days from the
      date of this order. This amount shall be paid regularly at every
      month to the complainant society till the occupancy certificate
E     is obtained and conveyance deed is executed in favour of the
      Society.
      14. As regard the objection of the appellants regarding
      pecuniary jurisdiction of the State Commission, it appears
      that this objection has not been taken before the State
F     Commission specifically. As the matter has now been decided
      by the State Commission on merits, the technical objection of
      pecuniary jurisdiction cannot be raised at this stage. This
      view gets support from the decision of the Hon’ble Supreme
      Court in Harshad Chiman Lal Modi Vs. DLF Universal and
      Anr., AIR 2005 SC 4446, wherein the Hon’ble Apex Court
G     has held as follows:-
         “So far as territorial and pecuniary jurisdictions are
         concerned, objection to such jurisdiction has to be taken
         at the earliest possible opportunity and in any case at or
         before settlement of issues. The law is well settled on the
H
 M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                              621
      HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

          point that if such objection is not taken at the earliest, it        A
          cannot be taken at a subsequent stage.”
      15. Based on the above discussion, the appellants are directed
      to pay Rs. 28,00,000/- (rupees twenty eight lakhs only) to the
      respondent No. 1 Society within a period of 45 days, failing
      which this amount shall carry an interest @ 8% p.a. from                 B
      date of this order till actual payment. Appellants are further
      directed to pay Rs. 1,000/- (rupees one thousand) per day
      after 60 days from date of this order to the Complainant Society
      till obtaining of the full Occupancy certificate. It is further
      directed that appellants shall convey the title of the property
      as detailed in the order of the State Commission in favour of            C
      the complainant Society by registered deed within a period of
      four months after obtaining the Occupancy Certificate. The
      impugned order of the State Commission stands modified
      accordingly. The cost of Rs. 50,000/- is also upheld. First
      Appeal No. 109 of 2015 stands disposed of accordingly.”                  D
       4. Assailing the order aforesaid, learned counsel for the appellants
has argued that as per the admitted position on record, the members of
the respondent-society had carried out additional constructions/alterations
to the building due to which, the Municipal Corporation was not issuing
the Occupancy Certificate and hence, the National Commission ought             E
not to have issued directions for obtaining the Occupancy Certificate.
The learned counsel has referred to the reply letter dated 01.10.2002 by
one Shri Nazeer H. Kadri in support of the contention that the members
of respondent-society did carry out alterations to their respective flats/
shops. The learned counsel has further submitted that the respondent-
society violated the terms of undertaking as mentioned in the pursi dated      F
21.03.2013 filed before the State Commission, wherein they had
undertaken to remove the illegal alteration, if so required by the Municipal
Corporation. The learned counsel has further pointed out that removal
of additional structures/changes/additions put up by the members of
respondent-society was the subject-matter of a writ petition, being W.P.       G
No. 970 of 2015, filed before the High Court of Judicature at Bombay,
which was disposed of by the order dated 12.06.2017 with directions
that a designated officer of the concerned ward shall visit the property
in question so as to ascertain whether there were illegal constructions/
unauthorized changes/additions/ alterations; and if such violations were
                                                                               H
622              SUPREME COURT REPORTS                               [2019] 9 S.C.R.


A     found, then to intimate the necessary parties prior to taking of any action
      for demolition or removal2.
             4.1 Learned counsel has also contended that when the State
      Commission had rejected the prayer for payment of Rs. 25,00,000/- to
      the respondent- society and the same was not the subject-matter of
B     appeal, the National Commission has gravely erred in awarding this
      amount to the respondent. Learned counsel has further submitted that
      even if handing over possession of flats to the members of the respondent-
      society in the absence of the Occupancy Certificate was being
      questioned, fact of the matter remains that illegal/unauthorized
      construction/alterations were carried out by the members of respondent-
C     society; and in these circumstances, the responsibility for delay in
      completion of all other requirements could not have been fastened on
      the appellants.
              5. Per contra, learned counsel for the respondent-society has
      supported the order passed by the National Commission as regards holding
D     the appellants responsible for the deficiency in services as also for the
      delay in obtaining the Occupancy Certificate. The learned counsel would
      submit that the appellants handed over the flats/commercial units not
      only without Occupancy Certificate but also without providing basic
      facilities such as water, electrical meter etc.; and in any case, non-
E     compliance with the conditions to obtain Occupancy Certificate speaks
      volumes about the deficiency of services on the part of the appellants.
      According to the learned counsel, the building is in the same condition as
      it was on the day of handing over possession to the members of
      respondent-society; in other words, the members of respondent-society
      have not carried out any alterations/constructions in the said premises.
F     While further refuting the contention of appellants that the Occupancy
      Certificate was not issued for unauthorized construction or alteration by
      the members of respondent-society, the learned counsel has contended,
      with reference to the correspondence with the Municipal Corporation,
      that Occupancy Certificate was not issued for want of compliance by
G     the appellants of various requisites and the attempt to shift the burden in
      that regard on the members of the respondent-society was entirely

      2
       The learned counsel for the appellants has further pointed out that the Municipal
      Corporation has initiated necessary proceeding, as noticed by the High Court in its
      order dated 07.01.2019 in Notice of Motion No. 221 of 2018 moved in W.P. No. 970 of
H     2015.
    M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                          623
         HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

unjustified. According to the learned counsel, the appellants had attempted   A
to amend the plan of the building which was resisted by respondent; and
there exists a dispute between the parties in relation to a portion of a
property demarcated for Recreational Ground inasmuch as the said portion
is being used by one garage owner as a parking space at the behest of
the appellants, which has resulted in harassment of the members of
                                                                              B
respondent-society.
       6. Having heard learned counsel for the parties and having perused
the material placed on record, we are satisfied that in the given set of
facts and circumstances, directions by the National Commission as
regards payment of a sum of Rs. 25,00,000/ by the appellants to the
respondent-society calls for no interference but then, other parts of the     C
order impugned call for suitable modification.
       7. The contention on the part of appellants as regards pecuniary
jurisdiction has only been noted to be rejected. The National Commission
has observed, and rightly so, that such a plea was not specifically raised
before the State Commission at the earliest opportunity; and the State        D
Commission having already decided the matter on merits, such a technical
objection as regards pecuniary jurisdiction could not have been
countenanced before the National Commission. We find no error in the
National Commission rejecting this plea as being wholly untenable at the
given stage.                                                                  E
       8. As regards merits of the case, to put it in a nutshell, the
respondent-society, while filing their complaint, sought for reimbursement
of the amount of: (i) Rs. 35,16,820/- that was borrowed by appellants;
(ii) Rs. 26,25,000/- collected towards possession charges; and (iii) Rs.
46,40,000/- towards the amount spent by the members for completing            F
the interior works in their respective units. By way of the application
dated 21.03.20133 the respondent-society did not press on prayer (d)
concerning the said amount of Rs. 35,16,820/- towards temporary loan
and at the same time, restricted their claim in prayer (f) to the extent of
Rs. 25,00,000/- with reference to the minutes of the meetings dated
17.12.2003 and 14.12.20034. The State Commission, while issuing               G
directions for executing the Deed of Conveyance by obtaining Completion
Certificate and Occupation Certificate, also directed the appellants to
pay Rs. 26,25,000/- with interest, being the amount illegally collected
3
    Reproduced hereinbefore in paragraph 3.4.
4
    Reproduced hereinbefore in paragraph 3.4.1.                               H
624            SUPREME COURT REPORTS                           [2019] 9 S.C.R.


A     towards possession charges. The State Commission, however, held that
      there was no documentary evidence to establish that the amount of Rs.
      46,40,000/- was incurred by the members of the respondent-society to
      complete the interior civil works. On the other hand, the National
      Commission agreed with the submissions of the appellants that the
      directions regarding refund of Rs. 26,25,000/- could not have been issued
B
      when there was no cogent proof and when the President of the society,
      who had issued the receipt in question, was deleted from the array of
      the parties on the request of the complainant. However, the National
      Commission ordered payment of Rs. 25,00,000/- by the appellants as
      agreed by them in the meeting dated 17.12.2003.
C             9. When the prayers made in the complaint are read along with
      the contents of the application dated 21.03.2013 as also with the findings
      of the State Commission and the National Commission, it may appear at
      the first blush that the amount claimed towards temporary loan in prayer
      (d) was given up by the respondent-society whereas no proof was found
D     in relation to amounts claimed in prayers (e) and (f) towards possession
      charges and interior civil works respectively. However, fact of the matter
      remains that there had been long drawn disputes between the parties on
      several issues, including those regarding monetary claims made by the
      respondent-society and its members; and meetings were held for resolution
      of such disputes. The prayers (d) to (f) for money recovery in the
E     complaint and the submissions made in the application dated 21.03.2013
      are required to be viewed in the context of such claims and the resolutions
      adopted in the meetings. In our view, it would be wholly inappropriate
      and unjustified to consider the prayers as made in the complaint and as
      modified in the application de hors the context and disjointed from the
F     decisions taken in the meetings aforesaid.
             10. Indisputably, in the application dated 21.03.2013 as moved
      before the State Commission, the respondent-society restricted its prayer
      for money recovery to a sum of Rs. 25,00,000/- with reference to the
      aforesaid minutes dated 17.12.2003 and 14.12.2003. It is at once clear
G     that the aforesaid sum of Rs. 25,00,000/- was agreed to be paid by the
      appellants in full and final settlement of the claim of the respondent-
      society. The appellants having agreed to make such payment, in our
      view, the National Commission has rightly put them to the terms of
      honouring their unequivocal commitment/promise. In the given set of
      facts and circumstance, we are unable to accept the contention that a
H
 M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                               625
      HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

particular part of order of the State Commission having not been                A
challenged by the respondent-society, the National Commission could
not have granted the relief otherwise available on the face of record. In
an overall view of the matter, when such a relief emanates from the
very commitment made by the appellants in the meetings aforesaid, the
National Commission had been fully justified in granting the same to the
                                                                                B
respondent-society. Therefore, we find no reason to consider any
interference in this part of direction by the National Commission (as
contained in paragraph 10 of the order impugned).
        11. Even when we find no reason to interfere with the above-
mentioned parts of the order impugned, it appears difficult to approve
the directions in the remaining parts thereof, particularly those relating      C
to other pecuniary reliefs. The National Commission has saddled the
appellants with a liability to pay compensation to the tune of Rs. 3,00,000/
- for not obtaining Occupancy Certificate and has issued further directions
to the appellants to obtain such certificate as also to execute the requisite
Deed and to pay Rs. 1,000/- per day for every day of delay. True it is          D
that Occupancy Certificate was not obtained by the appellants but then,
fact of the matter remains that the members of respondent-society chose
to take over possession without such certificate; and then, several
questions have arisen as regards the alteration allegedly carried out by
them for which, the Municipal Corporation has the objections to raise. In
any case, there appears nothing on record to find the basis for holding         E
the appellants liable for compensation and then, for assessing the quantum
of compensation, if at all there be any liability of the appellants. In other
words, there is no material on record to find if the respondent-society or
its members suffered any loss; and if so, the extent thereof. Therefore,
this part of the order impugned, directing the appellants to pay                F
compensation to the tune of Rs. 3,00,000/-, cannot be approved.
       12. As regards direction to appellants to convey the title of the
property in question by executing a registered Deed within a period of
four months after obtaining Occupancy Certificate, in our view, though
the appellants cannot avoid their legal obligation to execute the requisite     G
Deed but then, having regard to the facts and circumstances of the case
and more particularly the facts relating to the issuance of notices by the
Municipal Corporation; and the dispute/objection regarding alterations
by the members of the respondent-society having not been settled as yet
with the High Court having issued directions for inspection of the building
                                                                                H
626             SUPREME COURT REPORTS                            [2019] 9 S.C.R.


A     and for necessary follow-up steps, awarding of Rs. 1,000/- per day for
      every day of delay seems rather unwarranted. In the given situation,
      where the Municipal Corporation had been of the view that there were
      visible illegal constructions made by the members of respondent-society
      because of which the Certificate cannot be issued; and in view of the
      orders dated 12.06.2017 and 07.01.2019 passed by the High Court in
B
      W.P. No. 970 of 2015, the penalty of Rs. 1,000/- per day deserves to be
      waived at present but with the requirements on the parties to complete
      the respective requisites, while leaving it open for them to take recourse
      to appropriate remedies, in case of any grievance arising in future.
            13. Having regard to the fact and circumstances of this case and
C     looking to the nature of dispute, we find no justification for saddling the
      appellants with cost of Rs. 50,000/- either. The cost deserves to be made
      easy in this case.
            14. In the result:
D            (i) The impugned order dated 07.03.2018 is not interfered with, to
      the extent it relates to the payment of Rs. 25,00,000/- by the appellants
      to the respondent-society. The appellants shall make payment of this
      amount of Rs. 25,00,000/- within 45 days from today failing which, this
      amount shall carry interest @ 8% p.a. from today until payment.

E            (ii) The other part of the order impugned, saddling the appellants
      with liability to pay compensation to the tune of Rs. 3,00,000/- is set
      aside.
             (iii) Yet another part of the order impugned, requiring the appellants
      to pay Rs. 1,000/- per day after 60 days of the order and until obtaining
F     full Occupancy Certificate, is also set aside.
             (iv) As regards obtaining of Occupancy Certificate and execution
      of the Deed of Conveyance by the appellants, it is provided that: (a) the
      appellants shall complete all the requisites on their part for obtaining
      Occupancy Certificate within three months from today; and (b) the
      respondent-society and its members shall also ensure compliance of the
G
      requisites on their part (with reference to the orders passed by the High
      Court in W.P. No. 970 of 2015) within three months from today and for
      that matter, they may seek necessary directions from the High Court, if
      so required. Within two months of completion of all the requisites by the
      parties, the appellants shall execute the Deed of Conveyance in favour
H
 M/S TREATY CONSTRUCTION v. M/S RUBY TOWER CO-OP.                                 627
      HSG. SOCIETY LTD. [DINESH MAHESHWARI, J.]

of the respondent-society after obtaining the necessary Occupancy                 A
Certificate. As regards this part of the matter, it is also left open for the
parties to take recourse to appropriate remedies in accordance with law,
in case of any grievance arising in future.
        (v) The cost imposed on the appellants is waived and parties are
left to bear their own costs of this litigation.                                  B
       15. This appeal is partly allowed and the impugned order dated
07.03.2018 as passed by the National Commission stands modified to
the extent and in the manner indicated above.

Ankit Gyan                                               Appeal partly allowed.   C




                                                                                  D




                                                                                  E




                                                                                  F




                                                                                  G




                                                                                  H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Consumer Protection Act"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.