EXECUTIVE DIRECTOR, STEEL AUTHORITY OF INDIA & ORS.versusTYCOON TRADERS & ORS.
- Citation
- 2014 INSC 208
- Decided
- 26 March 2014
- Disposal
- Dismissed
- Bench
- GYAN SUDHA MISRA
Holding
The contract is unenforceable and illegal under Section 38(v) of the Wildlife (Protection) Act, 1972, and the High Court’s order to refund the entire amount stands.
Summary
The Steel Authority of India (SAIL) conducted an e‑auction for 1 lakh metric tonnes of iron‑ore fines, which Tycoon Traders won and paid the agreed price and security deposit. The contract was revalidated, but the Principal Chief Conservator of Forests refused permission to lift the ore because the Bhadra Wildlife Sanctuary had been declared a Tiger Reserve, invoking Section 38(v) of the Wildlife (Protection) Act, 1972. The Karnataka High Court held the contract frustrated and ordered SAIL to refund the entire amount paid by the respondent. SAIL appealed, contending a breach by the respondent and seeking to retain the earnest money. The Supreme Court examined whether the contract was enforceable or illegal under the Wildlife (Protection) Act and concluded that the contract’s object was forbidden by law, rendering it unenforceable. Consequently, the Court upheld the High Court’s decision and dismissed the appeal.
Issues considered
- Whether the contract for removal of iron‑ore fines is enforceable despite the denial of environmental clearance.
- Whether the contract is frustrated or illegal under Section 38(v) of the Wildlife (Protection) Act, 1972.
- Whether SAIL is entitled to retain the earnest money and security deposit.
Legislation cited
- Wildlife (Protection) Act, 1972s. 38(v)
Subjects
Judgment
[2014] 3 S.C.R. 838
A EXECUTIVE DIRECTOR, STEEL AUTHORITY OF INDIA &
ORS.
v.
TYCOON TRADERS & ORS.
(Civil Appeal No. 4026 of 2014)
B
MARCH 26, 2014
[GYAN SUDHA MISRA AND
PINAKI CHANDRA GHOSE, JJ.)
CONTRACT:
c
Contract becoming unenforceable impossible-Contract
for removal of iron ore fines-Granted in 2007 -- Renewed in
2009 -- Principal Chief conservator of Forests declining to
grant permission for lifting and transporting of iron ore fines
D by plying vehicles as the area was declared as 'Tiger Reserve'
-- High Court holding that contract stood frustrated and it was
illegal for SAIL not to refund entire amount -- Held: Contract
is unenforceable and further, it is a/so hit by s.38(v) of Wildlife
(Protection) Act -- High Court was correct in allowing the writ
E petition, and there is no reason to interfere - Wild life
(Protection) Act, 1972 - s.38(v).
In an e-auction for removal of iron ore fines,
respondent no.1, being the successful bidder deposited
the required amount and security deposits in March 2007.
F The contracted was revalidated till November 26, 2009.
However, the Principal Chief Conservator of Forests
declined to grant permission for lifting the iron ore fines
by plying vehicles as the area was declared as 'Tiger
Reserve'. The High Court allowed the writ petition of
G respondent no.1 holding that the contract itself stood
frustrated and could not have been performed by the
respondent even if it desired to do so, and further held
that in case of frustrated contract, parties must be
H 838
EXECUTIVE DIRECTOR, STEEL AUTH. OF INDIA v. 839
TYCOON TRADERS
restored to their original position and, as such, it was A
illegal for SAIL not to refund the entire money received
by it from the respondent.
Dismissing the appeal, the Court
HELD: B
The contract is unenforceable and further, the
contract is also hit by s.38(v) of the Wildlife (Protection)
Act, 1972 as amended in 2006 and, as such, the object
of the contract is forbidden by law. Therefore, the said c
contract is unlawful and cannot be given effect to. The
High Court was correct in allowing the writ petition, and
there is no reason to interfere with its order. [para 8-9]
[842-F-H]
CIVIL APPELLATE JURISDICTION : Civil Appeal No. D
4026 of 2014.
From the Judgment and Order dated 21.02.2012 of the
High Court of Karnataka at Bangalore in WP No. 38280 of
2011. E
Dr. Rajiv Dhawan, Anurag Sharma, Prashant Kumar,
Joseph Pookkatt, AP & J Chambers for the Appellants.
Shushil Kumar Jain, Satish G., H. Chandra Sekhar, AV.
Manavalan, V.N. Raghupathy for the Respondents. F
The Judgment of the Court was delivered by
PINAKI CHANDRA GHOSE, J. 1. Leave granted.
2. This appeal has been filed against the order dated
February 21, 2012 passed by the High Court of Karnataka in G
W.P. No.38280/2011.
3. The facts of the case reveal that on February 19, 2007,
Steel Authority of India (for short 'SAIL') had advertised for E-
auction of 1.00 lakh metric tons of iron ore (fines) from H
840 SUPREME COURT REPORTS [2014] 3 S.C.R.
A Kemmanagundi mines. On March 13, 2007, auction was held
and respondent No.1 was declared as the successful tenderer.
It would be evident from the sale order dated March 16, 2007
that the price was agreed upon at Rs.1, 132/- per metric ton plus
VAT of 4% aggregating to Rs. 11,32,00,000/- plus VAT of 4%.
s The appellant duly paid 176 lakhs being 15% of the total sale
value on March 15, 2007. Out of the said amount, Rs.58.86
lakhs being 5% of the total sale value was retained as Security
Deposit and a sum of Rs.117.74 lakhs was kept for adjustment
along with the final instalment. The balance payment was to be
c made in two monthly instalments with the grace period of 30
days with interest at the rate of 6% per annum. The entire
material was to be lifted within four months from the date of the
sale order.
4. On May 26, 2010, SAIL informed the respondent that
D the contract was revalidated by letter dated July 27, 2009 till
November 26, 2009 for a period of four months commencing
from July 27, 2009 and that the said contract had expired on
the lapse of the said period. It is also not in dispute that on
November 9, 2009, SAIL had addressed a letter to the Principal
E Chief Conservator of Forests (Wildlife) and Chief Wildlife
Warden, Karnataka, for renewal of permission granted for lifting
and transporting iron ore fines through Bhadra Wildlife
Sanctuary. The Principal Chief Conservator of Forests by letter
dated March 31, 2010, declined to grant such permission for
F the removal of 1.00 lakh tons of iron ore fines by plying vehicles.
In these circumstances, the High Court held that the contract
itself stood frustrated and could not have been performed by
the respondent even if it desired to do so, and further held that
in case of frustrated contract, parties must be restored to their
G original position.
5. On the basis of the aforesaid reason, the High Court
held that it is illegal and unconscionable for SAIL not to refund
the entire sum of money received by it from the respondent. The
High Court further held that the extension was granted at the
H
EXECUTIVE DIRECTOR. STEEL AUTH. OF INDIA v. 841
TYCOON TRADERS [PINAKI CHANDRA GHOSE, J.]
instance of SAIL and such extension amounts to waiver of the A
delivery conditions in the sale order dated March 16, 2007. The
High Court further held that the Bhadra Wildlife Sanctuary has
been declared as a 'Tiger Reserve' and that it is required to
be maintained as 'inviolate' for tiger population, and the
permission which has been refused cannot be granted in view B
of section 38(v) of the Wildlife (Protection) Act, 1972 as
amended in 2006. In this background, the writ petition was
allowed and SAIL was directed to refund the entire amount
within four weeks from the date of the order.
6. Being aggrieved, the appellant filed the present appeal C
before this Court. It was contended before us that this is a case
where there was a breach of contract which was committed by
the respondent and thereby SAIL has a right to forfeit the
earnest money and security deposit on the basis of such
breach. It is also stated whether it would come within the D
purview of a case of frustration of the contract. Dr. Rajiv
Dhawan, learned senior counsel appearing in support of the
appellants, has drawn our attention to the original agreement
and contended that there was a breach of the original
agreement since no clearances were obtained, payments were E
not made and further contract was not completed. It has been
further submitted that the respondent could not lift the iron ore
fines although SAIL could manage to get permission from the
State Government. Furthermore, it is the case of the appellant
that in the light of the respondent's request, the contract was F
revalidated on July 27, 2009 on the same terms and conditions
and, in fact, there was no waiver of any conditions stipulated
in the sale order dated March 16 2007; therefore, on this
question the High Court is not correct since, according to him,
there was no question of any waiver. He further submitted that G
there was rio frustration due to impossibility because the
Principal Chief Conservator of Forests had granted clearance.
7. Per contra, Mr. Sushil Kumar Jain, learned senior
counsel appearing on behalf of the respondent, drew our
attention to the letter dated March 31, 2010 whereby the H
842 SUPREME COURT REPORTS [2014] 3 S.C.R.
A Principal Chief Conservator of Forests (Wildlife) & Chief
Wildlife Warden, Bangalore, has specifically stated to the
General Manager (Operations) of the appellant that Bhadra
Wildlife Sanctuary was declared as a Tiger Reserve and was
required to be maintained as 'inviolate' for tiger population,
B hence, refused to allow the transportation through the said Tiger
Reserve under Section 38(v) of the Wildlife (Protection) Act,
1972 as amended in 2006. By the said letter, the request to
lift and transport the iron ore fines was rejected. Therefore, the
contract which was entered into between the parties, as would
c be evident, is in violation of the said Act and is against public
policy. Hence, the contract cannot be given effect to as the
contract is already frustrated. He also drew our attention to the
fact that the appellant by a fax message dated July 6, 2007 duly
relaxed condition Nos.8, 9 and 10 as stipulated in the G.O.
dated 2nd May, 2007. Learned senior counsel further
0
contended that by relaxing the said conditions, there was no
need for the respondent to obtain permission. On the contrary
it was the duty of the appellant to take permission from the
authority for implementation of such contract.
E 8. After considering the submissions made on behalf of
the parties, we find that there is substance to accept the
contentions of Mr. Jain, learned senior counsel in the matter.
In our opinion, the contract is unenforceable and further, the
contract is also hit by Section 38(v) of the Wildlife (Protection)
F Act, 1972 as amended in 2006. Therefore, the object of the
contract is forbidden by law. Hence, the said contract is unlawful
and cannot be given effect to. In these circumstances, we do
not accept the contention of Dr. Dhawan, appearing on behalf
of the appellants.
G
9. Accordingly, we hold the High Court was correct in
allowing the writ petition, and we do not find any reason to
interfere with the said order of the High Court. Hence, we do
not find any merit in the appeal, and the same is dismissed.
H R.P. Appeal dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.