Created byFuzzy Cloud

Supreme Court of India

ECE INDUSTRIES LIMITEDversusS.P. REAL ESTATE DEVELOPERS P. LTD. & ANR.

Citation
2009 INSC 1022
Decided
6 August 2009
Disposal
Dismissed

Holding

A higher court cannot disturb concurrent findings of lower courts rejecting an injunction unless those findings are perverse or arbitrary; in this case, the findings were sound and the balance of convenience opposed an injunction, so the appeals were dismissed.

Summary

ECE Industries Ltd., the plaintiff‑appellant, entered into a Development Agreement with S.P. Real Estate Developers for the construction of 1,800 apartments on a land parcel in Hyderabad. The respondents allegedly breached the agreement but proceeded with substantial construction, investing crores of rupees, and later deposited the full contract amount. The plaintiff sought injunctions under Order 39 Rule 1 & 2 read with Section 151 of the CPC to restrain further construction and alienation of the property. Both the trial court and the High Court, after examining an Advocate Commissioner’s report, found that substantial construction had already been completed and consequently refused the injunction, though the High Court modified some procedural directions. The Supreme Court held that when two lower courts concurrently reject an injunction, a higher court may interfere only if those findings are perverse or arbitrary; here they were not, and the balance of convenience lay against granting an injunction. Accordingly, the appeals were dismissed, leaving the lower courts' orders intact.

Issues considered

  • When can a higher court interfere with concurrent findings of lower courts rejecting an injunction?
  • Whether an injunction should be granted when substantial construction has been completed and the plaintiff has received the contract amount?
  • How does the balance of convenience affect the grant of an injunction under Order 39 and Section 151 CPC?

Legislation cited

Subjects

injunctionOrder 39Section 151balance of convenienceconcurrent findingsperverse findingscivil appealdevelopment agreementpossession suitconstruction

Judgment

                                 .'W
                     [2009] 12 S.C.R. 566

A                   ECE INDUSTRIES LIMITED                              t       ~

                                   v.
       S.P. REAL ESTATE DEVE!.,.OPERS P. LTD. & ANR.
             (Civil Appeal Nos. 5127=5128 of 2009)

                         AUGUST 6, 2009
8
        [TARUN CHATTERJEE AND R.M. LODHA, JJ.]

        Code of Civil Procedure, 1908 - 0. 39 r. 1 and 2, s. 151
  - Application for injunction under - Rejection by two courts
                                                                      ..,     .
c concurrently - Interference with - Held: Third court can
  interfere with the concurrent findings only when findings are
  perverse or arbitrary - On facts, courts below refused to grant
  injunction in favour of appellant from making any further
  construction in suit property - Findings of High Court and trial
D court as also report of Advocate Commissioner appointed by
  Supreme Court were to the effect that substantial construction
  has already bee1 made by respondent for which crores of
                                                                      .     ,

  rupees have been spent - Respondent has deposited the
  entire agreement amount though belatedly - Appellant will
E not suffer any substantial injury and balance of convenience
  lies against granting order of injunction - Thus, order of courts
  below justified - However, respondent would not claim
  equities over construction made.                                     ._ '

        In these appeals, thei order of High Court upholding
F the order of the triii\I court whereby it refused to grant the
    order of injunction restraining the respondent from
    making further construction in the suit property, is under
    challenge.

G       Dismissing the i'lppeals, the Court                             .,.
         HELD: 1.1. When two courts concurrently reject the
    application for injunction, it would not be open for the
                                                                                    ....
    third court to interf@re with the said concurrent findings
H                                566
              EGE INDUSTRIES LTD. v. S.P. REAL ESTATE           567
                       DEVELOPERS P.LTD .
., . -+
          until and unless it is brought to the notice of the third    A
          court that such findings are perverse or arbitrary; [Para
          12) [576-A-!3]

               1.2. As regard the construction on the suit property,
          the trial court came to the finding that as per the report   B
          of the commissioner and also as per the photographs
          produced that major construction work was undertaken
          and completed, and it must have required the respondent
1+        to invest crores of rupees. High Court came to the finding
          that the defendants/respondents have already taken over
          possession and made substantial construction. These          C
          are the two concurrent findings of fact arrived at by the
          High Court as well as by the trial court on the question
          of extent of construction on the suit property. [Para 12]
          [576-E-F]
                                                                       D
               1.3. In order to be satisfied on the question of
          construction in the suit property, Advocate
          Commissioner was appointed by this Court. A perusal of
          the report shows that out of 1800 flats to be constructed
          in the suit property in 8 Blocks, only in 295 apartments E
          in the Triangular area, work has not been started,
          whereas in the rest 1,555 apartments in 5 Blocks, work.
          is in progress at various stages. It is evident from the
          report that substantial progress has been made in the
          matter of construction on the suit property. Therefore, in
                                                                     F
          view of the concurrent findings of the courts below and
          also from the findings arrived at by the Advocate
          Commissioner appointed by this Court in his report, it is
          held that substantial construction has been made. [Paras
          13, 15 and 17] [576-D; 577-G-H; 578-A, E-F]
                                                                       G
              1.4. The Development Agreement-cum-General
          Power of Attorney was entered into by the defendants/
          respondents with the plaintiff-appellant and as per the
          terms and conditions, parties agreed that a sum of Rs.
          13.50 crores had to be paid besides 16.72 crores for the     H
    568    SUPREME COURT REPORTS             [2009] 12 S.C.R.

A service of consultancy and Rs. 28,36,175/- was the cost,         +•
  which comes to Rs. 30.50 crores. It was further agreed
  that it was only after the payment of the amount agreed
  upon, necessary documents were to be executed. Under
  the Agreement, the defendants/respondents had to
8 furnish bank guarantee in regard to the amount stated to
  have been paid in four cheques. It is true that the
  respondents, after paying the first installments had failed
  to pay the other installments payable within the time
  specified, under the agreement, but it is an admitted
C position that although, the deposits were belatedly made
  but the entire amount under the Agreement has already
  been deposited and in compliance with the Agreement,
  a Bank Guarantee has also been furnished. [Para 18)
    [578-G-H; 579-A-E]

D      1.5. Substantial construction has been made on the          ....
  suit property in respect of which crores of money have
  been invested by the defendants/respondents and since
  the defendants/respondents have already paid/deposited
  the amount payable in terms of the agreement, although
E belatedly, to the plaintiff/appellant, the plaintiff-appellant
  will not suffer any substantial injury if the construction
  work is not stopped by an order of injunction. The Court         1      •
  will not, as a matter of course, pass an order of injunction
  against the other party restraining the other party from
F raising any construction on the suit property till the
  disposal of the suit. If ultimately, the suit filed by the
  plaintiff-appellant is decreed, he can be compensated in
  damages or the defendants/respondents may be directed
  to pull down the construction and deliver vacant
G possession to the appellant when no equity can be
  claimed for such construction by the respondents. On
  the other hand, if at this stage, an order of injunction is
  granted against the defendants/respondents from
   proceeding with further construction in the suit property,
H it will undoubtedly destroy the constructions already
             ECE INDUSTRIES LTD. v. S.P. REAL ESTATE             569
                      DEVELOPERS P.LTD.
•   1   made by the defendants/respondents and the                      A
        defendants/respondents will suffer irreparable loss and
        injury for not allowing them to make construction on the
        suit property. That apart, the entire amount payable by
        the defendants/respondents having been paid/deposited
        in favour of the plaintiff/appellant, there is no reason to     B
        pass an order of injunction against the defendants/
        respondents when the plaintiff/appellant would not face
        substantial injury for permitting the defendants/
' +     respondents to proceed with the construction in the suit
        property. [Para 19] [579-E-H; 580-A-E]                          c
             1.6. The balance of convenience lies against granting
        an order of injunction, which, if granted, will substantially
        and irreparably injure and prejudice the defendants/
        respondents. The High Court was fully justified in
        upholding the order of the trial court refusing to grant any    D
        order of injunction in favour of the plaintiff/appellant.
        [Para 20] [580-F-G]

             1.7. When the High Court as well as the trial court had
        refused to grant injunction in favour of appellant based        E
        on consideration of materials on record and after
        considering the balance of convenience and
        inconvenience of the parties and when such findings of
        the High C()Urt as well as of the trial court does not suffer
        from any perversity or arbitrariness, it is not open to         F
        interfere with such order of the High Court as well as of
        the trial court. [Para 21] [580-G-H; 581-A]

             1.8. The trial court, while refusing to grant injunction
        in favour of the plaintiff/appellant gave certain directions
        to the defendants/respondents. Clause Nos. 1 and 2 as           G
        regard depositing the balance value of the property; and
        to furnish bank guarantee for the value of the unrealized
        post dated cheques need not remain as they have
        already been complied with by the defendants/
                                                                        H
    570       SUPREME COURT REPORTS                [2009] 12 S.C.R.


A respondents. Clause No. 3 that the defendants/
                                                                         I "
  respondents shall not claim equities over the
  construction made in the suit property and they would
  be bound by the decision in the suit, shall remain.
  Furthermore, the defendants/respondents, as directed by
B the trial court, shall furnish particulars of the prospective
  buyers of the residential units In advance to the
  Competent Authority/Urban Land Celling. [Para 22] [581·
  8-D]

C       CIVIL APPELLATE JURISDICTION : Civil Appeal No.
    5127-5128 '>f 2009.

        From the Judgment & Order dated 27.04.2009 of the High
    Court of Judicature Andhra Pradesh at Hyderabad in Civil
    Miscellaneous Appeal Nos. 1297, 1298 of 2008.
D
       R.F. Nariman, Dr. A.M. Singhvi, Akhil Sibal, Ajay
                                                                         ' '
  Bhargava, Vanita Bhargava (for M/s. Khaitan & Co.) Ananga
  Bhattcharyya, J. Mohan Reddy, Bupender Mahendra, Aribam
  Guneshwar Sharma, G. Ramakrishna Prasad for the appearing
E parties.

          The Judgment of the Court was delivered by

          TARUN CHATTERJEE, J. 1. Leave granted.

F      2. These two appeals have been filed from a common
  order passed by the High Court of Andhra Pradesh at
  Hyderabad, by which the High Court had affirmed an order of
  the Second Additional City Civil Judge at Hyderabad, disposing
  of an application for injunction filed at the instance of the
  plaintiff-appellant on two applications for injunction in a suit for
G recovery of possession and damages. The plaintiff/appellant
  alleged in their plaint that they are the owner of 67,824.50 sq.
  yards of land, situated at Borabanda, Fathenagar, Ashok Marg,                •
  Hyderabad (hereinafter referred to as the suit property). The
  plaintiff-appellant as well as the defendants/respondents
H executed a Development Agreement cum Power of Attorney
                             ECE INDUSTRIES LTD. v. S.P. REAL ESTATE                    571
                            DEVELOPERS P.LTD. [TARUN CHATTERJEE, J.]
                          on 21st of September, 2007. Under the said Agreement, the            A
         -( 1
                          defendants/respondents agreed to pay an aggregate sum of
                          Rs. 30.50 crores in the following manner :-

                               (i) Rs. 13.50 crores by way of non-refundable amount.

                              (ii) Rs. 16. 72 crores for utilizing the consultations, advice   B
                              and services of the petitioner over the suit property along
                              with service tax o the said amount for which invoices had
                              been raised by the plaintiff/appellant.
         ~        __,
                               (iii) Rs. 28,36,525/- towards the cost of land.                 c
                               3. It is the case of the plaintiff-appellant that since the
                          defendants/respondents had acted in breach of the agreement,
                          the same was duly terminated. Some of the breaches of the
                          agreement in question, as alleged by the plaintiff/appellant, are
                          as follows :-                                                        D
             f        "
                                (i)    The respondent No. 1 issued 12 post dated
                                       cheques for a total sum of Rs. 16. 72 crores - 11
                                       post dated cheqeus for Rs. 1.40 crores each and
                                       one post-dated cheque for a sum of Rs. 1.32. E
                                       Crores.

 (                             (ii)    The respondent did not furnish a Bank Guarantee
     f            I
                                       for the amqunt of Rs. 16.72 crores and also did not
                                       pay the service tax payable on the said. amount. \
                                                                                               F
                               (iii)   Out of the 12 post dated cheques given by the
                                       Respondent. 2-cheques were· honoured~ 4 of Rs. 1.4
                                       crores each were dishonoured on presentation and
                                       balance cheques were not presented.
,.                                                                                             G
                 )(
                               (iv)     The respondent no. 1 did not carry out construction
                                       in accordance with the sanctioned scheme.

                               (v)     The respondents entered into agreement with third
                                       parties without furnishing any details thereof.
                                                                                               H
    572      SUPREME COURT REPORTS                 [2009] 12 S.C.R.


A         (vi)   The respondents were selling dwelling units to
                                                                          I   '
                 persons who cannot be termed as members of the
                 weaker sections of thE? society."

      4. Since the agreement was terminable and when it was
  found by the plaintiff-appellant that the defendants/respondents
8
  were proceeding to change the nature and character of the suit
  property, a suit has been filed by the plaintiff/appellant for
  recovery of possession and damages.

       5. In the aforesaid suit, two applications for injunction under
C Order 39 Rule 1 and 2 read with Section 151 of the Code of
  Civil Procedure were filed by the plaintiff-appellant. In one
  application, the main relief that was claimed by the plaintiff-
  appellant was to restrain the defendants/respondents from
  alienating or transferring the suit property including the structures
D coming up thereon and in the other, for injunction over the suit
  property from changing the nature and character thereof
  pending disposal of the suit.

       6. While dealing with the applications for injunction, the
E Second Additional City Civil Judge at Hyderabad had
  appointed an Advocate Commissioner to find out the extent of
  construction raised by the defendants/respondents in the suit
  property as the plaintiff-appellant sought to contend that there
  was no construction at all in the suit property. The Advocate
  Commissioner appointed by the trial Court submitted his
F report, which is already on record. While deciding the
  applications for injunction, the said report was taken into
  consideration by the trial Court and after hearing the learned
  counsel for the parties, the trial Court was prim a facie satisfied
  that substantial construction was undertaken and completed by
G the defendants/respondents, which had required them to invest
  crores of rupees. The trial Court, considering this fact that
  substantial construction was completed, refused to grant an
  order of injunction in favour of the plaintiff-appellant from making
  any further construction in the suit property but the applications
H
                       ECE INDUSTRIES LTD. v. S.P. REAL ESTATE                    573
                      DEVELOPERS P.LTD. [TARUN CHATTERJEE, J.]
..         t        for injunction were, however, disposed of with the following          A
                    conditions :-

                        "(1) That the defendants/respondents shall deposit the
                        balance value of the property, which comes to around Rs.
                        28,00,0001- into Court within one month.                          B
                        (2) That it shall furnish bank guarantee for the value of the
                        unrealized post dated cheques, and pay/deposit the value
 j
                        of four cheques, which were dishonoured, within one
               '1
                        month from today.
                                                                                          c
                        (3) That the defendants/respondents shall not claim                   "
                        equities over the construction made in the land and they
                        are bound by the decision in the suit. The Defendants/
                        respondents shall furnish the particulars of the prospective
                        buyers of the residential units in advance to the Competent       D
      ~·        ~       Authority/Urban Land Ceiling, and it must be made clear
                        to the prospective buyers that their purchases are subject
                        to the result of the suit by making a 'specific recital' in the
                        agreement of sale or sale deed, as th·e case may be,"

                         7. Aggrieved by the order of the trial Court, two appeals        E
                  were preferred by the plaintiff/appellant before the High Court
. )
                1
                  of Andhra Pradesh at Hyderabad, which by the impugned
                  order, had affirmed the order of the trial Court on the question
                  of construction in the suit property, but set aside the directions
                  given by the trial Court so far as Clause Nos. 1 and 2, as              F
                  mentioned above, are concerned in the order of the trial Court.
                  It is these concurrent orders, which are now under challenge
                  before us in these appeals.


-                       8. At the time of admission of this matter, caveat had
                ,-already been filed by the defendants/respondents. In that view
                  of the matter, we fixed the hearing of the matter on 22nd of July,
                  2009. While hearing the petitions on merits, Mr. R. F Nariman,
                                                                                          G



                  learned senior counsel appearing for the plaintiff/appellant,
                  invited us to the report of the Advocate Commissioner and after
                                                                                          H
    574         SUPREME COURT REPORTS            (2009] 12 S.C.R.


A taking us through the same, sought to contend that in fact, no           ••
  construction has been made by the defendants/respondents
  and, therefore, in view of the admitted fact that the agreement,
  having been already cancelled, the defendants/respondents
  cannot be permitted to proceed with the construction on the suit
B property and the application for injunction, therefore, must be
  allowed. On the other hand, Dr. A. M. Singhvi, learned senior
  counsel appearing for the defendants/respondents also took us
  to the report of the Advocate Commissioner and other
  materials on record and at the same time, also had produced
                                                                           ,. .
c recent photographs, which were not produced in the Courts
  below and contended that the High Court was fully justified in
  affirming the orders of the trial Court inter alia holding prima
  facie that a substantial construction has already been made in
  the suit property, for which the defendants/respondents have
0 invested huge sum of money and in that view of the matter, the
  question of grant of injunction at this stage could not arise at     )     '
  all.

       9. After hearing the learned senior counsel for the parties
  and after going through the Advocate Commissioner's report
E and the impugned order of the High Court as well as of the trial
  Court, application for injunction and counter filed to the same,
  we were of the prima facie view that before deciding these           .         ;

  appeals finally on merits, it would be for ends of justice to find
  out the actual position of the suit property and for that reason,
F we appointed an Advocate Commissioner from this Court by
  our Order dated 23rd of July, 2009, who would inspect the suit
  property and submit a report by 27th of July, 2009 on the
  following points :-

          (i)    Whether constructions have been made on the
G
                 different blocks of the suit property and how many    *             -
                 blocks are still remaining vacant ?

          (ii) · If constructions have been made, what is the nature
                 and extent of such constructions ?
H
                     ECE INDUSTRIES LTD. v. S.P. REAL ESTATE                    575
                    DEVELOPERS P.LTD. [TARUN CHATIERJEE, J.]

i           1
                        (iii)   Whether such constructions can be said to be            A
                                substantial constructions or not ;

                        (iv)     Whether constructions have been completed in
                                 some blocks of the suit property and the flats
                                 constructed in such blocks are ready for use and
                                                                                        B
                                 occupation ;

                        (v)     · Also to see the local features.

• -f                    10. Accordingly, the learned Advocate Commissioner
                  visited the spot and submitted his report, which was also taken       c
                  up for consideration along with the main matter. The report of
                  the Advocate Commissioner may be kept on record.

                       11. On behalf of the plaintiff-appellant, Mr. Nariman, learned
                  senior counsel, submitted that even from the report submitted
                                                                                        D
                  by the Advocate Commissioner appointed by this Court, it
    ~       '>(
                  would be clear that substantial construction has not been made
                  in the suit property, whereas Dr. Singhvi, learned senior
                  counsel, also has drawn our attention to the report of the
                  Advocate Commissioner of this Court and submitted that there
                  cannot be any doubt that a substantial construction has already       E
                  been made by the defendants/respondents, for which a huge
                  sum of money has already been invested. On the question of
I           I
                  extent of construction made by the defendants/respondents in
                  the suit property, we have, therefore, considered the findings
                  of the High Court as well as of the trial Court and also the report   F
                  submitted by the learned Advocate Commissioner in this Court.
                  The High Court as well as the trial Court concurrently found, after
                  going through the report of the Advocate Commissioner, which
                  was appointed by the trial Court, that substantial construction
                  has already been made in the suit property. Since no objection        G
        _.,..
                  was raised by either of the parties to the report of the learned
                  Advocate Com·missioner, we accept the same without any
                  objection and direct that the same may be kept on record.

                       12. It is well settled now by catena of decisions of this
                                                                                        H
    576       SUPREME COURT REPORTS                 [2009] 12 S.C.R.


A Court that when·two Courts concurrently rejected the application
  for injunction, it would not be open for the third Court to interfere
  with the said concurrent findings until and unless it is brought
  to the notice of the third Court that such findings are perverse
  or arbitrary. So far as the findings of the trial Court regarding
B construction on the suit property is concerned, let us look into
  its said findings on the question of construction, which are as
  follows :-

          "In the light of the above circumstances, I find that, already
          as per the report of the commissioner and also as per
c         the photographs produced by him, major construction
          work was undertaken and completed, it must have
          required the respondent to invest crores of rupees."

       13. So far as the findings of the High Court on the question
D of extent of construction is concerned, it is also the finding of
  the High Court that the defendants/respondents have already              ••
  taken over possession and made substantial construction, as
  would be evident from the record and also from the report of
  the Advocate Commissioner, who was appointed by the trial
E Court. These are the two concurrent findings of fact arrived at
  by the High Court as well as by the trial Court on the question
  of extent of construction on the suit property. Still, in order to
  be satisfied on the question of construction in the suit property,       I   '
  as noted herinearlier, we appointed an Advocate
F Commissioner, who submitted its report.

        14. We have carefully examined the report of the Advocate
    Commissioner appointed by us, from which, following points
    may be noted :

G       "4. The Defendants/respondents' Counsel had supplied the
        layout of the site plan of the project. Principally, the entire
        project is divided into 8 Blocks. The plan for construction
        of 8 Blocks is approved by the authorities. A photocopy
        of the approved site plan of the project is annexed as
H
    ECE INDUSTRIES LTD. v. S.P. REAL ESTATE                   577
   DEVELOPERS P.LTD. [TARUN CHATTERJEE, J.]

      Annexure C-2. Each Block is divided into various Rows.         A
      There is no evennes\) in the number of Rows for each
      Block. Some Blocks have more Rows and some Blocks
      have less Rows. The Blocks are numbered in the site plan
      attached herewith as Annexure C-3. For better
      understanding and for better description of the areas in the   B
      Blocks, I had given numbers for the Rows in each Block
      separately in the site plan. The layout is as under :

 1. Block- I      2 Rows (60 Apartments)         295
 2. Block - II    2 Rows (150 Apartments)        Apartments          c
                                                 in the

 3. Block-Ill     2 Rows (85 Apartments)         Triangular
                                                 area. Work
                                                 has not been
                                                                     D
                                                 started.


4. Block- IV     6 Rows (330 Apartments)
5. Block-V       7 Rows (385 Apartments)         1,555
                                                                     E
6. Block-VI      2 Rows (240 Apartments)         Apartments

7. Block-VII     6 Rows (300 Apartments)         in the

8. Block-VIII    • 6 Rows (300 Apartments)       Rectangular
   area.                                         Work     in         F
                                                 progress at
                                                 various stages.

     5. It is stated that each Block will have ground floor (car
park) + 5 floors."
                                                                     G
     15. A perusal of the report of the learned Advocate
Commissioner therefore shows that out of 1800 flats to be
constructed in the suit property in 8 Blocks, only in 295
apartments in the Triangular area, work has not been started,
                                                                     H
    578      SUPREME COURT REPORTS               [2009] 12 S.C.R.


A whereas in the rest 1,555 apartments in 5 Blocks, work is in          ••
  progress at various stages. Therefore, it is evident from the
  perusal of the report of the Advocate Commissioner filed in this
  Court that substantial progress has been made in the matter
  of construction on the suit property as it is evident that such
B substantial construction has been completed at least 50% in
  the rectangular pieces of the suit property whereas work for
  Blocks IV to VIII are going on except Row Nos. 3 to 6 in Block
  No. VII where there is a mound of soil to a height of about 2
  floors and also boulders of granite rock cut into rectangular
                                                                       ,,.
                                                                              '
c pieces of identical sizes lying in the area. It is also found from
  the report that the constructions have been completed in Row
  Nos. 1 and 2 in Block No. VIII.

       16. Apart from that, 98% of the work is also completed on
  1st, 2nd and 3rd floors of Row Nos. 1 and 2 of Block No. VIII.
D Since the roads have not been laid and the parking has not
  been made available, according to the learned Advocate
                                                                       r      •       --
  Commissioner, the purchasers would not be in a position to
  occupy the flats. So far as other Blocks are concerned, the
  learned Advocate Commissioner was of the view that huge
E construction activity on a war-footing basis is under-way in
  respect of the disputed area which includes Blocks- IV to VIII.
                                                                       ;
       17. Therefore, in view of the concurrent findings of the.                  '
  Courts below and also from the findings arrived at by the
  Advocate Commissioner appointed by this Court in his report,
F
  we cannot but hold that substantial construction has been made
  and therefore, the submission of Mr. Nariman that substantial
  construction has not been made, cannot be accepted.

      18. Keeping this in mind, let us now proceed to consider
G whether substantial injury would be faced by the plaintiff-           ,,.
  appellant in the event an order of injunction is not granted to
  them. As noted hereinearlier, the Development Agreement-cum-
  General Power of Attorney was entered into by the defendants/
  respondents with the plaintiff-appellant and as per the terms
H
                       ECE INDUSTRIES LTD. v. S.P. REAL ESTATE                     579
                      DEVELOPERS P.LTD. [TARUN CHATTERJEE, J.]
     ~       ..     and conditions, parties agreed that a sum of Rs. 13.50 crores         A
                    had to be paid besides 16. 72 crores for the service of
    -·              consultancy and Rs. 28,36, 175/- was the cost, which comes to
                    Rs. 30.50 Crores. It was further agreed that it was only after
                    the payment of the amount agreed upon, necessary documents
                    were to be executed. That apart, under the Agreement, the             B
                    defendants/respondents ~ad to furnish bank guarantee in
                    regard to the amount stated to have been paid in four cheques.
                    In the plaint as well as in the application for injunction, it was
     ' -+           alleged by the plaintiff-appellant that the defendants/
                    respondents, after paying first installment, had failed to pay the    c
                    balance installments as agreed upon by them because of an
                                                                               ' the
                    order of injunction obtained by the plaintiff/appellant'agajnst
                   defendants/respondents in a writ petition filed by therlj in the
                    High Court of Andhra Pradesh at Hyderabad. It is true that the
                   defendants/respondents, after paying the first installment, had
              .,                                                                          D
         ~
                   failed to pay the other installments payable within the time
                   specified, under the Agreement, but it is an admitted position
                   that although, the deposits were belatedly made but the entire
                   amount under the Agreement has already been deposited and
                   in compliance with the Agreef!1ent, a Bank Guarantee has also
                   been furnished.                                                        E

                         19. Such being the state of affairs, i.e. substantial
     I
              •     construction has been made on the suit property in respect of
                   which crores of money have been invested by the defendants/
                    respondents and since the defendants/respondents have F
/                  already paid/deposited the amount payable in terms of the
                   agreement, although belatedly, to the plaintiff/appellant, we do
                   not think that the plaintiff-appellant will suffer any substantial injury
                   if the construction work is not stopped by an order ot injunction.
             1'
                   It is well settled that when construction has been made on a G
                   land, which is of considerable magnitude, and when the plaintiff
                   shall not face any substantial injury, if no order of injunction is
                   granted because of payment/deposit of the entire amount
                   payable by the defendant to the plaintiff under the Agreement,
                                                                                         H
    580     SUPREME COURT REPORTS                  [2009] 12 S.C.R.


A though belatedly, we are of the view that the Court will not, as         ••
  a matter of course, pass an order of injunction against the other
  party restraining the other party from raising any construction
  on the suit property till the disposal of the suit. If ultimately, the
  suit filed by the plaintiff-appellant is decreed, he can be
8 compensated in damages or the defendants/respondents may
  be directed to pull down the construction and deliver vacant
  possession to the plaintiff/appellant when no equity can be
  claimed for such construction by the defendants/respondents.
                                                                           + •
  On the other hand, in our view, if at this stage, an order of
c injunction   is granted against the defendants/respondents from
  proceeding with further construction in the suit property, it will
  undoubtedly destroy the constructions already made by the
   defendants/respondents and the defendants/respondents will
   suffer irreparable loss and injury for not allowing them to make
   construction on the suit property. That apart, in view of our
D                                                                          • •
   discussions made hereinabove, the entire amount payable by
   the defendants/respondents having been paid/deposited in
   favour of the plaintiff/appellant, there is no reason to pass an
   order of injunction against the defendants/respondents when the
   plaintiff/appellant would not face substantial injury for permitting
E the defendants/respondents to proceed with the construction in
   the suit property.
                                                                           • ,
        20. Accordingly, in view of our discussions made
  hereinabove, we are, therefore, of the view that the balance of
F convenience lies against granting an order of injunction, which,
  if granted, will substantially and irreparably injure and prejudice
  the defendants/respondents. For the reasons aforesaid, we are,
  therefore, of the view that the High Court was fully justified in
  affirming the order of the trial Court refusing to grant any order
G of injunction in favour of the plaintiff/appellant.                      '1"

         21. That apart, in our view, when the High Court as well
    as the trial Court had refused to grant injunction in favour of the
    plaintiff/appellant based on consideration of materials on record

H
                              ECE INDUSTRIES LTD. v. S.P. REAL ESTATE                     581
                             DEVELOPERS P.LTD. [TARUN CHATTERJEE, J.]

 "             -I         and after considering the balance of convenience and A
                          inconvenience of the parties and when such findings of the High
                          Court as well as of the trial Court do not suffer from any
"''                       perversity or arbitrariness, it is not open for this court to interfere
                          with such order of the High Court as well as of the trial Court.
                                                                                                  B
                                22. However, there is one another aspect of the matter.
                          As noted hereinearlier, the trial Court, while refusing to grant
                          injunction in favour of the plaintiff/appellant, has given certain
     ;          -i        directions to the defendants/respondents, which have already
                          been noted hereinearlier. In view of the fact that the Clause Nos.
                          1 and 2 have already been complied with by the defendants/ c
                          respondents, those clauses need not remain. So far as Clause
                          No. 3 is concerned, it appears to us that the said clause should
                          remain, that is to say, the defendants/respondents shall not
                          claim equities over the construction made in the suit property

           ,        -     and they would be bound by the decision in the suit. D
                          Furthermore, the defendants/respondents, as directed by the
                          trial Court, shall furnish particulars of the prospective buyers of
                          the residential units in advance to the Competent Authority/
  .                       Urban Land Ceiling as it must be made clear to the prospective
                          buyers that their purchases are subject to the result of the suit E
                          by making a 'specific recital' in the agreement of sale or sale
                          deed, as the case may be.
          ;.         •
                                23. In view of our disi::ussions made hereinabove, we do
                          not find any merit in these appeals.                           F
                               · 24. We, however, make it clear that whatever observations
                          we have made while deciding these two appeals, would not
                          stand in the way of the Courts below from deciding the merits
                          of the suit and it is also made clear that the trial Court shall not
                     -r   be influenced by any of the observations or findings made in G
                          this order or of the High Court, while deciding the application
         ,..              for injunction.

                              25. Considering the facts and circumstances of the present
                          case, we direct the trial Court to dispose of the suit at an early H
   582      SUPREME COURT REPORTS              [2009] 12 S.C.R.


A date, preferably within six months from the date of filing the            •
  written statement by the defendants/respondents. The
  defendants/respondents are directed to file their written
  statement within four weeks from this date, if not filed in the           -
  meantime.
B
       26. The appeals are thus dismissed. There will be no order
  as to costs.

   N.J.                                     Appeals dismissed.




                                                                    -.



                                                                    '   '


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "injunction"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.