Created byFuzzy Cloud

Supreme Court of India

DLF UNIVERSAL LTD.versusEKTA SETH & ANR.

Citation
2008 INSC 832
Decided
15 July 2008
Disposal
Disposed off

Holding

The forfeiture of earnest money was partially valid, requiring the seller to refund 50 % of the forfeited amount while the remaining 50 % stays forfeited.

Summary

DLF Universal Ltd sold a flat to Ekta Seth & others under an Apartment Buyer’s Agreement that allowed the seller to increase the price and stipulated forfeiture of earnest money for default. The buyers paid installments for five years but stopped after the seller demanded a cost‑escalation sum and failed to deliver possession within the agreed three‑year period. DLF cancelled the allotment, forfeited the earnest money and returned the balance. The buyers filed a petition under Section 12‑B of the Monopolies and Restrictive Trade Practices Act alleging unfair trade practice; the MRTP Commission ordered the return of the earnest money with interest. On appeal, the Supreme Court held that the parties were bound by the contract terms, that clause 4 gave DLF unrestricted power to raise cost and clause 16 relieved DLF of liability for possession delay, and that there were bona‑fide reasons for the delay. Exercising its discretion under Article 142, the Court ordered DLF to refund 50 % of the forfeited earnest money, the remaining 50 % to remain forfeited, with interest on delayed payment, and clarified that the order is specific to these facts.

Issues considered

  • The validity of forfeiture of earnest money under the Apartment Buyer’s Agreement despite delayed possession and cost escalation.
  • Whether the seller’s demand for additional payment constitutes an unfair trade practice under Section 12‑B of the MRTP Act.
  • Whether the MRTP Commission’s direction to return the earnest money with interest is maintainable.
  • The interpretation and effect of clause 4 (price escalation) and clause 16 (possession timeline) of the agreement.
  • The propriety of the Supreme Court exercising discretionary jurisdiction under Article 142 in granting partial relief.

Legislation cited

Subjects

contractearnest moneyforfeitureunfair trade practiceMRTP Actcost escalationpossession delayArticle 142discretionary jurisdictionapartment buyer agreement

Judgment

                                    [2008] 10 S.C.R. 999
      ~4




                                 DLF UNIVERSAL LTD.                            A
                                             V.
                                    EKTA SETH & ANR.
                             (Civil Appeal No. 4380 of 2008)
                                      JULY 15, 2008
      -,,                                                                      B
                [S.B. SINHA AND DR. MUKUNDAKAM SHARMA, JJ.]

                    Monopolies and Restrictive Trade Practices Act, 1969;
               S.12-B:
                       Unfair trade practice - Compensation - Apartment       c
                Buyer's Agreement - Default in payment of instalment by
                buyer - Cancellation of allotment and earnest money forfeited
                - Application claiming compensation on ground of unfair trade
                practice - MRTP Commission directing return of earnest
      L         money with interest - Correctness of - Held: Parties to con- D
          t     tract are governed by terms and conditions thereof - In terms
                of clause 4 of agreement, seller vested in itself unrestricted
                power to increase the cost - Allottee stopped payment of in-
                stalment after certain period as increase in cost of the flat was
                beyond his means - However, there were bonafide reasons E
              · on the part of the seller for not handing over possession of the
                flat in time and increase in cost - In such peculiar facts and
                circumstances of the case, in exercise of discretionary Juris-
                diction under Article 142 of the Constitution the seller directed
,),             to refund 50% of the amount of earnest money forfeited by it F
      ·\;
                to the buyerlallottee - Indian Contract Act, 1872 - Contract·-
                Enforcing of
                    Respondent booked a flat by entering into an Apart-
               ment Buyer's Agreement with the appellant. The sale price
               of the flat was payable in instalments. Respondent after G
               making payment of certain instalments stopped further
";..,.         payment. The appellant demanded further sum on ac-
               count of escalation of cost etc. in terms of the agreement,
               which was also not paid by the respondent. Therefore,
                                            999                            H
    1000      SUPREME COURT REPORTS              [2008) 10 S.C.R.


A appellant cancelled the allotment of the flat, forfeited the ·
  earnest money and returned the balance amount due.
  Aggrieved, the respondent filed an application before the
  M.R.T.P. Commission claiming compensation on the
  ground of unfair trade practice. The Commission directed
B the appellant to return the earnest money with certain rate        ~-
  of interest.· Hence the present appeal.
        Appellant contended that its action in forfeiting the
    earnest money was legal and justified.
c         Respondent submitted that the posse:ssion was pro-
    posed to be given to him within three years from the date
    of booking, i.e. in 1993 but the possession was not given
    even till 1998, therefore, the appellant could not have re-
    sorted to the power of forfeiture of the •~arnest money;
    that a sum of Rs.4,21,474.06/- demanded itowards cost of
0
    escalation,. increase in area, external electrification, fire
    fighting system and stand-by generators was exorbitant;
    and that it is unfair on the part of the appeillant to dema.nd
    such a huge amount in such a short span of six months.
E      · Disposing of the aJ>peal, the Court
           H~LD: 1.1. The parties to the contract are governed
  and bound by the terms and conditions c>f the agreemen~
  entered into. In the case in hand though it cannot be de-
  nied that the respondents at the time of s,igning the Apart-
F ment Buyer's Agreement was well awarn of the fact that             ~-
  additional amount could be demanded oin account of fac-
  tors enumerated in clause 4 of the agreiement, but what
  would be the max.iinum enhancement was not prescribed
  in' the agre·ement. It seems that by inserting the words "the
G decision of the Company in this regard would be final and
  blnding on the Apartment Allottee" in clause 4 of the agree-
  ment, the com·pany has vested in itself unrestricted power         -¥ ~
  to', increase
          .
                the cost. (Para - 10) [1006-G,D & "E] . .
                  .


           1.2 As per clause 16 of the agreement, it was pro-
H
                            DLF UNIVERSAL LTD. v. EKTA SETH &           1001
                                         ANR.

                   posed that the possession could be given within three A
                   years from the date of booking i.e. by 16th June, 1996 but
                 · the same was not done even till September 1998 and it is
                   evident from letter dated 22"d February, 1999 issued by
                   the Company that there was still some time and further
                   work to be done by it to enable it to hand over the pos- B
      -y
                   session. The only option given was that if there is delay
                   in delivering the possession t~en the allottee would be
                   entitled for refund of entire amount deposited with the
                   appellant but without any interest. In other words,.as per
                   the terms of the agreement no liability will accrue upon c
                   the appellant due to delay in handing the possession.
                   (Para - 11) [1006-F,G & H]
                        2.1 The instalments were duly paid by the respondent
                  for at least five years and payment was stopped thereafter
      >'.
                  on the ground that the increase in the cost of the flat was D
            )-    beyond his means and also the fact that appellant had failed
                  to deliver the possession of the flat in time. On the other
                  hand, there was bona fide reason on the part of the appel-
                  lant for their inability to handover the said possession with
                  the stipulated time and the increase in cost was on account E
                  of factors specifically enumerated in clause 2 (b) and clause
                  4 of the agreement. (Para -12) [1007-A & B]
                       2.2 In the facts and circumstances of the case, the
                  interest of justice would be subserved if this Court, in
 ).               exercise of its discretionary jurisdiction under Article 142 F
       -~
                  of the Constitution of India, direct that 50% of the amount
                  which was forfeited, to be refunded by the appellant to
                  the respondent within three months from the date of this
                  judgment and the balance 50% would be considered as
                  forfeited in terms of the provisions of the agreement. G
                  However, if the appellant fails to pay the said amount
\" -r·            within the stipulated period the same will carry an inter-
                  est @ 8% p.a. which will be calculated from the date when
                  the abovementioned period expires till the date of pay-
                  ment. (Para - 13) [1007-C,D & E]                             H
    1002       SUPREME COURT REPORTS               [:2008] 10 S.C.R.


A         3. It is clarified that this order is passe!d in the pecu-
    liar facts and circumstances of this case ;3nd would not
    be considered as precedence in any other matter. (Para -
    14) [1007-E]
         CIVILAPPELLATE JURISDICTION: Civil Appeal No. 4380
8   of 2008                                                             ·y-

         From the final Order dated 3/7/2006 of the Monopolies &
    Restrictive Trade Practices Commission, New Delhi in Com-
    pensation Application No. 53 of 2002
C        Ravinder Narain, Meghalee Barthakur, Akhil P. Chhabra,
    Su brat Deb and Rajan Narain for the Appellant.
      Amar Dave, E.C. Agrawala, Mahesh Agarwal, Rishi
  Agrawala, Amit Kumar Sharma, Ashutosh Gar{l, Neha Aggarwal
D and Gaurav Goel for the Respondents.
           The Judgment of the Court was delivere!d by
           Dr. MUKUNDAKAM SHARMA, J. 1. L1eave granted.
         2. This appeal is filed by the appellant challenging the le-
E gality of the judgment and order dated 3rd July, 2006 passed by
  the Monopolies and Restrictive Trade Practices Commission,
  New Delhi (for short "the Commission"). By tine aforesaid judg-
  ment and order the learned Commission made certain obser-
  vations and recorded findings against the appellant herein,
F which are under challenge in this appeal. The Commission re-
  corded a finding that the action of the appe,llant in increasing
  the cost which forced the respondent from making further pay-
  ments resulting in the cancellation referred 1to by the appellant
  was unfair trade practice and the appellant had no right to for-
G feit the earnest money. Consequently a direction was issued
  that the appellant should return the earnest money with interest
  thereon @ 9% per annum from the date of withholding the ear-
  nest money till the date of repayment in respect of the main flat
  as well as the parking space in respect of the letters dated 26th/
H 27th May, 1999.
                   DLF UNIVERSAL LTD. v. EKTA SETH &                  1003
                   ANR. [DR. MUKUNDAKAM SHARMA, J]
'*           3. We may briefly state the facts leading to the aforesaid       A
       direction of the Commission. The respondent herein booked a
       flat along with parking space in the appellant's DLF Regency
       Park, Gurgaon by entering into an Apartment Buyer's Agree-
       ment on 17th June, 1993. The sale price fixed by both the par-
- 'f
       ties was at Rs.16,37,448/- payable in 42 installments spread           B
       over a period of ten years commencing from 9th March, ending
       on 9th March, 2003. The respondent, herein admittedly paid all
       the installments due upto September 1998 which came to a
       sum of Rs.9,94,836/-. But thereafter he did not make any pay-
       ment of installment and therefor was considered to be a de-            c
       faulter by the appellant. In the meantime by letter date 19th Feb-
       ruary, 1998 the appellant demanded an additional amount of
       Rs. 4,21, 474.06 from respondent on account of cost of escala-
       tion, increase in area, external electrification, fire fighting sys-
       tern and stand-by generators. The said amount was to be paid
                                                                              D
"}     in four equal bi-monthly installment of Rs.1,05,368.52/- com-
       mencing from 15th March, 1998. The respondent did not honor
       the said demand. Consequently, the appellant cancelled the al-
       lotment of the flat vide its letter dated 26th May, 1999 and for-
       feited the earnest money and returned the balance amount due.
                                                                              E
             4. The respondent sent a legal notice dated 23rd May, 2001
       to the appellant contending that the cancellation of the allotment
       of the flat was illegal and arbitrary. The appellant sent a reply to
       the legal notice on 25th June, 2001 stating that the deductions
       made were lawful and in accordance with the terms of the agree-        F
       ment.

             5. The respondent, however, was not satisfied with the re-
       ply sent by the appellant and instead filed an application under
       Section 12-B of the Monopolies and Restrictive Trade Prac-
       tices Act, 1969 before the Commission for payment of com-              G
       pensation on the ground of unfair trade practice. It was con-
 "f-
       tended inter alia, by the respondent that the appellant was not
       entitled to forfeit the earnest money as they themselves were
       unable to give delivery of the flat within the stipulated time and
       more particularly, when the appellant has re-sold the said flat at     H
    1004       SUPREME COURT REPORTS                  [2008] 10 S.C.R.


A   a good price, therefore, as the appellant did not incur any loss,      """             ,:.,.~

                                                                                           1.l
    they could not and were not, entitled to forfeit th13 earnest money.
    The aforesaid submission of the respondent found favour with
    the Commission and it recorded the aforesaid finding and al-
    lowed the application filed by the respondent, consequent to
8   which the impugned directiol")S were issued which are under
                                                                           ~-
    challenge in this appeal.
        6. The issue which was raised and urged before us, there-
  fore, clearly revolves around the power and jurisdiction of the
  appellant in forfeiting the earnest money whiclh was to the tune
c of Rs.1,80,470/-. On going through the record w1e, however, found
  that out Rs.1,80,470/- an amount of Rs.1,69,012/-was forfeited
  as earnest money, out of which an amount of Rs. 1,62,412/-
  was for the flat and an amount of Rs. 6600/- was for the parking
  alloted to the respondent. The balance amount i.e Rs.9,571/-
D was forfeited by the appellant on account of interest on the de-
                                                                                -"
  layed payment.                                                           -\
           7~ On behalf of the learned counsel forthE~ appellant a spe-
    cific contention was raised before us that the appellant was
    entitled to forfeit the earnest money in terms of the stipulations
E   in the agreement arrived at between the parties with mutual
    consent. Learned counsel appearing for the appellant has drawn
    our attention to the various clauses of the said agreement which
    empowered the appellant to deduct the aforesaid earnest
    money. In this connection, reference was made to the provi-
F   sions contained in clause 8 and 9 of the said ;agreement which                   ..;
                                                                           )
    read as follows:
           "8. That the Company and the Apartment Allottee hereby
           agree that the amounts paid on registration to the extent
           of 10% of the sale price of the said premises and on
G
           allotment or in instalments as the case may be, will
           collectively constitute the earnest money. Non-fulfillment
           by the Apartment Allottee of the terms and conditions of        ¥""
           application fo( allotment, terms and conditions of sale arid
           those of this Agreement as also in the 1event of failure to
H
                              DLF UNIVERSAL LTD. v. EKTA SETH &                 1005
                              ANR. [DR. MUKUNDAKAM SHARMA, J]

                       sign this Agreement by Apartment Allottee within the time        A
                       allowed may entail the forfeiture of the earnest money.

                       9. That the time of payment of installments as stated in
                       schedule of payments (Annexure-11) is the essence of this
                       Agreement. It shall be incumbent on the ApartmentAllottee
      -y                                                                                B
                       to comply with the terms of payment and other terms and
                       conditions of sale, failing which he shall forfeit to the
                       Company the entire amount of earnest money and the
                       Agreement of sale shall stand cancelled and the Apartment
                       Allottee shall have no right, title, interest or claim of
                       whatsoever nature on the said premises. The Company              c
                       shall thereafter be free to resell and deal with the said
                       premises in any manner, whatsoever, at its sole discretion.
                       The amount(s), if any, paid over and above the earnest
                       money shall be however refunded to theApartmentAllottee
      /..              by the Company without any interest."                            D
            >-
                       Relying on the said provision it was contended by the
                       learned counsel for the appellant that the action of the
                       appellant in forfeiting the earnest money was legal and
                       justified.
                                                                                        E
                        8. Counsel for the respondent, however, refuted the afore-
                  said position contending, inter alia that the possession was pro-
                  posed to be given to the respondent on or before June 16, 1996
                  i.e. within three years from the date of booking, but the said
,.                possession was not given even till 1998, therefore, the appel-
            (                                                                           F
                  lant could and would not have resorted to the power of forfeiture
                  of the earnest money. It was submitted on behalf of the respon-
                  dent that a sum of Rs. 4,21,474.06/- demanded towards cost of
                  escalation, increase in area, external electrification, fire fight-
                  ing system and stand by gene.rators was exorbitant. It was also
                                                                                        G
                  submitted that it is unfair on the part of the appellant to demand
,;.   -,...,._.   such a huge amount in such a short span of six months.

                        9. The aforesaid submission of the respondent was also
                  advanced before the Commission and the same found favour
                  with the Commission. The learned Commission observed that             H
    1006      SUPREME COURT REPORTS                 [2008) 10 S.C.R.


A   substantial portion of the escalation has been attributed towards
    creating additional facilities and upgrading the flats, thus put-
    ting additional and unforeseen burden upon the allottee and that
    to, to be fulfilled in short span of time. The Commission further
    held that the contract was one sided and the respondent was
B   required to sign on the doted lines. While corning to the afore-
    said conclusion the Commission has relied upon one of its ear-
    lier order dated 2nd May, 2006 in Grahak Shayak Gurgon Vol-
    untary Consumer Association and Ors. v. DLF Universal Ltd.
    & Anr. wherein in respect to the same complex for which the
c   respondent filled the application for allotment, the escalation
    made by the appellant has been held to be unfair trade prac-
    tice.
          10. Th.e parties to the contract are governed and bound by
    the terms and conditions of the agreement emtered into. In the
D   case in hand though it cannot be denied that ithe respondents at
    the time of signing the Apartment Buyer's A{~reement was well
    aware of the fact that additional amount could be demanded on
    account of factors enumerated in clause 4, but what would be
    the maximum enhancement was not prescribed in the agree-
E   ment. It seem that by inserting the words "the decision of the
    Company in this regard would be final and bi.nding on the Apart-
    ment Allottee" in clause 4 of the agreement the company has
    vested in itself unrestricted power to increase the cost.
         11. Coming to the second aspect as per clause 16 of the
F agreement it was proposed that the possession could be given
  within three years from the date of booking i.e by 161h June, 1996
  but the same was not done even till September 1998 and it is
  evident from letter dated 22nd February, 199'9 that there was still
  some time and further work to be done by th13 appellant to· enable
G it to hand over the possession. As per clause· 18 the only option
  given was that if there is delay in delivering the possession then
  the allottee would be entitled for refund of entire amount depos-
  ited with the appellant but without any intemst. In other words as
  per the terms of the agreement no liability w!ll accrue upon the
H appellant due to delay in handing the poss ession.
                                               1
    '"):
                       DLF UNIVERSAL LTD. v. EKTA SETH &                  1007
                       ANR. [DR. MUKUNDAKAM SHARMA, J]

                 12. In the present case we find that the installments were       A
           duly paid for at least five years and payment was stopped there-
           after on the ground that the increase in the cost of the flat was
           beyond the means of the respondent and also the fact that ap-
    - '(   pellant had failed to deliver the possession of the flat in time.
           On the other hand as submitted there were bona fide reasons            B
           on the part of the appellant for their inability to handover the
           said possession within the stipulated time and the increase in
           cost was on account of factors specifically enumerated in clause
           2 (b) and clause 4.
                  13. Considering the entire facts and circumstances of the       c
           case, we are of the considered opinion that the interest of jus-
           tice would be subserved if we, in exercise of our discretionary
           jurisdiction under Article 142 of the Constitution o"f India, direct
 ;_        that 50% of the amount which was forfeited be refunded by the
      ?    appellant to the respondent within three months from the date          D
           of this Judgment and the balance 50% would be considered as
           forfeited in terms of the provisions of the agreement. However,
           if the appellant fails to pay the said amount within the stipulated
           period the same will carry an interest @ 8% p.a. which will be
           calculated from the date when the abovementioned period ex-            E
           pires till the date of payment.

                14. We also make it clear that this order is passed in the
           peculiar facts and circumstances of this case and would not be
>
      1    considered as precedence in any other matter.
                                                                                  F
                 15. The appeal stands disposed of in terms of the afore-
           said directions. There will be no order as to costs.

           S.K.S.                                       Appeal disposed of


l'~>f-


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "contract"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.