Created byFuzzy Cloud

Supreme Court of India

DELHI METRO RAIL CORPORATION LTD.versusDELHI AIRPORT METRO EXPRESS PVT. LTD.

Citation
2024 INSC 292
Decided
10 April 2024
Disposal
Case Allowed

Holding

The Court held that the curative petitions are maintainable and that the Supreme Court erred in restoring a patently illegal arbitral award, which must be set aside.

Summary

The Delhi Metro Rail Corporation (DMRC) and Delhi Airport Metro Express Private Ltd (DAMEPL) entered into a 2008 concession agreement for the Delhi Airport Metro project. DAMEPL alleged safety defects, issued a cure notice, and later terminated the agreement; an arbitral tribunal awarded substantial sums to DAMEPL. The High Court Division Bench set aside the award as perverse and patently illegal, citing the Commissioner of Metro Railway Safety (CMRS) certificate and the contract's "effective steps" clause. The Supreme Court, on a Special Leave Petition, restored the award, but a curative petition was filed alleging a miscarriage of justice. The Court held that the curative petition was maintainable and that the Supreme Court had erred in restoring an award that ignored vital evidence and was patently illegal, thereby setting aside the award and halting execution proceedings.

Issues considered

  • Whether the curative petition under Article 142 is maintainable in this case.
  • Whether the Supreme Court was justified in restoring the arbitral award set aside by the High Court Division Bench on the ground of patent illegality.
  • Whether the arbitral tribunal erred in interpreting clause 29.5.1(i) of the concession agreement regarding "effective steps".
  • Whether the CMRS certificate was a vital piece of evidence relevant to the validity of the termination.

Legislation cited

Subjects

Curative PetitionArbitral awardsMiscarriage of justicePatent illegalitySpecial leave to appealConcession AgreementArbitrationDefectsFaulty constructionDeficient designsCureEffective steps to cureVital evidence on record

Judgment

                  [2024] 4 S.C.R. 473 : 2024 INSC 292

                 Delhi Metro Rail Corporation Ltd.
                                  v.
                Delhi Airport Metro Express Pvt. Ltd.
                Curative Petition (C) Nos.108-109 of 2022
                                     In
                Review Petition (C) Nos.1158-1159 of 2021
                                     In
                  (Civil Appeal Nos 5627-5628 of 2021)
                                  10 April 2024
           [Dr Dhananjaya Y Chandrachud,* B R Gavai and
                          Surya Kant, JJ.]

                            Issue for Consideration
       (i) Whether the curative petition is maintainable; and (ii) Whether
       this Court (two-judge Bench) was justified in restoring the arbitral
       award which had been set aside by the Division Bench of the
       High Court on the ground that it suffered from patently illegality.

                                   Headnotes
       Curative Petition – Curative Jurisdiction may be invoked if
       there is a miscarriage of justice:
       Held: The Supreme Court laid down an overarching principle in
       Rupa Hurra v. Ashok Hurra [2002] 2 SCR 1006 that the Court may
       entertain a curative petition to (i) prevent abuse of its process; and
       (ii) to cure a gross miscarriage of justice – The enumeration of
       the situations in which the curative jurisdiction can be exercised
       is not intended to be exhaustive – The Court went on to lay down
       certain procedural requirements to entertain a curative petition
       such as a certificate by a Senior Advocate about fulfilling of the
       requirements. [Paras 33 and 34]
       Arbitration and Conciliation Act 1996 – s.34 – Scope of
       interference of courts with arbitral awards:
       Held: Section 34 of the Arbitration Act delineates the grounds for
       setting aside an arbitral award – In addition to the grounds on
       which an arbitral award can be assailed laid down in section 34(2),
       there is another ground for challenge against domestic awards,
       such as the award in the present case – Under Section 34(2-A)
       of the Arbitration Act, a domestic award may be set aside if the
* Author
474                                                               [2024] 4 S.C.R.

                        Digital Supreme Court Reports


       Court finds that it is vitiated by ‘patent illegality’ appearing on the
       face of the award. [Paras 36, 37]
       Arbitration and Conciliation Act 1996 – s.34 – Setting aside
       of domestic award – Ground of patent illegality:
       Held: The ground of patent illegality is available for setting aside
       a domestic award, if the decision of the arbitrator is found to be
       perverse, or so irrational that no reasonable person would have
       arrived at it; or the construction of the contract is such that no fair
       or reasonable person would take; or, that the view of the arbitrator
       is not even a possible view – A ‘finding’ based on no evidence
       at all or an award which ignores vital evidence in arriving at its
       decision would be perverse and liable to be set aside under the
       head of ‘patent illegality’ – An award without reasons would suffer
       from patent illegality – The arbitrator commits a patent illegality by
       deciding a matter not within his jurisdiction or violating a fundamental
       principle of natural justice. [Para 40]
       Constitution of India – Art.136 – Arbitration and Conciliation
       Act 1996 – ss. 34, 37 – Remedy u/Art. 136 against a decision
       rendered in appeal u/s. 37 of 1996 Act:
       Held: In the statutory scheme of the Arbitration Act, a recourse to
       s.37 is the only appellate remedy available against a decision u/s.
       34 – The Constitution, however, provides the parties with a remedy
       u/Art. 136 against a decision rendered in appeal u/s. 37 – This
       is the discretionary and exceptional jurisdiction of the Supreme
       Court to grant Special Leave to Appeal – While adjudicating the
       merits of a Special Leave Petition and exercising its power u/Art.
       136, this Court must interfere sparingly and only when exceptional
       circumstances exist, justifying the exercise of this Court’s discretion
       – The Court must apply settled principles of judicial review such
       as whether the findings of the High Court are borne out from the
       record or are based on a misappreciation of law and fact – In
       particular, this Court must be slow in interfering with a judgement
       delivered in exercise of powers u/s. 37 unless there is an error in
       exercising of the jurisdiction by the Court u/s. 37. [Paras 42 and 43]
       Curative Petition – The petitioner-DMRC and DAMEPL (a
       special purpose vehicle incorporated by a consortium)
       entered into the Concession Agreement (2008 agreement) –
       DAMPEL was to undertake among other things, the design,
       supply, installation, testing and commissioning of railway
[2024] 4 S.C.R.                                                             475

                    Delhi Metro Rail Corporation Ltd. v.
                    Delhi Airport Metro Express Pvt. Ltd.

     system – Dispute arose between the parties – DAMEPL
     alleged that the line was unsafe to operate – Operations were
     stopped – DAMEPL issued a notice to DMRC listing defects
     attributable to faulty construction and deficient designs
     which affected project safety – DMRC was requested to
     cure the defects within 90 days from the date of this notice
     – Thereafter, DAMPEL issued another notice terminating the
     2008 agreement as defects were not cured within 90 days –
     Arbitral Tribunal passed award in favour of DAMPEL – Single
     Judge of the High Court dismissed the petition filed u/s. 34
     of 1996 Act – Division Bench of the High Court allowed the
     appeal u/s. 37 of 1996 Act in part – DAMEPL moved a SLP
     u/Art. 136 of the Constitution – A two-judge bench of the
     Supreme Court allowed the appeal, and restored the award
     – Correctness:
     Held: Commissioner of Metro Railway Safety (CMRS), after inquiry
     and inspection had issued sanction for running of the metro line
     – In the instant case, the Division Bench of the High Court found
     the award to be perverse, irrational and patently illegal since it
     ignored the vital evidence of CMRS certification in deciding the
     validity of termination – It underlined the significance of the CMRS
     sanction under the Metro Railways (Operation and Maintenance)
     Act, 2002 – Also, clause 29.5.1(i) of the 2008 agreement entitles
     the concessionaire to terminate the agreement if DMRC “failed to
     cure such breach or take effective steps for curing such breach”
     within the cure period – Pertinently, the clause uses two separate
     phrases, “cure” and “effective steps to cure” – The Tribunal found
     that since certain defects remained after the cure period, this was
     indicative of the fact that the defects were not cured and that no
     effective steps were taken – The Tribunal fails to explain what
     amounts to an ‘effective step’ and how the steps taken by DMRC
     were not effective, within the meaning of the phrase – Parties
     clearly intended that once a cure notice was served on a party, it
     would be open to them to either cure defects or to initiate effective
     steps, even if they could not culminate into the complete curing of
     defects within the cure period – Incremental progress, even if it
     does not lead to complete cure, is an acceptable course of action
     to prevent termination according to the 2008 Agreement – The
     decisions of the Single Judge of the High Court and this Court
     (two-judge bench) are similarly silent on the aspect of “effective
     steps” – The judgment of this Court also never tested the relevance
476                                                             [2024] 4 S.C.R.

                        Digital Supreme Court Reports


       of the CMRS certificate vis-à-vis “effective steps” – Admittedly,
       some of the defects were cured in their entirety and steps were
       taken by DMRC to cure the remainders – DMRC did take certain
       steps to alleviate DAMEPL’s concerns so as to warrant this change
       of position – There is no explanation forthcoming in the award
       about why none of these steps initiated during the cure period
       were ‘effective steps’ – This gap in reasoning stems from the
       arbitral tribunal wrongly separating the issue of termination and
       the CMRS certificate – The structure and safety of the project,
       as certified by the CMRS, were thus relevant before the Tribunal,
       making the CMRS certificate a vital piece of evidence in deciding
       the issue – The CMRS certificate was relevant evidence about
       the safety of the structure – The arbitral tribunal erroneously
       rejected the CMRS sanction as irrelevant – The Division Bench
       correctly held that the arbitral tribunal ignored vital evidence on
       the record, resulting in perversity and patent illegality, warranting
       interference – The conclusions of the Division Bench are, thus, in
       line with the settled precedent including the decisions in Associate
       Builders and Ssangyong – The judgment of the two-judge Bench
       of this Court, which interfered with the judgment of the Division
       Bench of the High Court, has resulted in a miscarriage of justice
       – Thus, Curative Petitions allowed. [Paras 44, 48, 49, 50, 53,
       54, 58, 67, 68]

                                Case Law Cited
            Rupa Hurra v. Ashok Hurra [2002] 2 SCR 1006 : 2002
            4 SCC 388; Associate Builders v. Delhi Development
            Authority [2014] 13 SCR 895 : 2015 3 SCC 49;
            Ssangyong Engineering & Construction Co. Ltd. v. NHAI
            [2019] 7 SCR 522 : 2019 15 SCC 131 – relied on.

                                  List of Acts
       Arbitration and Conciliation Act 1996; Arbitration and Conciliation
       (Amendment) Act, 2015; Metro Railways (Operation and
       Maintenance) Act, 2002.

                               List of Keywords
       Curative Petition; Arbitral awards; Miscarriage of justice; Patent
       illegality; Special leave to appeal by the Supreme Court; Concession
       Agreement; Arbitration; Defects; Faulty construction; Deficient
       designs; Cure; Effective steps to cure; Vital evidence on record.
[2024] 4 S.C.R.                                                                            477

                         Delhi Metro Rail Corporation Ltd. v.
                         Delhi Airport Metro Express Pvt. Ltd.

                                       Case Arising From
       INHERENT JURISDICTION: Curative Petition(C) Nos. 108-109 of
       2022
       In
       Review Petition(C) Nos. 1158-1159 of 2021
       In
       Civil Appeal Nos. 5627-5628 of 2021
       From the Judgment and Order dated 23.11.2021 in R.P.(C) No. 1158
       and 1159 of 2021 and dated 09.09.2021 in C.A. No. 5627 and 5628
       of 2021 of the Supreme Court of India
                                   Appearances for Parties
       R. Venkataramani, AG., K.K. Venugopal, Parag P Tripathi, Maninder
       Singh, Sr. Advs., Tarun Johri, Ankur Gupta, Vishwajeet Tyagi,
       Srinivasan Ramaswamy, Chitvan Singhal, Ms. Ashita Chawla, Ankur
       Talwar, Ms. Arushi Mishra, Ameyavikrama Thanvi, Kartikey Aggarwal,
       Advs. for the Petitioner.
       Harish N Salve, Kapil Sibal, J.J. Bhatt, Prateek Seksaria, Sr. Advs.,
       Mahesh Agarwal, Rishi Agrawala, Shri Venkatesh, Megha Mehta
       Agarwal, Pranjit Bhattacharya, Ms. Madhavi Agarwal, Suhael Buttan,
       Vineet Kumar, Ms. Manisha Singh, Nishant Chothani, E.C. Agrawala,
       Advs. for the Respondent
                       Judgment / Order of the Supreme Court
                                             Judgment
       Dr Dhananjaya Y Chandrachud, CJI
       Table of Contents*

        A.     Factual Background............................................................ 3
        B.     DMRC’s claim and the Tribunal’s findings......................... 7
        C.     Decisions of the High Court............................................... 10
        D.     Judgment of this Court in appeal....................................... 11
        E.     Issues in the Curative Petition........................................... 12

* Ed. Note: Pagination as per the original Judgment.
478                                                                              [2024] 4 S.C.R.

                            Digital Supreme Court Reports



        F.    Submissions........................................................................ 12
        G. Analysis............................................................................... 16
              I. Curative Jurisdiction may be invoked if there is a
                 miscarriage of justice..................................................... 16
              II. Scope of interference of courts with arbitral awards..... 19
              III. The award was patently illegal....................................... 24
                     i. Interpretation of the termination clause by the
                        Tribunal was unreasonable.................................... 26
                     ii. The award overlooked vital evidence and
                         matters on the record............................................ 29
        H.    Conclusion........................................................................... 37


1.     The curative jurisdiction of this Court under Article 142 of the
       Constitution has been invoked in regard to its decision in Delhi Airport
       Metro Express Private Limited vs. Delhi Metro Rail Corporation
       Ltd.1. The judgment remained undisturbed in the exercise of the
       review jurisdiction of this Court.2
       A.     Factual Background
2.     The petitioner, Delhi Metro Rail Corporation3 is a state-owned
       company wholly owned by the Government of India and the National
       Capital Territory of Delhi. The respondent, Delhi Airport Metro
       Express Private Limited4 is a special-purpose vehicle incorporated
       by a consortium comprising of Reliance Infrastructure Limited
       and Construcciones Y Auxiliar de Ferrocarriles SA, Spain. The
       consortium bagged the contract for the construction, operation and
       maintenance of the Delhi Airport Metro Express Ltd5 in 2008. The
       Concession Agreement6 envisaged a public-private partnership


1    (2022) 1 SCC 131.
2    Review Petition (C) Nos. 1158-1159/2921.
3    “DMRC”
4    “DAMEPL”/” Concessionaire”
5    “AMEL”
6    “2008 Agreement”
[2024] 4 S.C.R.                                                          479

                     Delhi Metro Rail Corporation Ltd. v.
                     Delhi Airport Metro Express Pvt. Ltd.

      for providing metro rail connectivity between New Delhi Railway
      Station and the Indira Gandhi International Airport and other points
      within Delhi.
3.    Under the 2008 Agreement, DAMEPL was granted exclusive rights,
      license and authority to implement the project and concession in
      respect of AMEL. This included the right to manage and operate
      the Project as a commercial enterprise. DMRC was to undertake
      clearances and bear costs relating to land acquisition, and civil
      structures, while DAMEPL was to undertake among other things,
      the design, supply, installation, testing and commissioning of railway
      systems. DAMEPL was to complete the work in two years, and
      thereafter, to maintain AMEL until August 2038.
4.    In April 2012, DAMEPL sought a deferment of the concession fee,
      citing delays in providing access to the stations by DMRC. DAMEPL
      stated that while AMEL had been running without a glitch since 23
      February 2011, the retail activity had not picked pace. DAMEPL
      urged DMRC to extend their support, to this first-of-its-kind public-
      private partnership by deferring the concession fee payable by
      DAMEPL.
5.    There was an exchange of correspondence between the parties
      which ultimately led the Ministry of Urban Development to convene
      a meeting of stakeholders in July 2012. A Joint Inspection Committee
      was set up to inspect the defects alleged by DAMEPL.
6.    Meanwhile, DAMEPL expressed its intention to halt operations,
      alleging that the line was unsafe to operate. Operations were stopped
      on 08 July 2012. On 09 July 2012, DAMEPL issued a notice to DMRC
      containing a ‘non-exhaustive’ list of eight defects which according to
      them, affected the performance of their obligations under the 2008
      Agreement7. The notice stated that the defects were attributable to
      faulty construction and deficient designs which affected project safety.
7.    DAMEPL stated that the defects caused a “material adverse effect”
      on the performance of the obligations by it to operate, manage and
      maintain the project. DMRC was therefore requested to cure the
      defects within 90 days from the date of this notice, failing which
      it stated that it would be considered that a “Material Breach” and


7    “Cure Notice”
480                                                         [2024] 4 S.C.R.

                             Digital Supreme Court Reports


       a “DMRC Event of Default” had occasioned, entitling DAMEPL to
       terminate the 2008 agreement.
8.     On 8 October 2012, DAMPEL issued a notice terminating the 2008
       agreement.8 The termination notice stated that as 90 days had
       elapsed since the cure notice in spite of which the defects had not
       been cured within the ‘cure period’, DAMEPL as Concessionaire
       was terminating the agreement in terms of clause 29.5.1 of the
       2008 agreement.
9.     DMRC initiated conciliation under clause 36.1 of the 2008 Agreement.
       Since conciliation did not succeed, DMRC initiated arbitration
       proceedings on 23 October 2012 under clause 36.2 of the 2008
       agreement.
10. On 30 June 2013, DAMEPL halted operations and handed over the
    line to DMRC. Before this, on 19 November 2012, both parties made
    a joint application to the Commissioner of Metro Railway Safety9
    for re-opening of AMEL for public carriage of passengers. Enclosed
    with the application, was an administrative note jointly signed by
    representatives of both DAMEPL and DMRC, which we shall avert
    to in the course of the judgment.
11. Following this application, after inquiry and inspection, the CMRS
    issued sanction on 18 January 2013. This sanction was subject to
    certain conditions including speed restrictions. Specifically, the metro
    was to be run at a speed of 50kmph, and an increase in speed beyond
    50kmph up to 80kmph was to be authorized in steps of 10kmph at
    a time. For an increase in speed beyond 80kmph, DMRC was to
    approach the Commissioner for sanction with a justification as to
    the improvements carried out by it.
12. Consequently, on 22 January 2013, AMEL operations were
    commenced by DAMEPL. On 30 June 2013, the project assets were
    handed over by DAMEPL to DMRC. After that, from 01 July 2013,
    DMRC continued AMEL operations.
13. In August 2013, the arbitral tribunal comprising Mr AP Mishra, Mr
    SS Khurana and Mr HL Bajaj was constituted.10 On 11 May 2017,


8    “Termination Notice”
9    “CMRS”/”Commissioner”
10   “Tribunal”
[2024] 4 S.C.R.                                                       481

                          Delhi Metro Rail Corporation Ltd. v.
                          Delhi Airport Metro Express Pvt. Ltd.

       the three-member Tribunal passed a unanimous award in favour of
       DAMEPL11.
14. The award held that DAMEPL was entitled first, to the termination
    payment of Rs. 2782.33 Crores plus interest in terms of the
    concession agreement; second, to expenses incurred in operating
    AMEL from 07 January 2013 to 30 June 2013 and debt service made
    by DAMEPL during this period, of Rs 147.52 Crores plus interest at
    11% per annum from the date of payment of stamp duty; third, to
    the refund of the bank guarantee amounting to Rs 62.07 Crores plus
    interest at 11% p.a. which had been encashed; fourth, to security
    deposits with the service providers, amounting to Rs 56.8 Lakhs
    plus interest at 11% p.a.; and that DMRC was entitled to Rs 46.04
    Crores as Concession fee for the period from 23 February 2012 to
    7 January 2013.
15. Assailing the award, DMRC instituted an application under Section
    34 of the Arbitration and Conciliation Act 199612 before the Delhi High
    Court. The Single-Judge of the High Court dismissed the petition13.
    This gave rise to an appeal under Section 37 before a Division Bench
    of the High Court. The appeal was partly allowed.14
16. Against the decision of the Division Bench of the High Court, DAMEPL
    moved a Special Leave Petition under Article 136 of the Constitution.
    A two-judge bench of this Court allowed the appeal, and restored
    the award. The review petition assailing this decision was dismissed.
    Thus, the curative petition.
       B.      DMRC’s claim and the Tribunal’s findings
17. Before the Tribunal, DMRC claimed that – (i) it took steps to cure
    the defects immediately after it received the cure notice, including
    approaching SYSTRA -the original design consultant and convening
    meetings with the Ministry of Urban Development and that DAMEPL
    actively participated in all of these steps; (ii) that the real reason
    for the termination notice was that DAMPL had ceased to find the
    project financially viable. DMRC sought, inter alia, quashing of the


11   “Award”
12   “Arbitration Act”.
13   OMP (COMM) 307/2017 & OMP (I) (COMM) 200/2017 (‘Single Judge’)
14   FAO(OS)(COMM) 58/2018 & CM Nos. 13434/2018 (‘Division Bench’)
482                                                          [2024] 4 S.C.R.

                      Digital Supreme Court Reports


       termination notice; and a direction to the respondent to resume the
       performance of its obligations under the 2008 agreement. DAMEPL,
       on the other hand, claimed that there were defects attributable to
       DMRC’s faulty design; that these defects were not cured and no
       effective steps were taken to cure them within the 90-day cure
       period, resulting in material adverse effects to DAMEPL, entitling it
       to terminate the concession agreement.
18. The Tribunal was required to adjudicate on the validity of the
    termination notice. It framed the following issues:
            “Were there any defects in the civil structure of the airport
            metro line?
            If there were defects, did such defects have a material
            adverse effect on the performance of the obligation of
            DAMEPL under CA?
            If there were defects in the civil structure, which had
            a material adverse effect on the performance of the
            obligations under the CA by DAMEPL, have such defects
            been cured by DMRC and/or have any effective steps been
            taken within a period of 90 days from the date of notice
            by DAMEPL to cure the defects by DMRC and thus, were
            DMRC in breach of the CA as per 29.5.1 (i)?”
19. The Tribunal undertook an analysis of the defects in the structure
    and whether they had been cured or effective steps taken during
    the cure period. It noted that 72% of the girders were affected by
    cracks; the cause of the cracks was uncertain; the depth of the
    cracks was not reliably determined; and that the inspection for
    repairs carried out at the instance of DMRC was ‘non-serious’.
    Further, it noted that there were twists in about 80 girders and
    gaps between the shear key and the girders which were not cured
    by DMRC in the cure period. Taken together, these defects were
    considered to have compromised the integrity of the structure. This,
    the Tribunal held, amounted to a breach of DMRC’s obligations
    under the 2008 agreement resulting in a material adverse effect
    on the concessionaire.
20. The Tribunal framed the legal issues that arose for its consideration.
    The issue about the validity of the termination agreement was framed
    in the following terms:
[2024] 4 S.C.R.                                                             483

                            Delhi Metro Rail Corporation Ltd. v.
                            Delhi Airport Metro Express Pvt. Ltd.

              “D. Was DAMEPL entitled to or justified in termination of
              the CA, since the cost of repairs of the alleged defects was
              only approximately Rs.14 crores as compared to the total
              costs of the project of approximately Rs. 5700 crores?”
21. The issue pertaining to the CMRS certificate was framed as follows:
              “H. Did the issuance of certificate by CMRS show that the
              defects were duly cured?”
22. Both these issues were answered in the negative by the Tribunal. On
    Issue ‘D’ about the validity of the termination, it was held that since
    the Tribunal had found that there were defects in the civil structure,
    which remained uncured during the cure period, the amount incurred
    by DMRC in repairs compared to the overall cost of the project was
    irrelevant.15 On issue ‘H’, about the CMRS certificate, the tribunal
    found that the CMRS sanction mandated rigorous monitoring of
    operations of the line and imposed a speed restriction. Since the
    purpose of the line was to serve as a high-speed line, the tribunal found
    that the speed restrictions meant that this purpose was not served
    and therefore, the CMRS certificate or the subsequent operation of
    the line were not relevant in deciding the issues before it.16
      C.      Decisions of the High Court
23. The Single Judge of the High Court17, deciding the Section 34
    application, upheld the award, observing that so long as the award
    was reasonable and plausible, considering the material before the
    Tribunal no interference was warranted, even if an alternate view
    was possible. It was held that the Tribunal, in this case, had analysed
    material and evidence in great detail, and arrived at a plausible
    conclusion.
24. The Division Bench of the High Court18 partly set aside the award
    as perverse and patently illegal, for the following reasons:
      24.1. On the validity of the termination, ex-facie, the termination
            which was effective immediately from the date of termination


15   The Award, para 93.
16   ibid, paras 105-108.
17   “Single Judge”.
18   “Division Bench”.
484                                                          [2024] 4 S.C.R.

                       Digital Supreme Court Reports


              was invalid. There was some ambiguity on the relevant date
              of termination. The award did not interpret clause 29.5.1(i)
              of the concession agreement regarding the duration of the
              cure period;
       24.2. The speed restrictions were not stated as the reason for
             termination in the cure or termination notices and there was no
             deliberation on this being a justification for termination before
             the Tribunal. Thus, the award was silent and unreasoned on
             this issue; and
       24.3. Underlining the significance of the CMRS sanction under the
             Act of 2002, the findings of the tribunal on this issue were
             incorrect because (i) the award overlooked the legal effect
             of the CMRS certificate which was binding on the tribunal;
             and (ii) the award erroneously treated the CMRS certificate
             as irrelevant to the issue of the validity of the termination by
             wrongly separating the issue of defects and material adverse
             effects from the issue of the certificate.
       D.   Judgment of this Court in appeal
25. This Court set aside the decision of the Division Bench and restored
    the arbitral award on the following grounds:
       25.1. There was no ambiguity in the date of termination and even
             if a different view from that of the tribunal were possible,
             construction of the provisions of the contract was within the
             exclusive domain of the tribunal;
       25.2. The award was not perverse. The finding of the tribunal that
             the defects were not cured was a finding of fact, not warranting
             interference;
       25.3. DMRC had not contended before the Tribunal that the
             certificate was binding and conclusive of the fact that the
             defects were cured or that effective steps had been taken; and
       25.4. The Division Bench of the High Court was in error in
             holding that the issue of the CMRS certificate was wrongly
             separated from the issue of defects. It held that dealing with
             the certificate separately from the validity of termination did
             not render the tribunal’s findings on the latter erroneous. The
             Tribunal comprised of engineers and the award could not
[2024] 4 S.C.R.                                                         485

                     Delhi Metro Rail Corporation Ltd. v.
                     Delhi Airport Metro Express Pvt. Ltd.

                be scrutinised in the same manner as an award drawn by a
                legally trained mind.
26. The review petition against the above judgment of this Court was
    dismissed on 23 November 2021.
      E.     Issues in the Curative Petition
27. The issues that arise for our consideration are (i) whether the
    curative petition is maintainable; and (ii) whether this Court was
    justified in restoring the arbitral award which had been set aside by
    the Division Bench of the High court on the ground that it suffered
    from patently illegality.
      F.     Submissions
28. We have heard Mr R Venkataramani, Attorney General for India
    and Mr K K Venugopal, Mr Parag Tripathi, and Mr Maninder Singh
    senior counsel on behalf of the petitioners. They made the following
    submissions:
      28.1. Considering the definition of ‘material adverse effect’ under the
            concession agreement, the defects had no material adverse
            effect on DAMEPL’s performance of obligations under the
            agreement, as is apparent from the running of the metro
            line. The purpose of the agreement was fully subserved, as
            evinced by the continuous running of the line;
      28.2. The purpose of the cure notice was to demand cure
            compliance from DMRC. As long as ‘effective steps’ were
            taken by DMRC, culminating in cure compliance under the
            statutory process under the Metro Railways (Operation
            and Maintenance) Act, 200219, the termination notice was
            invalid;
      28.3. Clause 29.5.1 of the agreement shows that the termination
            ought to have been effected after 90 days from the cure notice
            plus 90 days in addition. Termination was thus effective only
            on 07 January 2013 and on this date, none of the defects
            were pending to be rectified by DMRC;



19   The 2002 Act
486                                                           [2024] 4 S.C.R.

                           Digital Supreme Court Reports


       28.4. The sanction/certificate granted by CMRS was issued on a
             joint application by both the parties after thorough inspection
             of the operations. The terms of the agreement and the
             provisions relating to the CMRS process under the 2002 Act
             are intrinsically connected;
       28.5. The Tribunal should have considered the binding effect of the
             CMRS sanction as the issue of speed was neither raised, nor
             deliberated before it and was irrelevant to the termination;
       28.6. The line has been running since 1 July 2013. The speed
             of operations was sanctioned at 50kmph, and has been
             progressively increased to 60 kmph in January 2013, 80 kmph
             in August 2013, 90 kmph in July 2019, and ultimately 100
             kmph and then 110 kmph in 2023. The metro was running
             at 80 kmph prior to the termination of the agreement. It is
             currently running at 120kmph for which a fresh sanction was
             obtained from the CMRS. The smooth operation of the metro
             line for five and a half years, until the date of the award was
             entirely ignored by the Tribunal, making the award perverse;
       28.7. The running of the metro line shows that even if there were
             defects, they did not render the metro unviable nor did they
             interfere with DAMEPL’s obligations under the agreement.
             Thus, the award is perverse and patently illegal;
       28.8. The tribunal ignored vital evidence, warranting the High
             Court’s interference under Section 37 of the Arbitration Act.
             The miscarriage of justice principle is informed by the scheme
             of the Arbitration Act;
       28.9. The High Court’s interference with the patent illegality was
             justified and this Court under Article 136 ought to have been slow
             to interfere with the decision of the Division Bench of the high
             Court. Miscarriage of justice in terms of the decision in Rupa
             Hurra vs. Ashok Hurra20 is linked with patent illegality. The High
             Court’s interference under Section 37 was justified because the
             exercise of jurisdiction under Section 34 was erroneous; and
       28.10. The issue of the fitness of the line was a matter falling under
              the 2002 Act under which the Commissioner was the final


20   [2002] 2 SCR 1006 : 2002 4 SCC 388
[2024] 4 S.C.R.                                                       487

                    Delhi Metro Rail Corporation Ltd. v.
                    Delhi Airport Metro Express Pvt. Ltd.

            authority to decide on the safety of the metro. The certificate
            could not have been substituted by the Tribunal’s finding on
            safety of the line.
29. We have heard Mr Harish Salve, Mr Kapil Sibal, Mr JJ Bhatt and Mr
    Prateek Seksaria, learned senior counsel for the respondent. They
    have made the following submissions:
     29.1. The curative petition is not maintainable as this Court cannot
           revisit the conclusions arrived at by the Tribunal;
     29.2. DMRC has taken over the project and has been operating
           it since 01 July 2012 without having paid for its operation
           between 01 January 2013 till 30 June 2013, except for a
           small fraction of the total awarded amount;
     29.3. Till early March 2023, the trains were running at 90kmph,
           as opposed to the speed of 120kmph at which they ought to
           have been running;
     29.4. The issue about the relevance of the CMRS certificate has
           been squarely addressed by the Single Judge and this Court.
           The arbitrator is the sole judge of the quality and the quantity
           of evidence;
     29.5. The award was made after 68 hearings and after consideration
           of 35,000 pages of documents and oral evidence. It has been
           two and a half years since this Court restored the award on
           09 September 2021 and the review against this decision was
           dismissed on 23 November 2021;
     29.6. According to the decision in Rupa Hurra (supra), the court is
           not supposed to sit over a judgment like a court of appeal. The
           scope of the review jurisdiction is narrow in itself and does
           not warrant rehearing and correction of a judgment. Curative
           proceedings cannot be treated as a second review; and
     29.7. DAMEPL is not unjustly enriching itself. DAMEPL completed
           the project with an investment of Rs 2802 Crores comprising
           of debt and equity contributions and it continued to service
           the debt even after handing over the line to DMRC. DMRC on
           the other hand, has paid the decretal amount of Rs 2599.18
           Crores while Rs 5088 Crores under the decree is outstanding
           as on 31 January 2024.
488                                                            [2024] 4 S.C.R.

                       Digital Supreme Court Reports


       G.   Analysis
       I.   Curative Jurisdiction may be invoked if there is a
            miscarriage of justice
30. Senior Counsel for the respondent set forth preliminary objections
    challenging the maintainability of the Curative Petition, in view of the
    scope of that jurisdiction delineated inter alia in the decision in Rupa
    Hurra (supra) We will first lay down the contours of the jurisdiction
    of this Court to entertain a curative petition in exercise of its inherent
    powers under Article 142.
31. In Rupa Hurra (supra), a Constitution Bench of this Court dwelt on
    whether any relief is available against a final judgement of this Court
    after the dismissal of a petition seeking review of the judgement.
    Two opinions were authored. The main judgment was by Justice
    Syed Shah Quadri (on behalf of Chief Justice S P Bharucha, Justice
    Variava, Justice Shivraj Patil and himself). A concurring opinion was
    authored by Justice U C Banerjee.
32. Justice Quadri observed that the concern of the Court for rendering
    justice in a cause cannot be considered less important than the
    principle of finality. There are certain situations, the opinion observed,
    which would require reconsideration of a final judgement even after
    the review has been dismissed to set right a miscarriage of justice.
    Such circumstances, the court held, are those where declining to
    reconsider the judgement would be oppressive to judicial conscience
    and cause the perpetuation of irremediable injustice. Justice Quadri
    observed:
            “42. … the duty to do justice in these rarest of rare cases
            shall have to prevail over the policy of certainty of judgment
            as though it is essentially in the public interest that a final
            judgment of the final court in the country should not be
            open to challenge, yet there may be circumstances, as
            mentioned above, wherein declining to reconsider the
            judgment would be oppressive to judicial conscience
            and would cause perpetuation of irremediable
            injustice.”
                                                    (emphasis supplied)
33. This Court laid down an overarching principle that the Court may
    entertain a curative petition to (i) prevent abuse of its process; and
[2024] 4 S.C.R.                                                                  489

                        Delhi Metro Rail Corporation Ltd. v.
                        Delhi Airport Metro Express Pvt. Ltd.

      (ii) to cure a gross miscarriage of justice. 21 The Court provided
      examples of such circumstances, such as a violation of the principles
      of natural justice; or a situation where the Judge fails to disclose his
      connection with the subject matter or the parties, giving scope for
      an apprehension of bias. However, the Court observed that it is not
      possible to exhaustively enumerate the grounds on which a curative
      petition may be entertained. The Court noted as follows:
              “50. The next step is to specify the requirements to entertain
              such a curative petition under the inherent power of this
              Court so that floodgates are not opened for filing a second
              review petition as a matter of course in the guise of a
              curative petition under inherent power. It is common ground
              that except when very strong reasons exist, the Court
              should not entertain an application seeking reconsideration
              of an order of this Court which has become final on
              dismissal of a review petition. It is neither advisable nor
              possible to enumerate all the grounds on which such
              a petition may be entertained.
              51. Nevertheless, we think that a petitioner is entitled to
              relief ex debito justitiae if he establishes (1) violation of the
              principles of natural justice in that he was not a party to
              the lis but the judgment adversely affected his interests or,
              if he was a party to the lis, he was not served with notice
              of the proceedings and the matter proceeded as if he had
              notice, and (2) where in the proceedings a learned Judge
              failed to disclose his connection with the subject-matter or
              the parties giving scope for an apprehension of bias and
              the judgment adversely affects the petitioner.”
34. The enumeration of the situations in which the curative jurisdiction
    can be exercised is thus not intended to be exhaustive. The Court
    went on to lay down certain procedural requirements to entertain a
    curative petition such as a certificate by a Senior Advocate about
    fulfilling of the requirements.
35. In his concurring opinion, Justice Banerjee also laid down a similar
    test of ‘manifest injustice’ to exercise the jurisdiction of this Court


21   Rupa Hurra, para 49.
490                                                             [2024] 4 S.C.R.

                        Digital Supreme Court Reports


       under Article 142 while entertaining a curative petition. In essence, the
       jurisdiction of this Court, while deciding a curative petition, extends
       to cases where the Court acts beyond its jurisdiction, resulting in
       a grave miscarriage of justice. We now proceed to lay down the
       scope of jurisdiction of this Court and the competent courts below
       while dealing with cases arising out of an application to set aside
       an arbitral award under Section 34 of the Arbitration Act.
       II.   Scope of interference of courts with arbitral awards
36. Section 34 of the Arbitration Act delineates the grounds for setting
    aside an arbitral award. The provision, as amended by the Arbitration
    and Conciliation (Amendment) Act, 2015 reads as follows:
             “34. Application for setting aside arbitral award.—
             …
             (2) An arbitral award may be set aside by the Court only if—
             …
             (b) the Court finds that--
             (i) the subject-matter of the dispute is not capable of
             settlement by arbitration under the law for the time being
             in force, or
             (ii) the arbitral award is in conflict with the public policy
             of India.
             Explanation 1. --For the avoidance of any doubt, it is
             clarified that an award is in conflict with the public policy
             of India, only if,--
             (i) the making of the award was induced or affected by
             fraud or corruption or was in violation of section 75 or
             section 81; or
             (ii) it is in contravention with the fundamental policy of
             Indian law; or
             (iii) it is in conflict with the most basic notions of morality
             or justice.
             Explanation 2. --For the avoidance of doubt, the test as
             to whether there is a contravention with the fundamental
[2024] 4 S.C.R.                                                            491

                       Delhi Metro Rail Corporation Ltd. v.
                       Delhi Airport Metro Express Pvt. Ltd.

             policy of Indian law shall not entail a review on the merits
             of the dispute.
             (2A) An arbitral award arising out of arbitrations other
             than international commercial arbitrations, may also
             be set aside by the Court, if the Court finds that the
             award is vitiated by patent illegality appearing on the
             face of the award:
             Provided that an award shall not be set aside merely on
             the ground of an erroneous application of the law or by
             reappreciation of evidence.”
                                                    (emphasis supplied)
37. The contours of the power of the competent court to set aside an
    award under Section 34 has been explored in several decisions of
    this Court. In addition to the grounds on which an arbitral award
    can be assailed laid down in Section 34(2), there is another ground
    for challenge against domestic awards, such as the award in the
    present case. Under Section 34(2-A) of the Arbitration Act, a domestic
    award may be set aside if the Court finds that it is vitiated by ‘patent
    illegality’ appearing on the face of the award.
38. In Associate Builders vs. Delhi Development Authority22, a two-
    judge Bench of this Court held that although the interpretation of a
    contract is exclusively within the domain of the arbitrator, construction
    of a contract in a manner that no fair-minded or reasonable person
    would take, is impermissible. A patent illegality arises where the
    arbitrator adopts a view which is not a possible view. A view can be
    regarded as not even a possible view where no reasonable body of
    persons could possibly have taken it. This Court held with reference
    to Sections 28(1)(a) and 28(3), that the arbitrator must take into
    account the terms of the contract and the usages of trade applicable
    to the transaction. The decision or award should not be perverse
    or irrational. An award is rendered perverse or irrational where the
    findings are (i) based on no evidence; (ii) based on irrelevant material;
    or (iii) ignores vital evidence. Patent illegality may also arise where
    the award is in breach of the provisions of the arbitration statute, as
    when for instance the award contains no reasons at all, so as to be


22   [2014] 13 SCR 895 : 2015 3 SCC 49.
492                                                            [2024] 4 S.C.R.

                           Digital Supreme Court Reports


       described as unreasoned. A fundamental breach of the principles
       of natural justice will result in a patent illegality, where for instance
       the arbitrator has let in evidence behind the back of a party. In the
       above decision, this Court observed:
             “31. The third juristic principle is that a decision which is
             perverse or so irrational that no reasonable person would
             have arrived at the same is important and requires some
             degree of explanation. It is settled law that where:
             (i) a finding is based on no evidence, or
             (ii) an Arbitral Tribunal takes into account something
             irrelevant to the decision which it arrives at; or
             (iii) ignores vital evidence in arriving at its decision,
             such decision would necessarily be perverse.
             …
             42.2. (b) A contravention of the Arbitration Act itself
             would be regarded as a patent illegality — for example
             if an arbitrator gives no reasons for an award in
             contravention of Section 31(3) of the Act, such award
             will be liable to be set aside.”
                                                    (emphasis supplied)
39. In Ssangyong Engineering & Construction Co. Ltd. vs. NHAI23,
    a two-judge bench of this Court endorsed the position in Associate
    Builders (supra), on the scope for interference with domestic awards,
    even after the 2015 Amendment:
             “40. The change made in Section 28(3) by the Amendment
             Act really follows what is stated in paras 42.3 to 45 in
             Associate Builders, namely, that the construction of the
             terms of a contract is primarily for an arbitrator to decide,
             unless the arbitrator construes the contract in a manner
             that no fair-minded or reasonable person would; in
             short, that the arbitrator’s view is not even a possible
             view to take. Also, if the arbitrator wanders outside the



23   [2019] 7 SCR 522 : 2019 15 SCC 131
[2024] 4 S.C.R.                                                                                   493

                        Delhi Metro Rail Corporation Ltd. v.
                        Delhi Airport Metro Express Pvt. Ltd.

              contract and deals with matters not allotted to him,
              he commits an error of jurisdiction. This ground of
              challenge will now fall within the new ground added
              under Section 34(2-A).
              41. … Thus, a finding based on no evidence at all or
              an award which ignores vital evidence in arriving at its
              decision would be perverse and liable to be set aside
              on the ground of patent illegality. Additionally, a finding
              based on documents taken behind the back of the parties
              by the arbitrator would also qualify as a decision based
              on no evidence inasmuch as such decision is not based
              on evidence led by the parties, and therefore, would also
              have to be characterised as perverse.”
                                                                   (emphasis supplied)
40. In essence, the ground of patent illegality is available for setting
    aside a domestic award, if the decision of the arbitrator is found to
    be perverse, or so irrational that no reasonable person would have
    arrived at it; or the construction of the contract is such that no fair
    or reasonable person would take; or, that the view of the arbitrator
    is not even a possible view.24 A ‘finding’ based on no evidence at all
    or an award which ignores vital evidence in arriving at its decision
    would be perverse and liable to be set aside under the head of
    ‘patent illegality’. An award without reasons would suffer from patent
    illegality. The arbitrator commits a patent illegality by deciding a
    matter not within his jurisdiction or violating a fundamental principle
    of natural justice.
41. A judgment setting aside or refusing to set aside an arbitral award
    under Section 34 is appealable in the exercise of the jurisdiction
    of the court under Section 37 of the Arbitration Act. It has been
    clarified by this Court, in a line of precedent, that the jurisdiction
    under Section 37 of the Arbitration Act is akin to the jurisdiction of
    the Court under Section 34 and restricted to the same grounds of
    challenge as Section 34.25



24   Patel Engineering Limited vs North Eastern Electric Power Corporation Limited (2020) 7 SCC 176.
25   MMTC Ltd. v. Vedanta Ltd, (2019) 4 SCC 163, para 14; Konkan Railways v. Chenab Bridge Project
     Undertaking, 2023 INSC 742, para 14.
494                                                                              [2024] 4 S.C.R.

                             Digital Supreme Court Reports


42. In the statutory scheme of the Arbitration Act, a recourse to Section
    37 is the only appellate remedy available against a decision under
    Section 34. The Constitution, however, provides the parties with a
    remedy under Article 136 against a decision rendered in appeal under
    Section 37. This is the discretionary and exceptional jurisdiction of
    this Court to grant Special Leave to Appeal. In fact, Section 37(3) of
    the Arbitration Act expressly clarifies that no second appeal shall lie
    from an order passed under Section 37, but nothing in the section
    takes away the constitutional right under Article 136. Therefore, in
    a sense, there is a third stage at which this court tests the exercise
    of jurisdiction by the courts acting under Section 34 and Section 37
    of the Arbitration Act.
43. While adjudicating the merits of a Special Leave Petition and
    exercising its power under Article 136, this Court must interfere
    sparingly and only when exceptional circumstances exist, justifying
    the exercise of this Court’s discretion.26 The Court must apply settled
    principles of judicial review such as whether the findings of the High
    Court are borne out from the record or are based on a misappreciation
    of law and fact. In particular, this Court must be slow in interfering
    with a judgement delivered in exercise of powers under Section 37
    unless there is an error in exercising of the jurisdiction by the Court
    under Section 37 as delineated above. Unlike the exercise of power
    under Section 37, which is akin to Section 34, this Court (under
    Article 136) must limit itself to testing whether the court acting under
    Section 37 exceeded its jurisdiction by failing to apply the correct
    tests to assail the award.
       III.   The award was patently illegal
44. In the case at hand, the Division Bench found the award to
    be perverse, irrational and patently illegal since it ignored the
    vital evidence of CMRS certification in deciding the validity of
    termination. This, the Division Bench held, overlooked the statutory
    certification deeming it irrelevant without reasons and thus the
    award was patently illegal according to the test in Associate
    Builders (supra).27



26   Chandi Prasad Chokhani v. State of Bihar, AIR 1961 SC 1708; Pritam Singh v. State, 1950 SCC 189.
27   Division Bench, paras 98-99.
[2024] 4 S.C.R.                                                                                     495

                          Delhi Metro Rail Corporation Ltd. v.
                          Delhi Airport Metro Express Pvt. Ltd.

45. This Court in appeal against the judgment of the Division Bench
    of the High Court held that the award was not perverse. Factual
    findings such as the finding that the cure period was 90 days and
    that DAMEPL was entitled to terminate the contract, could not, it was
    held, be interfered with.28 On the CMRS Certificate, this Court held
    that the arbitral tribunal was deciding whether there was a breach
    of the agreement and whether the defects were cured within the
    cure period; hence the safety of the line was not an issue before
    the tribunal. This Court held that the Commissioner may be the
    competent authority to determine the safety of the project but the
    certificate itself did not show that the defects were cured within 90
    days. This Court disagreed with the Division Bench and held that the
    CMRS certificate had no bearing on the validity of the termination.
46. There is a fundamental error in the manner in which this Court dealt
    with the challenge to the decision of the High Court. This jurisdiction
    of this Court was invoked under Article 136 of the Constitution. The
    Court was exercising its jurisdiction over a decision rendered by the
    Division Bench of the High Court in appeal under Section 37. The
    Division Bench had held that the award overlooked crucial facts and
    evidence on record that were crucial to the determination of the issues
    before the arbitral tribunal. This led to the award being perverse and
    patently illegal within the parameters of Section 34 as explained
    in the judgments of this Court in Associate Builders (supra) and
    Ssangyong (supra). The award overlooked the express terms of
    clause 29.5.1(i) which stipulated that if “effective steps” were taken
    during the cure period by DMRC, the contractual power to terminate
    could not be exercised. This Court incorrectly considered the CMRS
    certificate to be irrelevant to the validity of the termination.
      i.      Interpretation of the termination clause by the Tribunal was
              unreasonable
47. Interference with an arbitral award cannot frustrate the ‘commercial
    wisdom behind opting for alternate dispute resolution’, merely because
    an alternate view exists.29 However, the interpretation of a contract
    cannot be unreasonable, such that no person of ordinary prudence
    would take it. The contract, which is a culmination of the parties’


28   Civil Appeal, para 31.
29   Dyna Technologies Private Limited v. Crompton Greaves Limited, (2019) 20 SCC 1, paras 24, 25.
496                                                                             [2024] 4 S.C.R.

                            Digital Supreme Court Reports


       agency, should be given full effect. If the interpretation of the terms
       of the contract as adopted by the tribunal was not even a possible
       view, the award is perverse.30
48. Clause 29.5.1(i) entitles the concessionaire to terminate the
    agreement if DMRC “failed to cure such breach or take effective
    steps for curing such breach” within the cure period. Pertinently,
    the clause uses two separate phrases, “cure” and “effective steps
    to cure”. The clause reads as follows:
              “29.5.1 The Concessionaire may after giving 90 (ninety)
              days’ notice in writing to DMRC terminate this Agreement
              upon the occurrence and continuation of any of the following
              events (each a “DMRC Event of Default”), unless any
              such DMRC Event of Default has occurred as a result
              of Concessionaire Event of Default or due to a Force
              Majeure Event.
              (i) DMRC is in breach of this Agreement and such breach
              has a Material Adverse Effect on the Concessionaire and
              DMRC has failed to cure such breach or take effective
              steps for curing such breach within 90 (ninety) days of
              receipt of notice in this behalf from the Concessionaire;”
                                                                  (emphasis supplied)
49. The Tribunal found that since certain defects remained after the
    cure period, this was indicative of the fact that the defects were not
    cured and that no effective steps were taken. However, logically,
    the fact that defects existed at the end of the cure period relates
    to one aspect of the termination clause – that the defects were not
    completely cured. It does not explain whether effective steps were
    taken within the cure period. Effectively, the Tribunal considered that
    in-progress steps that had not yet culminated into completely cured
    defects were not “effective steps” to offset termination. This places
    the two components i.e. ‘curing of defects’ and ‘taking effective steps
    to cure defects’ at par, to mean that only the completed curing of
    defects is relevant. The Tribunal fails to explain what amounts to an
    ‘effective step’ and how the steps taken by DMRC were not effective,
    within the meaning of the phrase.


30   Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking, 2023 9 SCC 85.
[2024] 4 S.C.R.                                                      497

                    Delhi Metro Rail Corporation Ltd. v.
                    Delhi Airport Metro Express Pvt. Ltd.

50. Evidently, this could not have been the intention of the parties,
    because they have clearly agreed to include the phrase “effective
    steps”. They clearly intended that once a cure notice was served
    on a party, it would be open to them to either cure defects or to
    initiate effective steps, even if they could not culminate into the
    complete curing of defects within the cure period. Incremental
    progress, even if it does not lead to complete cure, is an acceptable
    course of action to prevent termination according to the 2008
    Agreement.
51. The Tribunal did not appreciate the individual import of the two
    phrases separately from each other. This was not a matter of mere
    “alternate interpretation” of the clause, but an unreasonable and
    uncalled for interpretation of the clause, which frustrated the very
    provision, and which no reasonable person would have accepted
    considering the terms of the clause. We must clarify that Tribunal
    could have still arrived at the conclusion that the steps taken during
    the cure period were not effective within the meaning of the clause
    for certain reasons. However, such discussion and reasoning is
    conspicuously absent.
52. Issue H framed by the Tribunal- “Did the issuance of certificate by
    CMRS show that the defects were duly cured” similarly glosses
    over the effective steps aspect of the clause. Given this framing,
    the issue was bound to be answered in the negative since
    the CMRS certificate does not conclude that the defects were
    completely cured.
53. The decisions of the Single Judge and this Court are similarly silent
    on the aspect of “effective steps”. In paragraphs 31 to 34 of its
    judgment, this Court noted that since the defects were not cured in
    90 days, the termination was valid. Impliedly, this Court found that
    the defects ought to have been fully cured within the cure period
    in order to avoid termination.
54. The judgment of this Court also never tested the relevance of the
    CMRS certificate vis-à-vis “effective steps”. This Court accepted a
    reading of the termination clause by the Arbitral tribunal and the
    Single Judge that was not even a possible view and could not
    have been arrived at on any objective assessment. This Court not
    only overlooked the plain words of the clause but also rendered the
    phrase “effective steps” otiose.
498                                                         [2024] 4 S.C.R.

                       Digital Supreme Court Reports


       ii.   The award overlooked vital evidence and matters on the record
55. The erroneous and misleading framing of the issue as noted above led
    to the ignoring of vital evidence relevant to the issue of termination.
    The arbitral tribunal held that since the Commissioner imposed
    conditions of inspection and speed restrictions, this meant that the
    defects were not fully cured.
56. Certainly, the imposition of conditions shows that the defects were
    not cured completely, to warrant an unconditional sanction for full
    speed operations. However, as the Division Bench of the High Court
    correctly observed, the separation of the validity of termination and
    relevance of the CMRS certificate was the reason for this erroneous
    finding. Since the ‘effective steps’ aspect was overlooked, the CMRS
    certificate was erroneously deemed to be irrelevant.
57.     On 19 November 2012, a joint application was made by the parties
       to the Commissioner under the 2002 Act. Significantly, the annexure
       to the application which was jointly signed by the parties states as
       set out below:
             “f) The repairs have been Inspected by an Independent
             Engineer M/s TUV, engaged by
             DMRC to conduct the technical check on the quality
             of work and to ensure that the repairs are carried out
             as per the approved repair methodology. The copies
             of the certificates obtained from TUV are enclosed as
             Annexures xvii.
             g) Cracks in soffit of some ‘U’ girders were also observed
             and, therefore, inspection of all the girders have been
             done and mapping of the cracks have been undertaken
             accordingly (Annexure-xviii). Cracks have beery noticed
             in 367 girders. These cracks were analysed by M/s
             SYSTRA and their report is, enclosed as Annexure xix.
             They have concluded that there is no effect on the
             integrity of the girders and that there is no reason
             to-be further worried. M/s SYSTRA have also given
             the repair methodology for these cracks from the point of
             view of durability and to avoid permeation of water during
             the service life of girders, (Included in Annexure-xvi).
             Accordingly, the cracks wider than 0.2 mm have been
[2024] 4 S.C.R.                                                        499

                    Delhi Metro Rail Corporation Ltd. v.
                    Delhi Airport Metro Express Pvt. Ltd.

           Injected with epoxy resin and cracks less than 0.2 mm
           have been sealed with epoxy sealant.
           h) Train trials after repairs by DMRC have been
           completed successfully and all systems have been
           checked for correct functioning at various speeds
           Including at speed of 120 kmph. Track recording was
           done with OMS-2000 during these trials and no peak of
           value ≥ 0.15g was recorded upto 120 Kmph (results of
           OMS 2000 are enclosed in Annexure XIV)”
                                                 (emphasis supplied)
58. Admittedly, some of the defects were cured in their entirety and
    steps were taken by DMRC to cure the remainders, based on which
    the parties had jointly sought permission under the 2002 Act. The
    parties stated that the repairs had been inspected by an independent
    engineer; an analysis of the cracks revealed that the integrity of the
    girders was intact and there was no cause of concern. Further, the
    parties stated that the train trials “after repairs by DMRC have been
    completed successfully and all systems have been checked for correct
    functioning at various speeds including the speed of 120kmph”. It is
    apparent on the face of the record that certain repairs were completed
    by DMRC and the trials had been completed at full speed as on the
    date of application, 19 November 2012.
59. On 9 July 2012, about four months before the date of the joint
    application, DAMEPL had averred in the cure notice that the project
    was not ‘safe for operations’ and that it posed a threat to life and
    property. The arbitral tribunal was correct in concluding that the joint
    application does not constitute a waiver of the termination, but this
    evidence was vital considering the change in DAMEPL’s position
    on the safety of the line from the date of the cure notice to the date
    of the joint application. DMRC did take certain steps to alleviate
    DAMEPL’s concerns so as to warrant this change of position. There
    is no explanation forthcoming in the award about why none of these
    steps initiated during the cure period were ‘effective steps’. This gap
    in reasoning stems from the arbitral tribunal wrongly separating the
    issue of termination and the CMRS certificate.
60. Besides the effective steps aspect, there is another reason why the
    CMRS certificate ought to have been treated as relevant. The Tribunal
    treats the cure notice as a crucial document. At paragraph 26 of the
500                                                             [2024] 4 S.C.R.

                             Digital Supreme Court Reports


       award, it noted that “since the cure notice dated 9th July 2012 is a
       crucial document in this case, it is useful to quote certain paragraphs
       of the said letter”. The cure notice, in turn, was heavily premised on
       the safety of operations.31 Interestingly, at paragraph 27 of the cure
       notice, DAMEPL avers that the trains can only be operated once
       the defects are cured to the satisfaction of the stakeholders about
       the safety of operations.
61. Reference may be made to the 2002 Act under which the CMRS is
    the relevant statutory stakeholder whose satisfaction about the safety
    of operations is necessary for running of the metro. The relevant
    provisions of the Act may be adverted to here:
              “14. Sanction of Central Government to the opening
              of metro railway.—The metro railway in the the National
              Capital Region, metropolitan city and metropolitan area shall
              not be opened for the public carriage of passengers except
              with the previous sanction of the Central Government.
              15. Formalities to be complied with before giving
              sanction to the opening of metro railway.—(1) The
              Central Government shall, before giving its sanction to the
              opening of the metro railway under Section 14, obtain a
              report from the Commissioner that—
              (a)    he has made a careful inspection of the metro railway
                     and the rolling stock that may be used thereon;
              (b)    the moving and fixed dimensions as laid down by
                     the Central Government have not been infringed;
              (c)    the track structure, strength of bridges, standards of
                     signalling system, traction system, general structural
                     character of civil works and the size of, and maximum
                     gross load upon, the axles of any rolling stock, comply
                     with the requirements laid down by the Central
                     Government; and
              (d)    in his opinion, metro railway can be opened for the
                     public carriage of passengers without any danger to
                     the public using it.


31   Cure Notice paras 18,21,26, and 27.
[2024] 4 S.C.R.                                                          501

                    Delhi Metro Rail Corporation Ltd. v.
                    Delhi Airport Metro Express Pvt. Ltd.

           (2) If the Commissioner is of the opinion that the metro
           railway cannot be opened without any danger to the
           public using it, he shall, in his report, state the grounds
           therefor, as also the requirements which, in his opinion,
           are to be complied with before sanction is given by the
           Central Government.
           (3) The Central Government, after considering the report
           of the Commissioner, may sanction the opening of the
           metro railway under Section 14 as such or subject to such
           conditions as may be considered necessary by it for the
           safety of the public.
           18. Power to close metro railway opened for public
           carriage of passengers.—Where, after the inspection
           of the metro railway opened and used for the public
           carriage of passengers or any rolling stock used thereon,
           the Commissioner is of the opinion that the use of the
           metro railway or of any rolling stock will be attended with
           danger to the public using it, the Commissioner shall send
           a report to the Central Government who may thereupon
           direct that—
           (i)    the metro railway be closed for the public carriage
                  of passengers; or
           (ii)   the use of the rolling stock be discontinued; or
           (iii) the metro railway or the rolling stock may be used
                 for the public carriage of passengers subject to such
                 conditions as it may consider necessary for the safety
                 of the public.
           21. Delegation of powers.—The Central Government
           may, by notification, direct that any of its powers or
           functions under this chapter, except power to make rule
           under Section 22, shall, in relation to such matters and
           subject to such conditions, if any, as may be specified in
           the notification, be exercised or discharged also by the
           Commissioner.”
62. In essence, the scheme of the 2002 Act, provides that no metro
    line will operate except with the previous sanction of the Central
502                                                                     [2024] 4 S.C.R.

                            Digital Supreme Court Reports


       Government.32 Before granting the sanction, the Central Government
       has to obtain a report from the Commissioner that (inter alia) the
       latter has carefully inspected the metro railway, the general structure
       of civil works and that in their opinion, the metro railway can be
       opened for passengers without any danger to the public.33 The
       Central Government may sanction the opening of the line as such or
       subject to conditions it considers necessary for public safety.34 If the
       Commissioner is of the opinion that the use of the metro will “attend
       danger to the public using it”, they may send a report to the Central
       Government, which may in turn direct that the metro be closed or
       may be open for public carriage only subject to certain conditions.35
       The powers of the Central Government may be delegated to the
       Commissioner.36
63. The structure and safety of the project, as certified by the CMRS,
    were thus relevant before the Tribunal, making the CMRS certificate
    a vital piece of evidence in deciding the issue. The CMRS certificate
    was relevant evidence about the safety of the structure. Considering
    the statutory scheme of the 2002 Act, especially Section 15, the
    Tribunal erred in deeming the sanction irrelevant to its central issue
    – which was the validity of the termination, which, according to the
    cure notice, was premised on safety.
64. Overall, the cure notice places great emphasis on the safety of the
    passengers, which, they claimed stood compromised by defects,
    justifying discontinuation of operations. This issue falls directly within
    the domain of the Commissioner under the scheme of the 2002 Act.
65. Rather than considering the vital evidence of the CMRS certificate
    towards safety and effective steps, the arbitral tribunal focussed on
    the conditions imposed by the Commissioner on speed and regarding
    inspections. While the Division Bench correctly noted that the
    certificate was relevant for the issue of the validity of termination, this
    Court held that safety was not in issue, even though DAMEPL insisted
    on discontinuing operations citing safety concerns. We respectfully


32   Section 14, Metro Railways (Operations and Maintenance) Act 2002.
33   Section 15, ibid.
34   Section 15(3), ibid.
35   Section 18, ibid.
36   Section 21, ibid.
[2024] 4 S.C.R.                                                          503

                    Delhi Metro Rail Corporation Ltd. v.
                    Delhi Airport Metro Express Pvt. Ltd.

     disagree with this Court’s re-assessment of the Division Bench’s
     interpretation. The cure notice was relevant for the reasons stated
     above. Moreover, the fact that DAMEPL premised it on safety could
     not have been overlooked by the Tribunal. In doing so, it overlooked
     vital evidence pertaining to an issue that goes to the root of the
     matter. The cure notice was obviously on the record and merited
     consideration for its contents bearing on vital elements of safety.
66. The cure notice, which contains statements bearing on the safety
    of the line and other material indicating that the line was running
    uninterrupted are matters of record. While the cure notice contains
    allegations about the line not being operational, there is evidence
    on the record indicating that the line was in fact running. Even if we
    were to accept that the finding of the arbitral tribunal that the defects
    were not completely cured during the cure period is a factual finding
    incapable of interference, it is clear from the record that DMRC took
    steps towards curing defects which led to the eventual resumption
    of operations. The award contains no explanation as to why the
    steps which were taken by DMRC were not ‘effective steps’ within
    the meaning of the termination clause.
67. In essence, therefore the award is unreasoned on the above important
    aspects. It overlooks vital evidence in the form of the joint application
    of the contesting parties to CMRS and the CMRS certificate. The
    arbitral tribunal ignored the specific terms of the termination clause. It
    reached a conclusion which is not possible for any reasonable body
    of persons to arrive at. The arbitral tribunal erroneously rejected the
    CMRS sanction as irrelevant. The award bypassed the material on
    record and failed to reconcile inconsistencies between the factual
    averments made in the cure notice, which formed the basis of
    termination on the one hand and the evidence of the successful
    running of the line on the other. The Division Bench correctly held
    that the arbitral tribunal ignored vital evidence on the record, resulting
    in perversity and patent illegality, warranting interference. The
    conclusions of the Division Bench are, thus, in line with the settled
    precedent including the decisions in Associate Builders (supra)
    and Ssangyong (supra).
     H.    Conclusion
68. The judgment of the two-judge Bench of this Court, which interfered
    with the judgment of the Division Bench of the High Court, has resulted
504                                                            [2024] 4 S.C.R.

                       Digital Supreme Court Reports


       in a miscarriage of justice. The Division Bench applied the correct test
       in holding that the arbitral award suffered from the vice of perversity
       and patent illegality. The findings of the Division Bench were borne
       out from the record and were not based on a misappreciation of law
       or fact. This Court failed, while entertaining the Special Leave Petition
       under Article 136, to justify its interference with the well-considered
       decision of the Division Bench of the High Court. The decision of
       this Court fails to adduce any justification bearing on any flaws in
       the manner of exercise of jurisdiction by the Division Bench under
       Section 37 of the Arbitration Act. By setting aside the judgement of
       the Division Bench, this Court restored a patently illegal award which
       saddled a public utility with an exorbitant liability. This has caused
       a grave miscarriage of justice, which warrants the exercise of the
       power under Article 142 in a Curative petition, in terms of Rupa
       Hurra (supra).
69. The Curative petitions must be and are accordingly allowed. The
    parties are restored to the position in which they were on the
    pronouncement of the judgement of the Division Bench. The execution
    proceedings before the High Court for enforcing the arbitral award
    must be discontinued and the amounts deposited by the petitioner
    pursuant to the judgment of this Court shall be refunded. The part
    of the awarded amount, if any, paid by the petitioner as a result of
    coercive action is liable to be restored in favour of the petitioner.
    The orders passed by the High Court in the course of the execution
    proceedings for enforcing the arbitral award are set aside.
70. Before concluding, we clarify that the exercise of the curative
    jurisdiction of this Court should not be adopted as a matter of ordinary
    course. The curative jurisdiction should not be used to open the
    floodgates and create a fourth or fifth stage of court intervention in
    an arbitral award, under this Court’s review jurisdiction or curative
    jurisdiction, respectively.
71. In the specific facts and circumstances of this case to which we
    have adverted in the course of the discussion, we have come to the
    conclusion that this Court erred in interfering with the decision of the
    Division Bench of the High Court. The judgment of the Division Bench
    in the appeal under Section 37 of the Arbitration and Conciliation Act
    1996 was based on a correct application of the test under Section 34
    of the Act. The judgment of the Division Bench provided more than
[2024] 4 S.C.R.                                                          505

                    Delhi Metro Rail Corporation Ltd. v.
                    Delhi Airport Metro Express Pvt. Ltd.

     adequate reasons to come to the conclusion that the arbitral award
     suffered from perversity and patent illegality. There was no valid
     basis for this Court to interfere under Article 136 of the Constitution.
     The interference by this Court has resulted in restoring a patently
     illegal award. This has caused a grave miscarriage of justice. We
     have applied the standard of a ‘grave miscarriage of justice’ in
     the exceptional circumstances of this case where the process of
     arbitration has been perverted by the arbitral tribunal to provide an
     undeserved windfall to DAMEPL.
72. The curative petitions are allowed in the above terms.
73. Pending applications, if any, stand disposed of.


     Headnotes prepared by: Ankit Gyan                    Result of the case:
                                                    Curative petitions allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Curative Petition"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

DELHI METRO RAIL CORPORATION LTD. versus DELHI AIRPORT METRO EXPRESS PVT. LTD. — 2024 INSC 292 - Legal Desk AI