Created byFuzzy Cloud

Supreme Court of India

DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD.versusM/S NAVIGANT TECHNOLOGIES PVT. LTD.

Citation
2021 INSC 140
Decided
2 March 2021
Disposal
Appeal(s) allowed

Holding

The limitation period for filing objections under Section 34 starts from the date the signed copy of the arbitral award is delivered to the parties, i.e., 19 May 2018.

Summary

The appellant, Dakshin Haryana Bijli Vitran Nigam Ltd., terminated a service level agreement with the respondent, Navigant Technologies Pvt. Ltd., leading to arbitration. The three‑member tribunal orally pronounced a majority award on 27‑04‑2018, but the dissenting arbitrator issued a separate opinion and the signed copy of the award was only delivered to the parties on 19‑05‑2018. The appellant filed a Section 34 petition on 10‑09‑2018, arguing that the limitation period began on the date the draft award was circulated (27‑04‑2018). The High Court and the trial court held that the limitation started on 27‑04‑2018 and dismissed the petition as time‑barred. The Supreme Court examined Sections 31 and 34 of the Arbitration and Conciliation Act, 1996, and held that the limitation period for a Section 34 petition commences only when a party receives the signed award, i.e., 19‑05‑2018. Consequently, the appeal was allowed and the petition restored for merits‑determination.

Issues considered

  • The date from which the limitation period for filing a Section 34 petition begins – whether from the circulation of the draft award or from receipt of the signed award.
  • Whether a dissenting arbitrator’s opinion forms part of the arbitral award for the purpose of computing the limitation period.
  • Whether the award is deemed made on the date of oral pronouncement despite the lack of signatures.

Legislation cited

Subjects

ArbitrationSection 34 petitionLimitation periodArbitral award signingDissenting opinionArbitration and Conciliation ActCivil appeal

Judgment

                           [2021] 1 S.C.R. 1135                             1135


      DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD.                               A
                                   v.
          M/S NAVIGANT TECHNOLOGIES PVT. LTD.
                    (Civil Appeal No. 791 of 2021)
                          MARCH 02, 2021                                    B
        [INDU MALHOTRA AND AJAY RASTOGI, JJ.]
       Arbitration and Conciliation Act, 1996 – s.31 and s.34 – Period
of limitation for filing the petition u/s. 34 – A service level agreement
was executed by the appellant-corporation in favour of the
                                                                            C
respondent-company providing call centre services – Agreement
provided arbitration clause – The appellant-corporation terminated
the service level agreement, which led to dispute between the parties
– The disputes were referred to arbitration by a three-member tribunal
– The arbitral tribunal orally pronounced the award [2:1] on
27.04.2018, whereby the claims of the respondent-company were               D
allowed – The parties were informed that the third arbitrator had
disagreed with the view taken by the majority of arbitrators, and
would be rendering his separate opinion – A copy of the draft award
was provided to the parties to point out any computation, clerical
or typographical errors in the award – On 12.05.2018, a copy of
                                                                            E
the dissenting opinion was provided by the third arbitrator to the
parties (even though the opinion was dated 27.04.2018) – The
matter was then posted to 19.05.2018, for the parties to point out
any typographical or clerical mistakes in the dissenting opinion
delivered by the third arbitrator – On 19.05.2018, the signed copy
of the arbitral award was provided to both the parties, and the             F
proceedings were terminated – Whether the period of limitation for
filing the Petition u/s.34 would commence from the date on which
the draft award dated 27.04.2018 was circulated to the parties, or
the date on which the signed copy of the award was provided i.e.
19.05.2018 – Held: s.31(1) makes it obligatory for each of the
                                                                            G
members of the tribunal to sign the award, to make it a valid award
– Further, the period of limitation for filing the objections to the
award u/s.34 commences from the date on which the party making
the application has “received” a signed copy of the arbitral award,
as required by s.31(5) of the Act – In the instant case, on 19.05.2018,
                                                                            H
                                 1135
1136            SUPREME COURT REPORTS                         [2021] 1 S.C.R.


 A     the signed copy of the award and the dissenting opinion, alongwith
       the original record, were handed over to the parties, as also to
       each of the arbitrators – Therefore, the period of limitation for filing
       objections would have to be reckoned from the date on which the
       signed copy of the award was made available to the parties i.e. on
       19.05.2018.
 B
             Allowing the appeal, the Court
              HELD: Whether the period of limitation for filing the
       Petition u/s.34 would commence from the date on which the draft
       award dated 27.04.2018 was circulated to the parties, or the date
 C     on which the signed copy of the award was provided
             1. The legal requirement of signing the arbitral award by a
       sole arbitrator, or the members of a tribunal is found in Section
       31 of the 1996 Act, which provides the form and content of an
       arbitral award. [Para 4(vii)][1149-C]
 D            2. Section 31 (1) is couched in mandatory terms, and
       provides that an arbitral award shall be made in writing and signed
       by all the members of the arbitral tribunal. If the arbitral tribunal
       comprises of more than one arbitrator, the award is made when
       the arbitrators acting together finally express their decision in
 E     writing, and is authenticated by their signatures. An award takes
       legal effect only after it is signed by the arbitrators, which gives
       it authentication. There can be no finality of the award, except
       after it is signed, since signing of the award gives legal effect and
       validity to it. The making and delivery of the award are different
       stages of an arbitration proceeding. An award is made when it is
 F     authenticated by the person who makes it. The statute makes it
       obligatory for each of the members of the tribunal to sign the
       award, to make it a valid award. The usage of the term “shall”
       makes it a mandatory requirement. It is not merely a ministerial
       act, or an empty formality which can be dispensed with.
 G     [Para 4(viii)][1149-G-H; 1150-A-C]
             3. Sub-section (1) of Section 31 read with sub-section (4)
       makes it clear that the Act contemplates a single date on which
       the arbitral award is passed i.e. the date on which the signed
       copy of the award is delivered to the parties. Section 31 (5) enjoins
 H
     DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                     1137
          NAVIGANT TECHNOLOGIES PVT. LTD.

upon the arbitrator / tribunal to provide the signed copy of the        A
arbitral award to the parties. The receipt of a signed copy of the
award is the date from which the period of limitation for filing
objections u/S. 34 would commence. This would be evident
from the language of sub-section (3) of Section 34(3).
[Para 4(ix)][1150-D-E]
                                                                        B
       4. The date on which the signed award is provided to the
parties is a crucial date in arbitration proceedings under the Indian
Arbitration and Conciliation Act, 1996. It is from this date that:
(a) the period of 30 days’ for filing an application under Section
33 for correction and interpretation of the award, or additional
award may be filed; (b) the arbitral proceedings would terminate        C
as provided by Section 32(1) of the Act; (c) the period of limitation
for filing objections to the award under Section 34 commences.
[Para 4(xvii)][1153-G; 1154-A]
       5. Section 34 provides recourse for judicial scrutiny of the
award by a Court, upon making an application under sub-sections         D
(2) and (3) for setting aside the award. The period of limitation
for filing the objections to the award u/S. 34 commences from the
date on which the party making the application has “received” a
signed copy of the arbitral award, as required by Section 31(5) of
the 1996 Act. Section 34(3) provides a specific time limit of three     E
months from the date of “receipt” of the award, and a further
period of thirty days, if the Court is satisfied that the party was
prevented by sufficient cause from making the application within
the said period, but not thereafter. [Para 4(xviii)][1154-B-D]
      6. Applying the law to the facts of the present case, this        F
Court finds from a perusal of the arbitral proceedings that even
though the award was pronounced on 27.04.2018, the signed copy
of the award was provided to the parties only on 19.05.2018. The
procedural orders of the tribunal reveal that on 27.04.2018, only
a copy of the award was provided to the parties to point out any
computation error, any clerical or typographical error, or any other    G
error of similar nature which may have occurred in the award on
the next date. It was also recorded that the third arbitrator had
dissented, and would be delivering his separate opinion. On
12.05.2018, the third arbitrator pronounced his dissenting
opinion. On that date, the tribunal posted the matter to                H
1138           SUPREME COURT REPORTS                     [2021] 1 S.C.R.


 A     19.05.2018, to enable the parties to point out any typographical
       or clerical mistakes in the dissenting opinion, and for handing
       over the original record of the proceedings to the parties. On
       19.05.2018, the signed copy of the award and the dissenting
       opinion, alongwith the original record, were handed over to the
       parties, as also to each of the arbitrators. The tribunal ordered
 B
       the termination of the proceedings. [Para 5][1160-C-F]
             7. This Court is of the considered opinion that the period
       of limitation for filing objections would have to be reckoned from
       the date on which the signed copy of the award was made available
       to the parties i.e. on 19.05.2018 in the instant case. [Para 6]
 C     [1160-G]
            Union of India v. Tecco Trichy Engineers & Contractors
            (2005) 4 SCC 239 : [2005] 2 SCR 983; P. Radha Bai v.
            P. Ashok Kumar (2019) 13 SCC 445 : [2018] 12 SCR
            143; Ssangyong Engineering and Construction Co.Ltd.
 D          v. NHAI (2019) 15 SCC 131 : [2019] 7 SCR 522
            – relied on.
            State of Maharashtra v. Ark Builders (2011) 4 SCC 616
            : [2011] 4 SCR 432; Anilkumar Jinabhai Patel v.
            Pravinchandra Jinabhai Patel (2018) 15 SCC 178 :
 E          [2018] 3 SCR 718; State of Himachal Pradesh v
            Himachal Techno Engineers (2010) 12 SCC 210 :
            [2010] 8 SCR 1025; Union of India v. Popular
            Construction (2001) 8 SCC 470 : [2001] 3 Suppl. SCR
            619; Simplex Infrastructure v. Union of India (2019)
 F          12 SCC 455 – referred to.
            Axios Navigation v. Indian Oil Corporation 2012 SCC
            Online Bom 4; Bharat Sanchar Nigam Ltd. v. Acome
            and Ors. AIR 2009 Delhi 102; Axion Navigation v.
            Indian Oil Corporation Ltd. (2012) 114 (1) Bom LR
 G          392; Oriental insurance Co. v. Air India Ltd. (2019)
            SCC Online Del 11634 – referred to.
                             Case Law Reference
       [2019] 7 SCR 522          relied on            Paras 3.1, 4.20
       [2005] 2 SCR 983          relied on            Para 4.10
 H
      DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                         1139
           NAVIGANT TECHNOLOGIES PVT. LTD.

[2011] 4 SCR 432              referred to            Para 4.11               A
[2018] 3 SCR 718              referred to            Para 4.11
[2010] 8 SCR 1025             referred to            Para 4.12
[2001] 3 Suppl. SCR 619 referred to                  Para 4.18
(2019) 12 SCC 455             referred to            Para 4.18               B
[2018] 12 SCR 143             relied on              Para 4.19
      CIVIL APPELLATE JURISDICTION : Civil Appeal No. 791
of 2021.
      From the Judgment and Order dated 11.12.2019 of the High Court         C
of Punjab & Haryana at Chandigarh in FAO No. 1954 of 2019.
     Hemant Gupta, Ms. Payal Gupta, Ms. Sunakshi Gupta, Tushar
Sharma, Sanjay Kumar Visen, Advs. for the Appellant.
      Joby P. Varghese, Adv. for the Respondent.
                                                                             D
      The Judgment of the Court was delivered by
      INDU MALHOTRA, J.
      Leave granted.
       1. The present Civil Appeal arises from a Petition filed under
                                                                             E
Section 34 of the Arbitration and Conciliation Act, 1996 by the Appellant-
Bijli Vitrain Nigam to challenge the arbitral award dated 27.04.2018
passed by a three-member tribunal (2:1) in favour of the respondent
company.
      2. The issue which has arisen for our consideration is as to whether
                                                                             F
the period of limitation for filing the Petition under Section 34 would
commence from the date on which the draft award dated 27.04.2018
was circulated to the parties, or the date on which the signed copy of the
award was provided.
      (i)    The background facts emanate from a Service Level
             Agreement dated 02.05.2011 executed by the appellant-           G
             corporation in favour of the Respondent-company providing
             call centre services.
             Clause 13 of the Agreement provided for resolution of
             disputes through arbitration by a three-member tribunal,
             under the Arbitration and Conciliation Act, 1996.               H
1140       SUPREME COURT REPORTS                             [2021] 1 S.C.R.


 A     Clause 13 reads as :
       “13. Arbitration
       All matter question, disputes, differences and/or claims arising
       out of and/or concerning and/or in connection and/or in
       consequences or relating to the Contract whether or not obligations
 B     of either or both parties under the Contract be subsisting at the
       time of such dispute and whether or not the contract has been
       terminated or purported to be terminated or completed, shall be
       referred to the arbitration which shall be conducted by three
       arbitrators, one each to be nominated by the Service Provider and
 C     the Nigam (Arbitrator to be approved by the MD DHBVNL or
       authority of the Nigam) and the third to be named by the president
       of the institution of Engineers, India. If either of the parties fails to
       appoint its arbitrator within thirty (30) days after receipt of a notice
       from the other party invoking the arbitration clause, the president
       of the institution of Engineers, India, shall have the power at the
 D     request of either of the parties, to appoint the arbitrator. A certified
       copy of the order of the institution of engineers (India) making
       such an appointment will be furnished to each of the parties.
       The decision of the majority of the arbitrators shall be final and
       binding upon the parties. The parties to the contract agree that
 E     the cost of arbitration shall be as per instructions to the Nigam
       issued/prevalent on the date of appointment of arbitral tribunal.
       The arbitrators may, from time to time, with the consent of the
       parties enlarge the time for making the award. In the event of any
       of the aforesaid arbitrators dying, neglecting, resigning or being
 F     usable to act for any reason, it will be lawful for the party
       concerned to nominate another arbitrator in place of the outgoing
       arbitrator.
       The arbitrator shall have full powers to review and/or revise any
       decision, opinion, direction, certification or valuation of the Engineer
 G     in consonance with the Contract, and neither party shall be limited
       in the proceedings before such arbitrators to the evidence or
       arguments put before the engineer for the purpose of obtaining
       the said decision.
       …
 H
   DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                           1141
NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

   Subject to aforementioned provisions, the provisions of the              A
   Arbitration and Conciliation Act, 1996 and the Rules there under
   any statutory modifications thereof for the time being enforce,
   shall be deemed to apply to the Arbitration proceedings under the
   clause.”
   (ii)    On 16.10.2014, the appellant corporation terminated the          B
           Service Level Agreement, which led to disputes between
           the parties. The disputes were referred to arbitration by a
           three-member tribunal.
   (iii)   The arbitral tribunal orally pronounced the award [2:1] on
           27.04.2018, whereby the claims of the respondent company         C
           were allowed. The parties were informed that the third
           arbitrator had disagreed with the view taken by the majority
           of arbitrators, and would be rendering his separate opinion.
           A copy of the draft award was provided to the parties to
           point out any computation, clerical or typographical errors
           in the award on the next date of hearing.                        D

              The proceedings of the tribunal dated 27.04.2018 read
              as under :
              “27.04.2018
              Present:-                                                     E
              Sh. Nishant Shrivastava, Advocate for the claimant with
              Sh. Ankur Bhatia, M.D. of the Claimant.
              Sh. Ashish Goyal, Advocate and Sh. Sanjeev Sharma,
              JE for the respondent.
                                                                            F
              Vide separately recorded award dated today, claims of
              the claimant have been allowed with cost. Dr. Shiva
              Sharma has agreed with same, whereas Sh. D.S. Yadav
              has disagreed. He shall file his separate award. Copies
              free of costs, of the award have been supplied to both
              the Ld. Counsels for the parties. To come up on               G
              12.05.2017, at 4:30 p.m. for award of Sh. D.S. Yadav,
              Arbitrator. On that date, parties are also required to show
              any computation error, any clerical or typographical error
              or any other error of similar nature occurred in the award
              if any.                                                       H
1142         SUPREME COURT REPORTS                        [2021] 1 S.C.R.


 A                  Vinod Jain, D&S Judge(retd.) Presiding Arbitrator
                                Sh. Shiva Sharma, D&S Judge (retd.)
                           Sh.D.S. Yadav, Director, DHBVN (retd.)”
                                                 (emphasis supplied)
       The matter was next posted to 12.05.2018.
 B     (iv)    On 12.05.2018, a copy of the dissenting opinion was
               provided by the third arbitrator to the parties (even though
               the opinion was dated 27.04.2018). The matter was then
               posted to 19.05.2018, for the parties to point out any
               typographical or clerical mistakes in the dissenting opinion
 C             delivered by the third arbitrator.
                  The order dated 12.05.2018 reads as :
                  “12.05.2018
                  Present:-
 D                Sh. Nishant Shrivastava, Advocate for the claimant
                  Sh. Sanjeev Sharma, JE for the respondent.
                  Arbitrator Sh. D.S. Yadav has filed his own dissenting
                  Award.

 E                Copies free of cost have been supplied to both the
                  parties to these arbitration proceedings. Both the
                  parties have not pointed out any computation or clerical
                  error etc. in the award dated 27.04.2018.
                  Now to come up on 19.05.2018 at the same venue to
                  point out any typographical or clerical mistakes if any in
 F
                  the award of today given by Sh. D.S. Yadav, Arbitrator.
                  Venue the same. Also on that date original record should
                  be handed over to the Ld. Counsel for the claimant for
                  safe custody with pen drives of the record to the other
                  party as well as to the Arbitrators.”
 G
                                                       (emphasis supplied)
       (v)     On 19.05.2018, the tribunal recorded that both the parties
               had not filed any application to point out any clerical or
               typographical mistakes in the award, or dissenting opinion.
               On this date, the signed copy of the arbitral award was
 H
   DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                           1143
NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

          provided to both the parties, and the proceedings were            A
          terminated. The proceedings of 19.05.2018 read as :
             “19.05.2018
             Present:-
             Sh. Nishant Shrivastava, Advocate for the claimant             B
             Sh. Ashish Goyal, Advocate with Sh. Sanjeev Sharma,
             JE for the respondent.
             Original record has been handed over to Sh. Nishant
             Shrivastava, Advocate for its safe custody with him and
             for its production before the appropriate authority in case    C
             of need. Pen drives of the record have been provided to
             both the counsels as well as to the arbitrators. Record is
             comprised of two files. First file of pleadings is comprised
             of 270 pages and second file of awards, evidence, zimini
             orders and misc. papers is comprised of 596 pages.             D
             Awards (signed copies) have also been provided
             to Ld. Counsel for both the parties free of cost.
             Both the parties also not filed any applications to point
             out any clerical or typographical mistakes in the awards.
             Proceedings now come to an end, so are hereby
                                                                            E
             terminated.”
                                                   (emphasis supplied)
   (vi)   The Appellant-corporation filed its Objections under
          Section 34 on 10.09.2018 before the Ld. Civil Court, Hisar,
          Haryana vide Arbitration Petition No. 316/2018 to challenge       F
          the award dated 27.04.2018, along with an Application for
          condonation of delay.
          It was submitted by the appellant corporation that the
          objections were filed within the period prescribed by Section
          34(3) i.e. within 3 months and 30 days from the date of           G
          receipt of the signed award on 12.05.2018.
   (vii) The Civil Court dismissed the Application for condonation
         of delay vide Order dated 14.02.2019. It was held that the
         Appellant had received the majority award on 27.04.2018.
         Thus, the period of limitation starts running from the same        H
1144      SUPREME COURT REPORTS                           [2021] 1 S.C.R.


 A           date. Accordingly, the period of limitation of three months
             starts from 27.04.2018 i.e. the date on which the Appellant
             received the arbitral award. The proviso to Section 34(3)
             provides that if the Court is satisfied that the applicant was
             prevented from sufficient cause from making the application
             within 3 months, it may entertain the application within a
 B
             further period of 30 days. In the present case, the application
             u/S. 34 was filed even after the expiry of the further period
             of 30 days. Merely because the dissenting opinion was
             erroneously styled as an award by the minority arbitrator, it
             cannot be said that the dissenting opinion attains the status
 C           of an award. Consequently, the objections were dismissed
             solely on the ground of delay.
       (viii) The appellant corporation filed Appeal No. 1954/2019
              (O&M) under Section 37 of the Arbitration Act before the
              High Court.
 D            The High Court vide the impugned Order dated 11.12.2019
              affirmed the Order passed by the Civil Court. It was held
              that a reading of Section 31 clearly reflects that once an
              award is signed and communicated by the majority of
              arbitrators, the same would constitute an “award”. The
              signed copy of the majority award i.e. signed by two of the
 E
              three arbitrators was received on 27.04.2018, and u/S. 34(3),
              the objections had to be filed within 3 months, which would
              expire on 27.07.2018. Even if the benefit of 30 days had
              been granted to the Appellants, the objections ought to have
              been filed by 26.08.2018, whereas the objections had been
 F            filed on 10.09.2018. There was no infirmity in the judgment
              of the Civil Court, and accordingly, the Appeal was
              dismissed.
       (ix) Aggrieved by the rejection of the objections under Section
              34 on the ground of delay, the appellant corporation has
 G            filed the present Appeal.
       3. Submissions of the parties
       (i)    The appellant corporation inter alia contended that its
              objections had been erroneously dismissed by the Additional
              Civil Judge, as well as the High Court on the sole ground of
              limitation, and not on merits. It was submitted that reference
 H
        DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                             1145
     NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

                to the ‘arbitral award’ in the Arbitration Act includes both       A
                the majority award as well as the minority opinion.
                Section 31(1) of the Act provides that all the members of
                the tribunal shall sign the award. Section 31(2) which permits
                an award to be rendered so long as it is signed by the majority
                of the members, and reasons for omission of the signature          B
                of the third arbitrator is mentioned, applies only in the case
                of a unanimous award. Section 31(2) has no application
                when there is dissenting view rendered by one of the
                arbitrators.
                Section 34 of the Act provides for objections to be filed
                against the arbitral award, and not the majority award alone.      C
                Consequently, the time limit to file objections against an
                award under Section 34(3) of the Act, does not relate to
                only the majority award, but to the arbitral award, which
                includes the opinion of the dissenting member of the tribunal.
                It was contended that if the majority award was taken to           D
                mean the arbitral award, the dissenting opinion of the
                minority would have no relevance. Such a view would cause
                grave prejudice to the award debtor.
                It was further submitted that even though the award of the
                majority was pronounced on 27.04.2018, the tribunal posted         E
                the matter on 12.05.2018 to enable the parties to point out
                any correction, or any typographical or clerical error in the
                award. On 12.05.2018, the dissenting opinion was
                pronounced, and a copy was provided to the parties. The
                matter was next posted on 19.05.2018, to consider any
                application for correction in the opinion of the minority. Since   F
                no application for correction of the award, or the minority
                opinion, was filed by the parties, the tribunal terminated the
                proceedings.
                It was further submitted that the dissenting opinion has been
                held to be the correct view by the Courts in various cases.        G
                Reliance was placed on the judgment of this Court in
                Ssangyong Engineering and Construction Co. ltd. v.
                NHAI.,1 wherein thedissenting opinion was upheld as being
                the correct view, and was affirmed. Reference was made
1
    2019 (15) SCC 131.                                                             H
1146                   SUPREME COURT REPORTS                          [2021] 1 S.C.R.


 A                       to the judgment of the Bombay High Court in Axios
                         Navigation v. Indian Oil Corporation,2 wherein it was
                         held that the view of the minority was relevant for the
                         adjudication of objections under Section 34 of the Act.
                (ii)     On the other hand, the Respondents contended that the
 B                       objections filed by the appellant corporation under Section
                         34 of the Arbitration Act are barred by limitation, and ought
                         to be dismissed as such. The contention of the Respondent
                         is that since the majority award was pronounced on
                         27.04.2018, the limitation period applicable under Section
                         34(3) would commence from this date.
 C
                         The Respondent placed reliance on Section 34(3) of the
                         Act to submit that a party may file objections to the award
                         within a period of three months from the date of receipt of
                         the award. On sufficient cause being shown to the
                         satisfaction of the Court, the three months period could be
 D                       extended by an additional period of thirty days. The
                         Respondent submitted that the time for filing objections was
                         available till 26.07.2018, or if sufficient cause was made
                         out, an additional period of 30 days’ which expired on
                         26.08.2018.
 E                       The dissenting opinion of the minority member was not an
                         award for the purposes of computing the limitation period
                         prescribed under sub-section (3) of Section 34.
                         Section 29(1) of the Act contemplates that the decision of
                         the majority of members of the tribunal, is the arbitral award.
 F                       Reliance was placed on Section 31(2) of the Act which
                         provides that the signature of all the members of the tribunal
                         was not required, so long as the award was signed by a
                         majority of the members, and reasons for omission of the
                         signature of the third arbitrator were recorded in the award.
 G                       The opinion of the minority was only a view, and could not
                         be enforced as an award. It could not be considered to be
                         the arbitral award for the purpose of computing limitation
                         under Section 34(3) of the Act.
       2
           2012 SCC Online Bom 4.
 H
       DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                        1147
    NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

             Reliance was placed on the judgments of the Delhi and           A
             Bombay High Court in Bharat Sanchar Nigam Ltd. v.
             Acome and Ors. 3, Axion Navigation v. Indian Oil
             Corporation Ltd., 4 and Oriental insurance Co. v. Air
             India Ltd.,5 wherein it was held that the limitation period
             under Section 34(3) of the Act shall commence from the
                                                                             B
             date when the award is passed.
      4. Discussion & Analysis
      We have heard the Ld. counsel for the parties. In order to
appreciate the rival contentions of the parties, we will first examine the
scheme of the Arbitration and Conciliation Act, 1996.
                                                                             C
      (i)    Section 2 (1)(c) of the 1996 Act defines “arbitral award” to
             include an interim award. The phrase “arbitral award” has
             been used in several provisions of the 1996 Act.
             The statute recognises only one arbitral award being passed
             by an arbitral tribunal, which may either be a unanimous
             award, or an award passed by a majority in the case of a        D
             panel of members. An award is a binding decision made by
             the arbitrator/s on all the issues referred for adjudication.
             The award contains the reasons assigned by the tribunal on
             the adjudication of the rights and obligations of the parties
             arising from the underlying commercial contract. The award      E
             must be one which decides all the issues referred for
             arbitration. The view of a dissenting arbitrator is not an
             award, but his opinion. However, a party aggrieved by the
             award, may draw support from the reasoning and findings
             assigned in the dissenting opinion.
                                                                             F
      (ii) The phrase ‘arbitral tribunal’ has been defined by Section
             2(1)(d) to mean a sole arbitrator, or a panel of arbitrators.
      (iii) Chapter VI of the Arbitration and Conciliation Act provides
             the procedure for making of an arbitral award, and
             termination of arbitral proceedings.
             Sections 28 to 31 relate to the procedure for making the        G
             award. Section 28 provides the rules applicable for the
             determination of a dispute by arbitration.
3
  AIR 2009 Delhi 102.
4
  (2012) 114 (1) Bom LR 392.
5
  (2019) SCC Online Del 11634.                                               H
1148      SUPREME COURT REPORTS                             [2021] 1 S.C.R.


 A     (iv)   Section 29 of the 1996 Act deals with decision making by a
              panel of arbitrators. Section 29 reads as :
                 “29. Decision making by a panel of arbitrators.-
                 (1) Unlessotherwise agreed by the parties, in arbitral
                 proceedings with more than one arbitrator, any decision
 B               of the arbitral tribunal shall be made by a majority of all
                 its members.
                 (2) Notwithstanding sub-section (1), if authorised by the
                 parties or all the members of the arbitral tribunal,
                 questions of procedure may be decided by the presiding
 C               arbitrator.”
                                                        (emphasis supplied)
              Sub-section (1) provides that unless the parties agree
              otherwise, in arbitral proceedings with more than one
              arbitrator, “any decision of the arbitral tribunal shall be made
 D            by a majority of all its members”.
              An “arbitral award” is the decision made by the majority
              members of an arbitral tribunal, which is final and binding
              on the parties.
              Section 35 provides that an arbitral award shall be “final
 E
              and binding” on the parties and persons claiming under them.
              A dissenting opinion does not determine the rights or liabilities
              of the parties which are enforceable under Section 36 of
              the Act.
       (v)    The reference to the phrase “arbitral award” in Sections
 F
              34 and 36 refers to the decision of the majority of the
              members of the arbitral tribunal. A party cannot file a petition
              u/S. 34 for setting aside, or u/S. 36 for enforcement of a
              dissenting opinion. What is capable of being set aside u/S.
              34 is the “arbitral award” i.e. the decision reached by the
 G            majority of members of the tribunal. Similarly, u/S. 36 what
              can be enforced is the “arbitral award” passed by the
              majority of the members.
       (vi)   Section 29A was inserted by the 2015 Amendment Act.
              Under sub-section (1), the arbitral tribunal [other than in an
 H            international commercial arbitration] is mandated by statute
   DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                          1149
NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

         to make the arbitral award within a period of 12 months’          A
         from the date of completion of pleadings, as provided by
         sub-section (4) of Section 23. Section 29A(4) provides that
         the “mandate” of the arbitrator/s shall terminate if the award
         is not made “within” the period specified in sub-section (1),
         or the extended period under sub-section (3). Therefore,
                                                                           B
         by prescription of law, the mandate of the arbitrator/s would
         terminate if the time limits are not followed.
   (vii) Legal requirement of signing the award
         The legal requirement of signing the arbitral award by a
         sole arbitrator, or the members of a tribunal is found in         C
         Section 31 of the 1996 Act, which provides the form and
         content of an arbitral award. Section 31 provides that :
             “31. Form and contents of arbitral award.- (1) An arbitral
             award shall be made in writing and shall be signed by
             the members of the arbitral tribunal.                         D
             (2) For the purposes of sub-section (1), in arbitral
             proceedings with more than one arbitrator, the signatures
             of the majority of all the members of the arbitral tribunal
             shall be sufficient so long as the reason for any omitted
             signature is stated.                                          E
             ….
             (4) The arbitral award shall state its date and the place
             of arbitration as determined in accordance with section
             20 and the award shall be deemed to have been made at
             that place.                                                   F
             (5) After the arbitral award is made, a signed copy shall
             be delivered to each party.
             …..                                                      ”
                                                  (emphasis supplied)      G
   (viii) Section 31 (1) is couched in mandatory terms, and provides
          that an arbitral award shall be made in writing and signed
          by all the members of the arbitral tribunal. If the arbitral
          tribunal comprises of more than one arbitrator, the award is
          made when the arbitrators acting together finally express
                                                                           H
1150              SUPREME COURT REPORTS                               [2021] 1 S.C.R.


 A                    their decision in writing, and is authenticated by their
                      signatures.6 An award takes legal effect only after it is signed
                      by the arbitrators, which gives it authentication. There can
                      be no finality of the award, except after it is signed, since
                      signing of the award gives legal effect and validity to it.
                      The making and delivery of the award are different stages
 B
                      of an arbitration proceeding. An award is made when it is
                      authenticated by the person who makes it.
                      The statute makes it obligatory for each of the members of
                      the tribunal to sign the award, to make it a valid award. The
                      usage of the term “shall” makes it a mandatory requirement.
 C                    It is not merely a ministerial act, or an empty formality which
                      can be dispensed with.
              (ix)    Sub-section (1) of Section 31 read with sub-section (4)
                      makes it clear that the Act contemplates a single date on
                      which the arbitral award is passed i.e. the date on which
 D                    the signed copy of the award is delivered to the parties.
                      Section 31 (5) enjoins upon the arbitrator / tribunal to provide
                      the signed copy of the arbitral award to the parties. The
                      receipt of a signed copy of the award is the date from which
                      the period of limitation for filing objections u/s. 34 would
 E                    commence. This would be evident from the language of
                      sub-section (3) of Section 34(3) which reads :
                         “34. Application for setting aside arbitral award.
                         …
                         …
 F                       (3) An application for setting aside may not be made
                         after three months have elapsed from the date on which
                         the party making that application had received the
                         arbitral award or, if a request had been made under
                         Section 33, from the date on which that request had
 G                       been disposed of by the arbitral tribunal:
                         Provided that if the Court is satisfied that the applicant
                         was prevented by sufficient cause from making the
       6
         Malhotra’s Commentary on the Law of Arbitration, Wolters Kluwer, 4 th Ed., Vol.1,
       p.794.
 H
        DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                             1151
     NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

                    application within the said period of three months it may      A
                    entertain the application within a further period of thirty
                    days, but not thereafter.”
         (x)    In Union of India v. Tecco Trichy Engineers &
                Contractors7, a three-judge bench of this Court held that
                the period of limitation for filing an application u/s. 34 would   B
                commence only after a valid delivery of the award takes
                place u/S. 31(5) of the Act. In para 8, it was held as under:
                    “8. The delivery of an arbitral award under sub-section
                    (5) of Section 31 is not a matter of mere formality. It is
                    a matter of substance. It is only after the stage under        C
                    Section 31 has passed that the stage of termination of
                    arbitral proceedings within the meaning of Section 32 of
                    the Act arises. The delivery of arbitral award to the
                    party, to be effective, has to be ‘received’ by the party.
                    This delivery by the Arbitral Tribunal and receipt by the
                    party of the award sets in motion several periods of           D
                    limitation such as an application for correction and
                    interpretation of an award within 30 days under Section
                    33(1), an application for making an additional award
                    under Section 33(4) and an application for setting aside
                    an award under Section 34(3) and so on. As this delivery       E
                    of the copy of award has the effect of conferring certain
                    rights on the party as also bringing to an end the right to
                    exercise those rights on expiry of the prescribed period
                    of limitation which would be calculated from that date,
                    the delivery of the copy of award by the Tribunal and
                    the receipt thereof by each party constitutes an important     F
                    stage in the arbitral proceedings.”
                                                          (emphasis supplied)
         (xi)   The judgment in Tecco Trichy Engineers (supra)was
                followed in State of Maharashtra v. Ark Builders, 8                G
                wherein this Court held that Section 31(1) obliges the
                members of the arbitral tribunal to make the award in writing
                and sign it. The legal requirement under sub-section (5) of
7
    (2005) 4 SCC 239.
8
    (2011) 4 SCC 616                                                               H
1152                SUPREME COURT REPORTS                          [2021] 1 S.C.R.


 A                     Section 31 is the delivery of a copy of the award signed by
                       the members of the arbitral tribunal / arbitrator, and not any
                       copy of the award. On a harmonious construction of Section
                       31(5) read with Section 34(3), the period of limitation
                       prescribed for filing objections would commence only from
                       the date when the signed copy of the award is delivered to
 B
                       the party making the application for setting aside the award.
                       If the law prescribes that a copy of the award is to be
                       communicated, delivered, despatched, forwarded, rendered,
                       or sent to the parties concerned in a particular way, and
                       since the law sets a period of limitation for challenging the
 C                     award in question by the aggrieved party, then the period of
                       limitation can only commence from the date on which the
                       award was received by the concerned party in the manner
                       prescribed by law.
                       The judgment in Tecco Trichy has been recently followed
 D                     in Anilkumar Jinabhai Patel v. Pravinchandra Jinabhai
                       Patel. 9
                (xii) In State of Himachal Pradesh v Himachal Techno
                      Engineers,10 this Court held that if one of the parties to the
                      arbitration is Government, or a statutory body, which has
 E                    notified holidays, and if the award was delivered to a beldar
                      or a watchman on a holiday or non-working day, it cannot
                      be considered to be “receipt of the award” by the party
                      concerned for the purposes of Section 31(5) of the Act.
                      When the award is delivered, or deposited, or left in the
                      office of a party on a non-working day, the date of physical
 F                    delivery is not the date of “receipt” of the award by that
                      party. For the purposes of Section 31(5), the date of receipt
                      will have to be the next working day.
                (xiii) Section 32 provides that the arbitral proceedings shall be
                       terminated after the final award is passed. With the
 G                     termination of the arbitral proceedings, the mandate of the
                       arbitral tribunal terminates, and the tribunal becomes functus
                       officio.
       9
           (2018) 15 SCC 178
       10
            (2010) 12 SCC 210
 H
     DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                                   1153
  NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

       (xiv) In an arbitral tribunal comprising of a panel of three                   A
             members, if one of the members gives a dissenting opinion,
             it must be delivered contemporaneously on the same date
             as the final award, and not on a subsequent date, as the
             tribunal becomes functus officio upon the passing of the
             final award. The period for rendering the award and
                                                                                      B
             dissenting opinion must be within the period prescribed by
             Section 29A of the Act.
       (xv) In the treatise on ‘International Commercial Arbitration’
            authored by Fouchard, Gaillard, Goldman, it has been opined
            that :
                                                                                      C
                  “1403.- A dissenting opinion can only be issued when
                  the majority has already made the decision which
                  constitutes the award. Until then, any document issued
                  by the minority arbitrator can only be treated as part of
                  the deliberations. However, once the majority decision
                  has been reached, it is preferable for the author of the            D
                  dissenting opinion to communicate a draft to the other
                  arbitrators so as to enable them to discuss the arguments
                  put forward in it. The award made by the majority could
                  then be issued after the dissenting opinion, or at least,
                  after the draft of the dissenting opinion...” 11                    E
       (xvi) There is only one date recognised by law i.e. the date on
             which a signed copy of the final award is received by the
             parties, from which the period of limitation for filing objections
             would start ticking. There can be no finality in the award,
             except after it is signed, because signing of the award gives            F
             legal effect and finality to the award.
       (xvii) The date on which the signed award is provided to the parties
              is a crucial date in arbitration proceedings under the Indian
              Arbitration and Conciliation Act, 1996. It is from this date
              that: (a) the period of 30 days’ for filing an application under        G
              Section 33 for correction and interpretation of the award,
              or additional award may be filed; (b) the arbitral proceedings
              would terminate as provided by Section 32(1) of the Act;
11
   Fouchard, Gaillard, Goldman, International Commercial Arbitration, Ed. Emmannuel
Gaillard, John Savage,, p.786 (Kluwer Law International).                             H
1154                SUPREME COURT REPORTS                           [2021] 1 S.C.R.


 A                     (c) the period of limitation for filing objections to the award
                       under Section 34 commences.
                 (xviii) Section 34 provides recourse for judicial scrutiny of the
                        award by a Court, upon making an application under sub-
                        sections (2) and (3) for setting aside the award.
 B                     The period of limitation for filing the objections to the award
                       u/S. 34 commences from the date on which the party
                       making the application has “received” a signed copy of the
                       arbitral award, as required by Section 31(5) of the 1996
                       Act.
 C                     Section 34(3) provides a specific time limit of three months
                       from the date of “receipt” of the award, and a further period
                       of thirty days, if the Court is satisfied that the party was
                       prevented by sufficient cause from making the application
                       within the said period, but not thereafter.
 D                     In Union of India v. Popular Construction,12 this Court
                       held that Section 5 of the Limitation Act, 1963 would not
                       apply to applications filed under Section 34 of the Arbitration
                       Act. It was held that :
                           “12. As far as the language of Section 34 of the 1996
 E                         Act is concerned, the crucial words are “but not
                           thereafter” used in the proviso to sub-section (3). In our
                           opinion, this phrase would amount to an express exclusion
                           within the meaning of Section 29(2) of the Limitation
                           Act, and would therefore bar the application of Section
 F                         5 of that Act. Parliament did not need to go further. To
                           hold that the court could entertain an application to set
                           aside the award beyond the extended period under the
                           proviso, would render the phrase “but not thereafter”
                           wholly otiose. No principle of interpretation would justify
                           such a result.”
 G
                       In Simplex Infrastructure v. Union of India,13 this Court
                       held that the phrase “but not thereafter” provided under
                       Section 34(3) of the Act makes it evident that the statutory
                       period of limitation for filing an application for setting aside
       12
            (2001) 8 SCC 470.
       13
 H          (2019) 12 SCC 455
        DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                           1155
     NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

                 is three months, which is extendable by thirty days, if         A
                 sufficient cause is made out. No further period of time can
                 be granted for the filing of an application under Section 34.
          (xix) If the objections are not filed within the period prescribed
                by Section 34, the award holder is entitled to move for
                enforcement of the arbitral award as a deemed decree of          B
                the Court u/S. 36 of the Act.
                 This Court in P. Radha Bai v. P. Ashok Kumar,14 held that:
                    “32.5. Once the time-limit or extended time-limit for
                    challenging the arbitral award expires, the period for
                    enforcing the award under Section 36 of the Arbitration      C
                    Act commences. This is evident from the phrase “where
                    the time for making an application to set aside the
                    arbitral award under Section 34 has expired”.
                    [“36. Enforcement.—Where the time for making an
                    application to set aside the arbitral award under            D
                    Section 34 has expired, or such application having been
                    made, it has been refused, the award shall be enforced
                    under the Code of Civil Procedure, 1908 (5 of 1908) in
                    the same manner as if it were a decree of the
                    Court.”(emphasis supplied)] There is an integral nexus
                    between the period prescribed under Section 34(3) to         E
                    challenge the award and the commencement of the
                    enforcement period under Section 36 to execute the
                    award.
                    36.2. Second, extending Section 17 of the Limitation
                    Act to Section 34 would do violence to the scheme of         F
                    the Arbitration Act. As discussed above, Section 36
                    enables a party to apply for enforcement of award when
                    the period for challenging an award under Section 34
                    has expired. However, if Section 17 were to be extended
                    to Section 34, the determination of “time for making an      G
                    application to set aside the arbitral award” in Section 36
                    will become uncertain and create confusion in the
                    enforcement of award. This runs counter to the scheme
                    and object of the Arbitration Act.”
14
     (2019) 13 SCC 445.                                                          H
1156                SUPREME COURT REPORTS                            [2021] 1 S.C.R.


 A            (xx) Relevance of a dissenting opinion
              (a)     The dissenting opinion of a minority arbitrator can be relied
                      upon by the party seeking to set aside the award to buttress
                      its submissions in the proceedings under Section 34.
              (b)     At the stage of judicial scrutiny by the Court under Section
 B                    34, the Court is not precluded from considering the findings
                      and conclusions of the dissenting opinion of the minority
                      member of the tribunal.
              (c)     In the commentary of ‘Russel on Arbitration’, the relevance
                      of a dissenting opinion was explained as follows :
 C                       “6-058. Dissenting opinions. Any member of the
                         tribunal who does not assent to an award need not sign
                         it but may set out his own views of the case, either within
                         the award document or in a separate “dissenting opinion”.
                         The arbitrator should consider carefully whether there
 D                       is good reason for expressing his dissent, because a
                         dissenting opinion may encourage a challenge to the
                         award. This is for the parties’ information only and does
                         not form part of the award, but it may be admissible as
                         evidence in relation to the procedural matters in the event
                         of a challenge or may add weight to the arguments of a
 E                       party wishing to appeal against the award.”15
                                                                  (emphasis supplied)
              (d)     Gary B. Born in his commentary on International
                      Commercial Arbitration opines that :
 F                       “Even absent express authorization in national law or
                         applicable institutional rules (or otherwise), the right to
                         provide a dissenting or separate opinion is an appropriate
                         concomitant of the arbitrator’s adjudicative function and
                         the tribunal’s related obligation to make a reasoned
                         award. Although there are legal systems where
 G                       dissenting or separate opinions are either not permitted,
                         or not customary, these domestic rules have little
                         application in the context of party-nominated co-
                         arbitrators, and diverse tribunals. Indeed, the right of an
       15
        David St. John Sutton, Judith Gill and Matthew Gearing QC, Russel on Arbitration,
 H     24th ed. (Sweet & Maxwell), p. 313.
        DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                                 1157
     NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

                   arbitrator to deliver a dissenting opinion is properly              A
                   considered as an element of his / her adjudicative
                   mandate, particularly in circumstances where a reasoned
                   award is required. Only clear an explicit prohibition should
                   preclude the making and publication to the parties of a
                   dissenting opinion, which serves an important role in the
                                                                                       B
                   deliberative process, and can provide a valuable check
                   on arbitrary or indefensible decision making.” 16
        It is further commented that :
                   “There is nothing objectionable at all about an arbitrator
                   “systematically drawing up a dissenting opinion, and
                   insisting that it be communicated to the parties”. If an            C
                   arbitrator believes that the tribunal is making a seriously
                   wrong decision, which cannot fairly be reconciled with
                   the law and the evidentiary record, then he / she may
                   express that view. There is nothing wrong – and on the
                   contrary, much that is right – with such a course as part           D
                   of the adjudicatory process in which the tribunal’s
                   conclusion is expressed in a reasoned manner. And, if
                   the arbitrator considers that the award’s conclusions
                   require a “systematic” discussion, that is also entirely
                   appropriate; indeed, it is implied in the adjudicative
                   process, and the requirement of a reasoned award.”17                E
        It is further observed that :
                   “…the very concept of a reasoned award by a multi-
                   member tribunal permits a statement of different reasons
                   – if different members of the tribunal in fact hold different
                   views. This is an essential aspect of the process by                F
                   which the parties have an opportunity to both, present
                   their case, and hear the reasons for the tribunal’s
                   decision; not hearing the dissent deprives the parties of
                   an important aspect of this process.”
        (e) In Ssangyong Engineering & Construction Co. Ltd v.                         G
                NHAI,18 this Court upheld the view taken in the dissenting
16
   Gary Born, International Commercial Arbitration, Wolters Kluwer, Ed. 2009, Volume
II, p. 2466.
17
   Gary Born, International Commercial Arbitration, Wolters Kluwer, Ed. 2009, Volume
II, p. 2469.
18
   (2019) 15 SCC 131.                                                                  H
1158   SUPREME COURT REPORTS                         [2021] 1 S.C.R.


 A       opinion to be the correct position in law. In this case, the
         Court was hearing a special leave petition from an order
         passed by a division bench of the Delhi High Court. This
         Court noted that:
            “12. A Section 34 petition which was filed by the
 B          appellant was rejected by the learned Single Judge of
            the Delhi High Court, by a judgment and order dated 9-
            8-2016 [Ssangyong Engg. and Construction Co.
            Ltd. v. NHAI, 2016 SCC OnLine Del 4536] , in which it
            was held that a possible view was taken by the majority
            arbitrators which, therefore, could not be interfered with,
 C          given the parameters of challenge to arbitral awards.
            The learned Single Judge also went on to hold that the
            New Series published by the Ministry could be applied
            in the case of the appellant as the base indices for 2004-
            2005 under the New Series were available. Having so
 D          held, the learned Single Judge stated that even though
            the view expressed in the dissenting award is more
            appealing, and that he preferred that view, yet he found
            that since the majority award is a possible view, the scope
            of interference being limited, the Section 34 petition was
            dismissed. A Section 37 appeal to the Division Bench of
 E          the Delhi High Court yielded the same result, by the
            impugned judgment dated 3-4-2017 [Ssangyong Engg.
            and Construction Co. Ltd. v. NHAI, 2017 SCC OnLine
            Del 7864 : (2017) 240 DLT 711].”
         This Court set aside the award. However, in paragraph 77
 F
         of the Judgment, the Court held as under :
            “77. The judgments of the Single Judge [Ssangyong
            Engg. and Construction Co. Ltd. v. NHAI, 2016 SCC
            OnLine Del 4536] and of the Division Bench
            [Ssangyong Engg. and Construction Co.
 G          Ltd. v. NHAI, 2017 SCC OnLine Del 7864 : (2017) 240
            DLT 711] of the Delhi High Court are set aside.
            Consequently, the majority award is also set aside. Under
            the scheme of Section 34 of the 1996 Act, the disputes
            that were decided by the majority award would have to
 H          be referred afresh to another arbitration. This would
   DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                            1159
NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

            cause considerable delay and be contrary to one of the           A
            important objectives of the 1996 Act, namely, speedy
            resolution of disputes by the arbitral process under the
            Act. Therefore, in order to do complete justice between
            the parties, invoking our power under Article 142 of the
            Constitution of India, and given the fact that there is a
                                                                             B
            minority award which awards the appellant its claim
            based upon the formula mentioned in the agreement
            between the parties, we uphold the minority award, and
            state that it is this award, together with interest, that will
            now be executed between the parties. The minority
            award, in paras 11 and 12, states as follows:                    C
            “11. I therefore award the claim of the claimant in full.
            12. Costs — no amount is awarded to the parties. Each
            party shall bear its own cost.”
         In Ssangyong, this Court upheld the view taken by the
                                                                             D
         dissenting arbitrator in exercise of its powers under Article
         142 of the Constitution, in order to do complete justice
         between the parties. The reason for doing so is mentioned
         in paragraph 77 i.e. the considerable delay which would be
         caused if another arbitration was to be held. This Court
         exercised its extraordinary power in Ssangyong keeping in           E
         mind the facts of the case, and the object of expeditious
         resolution of disputes under the Arbitration Act.
   (f)   In law, where the Court sets aside the award passed by the
         majority members of the tribunal, the underlying disputes
         would require to be decided afresh in an appropriate                F
         proceeding.
         Under Section 34 of the Arbitration Act, the Court may
         either dismiss the objections filed, and uphold the award, or
         set aside the award if the grounds contained in sub-sections
         (2) and (2A) are made out. There is no power to modify an
                                                                             G
         arbitral award.
         In McDermott International Inc. v. Burn Standard Co.
         Ltd., this Court held as under :
            “52. The 1996 Act makes provision for the supervisory
            role of courts, for the review of the arbitral award only        H
1160             SUPREME COURT REPORTS                           [2021] 1 S.C.R.


 A                      to ensure fairness. Intervention of the court is envisaged
                        in few circumstances only, like, in case of fraud or bias
                        by the arbitrators, violation of natural justice, etc. The
                        court cannot correct errors of the arbitrators. It can only
                        quash the award leaving the parties free to begin the
                        arbitration again if it is desired. So, the scheme of the
 B
                        provision aims at keeping the supervisory role of the
                        court at minimum level and this can be justified as parties
                        to the agreement make a conscious decision to exclude
                        the court’s jurisdiction by opting for arbitration as they
                        prefer the expediency and finality offered by it.”
 C            5. Applying the law to the facts of the present case, we find from
       a perusal of the arbitral proceedings that even though the award was
       pronounced on 27.04.2018, the signed copy of the award was provided
       to the parties only on 19.05.2018. The procedural orders of the tribunal
       reveal that on 27.04.2018, only a copy of the award was provided to the
 D     parties to point out any computation error, any clerical or typographical
       error, or any other error of similar nature which may have occurred in
       the award on the next date. It was also recorded that the third arbitrator
       had dissented, and would be delivering his separate opinion. The
       proceedings were then posted for 12.05.2018.
 E            On 12.05.2018, the third arbitrator pronounced his dissenting
       opinion. On that date, the tribunal posted the matter to 19.05.2018, to
       enable the parties to point out any typographical or clerical mistakes in
       the dissenting opinion, and for handing over the original record of the
       proceedings to the parties.

 F            On 19.05.2018, the signed copy of the award and the dissenting
       opinion, alongwith the original record, were handed over to the parties,
       as also to each of the arbitrators. The tribunal ordered the termination of
       the proceedings.
               6. We are of the considered opinion that the period of limitation
 G     for filing objections would have to be reckoned from the date on which
       the signed copy of the award was made available to the parties i.e. on
       19.05.2018 in the instant case.
              7. It is the admitted position that the objections were filed within
       the period of limitation prescribed by Section 34(3) of the Act, if reckoned
       from 19.05.2018. Undisputedly, in the instant case, the objections have
 H
     DAKSHIN HARYANA BIJLI VITRAN NIGAM LTD. v. M/S                           1161
  NAVIGANT TECHNOLOGIES PVT. LTD. [INDU MALHOTRA, J.]

been filed within the period of limitation prescribed under Section 34(3)     A
from the date of receipt of the signed award.
       8. In the aforesaid facts and circumstances, the Appeal deserves
to succeed. The judgment of the Court of the District and Sessions Judge,
Hissar, Haryana dated 14.02.2019, and the impugned order passed by
the High Court of Punjab & Haryana dated 11.12.2019 are accordingly           B
set aside.
       9. The Petition filed under Section 34 of the Arbitration and
Conciliation Act, 1996 being Arb. Pet. No. 316 of 2018 is restored to the
file of the Court of District and Sessions Judge, Hissar, Haryana to be
decided on merits in accordance with law.                                     C
       All pending applications are disposed of. Ordered accordingly.

Ankit Gyan                                                  Appeal allowed.

                                                                              D




                                                                              E




                                                                              F




                                                                              G




                                                                              H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.