CHANDRAKANT ADINATH UTTUREversusSTATE OF MAHARASHTRA & OTHERS
- Citation
- 2016 INSC 167
- Decided
- 15 February 2016
- Disposal
- Appeal(s) allowed
- Bench
- KURIAN JOSEPH
Holding
When there is a change in the slab reducing the exemption area in the benefitted zone, the procedure under Section 13(2) requiring a public notice inviting objections or suggestions must be followed.
Summary
The case arose from the Chikotra irrigation project where the State of Maharashtra first notified land acquisition under Slab III for the benefitted zone and later changed to Slab I, thereby increasing the area of land to be acquired. The petitioners contended that this change required a public notice under Section 13(2) of the Maharashtra Project Affected Persons Rehabilitation Act, 1986 to invite objections, while the State argued that no notice was needed for slab changes. The Supreme Court examined Sections 13 and 14 of the Act and held that the purpose of the notice is to allow objections when the benefitted zone is altered, and any reduction of exemption through a slab change must follow the procedure of Section 13(2). The Court rejected the High Court’s view that notice is unnecessary for slab changes and directed that the petitioners be permitted to file objections within a month, with the Collector to forward a report to the State Government. Consequently, the appeals were allowed and the government was ordered to consider the objections before revising the award.
Issues considered
- Whether a public notice under Section 13(2) of the Maharashtra Project Affected Persons Rehabilitation Act, 1986 is required when there is a change in the slab reducing the exemption area in the benefitted zone.
- Whether the procedure for issuing notice and inviting objections applies to changes in slab (Section 13(1)(c)) after the initial notification.
Legislation cited
- Land Acquisition Act, 1894s. 4, s. 5, s. 6, s. 9
- Maharashtra Project Affected Persons Rehabilitation Act, 1986s. 13, s. 14
Subjects
Judgment
[2016] 2 S.C.R. 193
CHANDRAKANT ADINATH UTTURE A
v.
STATE OF MAHARASHTRA & OTHERS
(Civil Appeal No. 1346 of2016)
FEBRUARY IS, 2016 B
[KURIAN JOSEPH AND ROHINTON FALi NARIMAN, JJ.)
Maharashtra Project Affected Persons Rehabilitation Act,
1986 - ss. 13, 14 - Rehabilitation of affected persons from the
benefitted zone -. Declaration of areas in affected and benefitted C
zone by State Government as also extent of land acquired in the
benefitted zone as per the slab - Change in slab or area to be
acquired, after the publication of the first notification - Requirement
of issuing notice to those whose lands would be acquired on account
'
of the change in the slab - Held:'#'hen there is a change in the
slab, reducing the area of exemption from acquisition in the benefitted D
zone, the procedure uls. 13(2) is to be followed which requires giving
of public notice inviting objections.
Allowing the appeals, the Conrt
HELD: 1.1 The whole purpose of notice under sub-Section
E
(2) of Section 13 of the Maharashtra Project Affected Persons
Rehabilitation Act, 1986 is to invite objections or suggestions in
respect of the lands falling under the affected or benefitted zone.
By change of slab, there is change in. the area of the benefitted
zone and that change can be brought out only on following the
procedure nnder sob-Section (2) after considering the objections F
and suggestions. [Para l2) [200cF-G]
1.2 Under sub-Section (4) of Section 14, the Government
is permitted to acquire land even from any other villages or areas
for the purpose of rehabilitating the affected persons from the
·affected zone or for rehabilitating those under any project who G
have remained to be rehabilitated. Once there is a change in the
notification on the slab reducing the size of exempted holding,
the people thus affected should get a chance to make their
objections and suggestions, so that the Government may consider
the report of the Collector on those objections and suggestions,
H
193
194 SUPREME COURT REPORTS (2016] 2 S.C.R.
A before issuing a revised notification u/s. 13(1) of the Act. [Para
13] (200-G-H; 201-A]
1.3 Passing of the award by itself does not mean that any
illegality should not be addressed. In the instant case, the writ
petitions were filed when the declaration under Section 6 of the
B Act was published, and in any case, it is submitted by the appellants
that they have not been dispossessed so far and no compensation
also has been paid. Therefore, the High Court was not right in
holding that the requirement of notice on objections and
suggestions need only be in respect of the lands coming under
Section 13(1)(a) of the Act (the affected zones) and Section
c 13(1)(b) of the Act (the benefitted zones). The High Court is right,
however, in holding that no notice is required in respect of the
lands belonging to the slab under Section 13(l)(c) of the Act,
when it is issued for the first time. However, in case there is a
change in the slab reducing the area of exemption from acquisition
D in the benefitted zone, the procedure under Section 13 (2) of the
Act is required to be followed. The appellants are permitted to
prefer their objections or submit their suggestions on the change
of slab from Slab III to Slab I before the Collector. [Paras 15 - 17)
(201-F-H; 202-A-B)
E CIVIL APPELLATE JURISDICTION : Civil Appeal No. I 346
of2016
From the Judgment and Order dated 07.06.2010 in WP No. 1144
of2002 by the High Court of Judicature at Bombay
WITH
F
C.A. No. 1348 of2016
& C.A. No. 1350 of2016
Harshvardhan Reddy, Senthil Jagadeesan, Aman Vachher,
Ashutosh Qubey, Abhishek Chauhan, (For P.N. Puri), Advs. for the
G Appellants.
Satyajit A. Desai, Akash Kakade, Nishant Ramakantrao
Katneshwarkar, Advs. for the Respondents.
The Judgment of the Court was delivered by
KURIAN, J.: !. Leave granted.
H
CHANDRAKANT ADINATH UTTURE v. STATE OF 195
MAHARASHTRA [KURIAN, J,]
2. The Maharashtra Project Affected Persons Rehabilitation Act, A
• · 1986 (hereinafter referred to as "the Act") is a piece of legislation
· intended for rehabilitation of persons affected on implementation of certain
projects in the State of Maharashtra "on the lands acquired from the
zones benefitted by the projects. The Act is applicable to all irrigation
projects of which the area of the affected zone exceeds 50 Hectares or
B
the area of the benefitted zone exceeds 200 Hectares or where a gaothan
. is affected. The State Government is also entitled to make the Act
applicable to other projects as well to which the Act is applicable. The
affected zone is defined as the area declared under Section 13 of the
Act to constitute the extent of the area affected uricle"t a partic_µlar project.
Benefitted zone means the area declared under Section 13 of the Act to c
constitute the area of the benefitted zone under the project. Rehabilitation
under the scheme of, the Act of the affected persons is done mainly by
acquiring lands corning under the benefitted zone. In the present case, it
is the Chikotra project.
3. Under Section 13 of the Act, the State Government has to D
make a declaration of areas in affected and benefitted zones and also
che extent ofland to be acquired irt the benefitted zone is as perthe slabs
·mentioned in Part 11 of the Schedule. As far as extent of area coi1stituting
the affected zone under the project and the extent of area constituting
the benefitted zone is cc\ncerned, it is cfoarly provided under Section ·
13(2) of the Act that a public notice inviting objections or suggestions· is E
to be issued. After considering the objections and suggestions only, a
notification under Section 13 (1) of the Act could be published in the
official gazette and by other modes of publication as provided under the
Act.
4. In the instant case, there is no dispute on that procedure. The F
dispute is in a narrow compass. In the gazette notification originally
published, the slab under Part JI was Slab III whereunder there is no
acquisition in case the holding in the benefitted zone is not more than 3
Hectares and 23 Ares. Under all slabs, larger the holding, proportionately
larger is the acquisition. After publishing the notification under Section G
13 with Slab Ill on 04.03 .1994, another notification was published on
26.07.1995 changing the slab under Part II from Slab III to Slab I wherein
the exemption from acquisition is only where the size of holding is not.
more than I Hectare and 61 Ares. Under Slab I (ifthe size of the benefitted
holding is more than 1 Hectare and 61 Ares but not more than 2 Hectares
and 42 Ares, the area to be acquired is that in excess of 1 Hectare and H
196 SUPREME COURT REPORTS [2016] 2 S.C.R.
A 61 Ares (the exempted area under Slab I) but not more thaR 40 Ares). If
the size of the holding is more than 2 Hectares and 42 Ares and not
more than 3 Hectares and 23 Ares (the exempted size of the holding
under Slab III), the area to be acquired is the area in excess of2 Hectares
and 2 Ares but not more than 80 Ares.
B 5. The simple question is, in case there is a change in slab or area
to be acquired, after the publication of the first notification, should there
be a notice to those whose lands will be acquired on account of the
change in the slab.
6. The High Court in the impugned judgment dated 07 .06.20 I 0,
c has taken the view that the public notice for hearing under Section 13 of
the Act need only be in respect of the lands ' in the affected zone and
benefitted zone and there is no requirement under the Act or under law,
for notice when there is a change in the slab, and hence, the appeals.
7. Being a pure question of law, it is not necessary to delve deep
D into the facts and yet we shall refer to a few dates.
8. Notices under Section l 3(2)'oftheAct inviting objections with
respect to lands in the affected and benefitted zones were published on
20.09.1993, 22.11.1993 and 03.12.1993. After considering the objections,
the notification under Section 13( 1) of the Act was issued and published
E in the gazette on 04.03.1994. There were around 500 project affected
khatedars and the land estimated for the rehabilitation was around 653
Hectares. As per the notified Slab III, exempted size of holding being
upto the extent of 3.43 Hectares, th.e land available for acquisition was
only around 179 Hectares, as per the respondent. However, if the slab
was changed from Slab III to Slab I, the land available for acquisition
F would be around 548 Hectares. It was hence and in that context, another
notification was published on 26.07 .1995 changing the slab from Slab III
to Slab I. According to the appellants, though there is no requirement
under Section 13 of the Act for a notice and hearing while issuing a
notification for the first time under Section 13(1) of the Act, when there
G is a change in the slab reducing the exempted area, the affected persons
are entitled to notice.
9. Jn order to appreciate the contention, we have to analyse the
scheme of the Act under Sections 13 and 14 of the Act dealing with the
declaration of areas in the affected and benefitted zones and the Schedule.
Sections 13 and 14 read as follows:
H
CHANDRAKANT ADINATH UTTURE v. STATE OF 197
MAHARASHTRA [KURlAN, J.]
"Section 13: Declaration of areas in affected or benefitted A
zones
( 1) The State Government shall, by notification in the Official
Gazette and also by pub~fication of such notification in the
manner provided in sub-section (2) of section 11, declare-
(a) th.e extent of area which shall constitute the area of B
affected zone under the project;
(b) if the project is an irrigation project, the extent of area
which shall constitute the area ofbenefitted zone under the
project;
c
(c)which ofthe slabs mentioned in Part II of the Schedule
shall apply to such project for the purpose of acquisition of
land in the benefitted zone.
(2) Before publishing a notification under sub-section (1 ), the
Collector shall give a public notice inviting objections or 0
suggestions in respect of the lands falling under clauses (a)
and (b) of sub-section( i}, by publishing in the manner specified
in sub-section (2) of section 11 and also in the Official Gazette
and in one daily newspaper in the Marathi language circulating
in the local area comprising such villages and areas ofaffected
and benefitted zone. Any person interested in the land in such E
areas may make, objections or suggestions, if any, to the
Collector within 30 days from the date on which such public
notice is published by beat of drum in the village or area
concerned or the date on which it is published in the newspaper
as aforesaid, whichever is later; and the Collector shall, with
F
all reasonable dispatch, forward any objections or suggestions
so made together with his report in respect thereof to the State
Governmentand on considering the report and the objections
and suggestions, if any, the State Government may pass such
order as it deems fit.
G
(3) If at any time during the course of execution of a project,
the project authority is satisfied that any change in the areas
mentioned in the notification under subsection (1) is necessary,
it shall communicate such change with reasons and the plans
and particulars relating to the change to the State Government
through the Collector. H
198 SUPREME COURT REPORTS [2016] 2 S.C.R.
A (4) On receipt of the communication under sub-section (3)
and the report of the Collector, if any, the State Government
rnay after considering the reasons given by the project authority
and in the report, if any, of the Collector and making such
enquiry, if any, as it thinks fit, make such change in the manner
laid down in sub-sections ( 1) and (2).
B
Section 14: Power to acquire land for purposes of this Act
( 1) The State Government or the Collector authorised by it by
general or special order in this behalf may enter into an
agreement with any person for the purchase or exchange of
c any land required for carrying out the purposes of this Act:
Provided that, the amount paid under an agreement under
this sub-section shall not be less than the amount of
compensation payable for the land, had it been acquired in
accordance with the provisions of sub-section (2).
D (2) Subject to the provisions of this section, the State
Government may for carrying out the purposes of t\lis Act,
also compulsorily acquire land under the Land Acquisition Act,
1894 (I of 1894); and the acquisition of any land for any of the
said purposes shall be deemed to be a public purpose within
E the meaning of that Act.
(3) The State Government may also acquire lands included in
a gaothan in the affected zone as far as practicable according
to the provisions of Part I of the Schedule.
( 4) For the purpose of rehabilitating affected persons from the
F affected zone under an-irrigation project, including those under
any irrigation project who have remained to be rehabilitated,
on land, the State Government may acquire land from holdings
in the benefitted zone of the project according to the slab
declared in the notification under sub-section ( 1) of section 13
and may also acquire, where necessary, land from any other
G
villages or areas, as it may deem fit.
(5) All lands acquired under this section shall form part of the
land pool."
10. Slab I and Slab III in Part II under the Schedule, to the
H extent relevant, read as follows:
CHANDRAKANT ADINATH UTTURE v. STATE OF 199
MAHARASHTRA [KURIAN, J.]
'"Size of holding Area to be acquired A
~ (l) (2)
(a) Not more than 1 Hectare- (a) NIL B
and 6I Ares.
(b) More than' 1 Hectare and 61 (b) The area in excess of 1
Ares and not more than 2 Hectare and 61 Ares but not
Hectares and 42 Ares. more than 40 Ares. c
(c) More than 2 Hectares and 42 (c) The area in excess of 2
Ares and not more than 3 Hectares and 2 Ares but not
Hectares and 23 Ares. more than 80 Ares.
( d) More than 3 Hectares and 23 (d) The area in excess of 2
D
Ares and not more than 3 Hectares and 42 Ares but not
Hectares and 4 Ares. mare than 1 Hectare and 21
·Ares.
xxx xxx xxx
Slab III E
(a) Not more than 3 Hectares (a) NIL
and 23 Ares.
(b} More than 3 Hectares and 23 (b) The area in excess of 3
Ares and not more than 4 Hectares and 23 Ares but not F
Hectares and 4 Ares. more than 40 ares.
xxx xxx
I I. Under S'ection 13 of the Act, before the State Government
makes a notification in the official gazette declaring the extent of area G
constituting affected and benefitted zones and the slab under Part II of
the Schedule, the Collector h~s to give a public notice under Section
13(2) of the Act inviting objections or suggestions in respect of the lands
falling under the affected zone and benefitted zone. The mode of
publication is gazette and daily newspaper in Marathi having circulation H
200 SUPREME COURT REPORTS [2016] 2 S.C.R.
A in the respective areas. The Collector has to forward a report on the
objections or suggestions made by the persons interested in the lands
coming under the affected or bencfitted zone and the State Government
has to pass appropriate orders on the report on the objections and
suggestions. Only after completing the process as above under sub-
B Section (2) of Section 13 of the Act, a notification of the affected and
benefitted zones and the slab under Part 11 of the Schedule can be
published. Under sub-Section (3), if, at any time, during the course of
execution of a project, in case, any change in the areas mentioned in the
notification under sub-Section (1) becomes necessary, such change can -
be made only in the manner laid down in sub-Sections (1) and (2). As
C per the first notifjcation under Section 13( 1) of the Act published on
04.03. 1994, since the slab was Slab Ill, there was no acquisition where
the size of the holding in the benefitted zone is not more than 3 Hectares
and 23 Ares; however, as per the subsequent notification dated 26.07. I995
published under Section 13(1 ), since there is a change of slab from Slab
llI to Slab I, there is acquisition from those who hold land more than I
0
Hectare and 6 I Ares. It is certainly a change as perceived under sub-
section (3) and such a change can be brought out during the course of
execution of a project only in the manner laid down in sub-Sections ( 1)
and (2) of Section 13 of the Act. The reason is that any adverse change
in the slab would have its impact on the extent on the lands in benefitted
E zone. That zone in the process gets reduced. In the instant case, while
publishing the second notification on 26.07.1995, the procedure under
sub-Section (2), admittedly, has not been followed.
I 2. It may be seen that the whole purpose of notice under sub-
section (2) of Section 13 of the Act is to invite objections or suggestions
F in respect of the lands falling under the affected or benefitted zone. By
change of slab, as noted above, there is change in the area of the
benefitted zone and that change can be brought out only on following the
procedure under sub-Section (2) after considering the objections and
suggestions.
G I 3. Sub-Section (4) of Section 14 of the Act is also another indicator
on the requirement of notice. The Government is permitted to acquire
land even from any other villages or areas for the purpose ofrehabilitating
the affected persons from the affected zone or for rehabi Iitating those
under any project who have remained to be rehabilitated. Once there is
a change in the notification on the slab reducing the size of exempted
H holding, the people thus affected should get a chance to make their
'
CHANDRAKANT ADINATH UTTURE v. STATE OF 201
MAHARASHTRA [KURIAN, J.]
<Jbjections and suggestions, so that the Government may consider the A
report of the Collector on those.objections and suggestions, before issuing
a revised notification under Section 13( 1) of the Act.
14. Learned Counsel for the respondent-State submits that
pursuant to the notifications issued under the Act, further steps, as noted
below, have been taken for acquisition of the land: B
S. No. Date Particular
I. 2L09.2000 Notification under Section 4 of Land
i
Acquisition Act was published in
Government Gazette. c
'
', 2. Notice u/s. 4(1) of the Land Acquisition
· Act was given to the petitioner.
3. 28.11.2000 Objections raised by the petitioner
u/s.5( 1) of the Land Acquisition Act D
were heard.
4. 14.12.200 I Declaration u/s. 6 of Land Acquisition
Act was published in Government
Gazette.
E
5. 15.01.2002 The notice u/s.9(3)(4) of the Land
-· Acquisition Act was issued to the
petitioner.
6. _21.01.2004 Final Award has been declared"
F
15. Passi.ng of the award by itself does not mean that any illegality
should not be addressed. In the instant case, the writ petitions were filed
when the declaration under Section 6 of the Act was published, and in
any case, it is submi,tted by the appellants that they have not been
dispossessed so far and no compensation also has been paid.
G
16. Therefore, the High Court is not right in holding that the
requirement of notice on objections and suggestions need only be in
respect of the lands coming under Section 13( 1)(a) of the Act (!he
affected zones) and Section i 3(1 )(b) of the Act (the benefitted zones).
The High Court is right, however, in holding that no notice is required in
respect of the lands belonging to the slab under Section l 3(1)(c) of the H
202 SUPREME COURT REPORTS [2016) 2 S.C.R.
A Act, when it is issued for the first time. However, in case there is a
change in the slab reducing the area of exemption from acquisition in the
benefitted zone, the procedure under Section 13 (2) of the Act is required
to be followed.
17. For the above reasons, these appeals are disposed of permitting
B the appellants to prefer their objections or submit their suggestions on
the change of slab from Slab Ill to Slab I before the Collector within one
month from today. The Collector shall make appropriate inquiry on the
objections or suggestions and forward his report to the State Government
within another two months. The State Government shall pass appropriate
orders on the report within another two months. Depending on the orders
c thus passed by the Government, the Collector shall revise the awards
already passed, ifrequired. The appeals are allowed to the above extent.
18. There shall be no order as to costs.
Nidhi Jain Appeals allowed.
D
'
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.