Created byFuzzy Cloud

Supreme Court of India

CHADURANGA KANTHRAJ URS AND ANR.versusP. RAVI KUMAR AND ORS.

Citation
2024 INSC 957
Decided
10 December 2024

Holding

The respondents wilfully disobeyed the Court's orders and must issue TDRs as per the Karnataka Stamp Act's market values, with the extra conditions of the 19‑03‑2024 order recalled.

Summary

The Supreme Court examined whether the State of Karnataka and its agencies wilfully disobeyed its earlier orders dated 21‑11‑2014, 17‑05‑2022 and 19‑03‑2024 directing the issuance of Transfer of Development Rights (TDR) for land acquired for road widening. The petitioners alleged that the respondents delayed and altered the implementation, suppressed facts, and failed to issue TDRs as per the Karnataka Town and Country Planning (Benefit of Development Rights) Rules and the Karnataka Stamp Act. The Court reiterated that contempt requires a finding of wilful, intentional disobedience and that contempt cannot be used as a tool for execution of a decree where alternative remedies exist. It held that the respondents’ conduct amounted to wilful disobedience, that the additional conditions imposed on 19‑03‑2024 were contrary to the earlier orders, and that the State must issue TDRs based on the market values fixed under the Stamp Act. The Court recalled the extra condition, directed issuance of TDRs within six weeks, ordered compliance affidavits, and allowed the contempt petitions while disposing of one petition.

Issues considered

  • Whether the respondents wilfully disobeyed the Supreme Court's orders dated 21‑11‑2014, 17‑05‑2022 and 19‑03‑2024.
  • Whether contempt of court jurisdiction can be invoked when alternative legal remedies are available.
  • Whether the additional conditions imposed by the Court on 19‑03‑2024 are valid or contrary to earlier orders.
  • Whether the valuation of TDRs must follow the market values prescribed under the Karnataka Stamp Act, 1957.

Legislation cited

Headnote

Issue for Consideration Whether orders dated 21.11.2014, 17.05.2022 and 19.03.2024 passed by this Court has been wilfully disobeyed by the respondents/contemnors. Headnotes† Contempt of Court – Disobedience of Order – to punish a contemnor, it has to be established that disobedience of the order is ‘wilful’ – It means knowingly-intentional, conscious, calculated and deliberate with full knowledge of consequences flowing therefrom – It would exclude casual, accidental, bonafide or

Subjects

Suppressio Veri Suggestio FalsiLex non cogit ad impossibiliaBonafideMalafideGovernment OrdersContemptModificationComplianceCompensationFinancial HardshipWilful DisobedienceDisobedience of orderAlternate remedyAction in disregardKnowledge of consequence

Judgment

                [2024] 12 S.C.R. 1287 : 2024 INSC 957

                  Chaduranga Kanthraj Urs and Anr.
                                v.
                      P. Ravi Kumar and Ors.
                 (Contempt Petition (Civil) No. 688 of 2021)
                                     In
                      (Civil Appeal No. 3310 of 1997)
                               10 December 2024
             [M.M. Sundresh and Aravind Kumar,* JJ.]


                            Issue for Consideration
       Whether orders dated 21.11.2014, 17.05.2022 and 19.03.2024
       passed by this Court has been wilfully disobeyed by the
       respondents/contemnors.

                                   Headnotes†
       Contempt of Court – Disobedience of Order – Willful
       Disobedience:
       Held: In order to punish a contemnor, it has to be established that
       disobedience of the order is ‘wilful’ – It means knowingly-intentional,
       conscious, calculated and deliberate with full knowledge of
       consequences flowing therefrom – It would exclude casual,
       accidental, bonafide or unintentional acts or genuine inability and
       would also not include involuntary or negligent actions – The
       deliberate conduct of a person means that he knows what he is
       doing and intends to do the same – It is too well settled that if two
       interpretations are possible, and if the action is not contumacious,
       a contempt proceeding would not be maintainable. [Para 1.10]

       Contempt of Court – Execution of decree – Alternate remedy:
       Held: The weapon of contempt will not be used for execution of
       the decree or implementation of an order for which alternative
       remedy in law is provided for – The paramount consideration is
       given to maintain court’s dignity and majesty of law. [Para 1.11]

       Contempt of Court – Wilful disobedience – Action in disregard:
       Held: The civil contempt would mean a wilful disobedience of
       a decision of this Court – What would be relevant is the “wilful
* Author
1288                                                         [2024] 12 S.C.R.

                         Supreme Court Reports


    disobedience” – Hence, knowledge of having acted in disregard
    to an order is sine qua non for being proceeded with if there is a
    deliberate, conscience and intentional act then the jurisdiction can
    be clutched. [Para 1.12]

    Contempt of Court – Allegation of wilful disobedience of the
    Orders dated 21.11.2014, 17.05.2022 and 19.03.2024 passed
    by this Court:
    Held: A plain reading of the orders dated 21.11.2014 and 17.05.2022
    would indicate that direction issued to the respondents is to the
    effect that TDR had to be issued as per TDR rules – There was
    no ambiguity or vagueness in the said orders – It is also not the
    case of the contemnors that any doubt being there in the said
    orders – The respondents seem to have dragged their feet and for
    no justifiable reason whatsoever have not implemented the said
    orders – Thus, explicitly there has been wilful disobedience of orders
    of this Court and respondents having failed in their attempt to seek
    modification of order dated 21.11.2014 cannot take umbrage under
    any circumstances whatsoever for not implementing the orders of
    this Court, particularly when clarification/modification prayer was put
    to rest on 17.05.2022 by this Court – In fact, this Court by Order
    dated 19.03.2024 with the hope that respondents would purge in the
    contempt by implementing the same in its letter & spirit had directed
    compliance of the Order dated 21.11.2014 and 17.05.2022 – An
    additional condition was imposed or in other words orders dated
    21.11.2014 and 17.05.2022 was tweaked by this Court – A valiant
    attempt has been made by the contemnors to contend that orders
    of this Court has been complied by passing of the order dated
    15.03.2024 and issuance of consequential notices and Government
    Orders – In the notices issued on 10.06.2024 and 26.06.2024 the
    authorities seems to be projecting a picture that the possession
    of the subject land has not been delivered and this is nothing but
    suppressing the true facts and making a false statement before
    this Court namely suppressio veri suggestio falsi – The State and
    its authorities have no doubt dragged their feet in implementing
    the orders of the Court – However, there seems to be thin line
    of doubt which has arisen in the mind of State and its authorities
    as regards the valuation and in this direction if steps have been
    taken to protect the interest of the revenue and several meetings
    have been held and these aspects are placed before the State
    Cabinet and a decision has been taken by the State cabinet, it
[2024] 12 S.C.R.                                                            1289

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     cannot be construed or held that State is not willing to implement
     the order and particularly in the background of several orders
     having been passed though not in consonance with the orders
     dated 21.11.2014 and 17.05.2022 – Hence, this Court deems it
     proper to extend one final opportunity to report compliance within a
     time frame – Since, the State and its authorities have intentionally
     dragged its feet for long number of years and having attempted
     to tap all the mirage remedies and left with no other option and
     to stave off these proceedings have passed the orders dated
     15.03.2024, 22.04.2024, 24.05.2024 and 10.06.2024 to utilise the
     subject land for road widening, fixing the extent to which each of
     the claimants would be entitled for compensation and to issue the
     TDR on an estimate value which is not accepted by this Court, still
     an opportunity to issue TDR’s as per market value as envisaged
     under Karnataka Stamp Act, 1957 ought to be extended to the
     respondents/contemnors – Hence, the respondent authorities
     directed to issue the TDR as per the value noticed by the Court in
     favour of the respective claimants – It is also explicitly made clear
     that the order dated 19.03.2024 to the extent of imposing additional
     conditions is hereby recalled, as it is diametrically opposite to the
     order dated 17.05.2022 and 21.11.2014 – The directions issued
     under Orders dated: 21.11.2014 and 17.05.2022 to be complied by
     the competent authority of BBMP. [Paras 5.3, 10, 15, 16, 23, 24, 25]

                              Case Law Cited
     Sudhir Vasudeva v. George Ravishekeran [2014) 4 SCR 27 :
     (2014) 3 SCC 373; Rita Markanday v. Surjit Singh Arora [1996]
     Supp. 7 SCR 56 : (1996) 6 SCC 14; Rama Narang v. Ramesh
     Narang [2021] 1 SCR 389 : (2021) 15 SCC 338; Ram kishan v.
     Tarun Bajaj & Ors [2014] 1 SCR 538 : (2014) 16 SCC 204; All
     Bengal Excise Licensees Associationv. Raghabendra Singh and
     Others [2007] 3 SCR 816 : (2007) 11 SCC 374 – referred to.

                                List of Acts
     Karnataka Town and Country Planning Act, 1961; Karnataka Stamp
     Act, 1957; Contempt of Courts Act, 1971.

                             List of Keywords
     Suppressio Veri Suggestio Falsi; Lex non cogit ad impossibilia;
     Bonafide; Malafide; Government Orders; Contempt; Modification;
1290                                                     [2024] 12 S.C.R.

                        Supreme Court Reports


    Contempt; Compliance; Compensation; Financial Hardship; Wilful
    Disobedience; Disobedience of order; Alternate remedy; Action in
    disregard; Knowledge of consequence.

                          Case Arising From
    INHERENT APPELLATE JURISDICTION : Contempt Petition (Civil)
    No. 688 of 2021
    In
    Civil Appeal No. 3310 of 1997
    From the Judgment and Order dated 21.11.2014, 17.05.2022 and
    19.03.2024 of the Supreme Court of India
    With
    Contempt Petition (Civil) No. 578 of 2022 in Civil Appeal No. 3305
    of 1997, Contempt Petition (Civil) No. 716 of 2023 in Civil Appeal
    No. 3307 of 1997 with Interlocutory Application No. 39734 of 2023,
    Contempt Petition (Civil) No. 555 of 2024 In Civil Appeal No. 3310
    of 1997, Contempt Petition (Civil) No. 556 of 2024 in Civil Appeal
    No. 3309 of 1997, Contempt Petition (Civil) No. 585 of 2024 in
    Civil Appeal No. 3306 of 1997

                       Appearances for Parties
    C. Aryama Sundaram, Dhruv Mehta, Aditya Sondhi, Gopal
    Sankarnarayanan, Sr. Advs., T. Harish Kumar, Navneet Dugar,
    Subham Kothari, Bharathi Subramanian, Bharathi Subramaniayan,
    Keith Varghese, Prashant, Anoop Krishna, Ms. Nayana Tara Bg,
    Rajat Sehgal, Mrs. Vandana Anand, Ms. Bina Madhavan, S. Udaya
    Kumar Sagar, P. Balaji Verma, Tushar Singh, Katubadi Ismail (for
    M/s. Lawyer S Knit & Co.), Mrs. Kanchan Kaur Dhodi, Mrs. Lalita
    Kaushik, Abhay Kumar, Manu Nair, Neelabh Shreesh, Aryan Roy,
    S. S. Shroff, Advs. for the Petitioners.
    Shashi Kiran Shetty, AG, Nishanth Patil, A.A.G., Dama Seshadri
    Naidu, Sr. Advs., V. N. Raghupathy, Adithya Bhat, Ms. Adoorya
    Bomakka Harish, Ayush P. Shah, Vignesh Adithiya S, Pai Amit,
    Kushal Dube, Ms. Pankhuri Bhardwaj, Tathagata Dutta, Abhiyudaya
    Vats, Nikhil Pahwa, Ssahel Sood, Abhinav Thakur, Mayank Jain,
    Ms. Uditha Chakravarthy, Tarun, Ankur S. Kulkarni, Pramod Dayal,
    Advs. for the Respondent.
[2024] 12 S.C.R.                                                                        1291

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


                   Judgment / Order of the Supreme Court

                                       Judgment

     Aravind Kumar, J.

1.   Alleging wilful disobedience of the Orders dated 21.11.2014,
     17.05.2022 and 19.03.2024 passed by this Court, these contempt
     petitions have been filed for punishing the respondents for their
     alleged contumacious act.
     1.1 For purposes of convenience the contempt petitions which
         have been filed with details appended thereto are tabulated
         herein below:
      Serial   CONTEMPT     COMPLAINANT/S        RESPONDENT/S ORDER ALLEGED TO
      No.      PETITION No.                                   HAVE BEEN FILED
      1        CP. No. 688   Chaduranga          Shri P. Ravi     Order dt. 21.11.2014
               of 2021 in    Kanthraj Urs and    Kumar and Ors.   passed in I.A. No. 13 of
               C.A. NO. 3309 Anr.                                 2011 in C.A. No. 3303 of
               -3310 /1997                                        1997.
      2        CP. No.         Chamundi Hotel    Smt. Vandita    Order dt. 21.11.2014
               578/2022 in     Private Limited   Sharma and Ors. passed in I.A. No. 13 of
               C.A. No. 3305                                     2011 in C.A. No. 3303 of
               of 1997                                           1997.

                                                                  ii. Order dt. 17.05.2022 in
                                                                  I.A. No. 98276 of 2021 in
                                                                  C.A. No. 3303 of 1997.

                                                                  iii. Order dt. 19.03.2024 in
                                                                  CP No. 578 of 2022.
      3        CP. No. 716 of M.L Varchusvin     Smt Vandita     i. Order dt. 21.11.2014
               2023 in C.A.   S.S. Raje Urs.     Sharma and Ors. passed in I.A. No. 13 of
               No. 3307 of                                       2011 in C.A. No. 3303 of
               1997                                              2011 in C.A. No. 3303 of
                                                                 1997.

                                                                  ii. Order dt. 17.05.2022 in
                                                                  I.A. No. 98276 of 2021 in
                                                                  C.A. No. 3303 of 1997.
      4        CP. No. 555 of Chaduranga         Dr. Rajneesh     i.Order dt. 17.05.2022 in
               2024 in C.A.   Kanthraj Urs and   Goel and Ors.    I.A. No. 98276 of 2021 in
               No. 3310 of    Anr.                                C.A. No. 3303 of 1997.
               1997 and C.P.
                                                                  ii. Order dt. 19.03.2024 in
               688 of 2021
                                                                  CP No. 578 of 2022.
1292                                                                  [2024] 12 S.C.R.

                             Supreme Court Reports



        5     CP. No. 556 of Smt. Indrakshi Devi Rajneesh Goel   i.Order dt. 21.11.2014
              2024 in C.A.                       and Ors.        passed in I.A. No. 13 of
              No. 3309 of                                        2011 in C.A. No. 3303 of
              1997                                               1997.

                                                                 ii. Order dt. 17.05.2022 in
                                                                 I.A. No. 98276 of 2021 in
                                                                 C.A. No. 3303 of 1997.
        6     C.P No. 585 of Kamakshi Devi      Rajneesh Goel    i.Order dt. 21.11.2014
              2024 in C.A.   Avaru              and ors.         passed in I.A. No. 13 of
              No. 3306 of                                        2011 in C.A. No. 3303 of
              1997                                               1997.

                                                                 ii.Order dt. 17.05.2022 in
                                                                 I.A. No. 98276 of 2021 in
                                                                 C.A. No. 3303 of 1997.


            The aforestated analogous petitions are taken up together
            and disposed of by this Common Order as they involve facts
            in common.
    1.2 The petitioners in the aforestated contempt petitions have
        contended that the order dated 21.11.2014 and 17.05.2022,
        including the order dated 19.03.2024 is clear and explicit
        whereunder the respondent authorities have been directed
        by this Court to issue TDR as per TDR Rules in favour of the
        respective land owners whose land has been acquired for
        widening of Bellary and Jayamahal Roads and yet respondents
        have failed to do so and thereby they have wilfully disobeyed the
        directions and orders passed by this Court. It is also contended
        that though Bengaluru Development Authority (for short BDA)
        and Bengaluru Bruhat Mahanagara Palike (for short BBMP)
        on the one hand were taking steps to issue TDR by calling for
        information from the petitioners, on the other hand Government
        of Karnataka passed an Order on 23.02.2021 expressing its
        difficulty to implement the orders of this Court on the ground
        of financial hardship being caused to exchequer which itself
        is clear wilful disobedience. It is also contended that State
        has taken the benefit flowing from the order dated 21.11.2014
        and utilized the land owned by petitioners to widen the roads
        and has issued the Government Order dated 08.12.2022
        after dismissal of the IA for modification on 17.05.2022, which
        amounts to over reaching the orders of this Court. It is also
        contended that the positive direction issued by this Court to
[2024] 12 S.C.R.                                                        1293

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


          the respondents to issue TDR as per TDR rules in favour of
          complainants had not been complied which not only undermine
          the dignity of this Court but also the authority of this Court. It is
          further contended that market value determined for the subject
          land for issuing TDR by no stretch of imagination can be the
          market value prescribed under the provisions of Karnataka Town
          and Country Planning Act, 1961 and the Karnataka Town and
          Country Planning (Benefit of Development Rights) Rules, 2016.
          It is also submitted that contemnors in the IA No.98276 of 2021
          had filed for modification of the order dated 21.11.2014 wherein
          they have clearly admitted that in the event of TDR is to be
          issued to the extent of 15 acres 39 guntas as per the orders of
          this Court which is the extent of land acquired by the BBMP for
          widening of the roads, it would result in issuance of TDR valued
          at Rs.1,396 crores as per TDR rules and yet determined the
          value under the notices dated 10.06.2024 diametrically opposite
          to the stand already taken by them. Hence, contending that
          respondents are acting in violation of the orders of this Court
          wilfully and as such they are liable to be proceeded with and
          punished for wilful disobedience of the order dated 21.11.2014,
          17.05.2022 and 19.03.2024.
     1.3 On being notified contesting respondents have filed affidavits
         of compliance in the respective petitions. Shri Jairam N.,
         Commissioner, BDA has stated that BBMP had proposed to
         grant Development Rights Certificate (DRC/TDR) in lieu of
         utilisation of Bengaluru Palace ground for “widening of Bellary
         road from BDA junction to Mekhri Circle” and in this regard
         the BBMP has issued the provisional acceptance order dated
         07.06.2024 and in response to the recommendations by the
         BBMP, the BDA has approved the issuance of DRC/TDR on
         10.06.2024 whereunder the details of the DRC has been
         enumerated. It is further contended that same is in compliance
         with the order dated 21.11.2014, 17.05.2022 and 19.03.2024. It
         is further stated that as per the recommendations of the BBMP,
         the petitioners have been served notice dated 10.06.2024 by
         BDA calling upon them to hand over the physical possession
         of the lands to the officials of BBMP, apart from informing them
         to hand over personal bonds simultaneously, to enable them to
         collect DRC. It is also stated that as indicated in the notice the
1294                                                  [2024] 12 S.C.R.

                       Supreme Court Reports


         officials of BBMP and BDA were present at Bengaluru Palace
         grounds on the appointed date and time to take possession
         of the lands, but petitioners had failed to appear and as such
         a joint mazar was drawn on 18.06.2024 by noting physical
         possession of the land was not taken and personal bonds was
         not furnished by the petitioners.
    1.4 It is further stated that one more opportunity was extended to
        the petitioners to collect the approved DRC and a notice dated
        26.06.2024 was issued in this regard and again the petitioners
        had failed to appear on the appointed place and time for handing
        over possession of the land. It is stated that possession of the
        subject land was taken on 01.07.2024 and respective authorities
        though were ready to handover DRC to the petitioners, they
        failed to appear and receive the same. Hence, it is contended
        that at no point of time the said respondent had any intention
        to wilfully disobey the orders of this Court and have tendered
        unconditional apology for the delay that has occasioned in
        implementing the orders of this Court. Contending that delay was
        neither deliberate or intentional they have prayed for dismissal
        of the contempt petitions.
    1.5 Mr. Tushar Giri Nath, Chief Commissioner, BBMP has filed an
        affidavit of compliance dated 17.03.2024 stating thereunder that
        in compliance of the order dated 21.11.2014 and 17.05.2022,
        the Government of Karnataka through decision of Cabinet
        decided on 14.03.2024 to utilise 15 acres 39 guntas namely
        the subject land for road widening and also decided to issue
        the TDR as per the Karnataka Town and Country Planning
        Act, 1961 and the TDR Rules and in furtherance of the same
        Government Order dated 15.03.2024 came to be issued. It is
        further stated that as per the said Government Order the BBMP
        would implement the orders of this Court by issuance of TDR/
        DRC as per rules. It is further stated that out of 15 acres 39
        guntas only an extent of 1,217.41 sq. meter has been actually
        utilised for the road widening purposes and the entire land
        would be utilised after issuance of DRC/TDR as per rules. It is
        further stated that at no point of time the respondent had any
        intention to wilfully disobey the orders of this Court and have
        tendered unconditional apology for the delay in implementing
        the orders of this Court.
[2024] 12 S.C.R.                                                   1295

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     1.6 Sri Jairam N., Commissioner, BDA had initially filed counter
         affidavit on 18.03.2024 in contempt petition No. 688 of
         2021 contending thereunder that on the basis of the orders
         dated 21.11.2014 and 17.05.2022 passed by this Court, the
         Government of Karnataka had taken a decision on 14.03.2024 to
         utilise 15 acres 39 guntas namely subject land for road widening
         subject to grant of DRC/TDR and as such Government Order
         dated 15.03.2024 came to be issued. It is further submitted
         that BDA is the planning authority as per the KTP Act and said
         authority would issue Development Rights Certificate-DRC after
         receiving recommendation by the public authority. It is further
         stated that at no point of time the contemnor had any intention
         to wilfully disobey the orders passed by this Court.
     1.7 The Chief Commissioner of BBMP has filed further affidavit
         on 28.07.2024 in contempt petition No. 555-556 of 2024
         narrating the sequential events culminating in the orders
         dated 21.11.2014 and 17.05.2022 apart from narrating the
         purported details about issuance of DRC/ TDR to the claimants.
         The sum and substance of the narration is pursuant to the
         orders passed by this Court, notices had been issued to the
         petitioners and except Smt. Deepamalini Devi none of the
         petitioners had turned up to hand over physical possession of
         15 acres 17.5 guntas of land, as a result thereof another notice
         dated 26.06.2024 came to be issued and on the appointed
         date 01.07.2024 none had appeared and after identifying the
         subject land i.e. 15 acres 17.5 guntas by metes and bonds
         by the survey wing of the revenue department possession of
         subject land was taken by BBMP on 01.07.2024. In paragraph
         5 of the said affidavit the sequential events leading to the
         issuance of DRC/TDR has been narrated and the summary
         of the same is to the effect that the BDA was the authority to
         issue/deal with Form No.3 and thereupon DRC/TDR and after
         the amendment to the KTCP Act in 2021 the BBMP public
         authority became the authority to issue/deal with form No.1
         and 3 and after the amendment the matter stood transferred
         to BBMP from BDA for further action as per the notification
         dated 23.09.2022 and accordingly notice came to be issued
         to the claimants on 21.03.2024. It is also stated that there
         were exchange of correspondence between the BDA and
         the claimants whereunder it is clearly admitted that 15 acres
1296                                                     [2024] 12 S.C.R.

                       Supreme Court Reports


         17.05 guntas is the land utilised/to be utilised for road widening
         purposes based on the survey settlement dated 22.04.2024. It
         is further stated that the Deputy Commissioner (TDR) BBMP
         vide order dated 22.04.2024 after considering all the claims
         and objections determined and finalised the extent of land
         of various claimants. It is further stated that on the basis of
         the request of BBMP the Government passed an order dated
         24.05.2024 permitting BBMP to utilise the land ad measuring
         15 acres 17.5 guntas for road widening and determined the
         value of the land at Rs. 11 crores for the entire land covered
         under the acquisition namely under BPAT and determined the
         compensation of subject land in proportion to the same value for
         issuance of DRC/TDR to be issued to the claimants. The Deputy
         Commissioner (TDR) after considering the objections raised
         to the order dated 24.05.2024 while rejecting the objections of
         the claimants/petitioners by order dated 06.06.2024 held the
         “market value” of the subject land cannot be beyond 2 lakhs
         and as such applied the said value for issuance of TDR. In
         other words, factor taken into consideration for determining
         the market value of the subject land is on the premise that
         land had stood vested with the State Government under the
         BPAT whereunder the total value of the entire land has been
         computed at Rs.11 crores namely for 472 acres 16 guntas and
         proportionate value is to be considered for the subject land
         which is the part of the larger extent and as such justifying
         the order dated 06.06.2024, the notices were issued to the
         petitioners/claimants to accept the DRC/TDR as per value
         determined thereunder and contending orders of this Court
         had been complied they have sought for contempt proceedings
         being dropped or petitions being dismissed.
    1.8 The complainant/petitioner in contempt petition No.716 of 2023
        has filed a rejoinder/affidavit dated 08.07.2024 reiterating the
        contentions raised in the contempt petitions and also contending
        the development that have taken place pursuant to the order
        dated 19.03.2024 and has highlighted the issue regarding
        reduction of the extent of land and determination of the market
        value at Rs. 120.68 per sq. meter as against the guidance
        value of Rs. 2,83,500 (for Bellary Road) and 2,04,000 (for
        Jay Mahal Road) per sq. metre as fixed under Section 45-B
        of The Karnataka Stamp Act, 1957. It is also contended that
[2024] 12 S.C.R.                                                     1297

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


          DRC/TDR which was forwarded through post and handed over
          to the minor daughter of the first petitioner would not absolve
          the liability of the respondents contemnors to comply with the
          orders of this Court in substance.
     1.9 The petitioner in contempt petition No.578 of 2022 has also
         filed a rejoinder affidavit in response to counter affidavit filed
         by respondent no.3 whereunder it has been contended that at
         all relevant point of time and in various forum the ownership
         rights over the subject land has been declared to be that of
         the petitioner and as such there is no dispute with regard to
         the ownership of the land and none of the legal heirs of Late
         Shri SDN Wadiyar could object to it either. Contending that the
         official respondents have failed to comply with the order dated
         21.11.2014 the petitioner have sought for appropriate action
         being taken against the respondents.

          DISCUSSION AND REASONING:
          Heard the arguments of the Learned Senior Advocates assisted
          by the Learned Advocates for appearing parties, perused
          the entire case papers and having bestowed our careful
          consideration to the rival contentions raised at the bar, we are
          of the view that following point would arise for our consideration
                “Whether orders dated 21.11.2014, 17.05.2022 and
                19.03.2024 passed by this Court has been wilfully
                disobeyed by the respondents/contemnors?”

          PREFACE:
     1.10 In order to punish a contemnor, it has to be established that
          disobedience of the order is ‘wilful’. It means knowingly-
          intentional, conscious, calculated and deliberate with full
          knowledge of consequences flowing therefrom. It would exclude
          casual, accidental, bonafide or unintentional acts or genuine
          inability and would also not include involuntary or negligent
          actions. The deliberate conduct of a person means that he
          knows what he is doing and intends to do the same. It is too
          well settled that if two interpretations are possible, and if the
          action is not contumacious, a contempt proceeding would not
          be maintainable.
1298                                                       [2024] 12 S.C.R.

                                 Supreme Court Reports


      1.11 The weapon of contempt will not be used for execution of the
           decree or implementation of an order for which alternative
           remedy in law is provided for. The paramount consideration is
           given to maintain court’s dignity and majesty of law. In Sudhir
           Vasudeva Vs. George Ravishekeran1 this Court has observed
           that a Court exercising jurisdiction under the Contempt of Courts
           Act, 1971 must not travel beyond the four corners of the orders
           in relation to which contempt has been alleged. That the Court
           hearing a contempt petition ought to restrict the scope of its
           enquiry to such directions which are explicit in the judgment or
           orders of which contempt has been alleged.
      1.12 The civil contempt would mean a wilful disobedience of a
           decision of this Court. What would be relevant is the “wilful
           disobedience”. Hence, knowledge of having acted in disregard
           to an order is sine qua non for being proceeded with if there is
           a deliberate, conscience and intentional act then the jurisdiction
           can be clutched.
      1.13 Having adumbrated position of law enumerated by this Court
           we proceed to deal with the alleged acts of contempt said to
           have been committed by the contemnors in the instant petitions.

      FACTUAL BACKGROUND:
2.    The background in which the orders dated 21.11.2014 and 17.05.2022
      came to be passed can be succinctly narrated as under:
      Undisputedly the land measuring 15 acres and 39 guntas (hereinafter
      referred to as ‘subject land’) and the adjoining properties collectively
      measuring 456 acres belonged to the erstwhile Maharaja of Mysore.
      The legal heirs of deceased Maharaja of Mysore amongst others
      and/or claiming through them are before this Court alleging wilful
      disobedience of the aforestated orders.
3.    The State enacted the Bangalore Palace (Acquisition and Transfer)
      Act 1996 (herein after referred to as “BPAT” Act) to acquire the
      Bangalore Palace and adjacent land including all the buildings around
      on the grounds enumerated therein. The constitutional validity of the



1    [2014) 4 SCR 27 : (2014) 3 SCC 373
[2024] 12 S.C.R.                                                         1299

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     same was unsuccessfully challenged by the legal heirs of Maharaja
     of Mysore before the High Court of Karnataka and an ad interim
     order of Stay of the operation of the Act came to be passed by the
     High Court on 10.12.1996. On conclusion of hearing writ petitions
     came to be dismissed vide Order dated 31.03.1997 and four weeks’
     time was granted to the writ petitioners to file an appeal before
     this Court and interim order granted on 10.12.1996 which was in
     operation till disposal of the writ petitions came to be continued till
     then. Subsequently, appeals came to be filed, and this Court by Order
     dated 22.04.1997 granted stay of dispossession and the Special
     Leave Petitions came to be admitted on 30.04.1997 and order of
     status quo came to be passed pending disposal of the appeals. The
     said appeals are pending before this Court.
4.   In Civil Appeal No. 3303 of 1997, an interlocutory application came
     to be filed by the State of Karnataka seeking permission of this Court
     to widen the Bellary Road and Jayamahal Road and to complete the
     same by utilising 15 acres and 39 guntas of the Bengaluru Palace
     ground; and, to pay compensation to the above land as per the
     calculation made in the original award. Appellants in various appeals
     virtually conceded to the needs of the State to widen the road and
     expressed their willingness to accept the proposal of BBMP made in
     its letter dated 26.12.2009, whereunder BBMP had agreed to issue
     TDR for the extent of land acquired as per the Karnataka Town and
     Country Planning Act and the TDR guidelines, subject to final decision
     of this Court. Having regard to the fact that the State did not grant
     its approval to the proposal mooted by the BBMP and had instead
     offered to pay compensation as per the rates relevant at the time
     of passing of the order, this Court disposed of the said application
     by order dated 21.11.2014 and permitted the road widening subject
     to the condition that the appellants would be given the TDR as per
     TDR Rules. Order dated 21.11.2014 reads:
          “10. In the above circumstances, having considered the
          submissions of learned counsel for the parties, including
          learned counsel for the parties in all the connected appeals,
          without prejudice to the rights of the parties, and keeping
          in mind the necessity of widening of the road, and the
          public interest, we think it just and proper to allow I.A.
          No. 13 of 2011 subject to condition that the appellants in
1300                                                            [2024] 12 S.C.R.

                                 Supreme Court Reports


             the present appeal and the connected appeals shall be
             given TDR for widening of the road as per TDR Rules.”
                                               (Emphasis Supplied by us)

5.    The respondent-authorities were required to implicitly implement the
      aforesaid order or in other words issue TDR as per the extant TDR
      rules. This Court in Rita Markanday v/s Surjit Singh Arora2 has
      taken the view that even if the parties have not filed an undertaking
      before the Court, but if the Court is induced to sanction a particular
      course of action or inaction on the basis of the representation of
      such a party and the Court ultimately finds that the party never
      intended to act on such representation or such representation was
      false then the party would be guilty of committing contempt of court.
      In fact, this Court having heard the parties on merits and taking into
      consideration the totality of circumstances into consideration had
      passed a positive direction to the respondents to issue TDR a per
      TDR Rules. However, under the guise of the said order requires
      to be modified, a valiant attempt was made by the State after
      Seven (7) years by filing an interlocutory application on 12.08.2021
      in IA No.98276 of 2021 seeking modification of the order dated
      21.11.2014 wherein it was specifically prayed that the order dated
      21.11.2014 may be clarified or modified, with a further prayer to
      direct the instrumentalities of the State to pay compensation as
      per the calculation made in the original award in the Act of 1996
      in similar terms of the order of this Court dated 15.02.1999 passed
      in IA No.2.
      5.1 Aforesaid application came to be rejected after adjudication
          vide order dated 17.05.2022 whereunder this Court reiterated
          its earlier order dated 21.11.2014 and observed there was no
          reason to modify the said order. The Order dated 17.05.2022
          reads:
                     “We have noticed from the order dated 21.11.2014
                     that this court has allowed the I.A. No. 13 of 2011
                     filed by the applicant subject to the condition that the
                     appellants will be given TDR for widening of the road
                     as per the TDR Rules. We do not see any reason to


2    [1996] Supp. 7 SCR 56 : (1996) 6 SCC 14
[2024] 12 S.C.R.                                                         1301

      Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


                   modify the said order. It is for the applicant(s) to
                   take action in terms of the order dated 21.11.2014.
                   The I.A. No. 98276 of 2021 stands rejected.”
                                            (emphasis supplied by us)

     5.2 This Court in Rama Narang Vs. Ramesh Narang,3 has held
         that contempt jurisdiction could be invoked in every case where
         the conduct of a contemnor is such as would interfere with the
         due course of justice.
     5.3 This Court exercising contempt jurisdiction would not enter
         into question which have not been dealt with and decided in
         the judgment or order, violation of which is complained by the
         applicant. This Court will consider whether the direction issued
         in the judgment or order is complied in true sense or in its letter
         and spirit and would not embark upon the journey of examining
         as to what the judgment or order should have contained.
         The primary concern would be as to whether there has been
         deliberate default or if there is any ambiguity in the directions
         issued therein, in which event it would be better to direct the
         parties to approach the court which disposed of the matter for
         clarification instead of clutching the contempt jurisdiction. A
         plain reading of the orders dated 21.11.2014 and 17.05.2022
         supra would indicate that direction issued to the respondents
         is to the effect that TDR had to be issued as per TDR rules.
         There was no ambiguity or vagueness in the said orders. It is
         also not the case of the contemnors that any doubt being there
         in the said orders.
     5.4 However, on the basis of an assumed doubt having arisen in
         the mind of the State that too after seven years of the passing
         of the order (dated 21.11.2014) and to stave off the impending
         contempt proceedings, an Interlocutory Application I.A. No.
         98276 of 2021 referred to supra came to be filed for modification
         of the said order dated 21.11.2014 primarily on the ground of
         financial hardship amongst other grounds, which came to be
         rejected.



3   [2021] 1 SCR 389 : (2021) 15 SCC 338
1302                                                      [2024] 12 S.C.R.

                        Supreme Court Reports


     5.5 It is apt and appropriate to note at this juncture itself that a
         specific plea came to be raised by the State in paragraph 9 of
         the aforesaid application, that if the TDR certificate is issued
         as per the order dated 21.11.2014 to the extent of 15 acres 39
         guntas the notional value of the same would be Rs.1,396 crores.
         At the cost of burdening this order the relevant plea raised by
         the respondent in that regard is extracted herein below:
               “9. The Respondents/Applicant-State of Karnataka
               respectfully submits that area of land sought to be
               acquired vide I.A. No. 13/2011 is an extent of 15 acres
               39 guntas. If the compensation was required to be paid
               in terms of the Award passed under the Act of 1996 for
               the extent of 15 acres 39 guntas, the compensation
               payable would be Rs.37,28,813. However, if the TDR
               certificate is to be issued for the said extent of
               15 acres 39 guntas, it would result in 13,91,742
               Sq. ft. additional built up area constructible in the
               city of Bengaluru and approximately it would be
               equivalent to notional value of Rs.1,396 crores.
               It is also relevant to note that TDR once granted is
               transferable. If the appellants were to be given TDR,
               the same may immediately be transferred by the
               appellants to any other parties/ builders. In event of
               the final judgment going against the appellants, then
               it would not be possible to recover the value of TDR
               from the appellants.”
                                         (Emphasis Supplied by us)

6.   On passing of the aforesaid order dated 17.05.2022 it was incumbent
     upon the respondents-authorities to implement the aforesaid two
     orders without a demur as they are crystal clear. However, same
     was conveniently ignored or in other words the authorities seem to
     have gone into deep sleep at least till 05.04.2017 on which date a
     notification came to be issued by BBMP for carrying out the work
     of widening the road.
7.   One another factor which cannot go unnoticed in the background of
     affidavits filed by both the parties is, that in respect of the subject
     property, Writ Petitions in Public Interest had also been filed seeking
[2024] 12 S.C.R.                                                     1303

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     widening of Bellary Road and Jayamahal Road before the High
     Court of Karnataka wherein several orders came to be passed by
     referring to the orders passed by this Court referred to supra, of
     which contempt is alleged. Hence, we deem it proper to refer to the
     order dated 07.09.2016 passed in W.P. No. 42927 of 2015 which
     would have direct bearing on the present proceedings and it reads:
          “We, therefore, direct the State Government to grant
          necessary clearance to the BBMP for widening the road
          and issue TDR certificates to the land owners in terms
          of the Order of the Supreme Court of India as per the
          existing TDR rules.
          We trust and hope that the widening of the road will be
          completed within a year.”
                                          (Emphasis supplied by us)

8.   For complying the aforesaid direction an attempt was made to issue
     notification dated 05.04.2017 namely to carry out the widening of
     Jayamahal Road from Mekhri Circle up to Cantonment Railway Station
     and Bellary Road from BDA Junction to Mekhri Circle. After two (2)
     years i.e., on 17.07.2019, the State Government issued a Government
     Order permitting BBMP to issue TDR to the concerned land owners.
     Hence, a communication dated 29.08.2019 was addressed by the
     complainants to the Commissioner BBMP seeking to expedite the
     process of issuance of TDR and documents in support of their claim
     were also forwarded. However, TDR’s were not issued for no reason
     at all. Thus, from 21.11.2014 till 17.07.2019 there was absolute
     silence on the part of contemnors and there is not even a whisper
     in the affidavits filed by the respondents in this regard viz., as to
     the reason for non-implementation of the Order dated 21.11.2014.
     Knowing fully, the consequences of non-implementing the orders of
     this Court, yet respondents consciously ignored to comply with the
     directions issued by this Court. After four (4) years notification came
     to be issued on 05.04.2017 to widen the road. Again, respondents
     went into deep slumber for two (2) years i.e., till 17.07.2019 date
     of government order issued resolving to issue TDR in favour of
     landowners. Silence on the part of the contemnors from 05.04.2017
     to 17.07.2019 has to be termed as deliberate with full knowledge
     of consequences flowing therefrom. Thus, delay of five (5) years in
1304                                                        [2024] 12 S.C.R.

                                 Supreme Court Reports


      implementation of the Order dated 21.11.2014 till 17.07.2019 not only
      remains unexplained but also prima-facie seems to be intentional
      and not bonafide or there being any genuine inability and this is
      the first stage of intentional delay. This Court in Ram kishan Vs.
      Tarun Bajaj & Ors4 has opined that deliberate conduct of a person
      means that he knows what he is doing and intends to do the same.
      Therefore, there has to be a calculated action with evil motive on
      his part. Though Government Order dated 17.07.2019 came to be
      issued, that too after five (5) years after passing of orders (direction)
      by this Court to issue TDR’s, yet it did not fructify. Thus, irresistible
      conclusion will have to be drawn that non-implementation of the
      orders of this Court was deliberate and intentional act on the part
      of contemnors.
9.    From the pleadings of these proceedings it would also emerge, yet
      another Writ Petition No. 6585 of 2020 (PIL) had also been filed
      for expediting the process for road widening and an order came to
      be passed by the High Court of Karnataka on 07.01.2021 in that
      regard whereunder the State Government was directed to report
      the compliance by implementing with the directions contained in
      paragraph 10 of this Court’s Order dated 21.11.2014 and paragraph
      12 of High Court Order dated 07.09.2016 passed in Writ Petition
      No. 42927 of 2015 and for reporting such compliance, the State
      Government was granted time till 15.02.2021. State Government was
      also called upon to produce records and documents depicting grant
      of TDR certificates in terms of the order of this Court as well as the
      order of the High Court. However, the State Government instead of
      complying with the Orders passed by this Court and the High Court
      and initially having made a show of its earnestness to comply with
      the order, had submitted before the High Court in Writ Petition No.
      6585 of 2020 on 17.02.2021 through the learned Advocate General
      that it would move this Court seeking modification of the Order
      dated 21.11.2014. Thus, Government Order came to be issued
      on 23.02.2021 wherein it has been stated that State Cabinet had
      decided to resile from its earlier decisions taken on 11.07.2019 vide
      Subject No. C435/2019 (pursuant to which the State Government
      had issued Government Order dated 17.07.2019 bearing No. MA.AA.
      EE.-MNY/2018 permitting issuance of TDR) and had resolved to file


4    [2014] 1 SCR 538 : 2014 (16) SCC 204 para 12
[2024] 12 S.C.R.                                                     1305

      Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     an application for modification of the Order dated 21.11.2014 and
     pursuant to the decision so taken, I.A. No. 98276 of 2021 came to be
     filed in C.A. No. 3303 of 1997 and connected appeals by the State of
     Karnataka on 12.08.2021 as already noted hereinabove. The present
     contempt petitions came to be filed on 17.08.2021 and this Court
     by Order dated 03.01.2022 directed the listing of these contempt
     petitions along with I.A. No. 98276 of 2021 filed for modification of
     the order dated 21.11.2014. Said application came to be heard and
     disposed of by this Court by Order dated 17.05.2022 by rejecting
     the same as already noticed herein above. Atleast then orders
     dated 21.11.2014 and 17.05.2022 ought to have been implemented.
     However, the Respondents seem to have dragged their feet and
     for no justifiable reason whatsoever have not implemented the said
     orders. Thus, explicitly there has been wilful disobedience of orders
     of this Court and respondents having failed in their attempt to seek
     modification of order dated 21.11.2014 cannot take umbrage under
     any circumstances whatsoever for not implementing the orders of
     this Court, particularly when clarification/modification prayer was put
     to rest on 17.05.2022 by this Court.
10. The wilful disobedience of the orders of this Court, at this stage is
    manifest and for no reason whatsoever it can be construed that
    respondents were under any doubt or there was lack of clarity in
    the orders of this Court. Infact the order dated 21.11.2014 is clear
    and explicit. However, under the guise of implementation of said
    order would result in grant of TDR to the extent of Rs. 1396 crores
    (the value of which is in serious dispute) modification was sought
    and said attempt made after Seven (7) years had also failed. This
    Court in the matter of All Bengal Excise Licensees Association v/s
    Raghabendra Singh and Others5 has taken a view that disobedience
    in a particular case would be continued as wilful based on facts
    and circumstances unfolded in a given case. Judicial orders are
    to be properly understood and complied with, even negligence
    and carelessness can amount to disobedience particularly when
    the attention of the person is drawn to the Court’s order and its
    implications. In the instant case respondents being aware of the
    consequences of non-implementation of the order of this Court dated
    21.11.2014 had sought for modification on the ground of financial


5   [2007] 3 SCR 816 : (2007) 11 SCC 374
1306                                                        [2024] 12 S.C.R.

                          Supreme Court Reports


     hardship and had also failed. Hence, they are estopped from feigning
     ignorance for not implementing the orders of this Court or not being
     aware of the consequences of its implementations.
11. In the Writ Petition No. 6585 of 2020 aforestated which was pending
    before the High Court of Karnataka, the State Government dragged
    its feet by taking adjournment after adjournment on one pretext or
    the other and had projected a picture of its earnestness to implement
    the orders of this Court, though parallelly it had resiled from its earlier
    order dated 17.07.2019 by issuance of Government Order dated
    23.02.2021 and later filed I.A. No. 98276 of 2021 on 12.08.2021 for
    modification of Order dated 21.11.2014 which ended in its dismissal
    also on 17.05.2022. It would be apposite to note that by Government
    Order No. UDD 269 MNY 2018 dated 08.12.2022 it was resolved to
    drop the proposal for widening of the roads itself and as such BBMP
    withdrew the proposal made to the State Government on 30.03.2009
    in this regard which came to be accepted by Government Order
    dated 08.12.2022. Strangely and curiously it may be noted that the
    BBMP took a contrary stand before the High Court in the pending
    Writ Petition No.6585 of 2020 by filing affidavits which reflected
    about the progress of the steps taken by BBMP to widen the road
    or in other words, State and its authorities or instrumentalities were
    blowing hot and cold. On the one hand State was depicting a picture
    before the High Court of implementing the Orders of this Court and
    simultaneously State and its authorities were filing application for
    modification of the order passed in 2014 and parallelly assuring the
    High Court that it was keen on implementing the orders of this Court,
    though it was postponing the implementation and dragging its feet
    on one pretext or the other and eventually shelved the proposal to
    widen the road, though substantial progress had been made to widen
    the road for which purpose possession of land had also been taken.
12. Turning our attention to the core issue on hand namely as to whether
    there has been compliance of the Order dated 21.11.2014 and
    17.05.2022 by the respondents, we will have to answer it in the
    negative and also further hold that there has been wilful disobedience,
    for the reasons assigned hereinbelow:
           “(i). In compliance of the Order dated 21.11.2014 a
           communication came to be issued by the Special Deputy
           Commissioner Land Acquisition and TDR BBMP requesting
           the applicants to provide an indemnity bond following which
[2024] 12 S.C.R.                                                        1307

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


          the relinquishment deed would be executed and registered
          and thereafter TDR would be issued, yet same was not
          issued though land owners complied with the demand
          made by BBMP;
          (ii). The State Government though passed a Government
          Order No. ma.aa.ee./269/MNY/2018 dated 17.07.2019
          permitting issuance of TDR yet, same was not issued;
          (iii). Though a communication was addressed by the State
          Government to the Commissioner BBMP on 29.08.2019
          to expedite the process of issuance of TDR yet, TDR was
          not issued;”
13. The above sequential events would clearly reflect that the State
    Government was projecting before this Court of its bona fides to
    implement the Orders of this Court and having failed in its attempt
    to seek modification of the Order dated 21.11.2014 on account of
    application for modification having been dismissed on 17.05.2022, yet
    during the interregnum arrived at a conclusion that the implementation
    of the Order of this Court would be neigh impossible and vide
    Government Order No. UDD269MNY2018 (Part-4) dated 23.02.2021
    which was pursuant to the Cabinet decision taken on 18.02.2021 vide
    subject No.C.82/21 the State had dropped the proposal to widen the
    road and thereby had failed to comply with the orders of this Court.
14. On present contempt petitions being filed in 2022 an attempt has
    been made by the authorities to project a picture as though all efforts
    were made to implement the orders of the Court. Two stages in which
    there has been wilful disobedience of the orders of this Court are:

          FIRST STAGE
          i.    After the order was passed on 21.11.2014 no steps
                were taken to implement the said order in its letter
                and spirit which ought to have been at least till 2017
                i.e., issuance of notification dated 05.04.2017 for
                carrying out widening of roads;
          ii.   Though State Government issued order on 17.07.2019
                permitting BBMP to issue TDR to the concerned land
                owners, yet TDR was not issued despite all demands
                of BBMP were complied by land owners:
1308                                                         [2024] 12 S.C.R.

                          Supreme Court Reports


          iii.   From the date of order dated 21.11.2014 till an
                 application namely IA No. 798276 of 2021 was filed
                 for modification, the saga of pushing the file from
                 table to table and keeping the same idle for a long
                 period and conveniently ignoring the order of this
                 Court by not implementing the same in its true spirit
                 had continued for years or atleast till 17.07.2019;

          SECOND STAGE
          iv.    After the order dated 17.05.2022 came to be passed
                 rejecting the application for modification/ clarification
                 yet the State and its authorities did not take steps to
                 implement the orders of this Court as expected of a
                 prudent litigant i.e., by the State which should have
                 acted as a model litigant.
15. In fact, this Court by Order dated 19.03.2024 with the hope that
    respondents would purge in the contempt by implementing the
    same in its letter & spirit had directed compliance of the Order dated
    21.11.2014 and 17.05.2022. However, an additional condition was
    imposed or in other words orders dated 21.11.2014 and 17.05.2022
    was tweaked by this Court. The direction so issued by this Court on
    19.03.2024 reads:
          “2. After some hearing, it is clear that the State shall issue
          necessary TDR as directed by this Court on 21.11.2014
          and on 17.05.2022. Taking note of the submissions of the
          learned Advocate General, we direct compliance within a
          period of eight weeks from today.”
          “3. Order dated 2 1.11.2014 does not specifically enable
          sale or transfer of the TDR, but directs grant of TDR
          as per Rules. To secure interests of all parties pending
          disposal of the Civil Appeals, we direct the recipient of
          the TDR to undertake return of the consideration received
          upon any sale or transfer of the TDR in the event the
          Civil Appeal(s) before Supreme Court are dismissed.
          An affidavit of Undertaking to this effect in the nature of
          personal bond(s) shall be furnished by the recipient of the
          TDR to the State before the sale or transfer of the TDR.
[2024] 12 S.C.R.                                                   1309

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


          We have not expressed any opinion with regard to inter
          se dispute between the parties.”
16. A valiant attempt has been made by the contemnors to contend that
    orders of this Court has been complied by passing of the order dated
    15.03.2024 and issuance of consequential notices and Government
    Orders.
     In the notices issued on 10.06.2024 and 26.06.2024 the authorities
     seems to be projecting a picture that the possession of the subject
     land has not been delivered and this is nothing but suppressing the
     true facts and making a false statement before this Court namely
     suppressio veri suggestio falsi. We say so for the simple reason
     that in the notices referred to hereinabove the respondents are
     attempting to give a picture as though possession of the land in
     question has not been taken, whereas in the Government Order
     dated 08.12.2022, it has been specifically mentioned that a sum of
     Rs. 56 crores has been provided for widening of the Bellary Road
     and Jayamahal Road and a Government Order No. UDD 56 MNY
     2020 dated 04.03.2020 in the form of tender is handed over to M/s
     JMC Organization by issuance of a work order. The said Government
     order would also indicate that the road project is in progress. In
     fact, in the affidavit filed through Additional Chief Secretary Shri
     Rakesh Singh, it has been stated in paragraph 13 that the work is
     almost complete from Mekhri Circle to Jayamahal and because of
     the untimely rain, the completion got delayed.
17. In Writ Petition No.6585 of 2020, an affidavit dated 20.01.2023 came
    to be filed by BBMP through Smt. Priyadarshini, Executive Engineer,
    Road Infrastructure (East) BBMP, which came to be recorded by the
    High Court on 03.02.2023 by noticing that in paragraph 6 of the said
    affidavit, the deponent has made a statement that the road widening
    work is in progress. In fact, photographs were also appended to
    the said affidavit as document No.5. It was deposed in unequivocal
    terms that the road widening work has commenced and same
    came also to be recorded by the Division Bench of the High Court
    of Karnataka by observing that “it can safely be said that necessary
    steps are taken by BBMP for widening of roads and the work is in
    progress at present”. It was further observed by the High Court that
    the BBMP can certainly explore some effective means and ways to
    see that that road widening work is done in a speedy manner and is
1310                                                        [2024] 12 S.C.R.

                         Supreme Court Reports


     not delayed on account of lame excuses or lethargy on the part of
     some officer of the BBMP or the executing agencies. Hence, BBMP
     was directed to file further progress report. A further affidavit was
     also filed on 13.03.2023 which came to be recorded by the Division
     Bench of the High Court on 29.09.2023 whereunder it was noticed
     that in paragraph 3 of the said affidavit it had been stated that the
     95% of the road widening project is completed in all respects and now
     there is free flow of traffic on the stretch, particularly, with reference
     to the stretch on Bellary Road to Kaveri theatre junction. The status
     report which was called upon to be filed by BBMP resulted in filing
     further affidavit of the Executive Engineer which again came to be
     recorded by the Division Bench of the High Court on 19.04.2023
     whereunder it was stated that in respect of different phases of the
     road widening, the project is complete to the extent of 25%, 95%,
     50% and 60% respectively.
     17.1 We are compelled to note or make references to the aforestated
          orders passed by the High Court of Karnataka, since the issue
          of road widening has been the core issue, and on the one hand
          the State is contending possession of the subject land was
          not taken or it was taken only in July 2024 and countered by
          the complainants that possession was taken long back. The
          pleadings above referred to would also leave no manner of
          doubt in the mind of this Court of possession of these lands
          having been taken either by the State or BBMP and same being
          in their possession since long, it is too late in the day for the
          State and its instrumentalities to contend that after the issuance
          of notices on 10.06.2024 and 26.06.2024 the possession of
          the subject land has been taken. It is for this reason we have
          held that the contemnors are guilty of supressing the truth and
          suggesting falsehood.
18. A theoretical implementation would not amount to compliance. The
    implementation of the order should be substantial and said order/s
    should clearly reflect the intention of the authorities of its bonafides,
    as otherwise it has to be necessarily held that the act of State and its
    officers are not bonafide but tainted or malafide. Lex non cogit ad
    impossibilia- Law does not compel a person to do the impossible
    (AIR 1996 SC 753) Unless an order is absolutely impossible to be
    executed or carried out, the authorities cannot be heard to contend
    that financial burden would be a hurdle to implement the orders of
[2024] 12 S.C.R.                                                     1311

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     this Court. If at all, there were any such hurdles, it was always open
     to authorities to approach this Court to seek appropriate orders
     and an attempt made in that regard had also failed. In the instant
     case, after having kept quiet for a period of almost 07 years i.e.,
     from 21.11.2014 till 12.08.2021 (till filing of IA No.98276 of 2021),
     no effective steps were taken by the State and its instrumentalities
     to implement the orders of this Court except exchange of inter-
     departmental correspondence which is already noticed herein above.
19. The affidavits of the Commissioner of BDA and Chief Commissioner
    of BBMP would reflect as though there is due compliance of the
    aforesaid two Orders passed by this Court and this is not only in clear
    violation of the Orders 21.11.2014 but also order dated 17.05.2022
    whereunder this Court in unequivocal terms or had categorically
    directed the respondents’ herein to issue TDR as per the TDR Rules
    and nothing short or long of it. In other words, the TDR which was
    required to be issued ought to have been as per the Karnataka Town
    and Country Planning (Benefit of Development Rights) Rules, 2016.
    This Court by order dated 19.03.2024 after hearing the matter for
    some time had passed the aforesaid order.
20. A perusal of the same would indicate that this Court in no uncertain
    terms and categorically has held that State should issue necessary
    TDR as directed by this Court on 21.11,2014 and 17.05.22. In fact,
    specific direction was issued that there should be compliance within
    eight (8) weeks. It was also ordered that the recipient of the TDR
    should undertake to return the consideration received upon sale or
    transfer of the TDR in the event of the civil appeals before this Court
    are dismissed and called upon the complainants to file an affidavit
    of undertaking to this effect in the nature of personal bond(s) to be
    furnished by the recipient of the TDR to the state before the sale or
    transfer of the TDR. We deem it appropriate to note at this juncture
    that order dated 19.03.2024 was passed for implementing the
    orders dated 21.11.2014 and 17.05.2022 and there was no occasion
    or necessity for this Court to impose further conditions which in
    effect would amount to tweaking the orders dated 21.11.2014 and
    17.05.2022. Infact there was no such prayer made by the State or
    its instrumentalities by filing appropriate applications. Attempt made
    in that regard by filing I.A. No. 98276 of 2021 had already been
    rejected by this Court by Order dated 17.05.2022 itself. Yet another
    reason which requires to be assigned for supporting such a view,
1312                                                      [2024] 12 S.C.R.

                       Supreme Court Reports


    emanates from the fact that State itself has admitted in the I.A. No.
    98276 of 2021 that if TDR is to be issued as per TDR Rules the
    market value will have to be determined as per TDR Rules, which
    in effect would mean value of the land has to be determined as per
    the value fixed under the Karnataka Stamp Act, 1957. Accordingly,
    the calculation had been made and pleaded financial hardship.
    Though, while applying the market value as fixed under the Stamp
    Act, 1957, 60% of the value has been deducted which we are not in
    agreement for reasons detailed herein below, yet, the fact remains
    that State itself has admitted and adopted the value fixed under
    Karnataka Stamp Act, 1957 to fix the value of TDR to be issued.
    We would hasten to add that Civil Appeals relating to challenge
    of acquisition of larger area (456 acres) is still pending before the
    court and sufficient safeguards to protect the interest of the State
    can be taken care of at the time of passing final order. Necessarily,
    the issuance of TDR as per TDR Rules would be subject to final
    outcome of Civil Appeals and as such filing of an undertaking by
    the recipients of TDR as opined by our Order dated 19.03.2024 is
    not warranted. Hence, we deem it proper to delete the additional
    condition imposed by this Court by order dated 19.03.2024 and
    making it explicitly clear that TDR issued by the competent authority
    would be subject to final orders that may be passed in Civil Appeals
    pending before larger bench and this order would have no bearing
    on the pending appeals.
    20.1   Though, initially there was resistance to the order dated
           21.11.2014 and 17.05.2022, the State and its machinery
           seems to have understood the gravity of the situation and to
           fall in line with the further directions issued by this Court, has
           made a feeble attempt on 19.03.2024 to demonstrate before
           this Court of having complied with the orders passed by this
           Court which is alleged to have been wilfully disobeyed by
           the contemnors. After having dragged their feet for the last
           10 years and having exhausted all remedies to stave off the
           orders dated 21.11.2024, 17.05.2022 and 19.03.2024, the
           respondent authorities or contemnors have filed affidavits
           by stating thereunder that orders of this Court have been
           complied. The affidavits dated 09.07.2024 filed by Shri Uma
           Shankar Additional Chief Secretary, Urban Development
           Department, Government of Karnataka- Respondent No.1
[2024] 12 S.C.R.                                                     1313

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


             would indicate that the deponent is depicting the picture
             of having complied with the orders dated 21.11.2014 and
             17.05.2022 without any whisper with regard to the order
             dated 19.03.2024. In fact the deponent has relied upon the
             Government Order No. DPAR 68 PSR 2024 dated 24.05.2024
             whereunder the TDR for 15 acres 17.5 guntas has been
             resolved to be issued to the complainants by determining the
             value as per the BPAT Act. The deponent also refers to the
             order dated 06.06.2024 passed by the Deputy Commissioner
             (TDR) who has again rested his oars on the Government
             Order dated 24.05.2024 namely determining the value of the
             land as per the value determined under the BPAT Act for the
             entire land of 436 acres. Pursuant to the said orders the TDR
             is said to have been forwarded to the complainant/claimant.
             On this ground contemnors are seeking from being absolved
             of the present proceedings or in other words seeking for
             contempt proceedings being dropped and clearly admitting
             there has been delay for which an unconditional apology
             has been tendered.
     20.2    The affidavit of compliance filed by respondent No.3 is as
             vague, vagueness could be. Except enclosing the order No.
             UDD 22 MNY 2023, Bengaluru dated 15.03.2024 whereby
             it has been resolved to utilise 15 acres 39 guntas of the
             Bengaluru Palace for road widening subject to the grant of
             TDR and undertaking that BPAT would implement the orders
             nothing further revolves around this affidavit.
     20.3    The compliance affidavit of Respondent No.4 namely the
             Commissioner of BDA would indicate the steps taken by
             the said authorities to implement the order namely issuance
             of notice dated 10.06.2024 and reply given thereto by the
             noticee and the purported joint mahazar having been drawn
             at the spot for taking possession of the subject land, nothing
             more turns around.
     20.4    The compliance affidavit filed on behalf of the Respondent
             Nos.5 to 6 is in same line with the affidavit filed by the
             Respondent No.4.
     20.5    We find from the afore-stated affidavits that the consistent
             stand taken by the State from day one till date is to the
1314                                                         [2024] 12 S.C.R.

                         Supreme Court Reports


             effect that: (i) petitioners were not entitled for the TDR; (ii) if
             at all they are entitled to, then they would be entitled to the
             compensation as per the Land Acquisition Act or the value
             of the land as fixed by the ULC authorities or the value of
             the land as determined by the authorities determining the
             wealth tax; (iii) even if value is to be determined and TDR
             is to be furnished the valuation of the land cannot be as per
             the value fixed for the adjacent lands under Section 45B of
             the Karnataka Stamp Act,1957 and the value is to be fixed
             as per the value of the land determined under the BPAT
             Act namely 11 crores for 472 acres and proportionately for
             15 acres 39 guntas the value of the subject land has to be
             determined.
21. Having dragged its feet for years in implementing the Orders of this
    Court the respondents seem to have conceptualized a novel method
    to over-reach the Orders of this Court and we say so for the simple
    reason that affidavit of the compliance does not indicate or clearly
    admit that the TDR certificate being issued is in accordance with
    the extant TDR Rules but it is on an assumed value. The notice
    dated 10.06.2024 which was preceded by Government Order dated
    24.05.2024 issued to the petitioners reflect that market value of the
    land acquired has been determined @ Rs.120.68/ per square meter
    inclusive of interest, which notice has also been duly replied to by the
    petitioners on 13.06.2024 contending valuation made is contrary to
    TDR Rules. The Government Order dated 24.05.2024 being contrary
    to the direction issued by this Court cannot be accepted or the value
    of the subject land as determined thereunder to be correct, or the
    value indicated therein can be taken as a determination as per TDR
    Rules and it is diametrically opposite to the TDR Rules. We say so
    for reasons more than one. Firstly, the gazette notification dated
    27.09.2023 issued in exercise of power vested under Section 45B of
    Karnataka Stamp Act, 1957 by the Government of Karnataka fixing the
    guidance value of the properties for the purposes of registration which
    has been appended to the counter affidavit filed by the complainants
    would indicate that the value of the subject property is fixed at Rs.
    2,83,500 per square meter on Bellary Road, and for Jayamahal
    Road it is fixed at Rs. 2,04,000 per square meter (see convenience
    compilation filed on 21.07.2024 at pages 248 and 249) and this value
    is not adopted. Secondly, the applicable rules for issuance of TDR is
[2024] 12 S.C.R.                                                     1315

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     known and called as Karnataka Town and Country Planning (Benefit
     of Development Rights) Rules 2016. Section 2(i) defines ‘Market
     Value’ to mean the value determined as per the guidance value of
     land in accordance with Section 45B of the Karnataka Stamp Act,
     1957. Thus, the TDR has to be issued as per the guidance value
     fixed under the Stamp Act and it is for this precise reason the State
     while determining the market value of the subject land had adopted
     the guidance value as specified under the Stamp Act for purposes of
     calculation/determination under I.A. No. 98276 of 2021 for pleading
     financial hardship. The State Government cannot now retrace its
     steps in this regard and determine the value of the subject property
     at its whims or fancies or on any imaginary value for the purposes
     of issuance of TDR. Thirdly, the market value of the property has to
     be prescribed under Rule 4 of TDR Rules, which clearly mandates
     the “market value” of a property to be as prescribed under Section
     45B of Stamp Act, as the basis for issuance of TDR. In fact, this
     Court by Orders dated 21.11.2014, 17.05.2022 and 19.03.2024 in
     no uncertain terms has ordered or directed the respondents to issue
     TDR as per TDR Rules. Fourthly, in the interlocutory application (I.A.
     No. 98276 of 2021) filed for modification by the State, it has been
     specifically pleaded by the State itself that “if the compensation was
     required to be paid in terms of the award passed under the Act of
     1996, then for the extent of 15 acres and 39 guntas the compensation
     payable would be Rs. 37,28,813. However, if the TDR certificate is
     to be issued as per TDR rules for the said extent of 15 acres 39
     guntas, it would result in 13,91,742 sq. feet additional built up area
     constructable in the city of Bengaluru and approximately it would
     be equivalent to notional value of Rs.1,396 crores” after deducting
     60% of the guidance value. The State specifically pleaded that TDR
     once granted is transferable and it would not be possible to recover
     the value of the TDR from the appellants if it is transferred to other
     parties/ builders, in the event of final judgment going against the
     appellants. In fact, it is for this precise reason we have opined supra
     that orders dated 21.11.2014 and 17.05.2022 was not required to be
     tweaked by this Court by adding additional conditions. Fifthly, it is
     to be noted that when value of adjacent and abutting land is fixed at
     Rs. 2,83,500 per sq. meter and 2,04,000 per sq. meter respectively
     under the Karnataka Stamp Act, 1957, the value of subject land
     cannot be diminished below the said value. The State specifically
1316                                                    [2024] 12 S.C.R.

                        Supreme Court Reports


     sought for modification of the order dated 21.11.2014 whereunder
     it was required to issue TDR as per TDR rules and wanted to pay
     compensation as per the calculation in the original award of 1996 in
     similar terms of the order dated 15.02.1999 passed on IA No.2 and
     this has been categorically turned down or rejected by this Court by
     order dated 17.05.2022. For these myriad reasons Government Order
     dated 24.05.2024 cannot be accepted as substantial compliance
     of the orders dated 21.11.2014, 17.05.2022 and 19.03.2024 and it
     stands rejected.
22. In fact, the State itself has categorically admitted in its Government
    Order dated 23.02.2021 the value of the TDR to be issued in favour
    of the claimants would be as under:
          Total area 15 Acres 36 Guntas, Total 639 Guntas
          639 x 1089 = 695871 sq. ft. x 2 = 1391742 sq. feet.
     It is also admitted that the gross value is Rs.2,70,000 per Sq.
     Meter. However, it has determined the value as 0.4 times of the
     land value that is 1,08,000 per Sq. Meter on the premise that it is
     to be construed as an agricultural land. This very plea came to be
     raised for the modification of the order dated 21.11.2014 and it was
     turned down by this Court by order dated 17.05.2022 and it was
     reiterated that the TDR is required to be issued as per TDR Rules
     namely by adopting market value of the land. The value of the land
     cannot be anything less than market value as already determined
     under Section 45B of the Karnataka Stamp Act 1957. At the cost
     of repetition it requires to be noticed that the State Government
     itself has considered the market value as per guidance value at
     Rs. 2,70,000 per sq. meter fixed under Karnataka Stamp Act, 1957
     and has adopted 0.4 times of the said value to calculate the TDR
     for the reason that the Bangalore Palace falls within agricultural
     zone which cannot be market value under TDR Rules. No material
     whatsoever has been placed by the State to depict that the subject
     land is to be construed as falling within agricultural zone. In fact,
     the subject property was utilized as a private residence of the then
     Maharaja of Mysore since long number of years and it is situated
     in the heart of city of Bangalore. There cannot be any cavial to the
     fact that TDR is required to be issued as per TDR Rules. In fact,
     not dwelling upon further on this aspect, it can be safely concluded
     that valuation of the subject land even according to the State was
[2024] 12 S.C.R.                                                     1317

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     determined as per the guidance value then prevailing but restricted
     it to 40% of the guidance value by treating it as agriculture land
     without any basis whatsoever. The notifications issued under Section
     45B of the Karnataka Stamp Act prescribes the guidance value and
     this value alone ought to have been adopted and there cannot be
     any reduction or subtraction in that regard. Thus, any amount of
     plea raised by the contemnors on the ground of financial hardship
     or otherwise would be in contravention of the Order passed by this
     Court on 21.11.2014, 17.05.2022 and 19.03.2024. Hence, we are
     of the considered view that the State and its instrumentalities and/
     or the competent authority being the BBMP is required to issue the
     TDR as per the then prevailing guidance value fixed under Section
     45B of Karnataka Stamp Act, 1957 namely 2,83,500 per sq. meter
     for Bellary Road and 2,04,000 per sq. meter for Jayamahal road as
     indicated under the notifications issued under Section 45B of the
     Karnataka Stamp Act.
23. Yet the fact remains that subsequent to the same the State has
    calculated the value of the TDR in terms of the Order dated 22.04.2024
    and 06.06.2024 as approved by the provisional acceptance order
    dated 07.06.2024, the correctness of which cannot be subject matter
    of the present contempt proceedings and the value of subject land
    as determined thereunder has not been accepted by this Court for
    the reasons already indicated supra. No doubt by way of attempting
    to purge in the contempt, these orders have been passed. The State
    and its authorities have no doubt dragged their feet in implementing
    the orders of the Court. However, there seems to be thin line of doubt
    which has arisen in the mind of State and its authorities as regards
    the valuation and in this direction if steps have been taken to protect
    the interest of the revenue and several meetings have been held and
    these aspects are placed before the State Cabinet and a decision
    has been taken by the State cabinet, it cannot be construed or held
    that State is not willing to implement the order and particularly in
    the background of several orders having been passed though not
    in consonance with the orders dated 21.11.2014 and 17.05.2022.
    Hence, we deem it proper to extend one final opportunity to report
    compliance within a time frame.
24. Since we have opined that the State and its authorities have
    intentionally dragged its feet for long number of years and having
    attempted to tap all the mirage remedies and left with no other option
1318                                                       [2024] 12 S.C.R.

                         Supreme Court Reports


     and to stave off these proceedings have passed the orders dated
     15.03.2024, 22.04.2024, 24.05.2024 and 10.06.2024 to utilise the
     subject land for road widening, fixing the extent to which each of
     the claimants would be entitled for compensation and to issue the
     TDR on an estimate value which is not accepted by this Court, still
     an opportunity to issue TDR’s as per market value as envisaged
     under Karnataka Stamp Act, 1957 as observed hereinabove ought
     to be extended to the respondents/contemnors.
25. Hence, we direct the respondent authorities to issue the TDR as per
    the value noticed hereinabove in favour of the respective claimants
    within six (6) weeks from today. We also make it abundantly clear
    that issuance of the TDR certificates would be subject to further
    orders that may be passed by this Court while disposing of the
    appeals which are pending before the larger Bench and both
    parties are at liberty to bring this fact to the notice of the court
    adjudicating the appeals. This order would also have no bearing on
    the respective contentions of both the parties in pending appeals
    or on any other collateral proceedings. We also make it explicitly
    clear that the order dated 19.03.2024 to the extent of imposing
    additional conditions is hereby recalled, as it is diametrically opposite
    to the order dated 17.05.2022 and 21.11.2014. The directions
    issued under Orders dated: 21.11.2014 and 17.05.2022 shall be
    complied by the competent authority of BBMP keeping in mind the
    observations made hereinabove within six (6) weeks from today
    and compliance affidavit shall be filed within the said period failing
    which the Commissioner, BBMP and the competent authority for
    issuance of TDR shall appear in person before this Court for having
    failed to comply with the orders of this Court, to enable this Court
    to pass further orders. On account of the faux pas situation that
    has been created by the respondent authorities, we direct that
    each of the complainants shall be paid a sum of Rs. 1 lakh each
    towards the cost of these proceedings except complainant in C.P.
    No. 578 of 2022.
26. In the light of the aforesaid observations contempt petition Nos.688
    of 2021, 716 of 2023, 555 of 2024, 556 of 2024 and 585 of 2024
    are allowed in above terms, CP No. 578 of 2022 stands disposed
    of reserving liberty to the complainants to pursue their grievance
    before the competent authority for issuance of TDR on resolution of
    the inter se dispute and it is needless to state that successful party
[2024] 12 S.C.R.                                                  1319

     Chaduranga Kanthraj Urs and Anr. v. P. Ravi Kumar and Ors.


     would be entitled to receive the TDR as ordered by this Court vide
     Order dated 21.11.2014, 17.05.2022 and 19.03.2024.
27. All pending applications stands consigned to records.
     For reporting compliance and/or appearance of the contemnors as
     the case may be. List these matters on 22nd January 2025.

     Result of the case: Matter listed for reporting compliance.



     †
         Headnotes prepared by: Ankit Gyan


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Suppressio Veri Suggestio Falsi"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.