CA RAMCHANDRA DALLARAM CHOUDHARYversusADANI INFRASTRUCTURE AND DEVELOPERS PRIVATE LIMITED
- Citation
- 2026 INSC 629
- Decided
- 1 June 2026
- Disposal
- Dismissed
- Bench
- DIPANKAR DATTA
Holding
The Court held that no condonation of delay is permissible once the 28‑day period for curing defects under the Supreme Court Rules has expired, and any appeal filed beyond the 60‑day limit under Section 62 IBC is time‑barred.
Summary
The liquidator of a corporate debtor filed an appeal under Section 62 of the Insolvency and Bankruptcy Code (IBC) after the 45‑day filing period but within the 60‑day grace period, and the appeal was marked defective. The liquidator failed to cure the defects within the 28‑day period prescribed by the Supreme Court Rules and subsequently re‑filed the appeal after an additional 82‑day delay, seeking condonation of both the original filing delay and the re‑filing delay. The Court examined whether the statutory scheme of the IBC and the Supreme Court Rules permit condonation of delay beyond the 28‑day cure period and whether the appeal could be entertained despite the cumulative delays. Relying on earlier decisions emphasizing strict adherence to IBC timelines, the Court held that once the 28‑day period for curing defects expires, no application for condonation of re‑filing delay can be entertained and the appeal is time‑barred. Consequently, the Court dismissed the defective appeal as barred by limitation and also dismissed the related applications for condonation.
Issues considered
- Whether the Supreme Court can condone delay in re‑filing an appeal under Section 62 IBC when the defects identified are not cured within the 28‑day period prescribed by the Supreme Court Rules.
- Whether an appeal filed beyond the 45‑day period but within the 60‑day statutory limit, and subsequently marked defective, can be re‑filed after the 28‑day cure period without condonation.
Legislation cited
- Constitution of India
- Insolvency and Bankruptcy Code, 2016s. 62
- Supreme Court Rules, 2013s. Order VIII Rule 6 (sub‑rules 3 and 4)
Headnote
Issue for Consideration Issue arose that where an appeal u/s.62 IBC is filed within time, i.e., 45 (forty-five) days or beyond the said period but before expiry of 60 (sixty) days as contemplated in the sub-sections thereof and are marked defective, for this Court can condone the delay in refiling of the appeal when the defects pointed out are not cured within 28 (twenty-eight) days. Headnotes† Insolvency and Bankruptcy Code, 2016 – s.62 – Supreme Court Rules, 2013 – Ord.VIII r.6 Sub-rules (3) and (4) – Condonation
Subjects
Judgment
[2026] 7 S.C.R. 208 : 2026 INSC 629
CA Ramchandra Dallaram Choudhary
v.
Adani Infrastructure and Developers Private Limited
(Civil Appeal Diary No. 5988 of 2026)
01 June 2026
[Dipankar Datta* and Satish Chandra Sharma, JJ.]
Issue for Consideration
Issue arose that where an appeal u/s.62 IBC is filed within time,
i.e., 45 (forty-five) days or beyond the said period but before expiry
of 60 (sixty) days as contemplated in the sub-sections thereof and
are marked defective, for whatever reason, whether this Court
can condone the delay in refiling of the appeal when the defects
pointed out are not cured within 28 (twenty-eight) days.
Headnotes†
Insolvency and Bankruptcy Code, 2016 – s.62 – Supreme Court
Rules, 2013 – Ord.VIII r.6 Sub-rules (3) and (4) – Condonation
of delay – Appeal u/s.62, at the instance of liquidator of a
corporate debtor under liquidation challenging the order
passed by NCLAT – Appeal presented beyond the period of
limitation prescribed in s.62(1), but within the grace period
stipulated in sub-section (2) – Office reported a delay of 7
days in filing the appeal – Application seeking condonation of
delay filed – Office also marked the appeal defective – Upon
curing the defects, the appeal came to be re-filed after a further
delay of 82 days, for which a separate application seeking
condonation of the delay in re-filing also filed:
Held: 45 (forty-five) days is available under subsection (1) of s.62
from date of receipt of the order of the NCLT to file an appeal
involving a substantial question of law before this Court – As
per sub-section (2), subject to sufficient cause being shown, the
Supreme Court may allow an appeal to be filed within 15 (fifteen)
days after the expiry of the said 45 (forty-five) days but not beyond –
Curing of defects arising out of a defectively filed appeal u/s.62
is permissible within 28 (twenty-eight) days of notification thereof
by the Registry – If the defects are cured within 28 (twenty-eight)
days, the appeal would deserve registration upon removal of the
* Author
[2026] 7 S.C.R. 209
CA Ramchandra Dallaram Choudhary v.
Adani Infrastructure and Developers Private Limited
“D No.” – However, there being no scope for curing defects after
lapse of the period of 28 (twenty-eight) days in respect of an
appeal u/s.62, filing of an application for condonation of the delay
in re-filing does not arise – Thus, no question of condonation of
delay [even for a day beyond 60 (sixty) days (in case of an appeal
which, apart from the little delay in filing beyond 45 (forty-five days),
is otherwise defect-free) and 28 (twenty-eight) days (in case of
a defective appeal)] arises for consideration – Where the statute
itself erects an insurmountable jurisdictional bar, no enquiry into the
adequacy of the cause shown would alter the legal consequence
that inexorably follows – Upon a perusal of the applications
seeking condonation of delay in filing and in re-filing, sufficient
cause not shown to satisfactorily explain the delay – Absent any
cogent or convincing justification, the delay in both the filing of
the defective appeal and re-filing of the appeal not liable to be
condoned – Defective appeal dismissed as time-barred having
been filed beyond the maximum period condonable in terms of
the IBC. [Paras 25-28]
Case Law Cited
Mobilox Innovations (P) Ltd. v. Kirusa Software (P) Ltd [2017]
10 SCR 1006 : (2018) 1 SCC 353; Kalparaj Dharamshi v. Kotak
Investment Advisors Limited [2021] 2 SCR 677 : (2021) 10
SCC 401; National Spot Exchange Ltd. v. Dunar Foods Ltd.
(Resolution Professional) [2021] 7 SCR 1024 : (2022) 11 SCC
761; V. Nagarajan v. SKS Ispat & Power Ltd [2021] 14 SCR 736 :
(2022) 2 SCC 244; Tata Steel Limited v. Raj Kumar Banerjee
& Others [2025] 5 SCR 814 : (2025) 9 SCC 483; PEC Ltd. v.
M/s Phulchand Exports Private Ltd., Civil Appeal (Diary) No.
37293 of 2022; Saturn Ventures and Advisors Pvt. Limited v. S.
Gopalakrishnan, 2025 SCC OnLine SC 2484; CA Ramchandra
Dallaram Choudhary v. Adani Infrastructure & Developers (P) Ltd.,
2025 SCC OnLine SC 1406 – referred to.
List of Acts
Insolvency and Bankruptcy Code, 2016; Supreme Court Rules,
2013; Constitution of India.
List of Keywords
Appeal u/s.62 IBC; Marked defective; Condone the delay in
refiling of appeal when defects pointed out not cured within 28
210 [2026] 7 S.C.R.
Supreme Court Reports
(twenty-eight) days; Condonation of delay; Liquidator of corporate
debtor under liquidation; Appeal presented beyond the period of
limitation; Curing of the defects.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal Diary No.
5988 of 2026
From the Judgment and Order dated 08.12.2025 of the National
Company Law Appellate Tribunal in CAAT (I) No. 2316 of 2024
Appearances for Parties
Advs. for the Appellant(s):
Sunil Fernandes, Abhijeet Sinha, Sr. Advs., Atul Sharma, Pankaj
Jain, Ms. Aditi Sharma, Vikram Choudhary, Shubham Bhalla.
Advs. for the Respondent(s):
Balbir Singh, Sr. Adv., Ms. Hetu Arora Sethi, Anirudh Bhat, Siddarth
Agarwal, Shamik Bhatt, Sanidhya Kumar, Vedant Kohli.
Judgment / Order of the Supreme Court
Judgment
Dipankar Datta, J.
1. This is an appeal under Section 62 of the Insolvency and Bankruptcy
Code, 20161, at the instance of the liquidator of a corporate debtor
under liquidation. Under challenge is the judgment and order dated
08th December, 20252 passed by the National Company Law Appellate
Tribunal, Principal Bench at New Delhi3 in Comp. App. (AT) (Ins)
No.2316 of 2024.
2. Having regard to the point on which we propose to decide the appeal,
we see no reason to comment on the correctness or otherwise of
the impugned order.
3. The appeal was presented on 29th January 2026, beyond the period
of limitation prescribed in sub-section (1) of Section 62, IBC but within
1 IBC
2 impugned order
3 NCLAT
[2026] 7 S.C.R. 211
CA Ramchandra Dallaram Choudhary v.
Adani Infrastructure and Developers Private Limited
the grace period stipulated in sub-section (2) thereof. Office reported
a delay of 7 (seven) days in filing the appeal. An application seeking
condonation of the said delay has been filed. Office had also marked
the appeal defective. Upon curing the defects, the appeal came to
be re-filed after a further delay of 82 (eighty-two) days for which a
separate application seeking condonation of delay in re-filing has
also been filed.
4. At the outset, it must be borne in mind that the scheme of limitation
under the IBC is a strict and time-bound one. The concept of
condonation of delay itself is alien to the statutory framework beyond
the period expressly contemplated under the statute. Section 62
of the IBC permits an appeal to be filed before this Court within
45 (forty-five) days, with a further grace period of only 15 (fifteen)
days, and that too, only upon sufficient cause being shown. Thus,
the outer limit statutorily permissible is 60 (sixty) days, beyond
which the appeal itself becomes barred and the Court’s jurisdiction
to condone the delay ceases.
5. The importance of strict adherence to timelines under the IBC has
been enunciated by this Court succinctly in its decision in Mobilox
Innovations (P) Ltd. v. Kirusa Software (P) Ltd.4 as follows:
36. … Even in appeals to the Supreme Court from the
Appellate Tribunal under Section 62, 45 days’ time is
given from the date of receipt of the order of the Appellate
Tribunal in which an appeal to the Supreme Court is to be
made, with a further grace period not exceeding 15 days.
The strict adherence of these timelines is of essence to
both the triggering process and the insolvency resolution
process. … .
6. Time bound resolution is the essence of the IBC was reiterated
in respect of an appeal under Section 61 thereof in Kalparaj
Dharamshi v. Kotak Investment Advisors Limited5 in the following
words:
158. This Court has held, that it is not open to the adjudicating
authority or appellate authority to reckon any other factor
4 (2018) 1 SCC 353
5 (2021) 10 SCC 401
212 [2026] 7 S.C.R.
Supreme Court Reports
other than specified in Sections 30(2) or 61(3) of the I&B
Code. It has further been held, that the commercial wisdom
of CoC has been given paramount status without any judicial
intervention for ensuring completion of the stated processes
within the timelines prescribed by the I&B Code. … .
(emphasis ours)
7. Reference can also be made to the decisions in National Spot
Exchange Ltd. v. Dunar Foods Ltd. (Resolution Professional)6, V.
Nagarajan v. SKS Ispat & Power Ltd7 and Tata Steel Limited v. Raj
Kumar Banerjee and Others8 which, though arising in the context
of appeals under Section 61 of the IBC, reaffirm that condonation
of delay beyond the period expressly prescribed by the statute itself
would be impermissible.
8. Furthermore, this Court in PEC Ltd. v. M/s Phulchand Exports
Private Ltd.9 held pithily as follows:
1 There is a delay of 21 days in filing the appeal under
Section 62 of the Insolvency and Bankruptcy Code
2016. The delay is beyond the maximum period which is
condonable in terms of the statute.
2 Hence, the civil appeal is dismissed on the ground of
limitation.
3 Pending applications, if any, stand disposed of.
9. In Saturn Ventures and Advisors Pvt. Limited v. S. Gopalakrishnan10,
delay of two days in presentation of an appeal under Section 62 of
the IBC was not condoned reasoning that the Court has no power
to condone the delay.
10. Let us now ascertain what the position is under the Supreme Court
Rules, 201311. Sub-rules (3) and (4), of Rule 6 of Order VIII, SCR,
lay down the regime governing re-filing of, inter alia, petitions and
6 (2022) 11 SCC 761
7 (2022) 2 SCC 244
8 (2025) 9 SCC 483
9 Civil Appeal (Diary) No. 37293 of 2022
10 2025 SCC OnLine SC 2484
11 SCR
[2026] 7 S.C.R. 213
CA Ramchandra Dallaram Choudhary v.
Adani Infrastructure and Developers Private Limited
appeals after curing defects. A period of 28 (twenty-eight) days is
earmarked for curing of defects. A litigant not curing the defects within
28 (twenty-eight) days may re-file the petition or the appeal, as the
case may be, together with an application seeking condonation of
re-filing delay. Needless to observe, condonation of re-filing delay
for petitions and appeals is discretionary.
11. Is it open to this Court [where an appeal under Section 62, IBC is
filed within time, i.e., 45 (forty-five) days or beyond the said period but
before expiry of 60 (sixty) days as contemplated in the sub-sections
thereof and are marked defective, for whatever reason] to condone
the delay in re-filing of the appeal when the defects pointed out are
not cured within 28 (twenty-eight) days? This was the question we
posed to Mr. Fernandes, learned senior counsel for the appellant
to answer.
12. Mr. Fernandes contends that the appellant is a neutral officer acting
under the aegis of this Court for the benefit of all stakeholders as
well as the corporate debtor under liquidation and having regard
to the nature of duties imposed on him, the insignificant delay in
filing the appeal as well as re-filing thereof ought to be considered
liberally rather than strictly. He also contends, notwithstanding that the
defects were not cured within 28 (twenty-eight) days of such defects
being notified, this Court’s power to condone re-filing delay of any
number of days beyond 28 (twenty-eight) days is not fettered and if
sufficient cause be shown to exist, which did preclude a party from
acting within the timelines provided in the IBC, re-filing delay of any
length of time is invariably condoned. According to him, under the
SCR, delay in re-filing after curing of the defects is treated differently
from delay in initial filing. If initially the appeal is filed within 45 (forty-
five) days, or even within the grace period of 15 (fifteen) days and
sufficient cause for condonation of filing delay is shown, the Court
would generally condone the delay – in filing and re-filing - if the
same is satisfactorily explained.
13. Mr. Fernandes has, in this connection, invited our attention to
a coordinate Bench decision between the same parties in CA
Ramchandra Dallaram Choudhary v. Adani Infrastructure &
Developers (P) Ltd.12 where re-filing delay in filing an appeal before
12 2025 SCC OnLine SC 1406
214 [2026] 7 S.C.R.
Supreme Court Reports
the NCLAT under Section 61 of the IBC was condoned. Particular
reliance was placed on the following passages:
9. Be that as it may, it is well-recognised principle of law
that the courts view applications relating to lawyer’s lapses
more leniently than applications relating to litigant’s lapses.
The classic example is the difference in approach of courts
to applications for condonation of delay in filing an appeal
and applications for the condonation of delay in refilling
the appeal after rectification of defects. Useful reference
may be made to the decision of the co-ordinate Bench of
this Court in Perumon Bhagvathy Devaswom v. Bhargavi
Amma [(2008) 8 SCC 321; 2008 SCC OnLine SC 1049.]
10. Having regard to the fact that the appellant despite
limitations had done all that was necessary for filing of the
appeal within 30 days, and then 15 days, i.e., within the
prescribed and extended period of limitation, respectively,
as well as dependency of the appellant on its lawyers who,
in turn, were dependent on their clerk to refile the appeal,
and there were some missteps contributing to the present
situation, coupled with the fact that the issue sought to
be raised by the appellant in the appeal filed before the
National Company Law Appellate Tribunal, if answered in
its favour, would enure to the benefit of the debtors, and
also that better justice is always achieved when a lis is
decided on a contested hearing rather than on default,
we need to take an overall view of the matter. We are of
the considered opinion that the words “sufficient cause” in
this case ought to have been construed liberally and that
interest of justice would be best served if, upon condonation
of delay in refilling of the appeal, the National Company
Law Appellate Tribunal proceeds with the hearing of the
appeal on merits. Ordered accordingly.
14. We propose to advert to the decision in CA Ramchandra Dallaram
Choudhary (supra) a little later.
15. Having regard to the statutory scheme of the IBC, since validated
by this Court in numerous decisions by holding that the strict
timelines are meant to prevent misuse by dilatory tactics, it is
difficult to accept Mr. Fernandes’ contention. It is axiomatic that an
[2026] 7 S.C.R. 215
CA Ramchandra Dallaram Choudhary v.
Adani Infrastructure and Developers Private Limited
appeal under Section 62 of the IBC to be regarded as having been
instituted within the prescribed period of 45 (forty-five) days must be
a defect-free appeal, which is capable of being acted upon by the
Registry for being immediately placed before the appropriate Bench
for consideration. Any appeal which is not filed within the stipulated
period in a form shorn of defects, for all practical and legal purposes,
remains a defective appeal.
16. Can or should a litigant be permitted to circumvent the rigours of
limitation by filing a defective appeal as a device to save limitation
and, thereafter, to opt to cure the notified defects at leisure? Can or
should this Court countenance such a practice? The answers to both
questions have to be a resounding ‘NO’. To hold otherwise would defeat
the object of the IBC and render nugatory the discipline of timelines
engrafted both in Section 62 as well as the SCR. Any such practice
of filing a defective appeal, if encouraged, could result in a litigant
dragging the process of re-filing for months and still being heard on
his application for condoning re-filing delay premised on the ground
that the IBC says nothing about re-filing delay and that the SCR being
a procedural law must be read in a manner to aid the rendering of
substantive justice to a party who is shown to be above board.
17. Consequently, no litigant can be permitted to subvert the statutory
scheme by seeking condonation of re-filing delay beyond the period of
28 (twenty-eight) days after having initially lodged a defective appeal.
Once the window of 60 (sixty) days prescribed by the IBC, followed
by the window of 28 (twenty-eight) days in re-filing the appeal upon
curing of defects permitted by the SCR is shut, the right to appeal
stands extinguished.
18. The argument that the SCR does not impose a cap beyond which
re-filing delays cannot be condoned and, hence, it is the acceptability
of the cause shown amounting to ‘sufficient cause’ which is and
should be decisive, irrespective of the length of time taken to cure
the defects, is equally unimpressive. The SCR is the subordinate
legislation in the field and whenever the IBC and the SCR clash, the
latter cannot override the express provisions of the former. The IBC
must prevail being the statutory edict. Though indisputable that the
standards for examining a prayer for condoning a re-filing delay is
certainly less rigorous than a filing delay but such standard would
stand true and be applicable for the general laws, like proceedings
216 [2026] 7 S.C.R.
Supreme Court Reports
arising from the Codes of Civil and Criminal Procedure, as well as
from remedies provided by the Constitution of India. Section 62,
IBC is, however, a complete code in itself for filing of appeals and is
different from other laws. An appeal under Section 62, IBC does not
remain alive after the 28 (twenty-eight) day period allowable under
the SCR for curing defects and the lis would stand frozen once
the defects are not cured within such period. An extended window
cannot be granted de hors the legislative intent behind stipulation
of the strict timelines in the IBC.
19. We may also observe that the fact of the appellant being a neutral
officer acting under the aegis of this Court for the benefit of all
stakeholders and the corporate debtor under liquidation is not
sufficient for us to invoke our extraordinary jurisdiction under Article
142 of the Constitution to dilute or override the express statutory
timeframes engrafted under the IBC. Pertinently, the IBC does not
mark a different threshold for officers like the appellant and hence,
reading words into the statute which are not used by the legislature
would not be a permissible interpretational exercise.
20. Moving on to the decision in CA Ramchandra Dallaram Choudhary
(supra), which has been pressed into service by Mr. Fernandes, the
peculiar factual matrix of the said appeal assumes significance and
warrants a recapitulation of the events.
a. Appellant had earlier challenged the order dated 21st June,
2024 passed by the National Company Law Tribunal13 before
the NCLAT in an appeal under Section 61, IBC. However, the
appeal before the NCLAT itself was not filed within the prescribed
period and was beset by delay in re-filing.
b. Vide its order dated 6th February, 2025, the NCLAT declined to
condone the delay. Aggrieved thereby, the appellant approached
this Court by filing an appeal14 under Section 62, IBC. This
Court, by its order dated 5th May, 2025, set aside the order
of the NCLAT and remanded the matter for consideration on
merits, whereupon the NCLAT proceeded to decide the appeal
and delivered the impugned order.
13 NCLT
14 Civil Appeal No. 5106 of 2025
[2026] 7 S.C.R. 217
CA Ramchandra Dallaram Choudhary v.
Adani Infrastructure and Developers Private Limited
c. Significantly, while concluding its order dated 5th May, 2025,
this Court specifically recorded that such order is not to be
treated as a precedent.
21. It would, therefore, appear that notwithstanding the indulgence shown
by this Court to the self-same appellant at an earlier stage, the appeal
presently under consideration has been re-filed after substantial delay.
The explanation for the re-filing delay reads as follows:
4. That it is most humbly submitted that essentially the
delay in refiling arose due to an internal oversight within
the Office of the Liquidator. While the defects were duly
communicated by the Registry, a concerned officer within
the Liquidator’s office either mistakenly believed that the
requisite details had already been conveyed or did not
promptly relay them to the Advocate-on Record. It is also
pertinent to mention that this officer has since left the
position, leading to a gap in communication. The delay,
thus, was neither intentional nor negligent but arose from
a bona fide administrative lapse within the office.
(emphasis ours)
22. The circumstance that this Court had earlier interdicted refusal of the
NCLAT to condone the delay in re-filing the appeal under Section 61
of the IBC does not advance the appellant’s case, rather even on
a cursory comparison of the two situations, it only accentuates the
reason as to why the earlier exercise of discretion cannot be extended
to the present proceedings. While setting aside the order of the
NCLAT, this Court had emphasized the differing degrees of liberality,
which ought to be extended in the cases of lapses attributable to
the advocate-on-record and to the litigant, as far as re-filing delay
is concerned. It was in this factual milieu, the controversy warranted
examination on merits, thereby necessitating the condonation of
delay in re-filing of the appeal before the NCLAT and restoration of
the appeal before it.
23. The decision in CA Ramchandra Dallaram Choudhary (supra)
reiterates the principle which must guide the exercise of judicial
discretion in matters of condonation of delay. The present case
stands on an entirely different pedestal, wherein the appellant
seeks condonation not merely of delay in re-filing but also of delay
218 [2026] 7 S.C.R.
Supreme Court Reports
in invoking the appellate jurisdiction of this Court under Section 62,
IBC. Importantly so, the appellant approaches this Court after having
availed the benefit of a liberal construction of “sufficient cause” at the
previous stage of the same litigation. A litigant who has once secured
indulgence in relation to delay cannot legitimately proceed on the
assumption that further defaults engendered at the next appellate
stage would automatically attract a similar exercise of discretion.
To hold otherwise would render the law of limitation under the IBC
progressively elastic at every successive stage of challenge, defeating
the legislative objective of expedition and finality.
24. Restating what has already been enunciated, the appellant can
derive no advantage from the earlier order condoning the delay in
re-filing the appeal under Section 61, IBC before the NCLAT. That
exercise of discretion was confined to the peculiar facts of that case
and cannot be construed as a warrant for repeated indulgence. The
discipline of limitation, particularly in the context of the IBC, does
not countenance serial condonations of delay across successive
appellate stages. Having once availed the benefit of a liberal
approach, the appellant cannot legitimately seek a further relaxation
when the present appeal under Section 62 is itself beset by delay
both in filing and in re-filing.
25. To sum up our discussion, 45 (forty-five) days is available under sub-
section (1) of Section 62, IBC from date of receipt of the order of the
NCLT to file an appeal involving a substantial question of law before
this Court. As per sub-section (2), subject to sufficient cause being
shown, the Supreme Court may allow an appeal to be filed within
15 (fifteen) days after the expiry of the said 45 (forty-five) days but
not beyond. Curing of defects arising out of a defectively filed appeal
under Section 62, IBC is permissible within 28 (twenty-eight) days
of notification thereof by the Registry. If the defects are cured within
28 (twenty-eight) days, the appeal would deserve registration upon
removal of the “D No.”. However, there being no scope for curing
defects after lapse of the period of 28 (twenty-eight) days in respect
of an appeal under Section 62, IBC, filing of an application for re-filing
delay does not arise. Consequently, no question of condonation of
delay [even for a day beyond 60 (sixty) days (in case of an appeal
which, apart from the little delay in filing beyond 45 (forty-five days),
is otherwise defect-free) and 28 (twenty-eight) days (in case of a
defective appeal)] arises for consideration.
[2026] 7 S.C.R. 219
CA Ramchandra Dallaram Choudhary v.
Adani Infrastructure and Developers Private Limited
26. Thus, the legal position being settled beyond cavil, it is unnecessary
for us to venture into the merits of the explanations furnished in
support of the applications for condonation of delay in filing and
re-filing herein. Where the statute itself erects an insurmountable
jurisdictional bar, no enquiry into the adequacy of the cause shown
would alter the legal consequence that inexorably follows.
27. Apart from what has been held above, upon a perusal of the
applications seeking condonation of delay in filing and in re-filing,
we find sufficient cause not having been shown to satisfactorily
explain the delay(s). Absent any cogent or convincing justification,
the delay(s) in both the filing of the defective appeal and re-filing of
the appeal are not liable to be condoned.
28. Be that as it may, the defective appeal stands dismissed as time-
barred having been filed beyond the maximum period condonable
in terms of the IBC.
29. Connected applications too stand dismissed.
Result of the case: Appeal dismissed.
†
Headnotes prepared by: Nidhi Jain
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.