Created byFuzzy Cloud

Supreme Court of India

BOC INDIA LTD.versusBHAGWATL OXYGEN LTD.

Citation
2007 INSC 279
Decided
12 March 2007
Disposal
Dismissed

Holding

The award was not liable to be set aside as it was based on a plausible interpretation of the contract and did not involve an error of law apparent on the face of the award.

Summary

BOC India Ltd. entered into a turnkey contract with Bhagwati Oxygen Ltd. for the erection, installation and commissioning of an oxygen plant at a lump‑sum price, subject to variations for imported components. Due to exchange‑rate and customs‑duty changes the price rose, and the parties later disputed a sum of Rs 17,95,710 claimed by the respondent as a refund for indigenous supply. An arbitrator awarded the claim in favour of the respondent and rejected the appellant's counter‑claim. The appellant sought to set aside the award under Section 30 of the Arbitration Act, 1940, alleging error apparent on the face of the award, misconduct and excess of jurisdiction. The Supreme Court examined whether the arbitrator had mis‑interpreted the contract or erred in law, and held that the award was based on a plausible contractual interpretation and did not contain an error of law apparent on its face. Consequently, the Court dismissed the appeal, upholding the arbitrator’s award.

Issues considered

  • Whether the arbitrator's award can be set aside under Section 30 of the Arbitration Act, 1940 on the ground of error apparent on the face of the award or misconduct.
  • Whether the award of Rs 17,95,710 to the respondent is contrary to the terms of the lump‑sum contract and the indigenous‑supply clause.
  • Whether the arbitrator exceeded his jurisdiction by interpreting the lump‑sum price to include the disputed amount.

Legislation cited

Subjects

ArbitrationSection 30Error apparent on the face of the awardContract interpretationLump sum priceIndigenous supplyJurisdictionAward setting aside

Judgment

                                  BOC INDIA LTD.                                      A
                                        v.
                               BHAGWATl OXYGEN LTD.

                                     MARCH 12, 2007

               [DR. AR. LAKSHMANAN AND TARUN CHA TIERJEE, JJ.]                         B

 ••
 ,            Arbitration Act, 1940-Sections 30, 33 and 8-Works contract-Lump
        sum price fvced-Party raising invoices against indigenous supply and
        realising excess amount-Claim of refund by other party-Award by· the
        arbitrator allowing the claim-Interference with-Held: Arbitrator took a       c
       plausible view on interpretation of contract-Award was not based upon an
        erroneous proposition of law or error of law appeared from the award or
       from any document-Award was passed considering the terms of contract,
       arbitration clause, materials on record and the statement of claim-Figure
        in dispute was only a mark upto which parties agreed to keep in contract
                                                                                 D
       for rendering of service-Thus, award calls for no interference.

              Appellant and NSKK entered into an agreement to facilitate the
        respondent to import components for setting up Oxygen plant. Appellant and
        respondent entered into a contract for erection, installation and commission
        of the plant. Respondent issued purchase orders in favour of the appellant for E
       supply, installation and commissioning of oxygen plant at a lump sum price
       of Rs.347.40 lacs. The fixed price was subject to variation of importation of
       the contract and exchange rates. Due to variation in exchange rate and
       customs duty, the lump sum price of Rs.347.40 lacs was increased to
       Rs.4,62,60,543. Appellant submitted its bill inclusive of taxes as per the
- )-
       contract. In view of the arbitration clause respondent raised claims after F
       payment. Since the appellant did not refund the amount, respondent filed an
       application for the appointment of an arbitrator under sections 8 and 33 of
       the Arbitration Act, 1940 and submitted its claim before the arbitrator under
       12 heads. Appellant also submitted its counter claim. Arbitrator was appointed
       and he passed an award in favour of the respondent allowing five claims of the G
 ~.    respondent. However, it rejected the counter claim of the appellant. Appellant
-~

       then filed an application for setting aside the award. Appellant raised objection
       that the award suffered errors apparent on the face of it; and that the arbitrator
       erred in awarding the claim of the respondent for a sum of Rs. 17,95,710/-
                                           915
                                                                                      H
    916                      SUPREME COURT REPORTS                    [2007] 3 S.C.R.

A relating to claim no. 9 although the arbitrator held issue no. 4 in favour of
    the appellant. High Court rejected the objection filed and upheld the award.
    Aggrieved appellant filed an appeal. Division Bench of High Court dismissed
    the same. Hence the present appeal.

          Dismissing the appeal, the Court
B
          HELD: 1.1. When the Arbitrator had taken a plausible view on
    interpretation of contract, it is not open to the court to set aside the award on
                                                                                        ' <
    the ground that the Arbitrator had misconducted himself in the proceedings
    and therefore, the award was liable to be set aside. !Para 251 1927-GI

c          l.2. The Arbitrator came to a conclusion that the figure of
    Rs. 17,95,710/-, was included as lump sum contract price as consideration
    payable to the respondent for service rendered by them for importation of plants
    and components. The Arbitrator in his award also considered that the break-
    up and the sum ofRs.17,95,710/-, the appellant had recovered under the bill
    issued against indigenous supply and the respondent paid the amount without
D   any objection. While the Arbitrator has considered the fact that the appellant
    had realised the differential amount of Rs.17,95,710/- from the respondent
    against indigenous supply, it cannot be said to mean that the value of
    indigenous supply had gone up from Rs.SO lacs to Rs.67,95,710/- as according
    to the terms of the contract the value of indigenous supply remained at
E   Rs.67,95,710/- and the appellant realised the differential amount of
    Rs.17,95,710/- against indigenous supply. Accordingly the Arbitrator was
    justified in holding that the said sum of Rs.17,95,710/- was on account of
    expenses that might have been incurred by the respondent in executing the
    contract. (Paras 21, 22 and 261 (925-C, F, GI

F       1.3. The award of the Arbitrator cannot at all be interfered with as the        ....... -
  award was not based upon either a proposition of law which is unsound or an
  erroneous proposition of law was established to have vitiated the decision. The
  Arbitrator had considered all aspects of the matter including the terms of
  the contract, arbitration clause, all the materials on record produced by the
  parties and the statement of claim of the respondent disputed by the appellant
G and came to a conclusion of fact. According to the Arbitrator, this figure was
                                                                                        . ,___
  nothing but a mark up which the parties agreed to keep in the contract for
  rendering of service towards importation of plant components. The appellant
  had realized this difference amount of Rs. 17 lacs from the respondent against
  indigenous supplies. Therefore, it was not the case that the arbitrator had
H
                        BOC INDIA LTD. 1·. BHAGWATI OXYGEN LTD. [TARUN CHATTER.IEE . .lj     917

                  misconducted himself in passing the award by ignoring to consider material         A
.,   -,I
                 documents. It was not the case that the arbitrator had decided erroneously a
                 question of law referred to him but on consideration of the terms of contract
                 and statement of claim came to a conclusion that Claim No. 9 of the respondent
                 should be awarded in its favour. Such being the position, there is no reason to
                 interfere with the award of the arbitrator which was passed on consideration
                 of all material pat on record. It is not open to the court to set aside the award
                                                                                                     B
                 on the ground that the Arbitrator had, while continuing with the proceeding,
     ,.. ,       acted beyond his jurisdiction and violated the contract while awarding Rs.
                 17,95,710/- in the form of Award No.9. This cannot be said to be an award,
      .)
                 which is contrary to the contract entered into by the parties.
                                                (Paras 24, 25 and 261 (926-F, H; 927-B, C, DI        c
                      K.P. Pou/ose v. State of Kera/a, [1975) 2 SCC 236; Trustees of the Port
                 ofMadras v. Engineering Construction Corporation Ltd., AIR (1995) SC 2423
                 and lndu Engineering and Textile Limited v. Delhi Development Authority,
                 1200115 sec 691, referred to.
                                                                                                     D
                       CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1280 of2007.

                       From the Final Judgment and Order dated 20.05.2005 of the High Court
                 of Calcutta in APOT No. 334 of 2002.

                     Soli J. Sorabjee, Dhruv Mehta, Harshvardhan Jha, Yashraj Deora and              E
                 Mannoj Mehta (for K.L. Mehta & Co.) for the Appellant.

                      Bhaskar P. Gupta, R.K. Ghosh, A. Dutta and Praveen Kumar for the
                 Respondent.

                      The Judgment of the Court was delivered by                                     F
     - ;.~
                      TARUN CHATTERJEE, J. I. Leave granted.

                        2. This is an appeal from a judgment of a Division Bench of the Calcutta
                 High Court dismissing an appeal which was filed against the judgment of a
                 learned Judge refusing to accept the objection filed by the appellant under G
                 Section 30 read with Section 33 of the Arbitration Act, 1940 (hereinafter
      _J~    .   referred to as the "Act").

                      The brief facts of this appeal are as follow:
                                                                                                     H
    918                    SUPREME COURT REPORTS                     (2007) 3 S.C.R.

A          3. BOC Ltd. being the appellant herein and one Nippon Sansa K.K.
                                                                                            11-       ,.
    (NSKK) entered into an agreement in order to facilitate the respondent to
    import components for setting up a 25 tons per day Oxygen plant at Ghatsila,
    Bihar (now in the State of Jharkhand). In the month of April/May 1990 the
    appellant and the respondent entered into a contract for erection, installation
    and commission of the aforesaid plant at Ghatsila, Jharkhand. On 5th June
B   1990 a tripartite meeting between the representatives of the appellant and the
    respondent and NSKK were held where the letter of intent was signed and
    purchase orders were issued by the respondent in favour of the appellant.           .   ~



    The respondent awarded a turnkey contract on 6th June, 1990 to the appellant            l
    for manufacture, supply, erection and commission of the said plant. Vide
c   letter dated 18th December 1990, the respondent had agreed to pay interest
    on margin money and reimburse the same to the appellant. The appellant
    thereafter on 31st March 1992 raised final invoices and subsequently on
    13th April 1992 the respondent raised claims and sought refund from the
    appellant. By a letter dated 9th March 1993 the appellant informed the
    respondent indicating therein the interest payable by them to the respondent.
D
    Finally, when the prior invoice and letter were not responded to, on 13th
    September 1993 the respondent again raised claims and sought refund from
    the appellant.     When the refund was not made by the appellant, the
    respondent made an application under Sections 8 and 33 of the Act for the
    appointment of an arbitrator on 24th November 1995 in the High Court at
E   Calcutta.

          4. In the meantime, on 21st September 1995 the High Court directed the
    appellant to release the spares to the respondent on payment of
    Rs. 10,19,000/- by them. A lawyer was thereafter appointed as Arbitrator by
    consent of the parties and the said arbitrator subsequently was replaced on
F   12th February, 1996 by Late Arbitrator Shri P.K. Roy. On 29th July 2000, Late
                                                                                        ~i..      .
    Shri Roy had passed his award in favour of the respondent for a sum of Rs.
    24,92, 165/- with an interest of 12 per cent on the amount. However, the
    counter claim of the appellant was rejected.

G         5. On 30th October, 2000, the appellant filed an application for setting
    aside the award passed by the arbitrator under Section 30 of the Act before
    the High Court at Calcutta. In the said application, the appellant raised
                                                                                        "\._
    objection to the effect that the award in question suffered errors apparent
    on the face of it. It was alleged that the arbitrator erred in awarding the claim
    of the respondent for a sum of Rs. 17,95, 7I 0/- relating to claim no. 9 although
H   the learned arbitrator held issue no. 4 in favour of the appellant. It was also
                     BOC INDIA LTD. 1·. BHAGWATI OXYGEN LTD. [TAR UN CHATTERJEE, J.l    919

~
        -,J    alleged that since the appellant had not realised any sum in excess of Rs. 50 A
               lacs against indigenous supply, the award of the learned arbitrator to the
                                                                                                   ... ~:
               effect that the respondent was entitled to receive back from the appellant, the
               said sum of Rs. 17,95,710/-, was not only erroneous on the face of the award
              but also contradictory and inconsistent with the findings of the arbitrator
              against issue no. 4. It was further alleged by the appellant under Section 30
              of the Act that the learned arbitrator committed error apparent on the face of B
              the award and had acted in excess of his jurisdiction by awarding the aforesaid
        ' '   sum of Rs. 17,95, 710/- in favour of the respondent as the award was contrary
        ,;    to the findings made by the learned arbitrator himself and therefore was liable
              to be set aside. We are not dealing with the other objections taken by the
              appellant in its objection under Section 30 of the Act as noted herein after.   c
              A learned Judge of the High Court by a detailed judgment had rejected the
              objection filed under Section 30 of the Act and had refused to set aside the
              award passed by the arbitrator on the ground that on the materials on record,
              the award was not liable to be set aside on such grounds.

                    6. Feeling aggrieved by the judgment of the learned Single Judge, the     D
              appellant filed an appeal before the Division Bench of the High Court which
              was also dismissed against which the present Special Leave Petition was filed
              in respect of which leave has been granted.

                    7. We have heard Mr. Soli J. Sorabjee, learned senior counsel appearing
              for the appellant and Mr. Bhaskar P. Gupta, learned senior counsel appearing    E
              for the respondent. We have also considered the award passed by the Sole
              Arbitrator Late Mr. P.K. Roy and the objection raised against such award
              under Section 30 of the Act and also the judgment of the learned Single Judge
              as well as the Division Bench of the High Court in detail.
    -   ;~
                                                                                              F
                     8. Before we proceed further, as noted herein earlier, we keep it on
              record that before the Division Bench of the High Court, the appellant restricted
              his grounds for setting aside the award in respect of Claim No.9 of the
              statement of claim only and prayed for the same. Before us, Mr. Sorabjee also
              restricted his submissions only in respect of Claim No.9 of the statement of
;             claim and also prayed for setting aside the award restricted to Claim No.9 only. G
    _j-·      In view of this stand taken by the appellant, we need not dwell upon other
              questions and are concentrating only on the issue raised before us by the
              learned senior counsel appearing for the appellant.

                   9. As noted, we may reiterate that the respondent placed Purchase
                                                                                              H
    920                      SUPREME COURT REPORTS                      [2007] 3 S.C.R.

A Order (P.O.) dated 6th of June, 1990 to the appellant for supply, installation               ..
    and commissioning of oxygen plant at a lump sum price of Rs.347.40 lacs. This
    fixed price was, however, subject to variation only in respect of imported
    components of supply on account of exchange rate variation and customs
    duty variation. This would be evident from clause 1.1 of the P.O. as quoted
B   herein after. It is not in dispute that the job was completed in June/July, 1992.

            I0. Due to variation in exchange rate and also in customs duty, the lump
    sum price ofRs.347.40 lacs increased to Rs.4,62,60,543. The appellant submitted       ,•
    its bill inclusive of taxes as per the contract and the break up which is as
    follows:
c         "A. Annexure I

          Invoice No.     3224                         Rs. 4,62,60,543/-

          8. Invoice dated 31.3 .1992                 Rs. 5,91,625/-

D         C. Taxes paid as per contract

          (as mentioned in Invoice

          No. 3225 and 3227)                           Rs. 6,25,984/-

E
                                        Total          Rs. 4,74,78,152/-"



F       11. As stated herein earlier, in view of the arbitration clause accepted
  by the parties, the respondent had raised a dispute after payment and the
  matter was referred to arbitration. The respondent submitted its claim before
  the arbitrator under 12 heads for a total amount of Rs.1,79,76,716/-. The
  appellant also submitted its counter claim. The sole arbitrator Late Shri
  P.K.Roy passed an award on 29th of July, 2000, as noted herein earlier and
G allowed the claim of the respondent in respect of the following items:
          "A. Claim No. I: Interest
                on margin money                                Rs.1,80,000/-

           B. Claim No.3: Bank charges
H
             BOC INDIA LTD. 1·. BHAGWATI OXYGEN LTD. [TARUN CHATTER.IEE, .I.]      921

-;                  and interest                               Rs.3, 10,932/-            A
            c. Claim No.7: Refund
                    on REP Licence                             Rs. 35,0001-

            D. Claim No.8 : Foreign Technician
                    fees, Air fare, hotel expenses             Rs. I, 70,523/-           B
             E. Claim No.9 Indigenous Supply                   Rs.17,95,7101-
~·

,;

                                                               .Rs.24,92, 1651-"
                                                                                         c
            12. As noted herein earlier, the arbitrator, however, dismissed all other
      claims of the respondent and also the counter claim of the appellant.

             13. Mr. Sorabjee contended that since the award in question was contrary
      to the findings of the learned arbitrator himself, the learned arbitrator in       D
      passing the award had misconducted himself and accordingly the award was
      arbitrary and liable to be set aside in respect of claim No.9 of the respondent.

            14. Mr. Sorabjee had drawn our attention to the purchase order, which
      contained price for manufacture and supply of plant and equipment comprising       E
      both imported and indigenous components for installation, erection and
      commissioning thereof. He had also drawn our attention to the fact that a
      lump sum of Rs.379.49 lacs was fixed as a price for doing the job. The 'basis
      of price' is mentioned in Clause 1.1. of the contract which, is as follows:-

            "Basis of price includes -                                                   F
            I.I.I The value of the imported components will be 128.66 million YEN
                  CIF Calcutta.
             1.1.2 Customs duty @ 80% of CIF value based on 'Project Import".
            1.1.3 Stevedoring, port handling, customs clearance, inland                  G
                  transportation and transit insurance from port to site @ 5% of CIF
 J·               Value.
            1.1.4 Exchange rate has been taken at I 00 yen            Rs.10.9.
            1.1.5 The price includes excise duty towards supply wherever applicable
                                                                                         H
    922                     SUPREME COURT REPORTS                    [2007] 3 S.C.R.

A               as on date, but does not include sales tax, entry tax, income tax
                on foreign technicians and other Govt. impositions, if any, which
                will be paid extra, as applicable.
           1.1.6 Any variation in I. I to 1.1.5 except 1.1.3 indicated above will be
                 adjusted.
B          1.1.7 The premium of Rs.5 lakhs towards purchase of REP Licences is
                 the maximum amount payable by us. Any decrease below Rs. 5
                 lakhs will ·be passed on to us.                                       . ..
          1.1.8 The above price is also subject to 'General Conditions of sale and
                installation of Pla9t and Equipment'. In the event of any conflict
c               between the clauses, one mentioned herein shall prevail. Where
                General Conditions are not applicable, have been marked
                accordingly and initiated by competent authority."

           Clause 4 of the contract contains Terms of Payment. Indigenous supply
    is included in clause 4.4 which reads as following-
D
          "Supply Portion                      Rs.SO lacs.

                                               10% advance against order.

                                               I0% advance within 3 months.
E
                                               80% advance against proforma
                                               invoice before dispatch.

          4.5 For Erection and                 Rs.15 Jakhs.

F         commissioning -                      I0% advance against order

                                               10% advance on opening of site

                                               70% pro rata on monthly basis.

                                               I 0% on completion of erection
G                                              and commissioning."

          15. Jn the statement of claim, as made by the respondent, the value of
    projected imported components worked out to Rs.264.44 lacs in the order
    shown below :-
H
            BOC INDIA LTD. r. BllAGWATI OXYGEN LTD. [TA RUN CllATTER.IEE. J.]        923
           "(i) CIF value of JY 128.66 million                Rs.1,40,23,940/-             A
           (ii) Handling charges @ 5% of CIF-                 Rs. 7,01,198/-

           (iii) Import Duty @ 80% (based on
                                Project Import)               Rs. I, 12.I 9, 152/-
                                                                                           B
           (iv) REP Licence premium                           Rs.     5,00,000/-



.f
                                                 Total        Rs.2,64,44,290/-"
                                                                                           c
            16. In the said statement of claim the total value of the order worked
     out as imported components (Rs.264.44 lacs) plus indigenous components
     (~s.50 lacs) plus erection and commissioning (Rs.15 lacs) comes to Rs.329.44
     lacs. But the value was kept at Rs.347.40 lacs, i.e., a cushion money of Rs.18 D
     lacs approximately was provided for securing the forward cover for foreign
     exchange and other variations.

           17. In paragraph 21 of the said statement of claim, the respondent stated
     that under the aforesaid order, the appellant was required to supply indigenous
     components plants and machinery as set out in Clause 2.1.2 to 2.3.4 of the E
     order for a sum of Rs.50 lacs. The appellant further stated that the indigenous
     supply was not subjected to variation as per the order. The appellant contrary
     to and in breach of the said order raised invoices for a sum of
     Rs.67,95,710/- against indigenous supply and realized an excess amount of
     Rs.17,95, 710/- from the respondent. Therefore, the respondent claimed refund
     ofRs.17,95,710/- from the appellant.                                            F
            18. According to Mr. Sorabjee, the learned Arbitrator had misconducted
     himself in passing the award under Section 30(l)(a) of the Act and thus the
     award was liable to be set aside so far as Claim No.9 (Award No.9) of the
     Arbitrator is concerned. According to Mr. Sorabjee, the award in respect of G
     Award No.9 is contrary to the findings of the learned Arbitrator and liable to
     be set aside as it amounted to judicial misconduct. As noted herein earlier,
     purchase order dated      5th June, 1990 provided for a lump sum price of
     Rs.347.40 lacs subject to variation of importation of the contract and exchange
     rates. He further submitted that since price was a lump sum amount no
                                                                                           H
    924                     SUPREME COURT REPORTS                    12007] 3 S.C.R.

A specific price could be allotted to a particular item. He contended that the
    value of Rs.50 lacs and Rs.15 lacs mentioned against indigenous .supply
    under Clause 4.4 of the P.O. and against erection and commissioning mentioned
    in Clause 4.5 of the P.O. was not appearing as a component of price but
    appearing as "terms of payment" (4.0 of P.O.). Accordingly, Mr. Sorabjee
    sought to contend that the Arbitrator had gone beyond his jurisdiction in
B   awarding Rs.50 lacs and Rs.15 lacs, mentioned against indigenous supply and
    against erection and commissioning, as the same was not appearing as
    'component of price'. Therefore, he had misconducted himself in awarding the
    amount in respect of Av.ard No.9 (Claim No. 9 of the Statement Of Claim). In
    support of this contention, Mr. Sorabjee relied on a decision of this Court in
C   K.P. Poulose v. State of Kera/a, [1975] 2 SCC 236. Mr. Sorabjee particularly
    relied on para 6 of the judgment and submitted that the Arbitrator was guilty
    of legal misconduct as he had gone beyond his jurisdiction to pass an award
    on Claim No.9.

          19. This submission of Mr. Sorabjee was contested by Mr. Bhaskar P.
D Gupta, learned Senior Counsel, appearing on behalf of the respondent. Mr.
  Gupta contended that considering the terms of the contract, it cannot be said
  that the Arbitrator had acted beyond his jurisdiction in passing the award in
  respect of Claim No.9. So far as the decision of this Court, relied on by Mr.
  Sorabjee, is concerned, Mr. Gupta submitted that this decision cannot be
E applied in the facts and circumstances of the present cas'e. In that decision,
  according to Mr.Gupta documents produced before the Arbitrator were contrary
  to the award passed. In this connection, Mr. Gupta had also drawn our
  attention to the fact that the arbitrator in that case had ignored two very
  material documents resulting in miscarriage of justice. If we read para 6 of this
  decision carefully we will find that the princi pie which was laid down in the
F decision was that an award could be set aside on the ground that the
  arbitrator had misconducted himself when it was found that the arbitrator on         ·-\ ·
  the face of the record arrived at an inconsistent decision even on his own
  finding or arrived at a decision by ignoring very material documents which
  throw abundant light on the controversy to help in arriving at a just and fair
  decision. Keeping this principle in mind, this court held that the arbitrator had
G misconducted the proceedings in that case. ·
                                                                                       'l
          20. This is not the position in the present. case. For deciding this
    question, it would be necessary for us to look into the P.O. Clause 4.0
    contains "terms of payment". Clause 4.4 of the P.O. contains the indigenous
H
            BOC INDIA LTD.>. BHAGWATI OXYGEN LTD. [TARUN CHATTERJEE, J.]      925
     supplies which clearly indicates Rs.50 lacs would be the advance at the rate A
     of I0% against the date of order within 30 days and I 0% advance within three
     months and 80% advance against proforma invoice before dispatch. Clause
     4.5 of the terms of payment provi.des for erection and commissioning which
     indicates Rs.15 lacs in respect of which 10% advance against order, I 0%
     advance on opening of site, 70% on pro rata on monthly basis, I0% on B
     completion of erection and commissioning. The Arbitrator had taken into
     consideration the claim of the respondent on indigenous supplies. He had
     also taken into consideration the total value of the contract which was
     Rs.34 7.40 lacs.

            21. A bare perusal of the award of the Arbitrator would show that he C
     had considered the figure of 17,95,710/- which is included in the lump sum
     contract price as consideration payable to the respondent for services rendered
     by it towards importation of plants components. From the award it will also
     be evident that in respect of the claim of Rs.17,95,710/- against indigenous
     supply attention was drawn to the works given in para 10 [a], 10 [b] and 10 D
     [c] of the statement of claim. Ifwe assign individual value to the individual
     jobs, the total works out to Rs.3,29,44,290/- leaving a balance of Rs.17,95, 710/
     -.

            22. The learneC: Arbitrator in his award also considered that the break-
     up was an admitted position which would appear from para IO[ c] of the E
     Statement of Claim and the sum of Rs.17,95,710/-, the appellant had recovered
     under the bill issued against indigenous supply and the respondent paid the
     amount without any objection. While the Arbitrator has considered the fact
     that the appellant had realised the differential amount of Rs.17,95,710/- from
     the respondent against indigenous supply, it cannot be -said to mean that the F
     value of indigenous supply had gone up from Rs.50 lacs to Rs.67,95,710/- as
     according to the terms of the contract the value of indigenous supply remained
     at Rs.67,95,710/- and the appellant realised the differential amount of
     Rs.17,95, 710/- against indigenous supply. Accordingly the Arbitrator was
     justified in holding that the said sum of Rs.17,95, 710/- was on account of
     expenses that might have been incurred by the respondent in executing the G
     contract.
)•
          23. In the case of Trustees of the Port of Madras v. Engineering
     Construction Corporation Ltd., AIR (1995) SC 2423, while this Court dealing
     with a situation when an award can be set aside under Section 30 of the H
     Arbitration Act
    926                         SUPREME COURT REPORTS                 [2007] 3 S.C.R.

A         held as under:
                                                                                                    .
            "The above decisions make it clear that the error apparent on the face
            of the award contemplated by Section 16(1)(c) as well as Section 30(c)
            of the Arbitration Act is an error of law apparent on the face of th1~
            award and not an error of fact. It is equally clear that an error of law
B           on the face of the award means an error of law which can be discovered
            from the award itself or from a document actually incorporated therein.
            A note of clarification may be appended viz., where the parties choose
            to refer a question of law as a separate and distinct matter, then th(:     '    .
            Court cannot interfere with the award even if the award lays down a1
c           wrong proposition of law or decides the question of law referred to
            it in an erroneous fashion. Otherwise, the well settled position is that
            an arbitrator "cannot ignore the law or mis-apply it in order to do what
            he thinks is just and reasonable." (See Thawardas Perumal v. Union
            ofIndia (1955] SCR 48: (AIR 1955 SC 468)."
D          24. In paragraph 20 of the said decision this Court also held that the
    proposition that emerges is that in the case of a reasoned award, the Court
    can interfere if the award is based upon a proposition of law which is
    unsound in law and that the erroneous proposition of law must be established             1·
    to have vitiated the decision. It has also been held in that decision that the
E error of law must appear from the award itself or from any document or note
    incorporated in it or appended to it. This Court also held that it was not
    permissible to travel and consider materials not incorporated or appended to
    the award. So far as the facts of the present case are concerned, we do not
    think that the award of the Arbitrator can at all be interfered with as the award
F . was not based upon either a proposition of law which is unsound or an
    erroneous proposition of law was established to have vitiated the decision.
    As noted herein earlier, the Arbitrator had considered all aspects of the matter
    including the terms of the contract and all the materials on record and the
    statement of claim and has come to a conclusion of fact. Such being the
    position, we cannot but hold that the award was not based upon a propositiqn
G of law which is unsound or an error of law must have appeared from the award
    itself or from any document or note incorporated in the award or appended
    to it.
                                                                                            • -1,

          25. That apart, according to the Arbitrator, this figure was nothing but
H


                       ..   '
                   BOC INDIA LTD.,.. BHAGWATI OXYGEN LTD. (TA RUN CHATTERJEE. J.]     927

            a mark up wh.ich the parties agreed to keep in the contract for rendering of A
            service towards importation of plant components from Japanese supplies. The
            appellant had realized this difference amount of Rs. 17 lacs from the respondent
            against indigenous supplies. Therefore, it was not the case that the arbitrator
            had misconducted himself in passing the award by ignoring to consider
            material documents, which had thrown light on the controversy raised by the
                                                                                              B
            parties. As noted herein earlier, the arbitrator had looked into the terms of the
            contract, arbitration clause and the statement of claim of the respondent
   ~
            disputed by the appellant. It was not the case that the arbitrator had decided
    .....
            erroneously a question of law referred to him but on consideration of the
            terms of contract and statement of claim came to a conclusion that Claim No.
            9 of the respondent should be awarded in its favour. Such being the position,   c
            we do not find any reason to interfere with the award of the arbitrator which
            was passed on consideration of all material put on record.

                   26. In this view of the matter, it is not open to the court to set aside
            the award on the ground that the learned Arbitrator had, while continuing
                                                                                             D
            with the proceeding, acted beyond his jurisdiction and violated the contract
            while awarding Rs. 17,95,710/- in the form of Award No.9. In our view, this
 -)
            cannot be said to have an award, which is contrary to the contract entered
            into by the parties. It is also not the case where the learned Arbitrator had
            failed to consider material documents produced by the parties for arriving at
            a right decision. On the other hand as noted herein earlier, we are of the E
            considered view that the Learned Arbitrator had duly considered the statement
            of claim and the terms and conditions of the contract and the material documents
            produced by the parties, which were available on record, and came to a
            conclusion rightly in favour of the respondent. The Learned Arbitrator also
            came to a conclusion that the aforesaid figure of Rs. 17,95,710/-, was included F
- ,J..      as lump sum contract price as consideration payable to the respondent for
            service rendered by them for importation of plants and components. In any
            view of the matter, when the Arbitrator had taken a plausible view on
            interpretation of contract, it is not open to the court to set aside the award
            on the ground that the Arbitrator had misconducted himself in the proceedings
            and therefore, the award was liable to be set aside.
                                                                                             G
 J·                27. In !ndu Engineering and Textile Limited v. Delhi Development
            Authority, [2001] 5 SCC 691 this court laid down a principal when the cou.rt.
            cou Id set aside an award in the exercise of its powers under Section 30 o( the       ·'""""
            Act. This court in the said decision held that when a plausible view had been H
    928                     SUPREME COURT REPORTS                    [2007) 3 S.C.R.

A taken by the arbitrator and unless the award of the arbitrator was vitiated by
    a manifest error on the face of the award or was wholly improbable or
    perverse, it was not open to the court to interfere with the award within the
    statutory interpretation set out in Section JO of the Act.

          28. That apart, the amount of Rs.17,95,710/- was recovered by the
B   appellant under the bill issued against indigenous supplies and amount were
    paid without any objection by the respondent. Such being the position we
    are unable to agree with Mr. Sorabjee that the award was liable to be set-aside
    on the aforesaid ground.
                                                                                       .   .
C         29. We, therefore, do not find any merit in this appeal. The appeal is
    dismissed without any order as to costs.

    N.J.                                                       Appeal dismissed.




                                                                                           ..




                                                                                           ·~


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.