Created byFuzzy Cloud

Supreme Court of India

BHARAT SEWA SANSTHANversusU.P. ELECTRONICS CORPORATION LTD.

Citation
2007 INSC 875
Decided
29 August 2007

Holding

The Supreme Court held that the dispute must be referred to arbitration under the arbitration clause and that Article 142 cannot be invoked to override the Arbitration and Conciliation Act, 1996.

Summary

Bharat Sewa Sansthan, a charitable society, leased premises to U.P. Electronics Corporation Ltd. under a lease that contained an arbitration clause. The society sued for recovery of rent arrears, water and sewerage taxes, and interest, while the corporation moved for reference of the dispute to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996. The trial court rejected the corporation's applications, but the Allahabad High Court allowed the Section 8 application and directed the matter to arbitration, taking photocopies of the lease into record. The society appealed to the Supreme Court, seeking relief under Article 142 of the Constitution, arguing that arbitration would delay justice. The Court held that the existence of a valid arbitration clause makes the dispute arbitrable and that Article 142 cannot be used to bypass the statutory arbitration procedure, and therefore dismissed the appeal, affirming the High Court's order.

Issues considered

  • The dispute is arbitrable under the arbitration clause in the lease agreement.
  • Whether the Supreme Court can, under Article 142 of the Constitution, grant relief on rent arrears, taxes and interest notwithstanding the existence of an arbitration agreement.
  • Whether photocopies of the lease agreement may be admitted under Section 8 of the Arbitration Act to ascertain the arbitration clause.

Legislation cited

Subjects

ArbitrationSection 8Article 142Lease agreementArbitration clauseRent arrearsWater and sewerage taxInterestSupreme CourtCivil appeal

Judgment

                       BHARATSEWASANSTHAN                                          A
                                  v.
                 U.P. ELECTRONICS CORPORATION LTD.

                                AUGUST 29, :2007

           (H.K. SEMA AND LOKESHWAR SINGH PANTA, JJ.)                              B


      Arbitration Act, .1940:

       s.8-Photocopies of the lease agreement could be taken on record
,uls. 8 for ascertaining the existence of arbitration clause.                      C
      Object of Act-Discussed.

      Constitution of India, 1950:

      Article 142-Arbitration agreement-Suii' for recovery of arrears of D
rent and ejectment of respondent~Corporaiion from demised premises-
Respondent-Corp·oration seeking appointment of arbitrator in view of
arbitration agreement-Rejected by District Judge-Writ petition allo'Wed by
High Court-Challenge against-Held, it is not a fit case to grant relief to
appellant-Sansthan as claimed by it which is vehemently disputed by E
resporident-Corporation-Dispute raised by parties .10 he adjudicated by
arbitrator on its own merit in accordance with law-Arbitration Act, 1940-
S.8(1).

      Article I 42-Power under-Scope and ambit of-Discussed.
                                                 .                                 .F
      In November 1980, the respondent-Corporation took from the appellant-
Sansthan an area measuring 14,925 sq. ft. on monthly rent under a lease
agreement. In June 1981, the respondent-Corporation took an additional
accommodation measuring 3000 sq. ft. area on monthly rent for setting up
Office of its subsidiary company. The appellant-Sansthan filed suit for recovery
of arrears of rent and ejectment of the respondent-Corporation from the            G
demised premises. In the trial Court, the respondent-Corporation preferred
two applications, i.e. one under s. 8(1) of the Arbitration Act and second under
Order XI Rule 14 CPC for summoning of the original lease deed from the
appellant-Sansthan. The Additional District Judge rejected both the

                                      533                                          H
    534                       SUPREME COURT REPORTS                  [2007] 9 S.C.R.

A applications.
          The respondent-Corporation filed writ petition before the High Court.
    It was the specific case of the respondent-Corporation before the High Court
    that the original agreements are in the possession of the appellant-Sansthan,
    and it had placed on record the photocopies of the agreements along with an
B   application under s. 8(1) of the Arbitration Act. ·

          The High Court allowed the writ petition holding that the Trial Court
    has wrongly rejected the application under s.8 of the Arbitration Act as the
    subject-matter of the suit is arbitral with further direction to the Additional
C   District Judge to refer the matter to .arbitration. Hence the present appeaL

          The appellant-Sansthan contended that this Court in exercise of its
    jurisdiction under Article 142 of the Constitution of India for doing complete
    justice to the appellant-Sansthan is empowered to pass an order of payment
    of arrears towards water and sewerage tax and payment of interest at the rate
D   of 12% p.a. on the arrears of rent in terms of the agreement and that sending
    the matter at this stage to the Arbitrator will prolong the agony of the
    appellant-Sansthan in getting its legitimate claims settled as per the
    calculation statement submitted before this Court in terms of its interi8'           >
    orders.

E         The respondent-Corporation contended that the balance amount of
    arrears of rent, payment of water and sewerage tax and the amount of interest
    as claimed by the appellant-Sansthan in its calculation statement cannot be
    decided by this Court in the absence of any satisfactory and tangible evidence
    appearing on record of this appeal and in terms of the clause of the Agreement,
    this Court will be slow in exercise of its jurisdiction under Article 142 of the
F   Constitution of India as the parties are governed by the procedure of the          -'"If.
    Arbitration Act, which is speedy and less expensive for effectin adjudication
    of the dispute in issue.

          Dismissing the appeal, the Court

G          HELD: 1. The High Court, has rightly held that the photocopies of the
    lease agreen:ients could be taken on record under s.8 of the Arbitration Act,
    1940 for ascertaining the existence of arbitration clause. Thus, in terms of
    the arbitration clause contained in the lease agreement the dispute raised by
              I.   ·-   -·-     •


    the appellant-Sansthan against the respondent-Corporation is arbitral.
H                                                            (Para 21) )545-F, GI
                      BHARATSEWASANSTHAN". U.P.ELECTRONICSCORPN.LTD.               535

             2. The nature and ambit of the power of this Court under Article 142 of       A
       the Constitution of India, is meant to do complete justice between the litigating
       parties, but at the same time the power is conceived to meet the situations
       which cannot be effectively and appropriately tackled by the existing provisions
       oflaw. Human and equitable approach should be balanced to do complete justice
       to both the parties and not be tilted in favour of either party without ignoring
       the statutory provisions. This Court in exercise of its jurisdiction can grant      B
       appropriate relief where there is some manifest illegality, or where there is
       manifest want of jurisdiction,or where some palpable injustice is shown to

•      have resulted to the parties. (Para 22) (546-B, CJ

             3. In the light of factual aspects, the claim relating to balance arrears     C
       of rent, balance arrears of water and sewerage tax and rate of interest on
       payment of arrears of rent raised by the appellant-Sansthan in its calculation
       statement filed before this Court is at variance with the calculation statement
       submitted by the respondent-Corporation. The respondent-Corporation has
       denied the payment of interest to the appellant-Sansthan. The disputed claims
       can be appropriately tackled and adjudicated upon by the Arbitrator in terms        D
       of the arbitration clause. The main objectives of the Arbitratioh Act is to make
       provision for an arbitral procedure which is fair, efficient and capable of
       meeting the needs of the specific arbitration and to minimise the supervisory
       role of courts in the arbitral process and to permit an arbitral Tribunal to
       use mediation, conciliation or other procedures during the arbitral                 E
       proceedings in settlement of disputes, etc. This Court ordinarily will not be
       obliged to bypass the provisions of the Arbitration and Conciliation Act, 1996
       in exercise of its power and jurisdiction under Article 142 of the Constitution
       of India. {Para 23) {546-C, D, E, FJ

,.._         4. In the backdrop, it is not a fit case to grant relief to the appellant-    F
       Sansthan as claimed by it in its calculation statement which is vehemently
       disputed by the respondent-Corporation. Therefore, the contention of the
       appellant-Sansthan that this Court can grant the payment of balance amount
       of arrears of rent and arrears of water and sewerage tax and interest on
       arrears of rent detailed in calculation statement submitted before this Court,
       does not merit acceptance. The dispute raised by the parties shall be               G
       adjudicated upon by the Arbitrator(s) on its own merit in accordance with law.
                                                    (Paras 24 and 28) {546-G; 547-D\

             CIVIL AP PELLATE JURISDICTION : Civil Appeal No. 2016 of 2006.

             From the final Judgment and Order dated 14.09.2004 of the High Court          H
    536                      SUPREME COURT REPORTS                    [2007] 9 S.C.R.

A of Judicature at Allahabad sitting at Lucknow in Writ Petition No. 3388 of2004
    (M/S).

          Shanti Bhushan, Sumeet Sharma, Sanjai K. Pathak and Prashant Bhushan
    for the Appellant.

B        Manoj Swarup and Lalita Kohli (for Mis Manoj Swarup & Co.) for the
    Respondent.

          The Judgment of the Court was delivered by



c
         LOKESHWAR SINGH PANT A, J. I. Bharat Sewa Sansthan has filed
    ' appeal challenging the final judgment and order dated 14.09.2004 of the
  .this
                                                                                         •
   learned Single Judge of the High Court of Judicature at Allahabad, Lucknow
   Bench, in Writ Petition.No. 3388/2004(MS) by which the order of the learned
   Additional District Judge (Special Judge, E.C. Act) Lucknow, dismissing the
   application filed by the U.P. Electronics Corporation Limited [hereinafter referred
   to as the 'respondent-Corporation'] under Section 8 of the Arbitration and
D Conciliation Act, 1996, has been set aside with direction to the learned
   Additional ~istrict Judge to refer the matter to arbitration and both the parties
   are directed to appoint their Arbitrator as per the arbitration clause in the         :>
   lease agreement.

             2. Backgrou,nd facts in a nutshell are as follows:
E
          13harat Sewa Sansthan [hereinafter referred to as the 'appellant-Sansthan]
    is a charitable society registered under the Societies Registration Act. The
    main object of the appellant-Sansthan is to work for the social, economic,
    educational and cultural upliftment qf the people. The appellant-Sansthan is
F   the sole and excJusive owner of multi-storeyed building known as "Chandra
    Bhanu Gupta Smarak Nav Chetna Kendra" located at No. l 0, Ashok Marg in
    the city of Lucknow (U -~ .). On 11.11. I 980, the respondent-Corporation took
    for office accommodation an area measuring 14,925 square feet on the first
    floor of the multi-storeyed building of the appellant-Sansthan on monthly rent
    of Rs. 47,760/- @ Rs. 3.20p per square foot, which comprised (a) basic rent
G   @ Rs. 2/- per square foot amounting to Rs. 29,850/- and (b) the balance
    amount of Rs. 17,910/-@ Rs. l.20p per square foot towards the ancillary
    services provided for the said accommodation in the form of elevators (lifts),
    a designated area for parking of vehicles, lights for public and common              '::>-
    passages and sewerages etc. under a lease granted by the appellant-Sansthan
H   to the respondent-Corporation on 01.12.1980.
BHARATSEWA SANSllIAN ''· U.P. ELECTRONICSCORPN. LTD. [LOKESHWAR SINGH PANTA, J.J 537


      3. It is the case of the appellant-Sansthan that in the month of June,           A
1981 the respondent-Corporation expressed its requirement to the appellant-
Sansthan for some additional accommodation on the first floor of the building
adjoining to the accommodation which the respondent-Corporation had earlier
occupied for setting up a Marketing Office and a Registered Office of Mis
Uptron India Limited, which is the subsidiary of the respondent-Corporation.           B
Mis Uptron India Limited was established for the manufacturing of electronic
equipments and components, such as the television, computer, capacitors,
process control, EPABX systems etc. It was mutually agreed between the
appellant-Sansthan and the respondent-Corporation that additional
accommodation measuring 3000 sq. ft. in area shall be leased out to the
respondent-Corporation w.e.f. 25.06.1981 on a monthly rent of Rs. 9,7501- i.e.         C
@Rs. 3.20 per sq. ft., which comprised of (a) basic rent@ RS. 21- per sq. ft.
amounting to Rs. 60001- and (b) balance amount of Rs. 37501-@ Rs. 1.20p.
per sq. ft. towards such ancillary charges as has been included in the case
of the lease in respect of the first portion of the accommodation let out to
the respondent-Corporation.
                                                                                       D
      4. It is further the case of the appellant-Sansthan that the tenancy of
both the portions of the accommodation let out to the respondent-Corporation
had continued without any interruption from the respective dates of
commencement of lease, subject to periodical escalation of the rent including
other charges on the basis of mutual agreement with the result that the                E
consolidated monthly rent of the two portions of the accommodation let out
to the respondent-Corporation had risen to Rs. 79,083.75p. (Rupees Seventy
nine thousand and eighty three and seventy five paise only) well before
29.07.1999, on which day the lease was determined. The appellant-Sansthan
on 10.03.2000 filed Suit No. 1612000 for eviction and recovery of arrears of rent
against the respondent-Corporation in the Court of learned Additional District         F
Judge (Special Judge, E.C. Act) at Lucknow. In the said suit, the respondent-
Corporation presented two applications before the Trial Court before filing of
the written statement. The first application being C-12 was moved under
Section 8(1) of the Arbitration and Conciliation Act, 1996 (for short "Arbitration
Act") and the second application No.C-17 was filed under Order XI Rule 14
of the Civil Procedure Code for summoning of the original lease deeds from             G
the appellant-Sansthan.

     5. Learned Additional District Judge (Special Judge, E.C. Act), Lucknow,
had rejected both the above-said applications. Being aggrieved, the
respondent-Corporation has assailed the order of the Trial Court by way of             H
    538                    SUPREME COURT REPORTS                     [2007] 9 S.C.R.

A Writ Petition before the High Court. The learned Single Judge of the High
    Court allowed the writ petition and held that the learned Trial Court has
    wrongly rejected the application under Section 8 of the Arbitration Act as the
    subject-matter of the suit is arbitral with further direction to the learned
    Additional District Judge (Special Judge, E.C. Act), Lucknow, to refer the
B   matter to arbitration and both the parties may appoint their Arbitrator as per
    the arbitration clause in the lease agreement.

          6. Feeling aggrieved, the appellant-Sansthan has filed this appeal, by
    special leave, challenging the correctness and validity of the impugned
    judgment and order of the learned Single Judge of the High Court.
c        7. When the matter came up before the Court on 24.03.2006, this Court
    passed the following orders:-

            "I.A. No. 2 of 2005 is allowed.

            Leave granted.
D
            Since this appeal pertains to a charitable institution and appears to be
            an urgent matter, the appeal shall be placed on Board for expeditious
            final hearing on 11th July, 2006."

         8. It appears from the record that the appeal was called on for hearing
E   on 11.07.2006, when the following-order came to be passed:-

            "The case was argued at length by Mr. Shanti Bhushan, learned
            Senior Counsel for the appellant. We also heard reply on certain
            preliminary issues from Mr. Manoj Swarup, learned counsel for the
            respondents. We also permit Mr. Manoj Swamp to file additional
F           documents in this appeal"

            In the meanwhile, the respondent- U.P. Electronics Corporation Limited
            shall handover peaceful vacant possession of the area which was
            under the occupation of Mis. Uptron Limited, sub-lessee of respondent
            No. 1 herein, within one week from today. This Court will decide the
G           arrears of rent payable by Uptron Limited at the next hearing. In the
            meantime, U.P. Electronics Corporation Limited shall pay entire arrears
            of rent for the portion in their occupation at the admitted rate.

            Since some details are required, we direct both the parties to file a
            memo of calculation before this Court so that this Court will be in a
H
BHARATSEWASANSTHAN 1·. U.P. ELECTRONICSCORPN. LTD. [LOKESHWARSINGHPANTA,J.J 539


       position to pass a detailed order. Treat this matter as part-heard.         A
        Post this matter at 2.00 p.m. on 12th July, 2006."

      9. On 12.07.2006, this Court passed a detailed order, which reads as
follows:-
                                                                                   B
       "After hearing both the parties, we passed the following order on l lth
       July,2006.

       "The case was argued at length by Mr. Shanti Bhushan, learned
       Senior Counsel for the appellant. We also heard reply on certain
       preliminary issues from Mr. Manoj Swarup, learned counsel for the           c
       respondent. We also permit Mr. Manoj Swarup to file additional
       documents in this appeal"

       In the meanwhile, the respondent U. P. Electronics Corporation Ltd.
       shall handover peaceful vacant possession of the area which was             D
       under the occupation of Mis UPTRON LTD., sub-lessee of respondent
       No. I herein, within one week from today. This Court will decide the
       arrears of rent payable by the UPTRON Ltd. at the next hearing. In
       the meantime, U. P. Electronics Corporation Ltd., shall pay entire
       arrears of rent for the portion in their occupation at the admitted rate.   E
       Since some details are required, we direct both the parties to file a
       memo of calculation before this Court so that this Court will be in a
       position to pass a detailed order. Treat this matter as part-heard.

        Post this matter at 2.00 PM on 12th July, 2006."                           F
       As directed Mr. Manoj Swarup, learned counsel for the respondent-
       Corporation placed before us a Fax Message from U.P. Electronics
       Corporation Limited in regard to the total rent payable to the appellant
       upto 30.06.2006. The Fax Message reads thus:
                                                                                   G
       "U.P. ELECTRONICS CORPORATION LTD.
       Total rent payable to BSS upto 30.06.2006




                                                                                   H
         540                   SUPREME COURT REPORTS                     (2007] 9 S.C.R.

     A    Financial        Rent               UIL           UPLC          TDS Paid
          year
          1                 2                  3              4            5
          Upto           3556068.75          2367966.75     1188104.00    218145.00
          31.3.2001
     B    2001-2002      948285.00           558742.50      389542.50     85700.00
          2002-2003      948285.00           558742.50      389542.50     85700.00
          2003-2004      948285.00           558742.50      389542.50     85700.00
          2004-2005      948285.00           558742.50      389542.50     85700.00
          2005-2006      948285.00           558742.50      389542.50     85700.00
     c
          l.04.06-        133335.00                  0      133335.00             0
          30.6.06
          TOTAL          8430830.75          5161682.25     3269155.50    646650.00

                 Frortl 1.4.2006 to 30.6.2006@ Rs. 44445/- per month (50% proposed to
     D           be retained)

                 UPLC Liability - Rs.2622505.50 (payable as per area occupied and          >
                 approved by the Management)
                                                            UPLC           UIL
     E    Rent of Front Portion ·
          64923.75 x 12 =Area 14925@            779085.2    389542.50      389542.50
          Rs. 4.35 per sq. ft.
          Rent of Rear Portion
           14100 x 12 =Area 3000@ Rs.           169200        -            169200.00
          4.72 per sq. ft. (exclusively in
                                                               .
     F
          the use of UPTRON)
          Total Rent per annum                  948285.00    389542.50     558742.50

          According to the learned counsel for the appellant, there is some discrepancy
          in regard to the calculation of rent payable as per the agreement. We,
     G    therefore, as an interim measure, without going into the correctness of the
          statement now placed before us, direct the U.P. Electronics Corporation
          Limited to pay a sum of Rs. 32,69.155.50 to the appellant herein within four
,.        weeks from today. The U.P. Electronics Corporation Limited has also deducted
          the tax in a sum of Rs. 6,46,650/-. Thus, as per the fax message, the rent is
     H    calculated upto 30.6.2006. We, therefore, direct U.P. Electronics Corporation
         ,
        __




             BHARAT SEWA SANSTHAN v. U.P. ELEClRONICS CORPN. LTD. [LOKESHW AR SINGH PANTA, J.)541

              Limited to pay rent from 1st July, 2006 to the appellant herein for the actual        A
..,..         area in their occupation as per the tenns of the agreement.

                     The rent shall be paid on or before I 0th of every succeeding month
                     without any default. The respondent shall hand over peaceful vacant
                     possession to the appellant herein within one week from today the
                     portion in the occupation of UPTRON India Limited, a sub-lessee of             B
                     respondent No. I herein, which according to respondent no. l is 60%
                     of the total area namely, 17,925 sq. ft. This Court will decide the arrears
                     of rent payable by the UPTRON India Limited at the time of final
                    ·hearing.

                     It is also stated by the learned counsel for the appellant that U.P.           C
                     Electronics Corporation Limited has not paid the electricity charges
                     and water and sewerage taxes to the authorities concerned in full. The
                     U.P. Electronics Corporation Limited is directed to pay the entire
                     arrears to the authorities concerned within four week from today.

                     This order is passed as an interim measure without prejudice to the            D
                     rights and contentions of both the parties. It is open to· both the
                     parties to file additional documents.

                     Treat this matter as part-heard. Post after six weeks for reporting
                     compliance of the aforesaid directions. Pendency of this appeal before
                     this Court will not prevent the parties from settling the matter amicably."    E
                   10. The appeal was listed for hearing on 08.09.2006, when further
             following order was recorded:-

                     "Learned senior counsel for the appellant has placed before us a fresh
                     calculation memo with the Statement of Accounts duly stamped by a              F
                     Chartered Accountant. Mr. Krishnamani, learned senior counsel
                     appearing for the respondent seeks time to respond to the Memo of
                     Calculation filed now. Three weeks' time is granted for the purpose.
                     The respondent is directed to file reply to this Calculation Memo
                     within the said time. Parties will discuss further in regard to the            G
                     possession and re-adjustment of the areas and file reply thereto.

                     Further directions will be made on the next adjourned date of hearing."

                   11. On 7.11.2006, upon hearing the counsel on both sides, this Court
             made the following order:-
                                                                                                    H
    542                   SUPREME COURT REPORTS                     [2007] 9 S.C.R

A          "Memo of Understanding between the parties to this appeal filed in
           this Court, pursuant tq this Court's order dated 8.9.2006, is taken on
           record. A rough sketch plan is also attached to the Memo of Settlement.
           Clause (c) of the Memo says that the respondent, namely, U.P.
           Electronics Corporation Limited will vacate the portion marked in pink
           as per the map within two weeks frnm date of Memo of Understanding
B          i.e. I 0.10.2006. It is now represented by Mr. Prashant Bhushan, learned
           counsel for the appellant that in spite of the undertaking under clause
           (c) of Memo of Settlement, the U.P. Electronics Corporation Limited
           have not vacated the entire portion marked in pink and also constructed
           wall separating the pink and green marked portion. Since the
                                                                                      ...
c          undertaking has not been complied by Mis. U.P. Electronics Corporation
           Limited further time is given to them to comply with the undertaking
           by three weeks from day. The clause (c) of the Memorandum shall be
           complied with in full and the entire portion shall be handed over to
           the appellant within that time and also the construction of the wall
           shall be completed in time.
D
           When the matter came up for hearing on 8.9.2006, the learned senior
           counsel appearing for the respondent had sought some time to respond
           to the Memo of Calcutat-ion filed and that three weeks' time was
           granted for the purpose. So far no response ha5 been filed to the
           Memo of Calculation. The r~spondent is directed to file the response
E          to Memo of Calculatioh within two weeks from today.

            Call after four weeks for reporting compliance."

          12. Again on 26.02.2007, the following order came to be passed:-

F           "Mr. Prashant Bhushan, learned counsel for the appellant placed
            before us a Statement in respect of the amount due in regard to 60%
            area occupied b y the respondent and their subsidiaries upto June,
            2006. A copy of the said Statement has also been furnished to the
                                                                                       I-
            learned counsel for the respondent. Post after two weeks for filing
            response by the respondent."
G
           13. In terms of the above extracted interim orders passed by this Court
    on a number of hearings, the appellant-Sansthan submitted its statement of
    accounts in which a total sum of Rs. 95,09,467.50 has been claimed as arrears
    of rent for the Front Block and the Tower Block, measuring 17,925 sq. ft. of
H   area, out of which a sum of Rs.32,69, 155.50 in terms of interim order dated
BHARAT SEWA SANSlHAN v. U.P. ELEClRONICS CORPN. LTD. [LOKESHWAR SINGH PANTA, J.] 54J


12.07.2006 passed by this Court has been paid to the appellant-Sansthan by             A
the respondent-Corporation for 40% area in its occupation. In addition to the
arrears of rent from July 1997 to June 2006, the appellant-Sansthan has
claimed a sum ofRs.6,46,645.00 in regard to TDS Certificates. Further, a sum
ofRs.13,38,492.43 has been claimed on account of water & sewerage tax from
July 1997 to June 2006. The appellant-Sansthan has also claimed a sum of
Rs.40,95,867/- on account of interest at the rate of 12% p.a. on the arrears of        B
rent in relation to 15,925 sq. ft. area which was let out to the respondent-
Corporation in the year 1980.

       14. In response to the order of this Court, the respondent-Corporation
has filed affidavit dated 18,. 11.2006 along with details of calculations of arrears   C
of rent of 40% area; arrears of rent of 60% area and also details of calculation
of amount for water & sewerage tax. The stand of the respondent-Corporation
in the affidavit is that in pursuance to the interim order of this Court dated
12.07 .2006, a sum of Rs.32,69, 155.50 towards arrears of rent (Rs.25,95,310.50
as rent and Rs.6, 73,845.00 as TDS] for the 40% portion, which was actually
occupied by the respondent-Corporation, has been paid to the appellant-                D
Sansthan. The respondent-Corporation stated that as per its statement of
calculation and after deduction of the amount already paid in pursuance to
the interim order of this Court, the amount payable in respect of the portion
which was under occupation ofM/s Uptron India Limited and the possession
thereof has already been handed over to the appellant-Sansthan (subject to             E
the adjustment made in the MOU dated 10.10.2006) comes to Rs.75,47,368.50
which is more than what has been calculated and indicated by the appellant-
Sansthan in paragraph 6 of its affidavit dated 06.09.2006 and an amount of
Rs.6,46,645.00 is taken into account twice and shown as paid in excess.

      15. 1t is also submitted that during the pendency of this case and in            F
compliance of order dated 12.07.2006, another sum ofRs.3,97,161.00 was also
paid to the appellant-Sansthan. Thus, the total payment made by the
respondent-Corporation to the appellant-Sansthan towards water & sewerage
tax comes to Rs.5,95,238.80 for the area which is in possession of the
respondent-Corporation. The respondent-Corporation contended that as per
the calculation sheet annexed with the affidavit-in-reply, the balance amount          G
comes to Rs.24,558.20 towards water & sewerage tax for the portion in
possession of respondent-Corporation, which is also tendered to the appellant-
Sansthan by Cheque No.275979 dated 12.10.2006 of Andhra Bank, Lucknow.
The balance amount of Rs.9,26,763.00 towards water & sewerage tax is due
in regard to the portion vacated by M/s Uptron India Limited and the                   H
    544                     SUPREME COURT REPORTS                      [2007] 9 S.C.R.

A   possession of that area has already been handed over to the appellant-
    Sansthan.

           16. The Divisional Incharge (Personnel), working in the respondent-
    Corporation in his reply affidavit to calculation statement filed by the appellant-
    Sansthan on 26.02.2007, states that in terms of the order dated 12.07.2006 of
B   this Hon'ble Court, the entire amount is paid in respect of the portion in
    possession of the respondent-Corporation. The possession of 60% area which
    was previously in use and occupation of M/s Uptron India Limited, which is
    a Sick Industrial Company, has already been given to the appellant-Sansthan
    and the payment of rent for the said area is not covered under the directions
C   of this Court. It is stated that the calculation chart submitted by the appellant-
    Sansthan showing the amount due and payable pertains to 60% portion for
    which rent was paid by Mis Uptron India Li!flited through the respondent-
    Corporation and the first part of the calculation chart filed by the appellant-
    Sansthan indicating total amount of Rs.66,74, 131.50 due, is in respect of 60%
    portion of the leased area. It is also stated that the respondent-Corporation
D   was always ready and willing to make payment of agreed rent for the portion
    under its occupation and, in fact, it had tendered the amount, which was not
    accepted by the appellant-Sansthan. It is also stated in the affidavit that
    Clause 1(3) of the lease agreement as alleged by the appellant-Sansthan is not
    applicable in the present case and as such no interest at the rate of 12%, as
E   claimed, is payable and the appellant-Sansthan has calculated the interest on
    total amount of rent payable in respect of total area including the one which
    was under use and occupation of M/s Uptron India Limited.

          17. We have heard the learned counsel for the parties and examined the
    material on record.
F
          18. Shri Shanti Bhushan, learned senior counsel appearing on behalf of
    the appellant-Sansthan, submitted that this Court in exercise of its jurisdiction ·
    under Article 142 of the Constitution of India for doing complete justice to
    the appellant-Sansthan is empowered to pass an order of payment of arrears
    towards water & sewerage tax and payment of interest at the rate of 12% p.a.
G   on the arrears of rent in terms of the agreement. He submitted that sending
    the matter at this stage to the Arbitrator will prolong the agony of the
    appellant-Sansthan in getting its legitimate claims settled as per the calculation
    statement submitted before this Court in terms of its interim orders.
                                                                                          >.
         19. Per contra, Shri Manoj Swamp, learned counsel for the respondent-
H   Corporation, submitted that the balance amount of arrears of rent, payment
BHARAT SEWA SANSTIIAN v. U.P. ELEC1RONICS CORPN. LTD. [LOKESHWAR SINGH PANTA, 1.) 545


of water & sewerage tax and the amount of interest as claimed by the                    A
appellant-Sansthan in its calculation statement cannot be decided by this
Court in the absence of any satisfactory and tangible evidence appearing on
record of this appeal. He next submitted that in terms of the clause of the
Agreement, this Court will be slow in exercise of its jurisdiction under Article
142 of the Constitution of India as the parties are governed by the procedure
of the Arbitration Act, which is speedy and less expensive for effective                B
adjudication of the dispute in issue.

      20. We have carefully considered the respective contentions of the
learned counsel for the parties.

       21. It is not in dispute that on 11.11.1980 the respondent-Corporation           C
took from the appellant-Sansthan an area measuring 14,925 sq. ft. on monthly
rent under a lease agreement. In June 1981, the appellant-Sansthan let out
additional accommodation measuring 3000 sq. ft. area on monthly rent for
setting up Marketing Office of M/s Uptron India Limited, which is the
subsidiary of the respondent-Corporation. The appellant-Sansthan filed suit             D
for recovery of arrears of rent and ejectment of the respondent-Corporation
from the demised premises. In the trial court, the respondent-Corporation
preferred two applications, i.e. one under Section 8(1) of the Arbitration Act
and second under Order XI Rule 14 CPC for summoning of the original lease
deed from the appellant-Sansthan. The learned Additional District Judge
(Special Judge, E.C. Act), Lucknow, has rejected both the applications. The             E
High Court in writ petition filed by the respondent-Corporation against the
order of the trial court, allowed the application of the respondent-Corporation
filed under Section 8(1) of the Arbitration Act. It was the specific case of the
respondent-Corporation before the High Court that the original agreements
are in the possession of the appellant-Sansthan, whereas the stand of the               F
appellant-Sansthan was that the original agreements are not in its possession.
The respondent-Corporation placed on record of the trial court photocopies
of the agreements along with an application under Section 8(1") of the
Arbitration Act. The High Court, in our view, has rightly held that the
photocopies of the lease agreements could be taken on record under Section
8 of the Arbitration Act for ascertaining the existence of arbitration clause.          G
Thus, the dispute raised by the appellant-Sansthan against the respondent·
Corporation in terms of the arbitration clause contained in the lease agreement
is arb itral.

      22. Now, the question pressed before us is whether we should, in                  H
    546                     SUPREME COURT REPORTS                     [2007) 9 S.C.R.

A exercise of our power and jurisdiction under Article 142 of the Constitution
    of India as submitted by Shri Shanti Bhushan, grant the payment of balance
    of arrears of rent, payment of balance arrears of water & sewerage tax and
    interest on the arrears of rent to the appellant-Sansthan, which amounts are
    disputed by the respondent-Corporation before us. The nature and ambit of
    the power of this Court under Article 142 of the Constitution of India, no
B   doubt, is meant to do complete justice between the litigating parties, but at
    the same time this Court has to bear in mind that the power is conceived to
    meet the situations which cannot be effectively and appropriately tackled by
    the existing provisions of law. Human and equitable approach should be
    balanced to do complete justice to both the parties and not be tilted in favour
C   of either party without ignoring the statutory provisions. This Court in exercise
    of its jurisdiction can grant appropriate relief where there is some manifest
    illegality, or where there is manifest want of jurisdiction, or where some
    palpable injustice is shown to have resulted to the parties.

         23. In the light of above factual aspects, the claim relating to balance
D arrears of rent, balance arrears of water & sewerage tax and rate of interest
  on payment of arrears of rent raised by the appellant-Sansthan in its calculation
  statement filed before this Court is at variance with the calculation statement
  submitted by the respondent-Corporation. The respondent~Corporation ·has
  denied the payment of interest to the appellant-Sansthan. The above-said
E disputed claims can be appropriately tackled and adjudicated upon by the
  Arbitrator in terms of the arbitration clause. The main objectives of the
  Arbitration Act is to make provision for an arbitral procedure which is fair,
  efficient and capable of meeting the needs of the specific arbitration and to
  minimise the supervisory role of courts in the arbitral process and to permit
  an arbitral Tribunal to use mediation, conciliation or other procedures during
F the arbitral proceedings in settlement of disputes, etc. etc. This Court ordinarily   -(.
  will not be obliged to bypass the provisions of the Arbitration and Conciliation
  Act, 1996 in exercise of its power and jurisdiction under Article 142 of the
  Constitution of India.

          24. In the backdrop of this case, we do not find it a fit case to grant
G relief to the appellant-Sansthan as claimed by it in its calculation statement
    which is vehemently disputed by the respondent-Corporation. Therefore, the
    contention of the appellant-Sansthan that this Court can grant the payment
    of balance amount of arrears of rent and arrears of water & sewerage tax and
    interest on arrears of rent detailed in calculation statement submitted before
H   this Court, does not merit acceptance.
         BHARATSEWASANSTHANv. U.P.ELEClRONICSCORPN.LID.[LOKESHWARSINGHPANTA,J.J547


                25. Shri Shanti Bhushan, learned senior counsel, has fairly stated that      A
-~
         in Civil Suit No.16/2000 the appellant-Sansthan has not claimed the arrears of
         rent and water & sewerage tax for the additional area of 2000 sq. ft., which
         was subsequently let out to the respondent-Corporation, as such the claim
         to that extent in terms of the calculation statement filed before this Court is
         not pressed in this appeal. He submitted that for claiming the relief for 2000      B
         sq. ft. area, the appellant-Sansthan will take appropriate proceedings before
         the Court/Forum. We do not wish to express any views on this aspect of the
         matter in this appeal.
..   -
               26. In this view of the matter, we do not find any perversity or infirmity
         in the order of the High Court to warrant any interference.                         C
               27. For the afore-stated reasons, the appeal deserves and it is accordingly
         dismissed. The order of the learned Single Judge dated 14.09.2004 passed in
         Writ Petition No.3388 (M/S) of2004 shall stand affirmed. However, the parties
         are left to bear their own costs.
                                                                                             D
               28. Before parting, we may make it clear that any observation made in
         this judgment shall not be construed as an expression of opinioif on the
         merits of the case. The dispute raised by the parties shall be adjudicated upon
         by the Arbitrator(s) on its own merit in accordance with law.

         D.G.                                                         Appeal dismissed.      E


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.