Created byFuzzy Cloud

Supreme Court of India

BHARAT BHUSHAN BANSALversusU.P. SMALL INDUSTRIES CORPORATION LTD., KANPUR

Citation
1999 INSC 18
Decided
21 January 1999
Disposal
Dismissed

Holding

The contractual clauses do not amount to an arbitration agreement, so Section 8 cannot be invoked and the appeal is dismissed.

Summary

The appellant entered into a construction contract with the respondent that contained clauses making the decisions of the Executive Engineer and the Managing Director final and binding on the parties. Disputes arose over payments and work, and the appellant sought appointment of an arbitrator under Section 8 of the Arbitration Act, 1940. The Civil Judge appointed an arbitrator, but the High Court set aside the order, holding that the contract did not contain an arbitration clause and therefore Section 8 could not be invoked. The Supreme Court examined the language of clauses 23 and 24, distinguishing an expert or certifier’s decision from a true arbitration, and held that the clauses were not arbitration agreements. Consequently, the appellant's application under Section 8 was misconceived and the appeal was dismissed.

Issues considered

  • Whether clauses 23 and 24 of the contract constitute an arbitration agreement within the meaning of the Arbitration Act, 1940.
  • Whether Section 8 of the Arbitration Act, 1940 can be invoked to appoint an arbitrator when the contract lacks an arbitration clause.
  • How to differentiate between an expert determination/certifier and an arbitrator under the Act.

Legislation cited

Subjects

arbitration agreementArbitration Act 1940Section 8 jurisdictionexpert determinationcertifier vs arbitratorconstruction contractfinal and binding decisionarbitration clause

Judgment

                                                                                                A
-     -t-                          BHARAT BHUSHAN BANSAL
                                              v.
                       U.P. SMALL INDUSTRIES CORPORATION LTD., KANPUR

                                              JANUARY 21, 1999
                                                                                                    I
                                                                                                B
·•          ;.._
                          [MRS. SUJATA V. MANOHAR AND R.C. LAHOTI, JJ.]

                        Arbitration Act, 1940: Sections 2(a) and 8.

                          Arbitration agreement-Existence of-Arbitration claus~Ingredients
                   of-Agreement of contract provided that in respect of questions arising from  c
                   or relating to any claim or right, matter or thing in any way connected with
                   the colltract, the decision of Executive Engineer was final, conclusive and
                   binding on both parties to the contract-In respect of the remaining claims
                   the decision of the Managing Director was final, conclusive and bind-
                   ing-Contractor made application under S.8 for appointmellf of an Ar-
 ;                 bitrator-Civil Judge allowed the application-In appeal,· High Court while D
        x          upholding the finding that there was an arbitration clause held that the court
                   had no jurisdiction under S.8 to appoint an Arbitrator because none of the
                   clauses of S.8 were attracted and, therefore, set aside the order of the Civil
                   judge-Held : The agreement of contract does not contemplate a full-fledged
                   arbitration under the Arbitration Act-There/ore, application under S.8 is E
                   misconceived-High Court's decision is correct though for different reasons.

                          Section 2(a)-Arbitration agreement-There is a difference between an
                   expert detem1ination and an arbitration.
...                     Words and Phrases :                                                     F
      --<
                        "Certifier" and "arbitrator''-Meaning of

                         The appellant had entered into a contract with the respondent under


_,_                which the appellant had undertaken the work of construction of factory
                   and allied buildings of the respondent. The agreement provided that in G
                   respect of certain claims the decision of the Executive Engineer was final,
                   conclusive and binding on both the parties to the contract. In respect of
                   the remaining matters the decision of the Managing Director was final,
                   conclusive and binding on both the parties to the contract. The agreement
                   did not mention that any dispute could be referred to the arbitration of H
                                                       181
                      RR BANSAL v. U.P. SMALLINDUS. CORPN. LTD. (SUJATAV. MANOHAR, J.)    183
      ..,.._
-                     K.K. Mohan for the Appellant.

                      The Judgment of the Court was delivered by
                                                                                                 A


                       MRS. SUJATA V. MANOHAR, J. The appellant had entered into a
                 contract with the respondent under which the appellant had undertaken
                 the work of construction of factory and allied buildings of the respondent      B
•        ).-
                 at India Complex, Rae Bareilly. The agreement is dated 19.10.1973. Clauses
                 23 and 24 of the agreement are as follows :

                         "Decision of the Executive Engineer of the UPSIC to be final on
                         certain matters :
                                                                                                 c
                         Clause 23 : Except where otherwise specified in the contract, the
                         decision of the Executive Engineer shall be final, conclusive and
                         binding on both the parties to the contract on all questions relating
                         to the meaning, the specification, design, drawings and instructions
...                      herein before mentioned, and as to the quality of workmanship or
                         materials used on the work or as to any other question whatsoever
                                                                                                 D
        -"
                         in any way arising out of or relating to the designs, drawings,
                         specifications, estimates, instructions, orders or otherwise concern-
                         ing the works or the execution or failure to execute the same
                         whether arising during the progress of the work, or after the
                         completion thereof or abandonment of the contract by the con-           E
                         tractor shall be final and conclusive and binding _on the contractor.

                         Decision of the M.D. of the U.P.S.l.C. on all other matters shall
                         be final:

                         Clause-24 : Except as provided in Clause 23 hereof the decision         F
                         of the Managing Director of the U.P.S.l.C. shall be final, conclusive
                         and binding on both the parties to the contract upon all questions
                         relating to any claim, right, matter or thing in any way arising out
                         of or relating to the contract or these conditions or concerning
                         abandonment of the contract by the contractor and in respect of
                                                                                               G
                         all other matter arising out of this contract and not specifically
  ............           mentioned herein."

                       There were disputes between the appellant and the respondent in
                 connection with the payments to be made under the terms of the said
                 contract and in connection with the work of the said contract. The appel- H
      184                    SUPREME COURT REPORTS                    [1999] 1 S.C.R.
· A lant made an application under Section 8 of the fodian Arbitration Act                  .
                                                                                         _,..
      1940 before the Civil Judge, Kanpur. He applied for the appointment of'
      an independent Arbitrator in the place of the Managing Director. The
      respondent denied that there was any arbitration claus\: in the said con-
      tract. The court, however, allowed the petition of the appellant under
 B    Section 8 of the Arbitration Act and appointed one D.D. Sharma. Executive
      Engineer, as Arbitrator. In appeal, the High Court, while upholding the finding
      that there was an arbitration clause, held that the court below had no juris-
      diction under Section, 8 to appoint another Arbitrator in the place of Manag-
      ing Director since none of the clauses of Section 8 was attracted in the present
      case. The High Court, therefore, set aside the order of the court below and
  C   dismissed the application of the appellant under Section 8. From this judgment
      the appellant has filed the present appeal.

          The first question that requires consideration is whether there is any
   clause in the contract which provides for arbitration between the parties.
 D The relevant Clauses are Clauses 23 and 24. under Clause 23, the decision
   of the Executive Engineer is final, conclusive and binding on both the
   parties to the contract on all questions relating to the meaning, specifica-
   tions, designs etc. and as to the quality of workmanship or materials used
   or relating to any other question whatsoever in any way arising out of or
   relating to the designs, drawings, specifications etc. or otherwise concern-
 E ing the execution or failure to execute the same. Under Clause 24, except
   as provided in Clause 23, the decision of the Managing Director of the
   respondent shall be final, conclusive and binding on both the parties to the
   contract upon all questions relating to any claim, right, matter or thing in
   any way arising out of or relating to the contract and in respect of all other
 F matters arising out of the contract and not specifically mentioned in the
   said Clause. Therefore, in respect of certain claims the decision of the
   Executive Engineer is final and binding on both the parties to the contract.
   While in respect of the remaining matters,. the decision of the Managing
   Director of the respondent is final, conclusive and binding on both the
    parties to the contract. Clause 24 does not mention that any dispute can
 G be referred to the arbitration of the Managing Director. Clause 24 also
    does not spell out any duty on the part of the Managing Director to record
    evidence or to hear both parties before deciding the questions before him.
    From the wording of Clause 24 it is difficult to spell out any intention of
    the parties to leave any disputes to the adjudication of the Managing
 H Director of the respondent as an Arbitrator.
                         B.B. BANSAL v. U.P. SMAI.l. INDUS. CORPN. LID. (SUJATA V. MANOHAR, J.)   185

       ~-   ....          In the case of KK Modi v. KN. Modi & Ors., [1998) 3 sec 573, a                A
 ...               bench of this Court (of which one of us was a member) had the occasion
                   to consider the essential ingredients of an arbitration clause. Among the
                   ingredients which are described in the said judgment, two important in-
                   gredients are; that the agreement between the parties must contemplate
                   that substantive rights of parties will be determined by the agreed Tribunal
                   and that the Tribunal will determine the rights of the parties in an impartial
                                                                                                        B
 >
            >-     and judicial manner with the Tribunal owing an equal obligation of fairness
                   towards both sides and also that the agreement of the parties to refer their
                   disputes to the decision of the Tribunal must be intended to be enforceable
                   in law. There is a difference between an expert determination and arbitra-
                   tion. S.K. Chawla in the Law of Arbitration and Conciliation at page 164             c
                   states as follows :

                           "4. Arbitration agreement to be distinguished from agreement for
                           decision by an engineer or expert, Contracts may contain a clause
                           that on certain questions the decision of an engineer, architect or
,.                                                                                                      D
                           another expert shall be final. The decision given in such cases by
       x                   the engineer etc., is not an award. As pointed out by Bernstein,
                           such a person is under no obligation, unless the contract otherwise
                           provides, to receive evidence or submissions and is entitled to
                           arrive at his decision solely upon the results of his own expertise
                           and investigations. The procedure involved is not arbitration, and           E
                           the Arbitration Act does not apply to it. The primary material on
                           which such person acts is his own knowledge and experience,
                           supplemented if he thinks fit by (i) his own investigations; and/or
                           {ii) material {which need not conform to rules of 'evidence') put
                           up before him by either party. An Arbitrator on the other hand,              F


>
                           acts primarily on material put before him by the parties. The
                           determination by an engineer or an expert would involve a less
                           thorough investigation. Only one mind will be brought to bear on
                           the problem. There will be no discovery of documents, there will
                           not normally be any oral 'evidence' or oral submissions."
                                                                                                        G
.,,                       In the present case, reading Clauses 23 and 24 together, it is quite
                   clear that in respect of questions arising from or relating to any claim or
                   right, matter or thing in any way connected with the contract, while the
                   decision of the Executive Engineer is made final and binding in respect of
                   certain types of claims or questions, the decision of the Managing Director H
    186                    SUPREME COURT REPORTS                   [1999] 1 S.C.R.
A is made final and binding in respect of the remaining claims. Both the
    Executive Engineer as well as the Managing Director are expected to
    determine. the question or claim on the basis of their own investigations
                                                                                       --
    and material. Neither of the clauses contemplates a full-fledged arbitration
    covered by the Arbitration Act.

B       A clause very similar to the present clause was also held to be not
  an arbitration clause by this Court in the case of State of Orissa & Anr. v.
  Daniodar Das, [1996] 2 SCC 216. The language of that clause was very
  similar to the present clause. Under the clause in question "except where
  otherwise specified in this contract, the decision of the Public Health
C Engineer, for the time being", was to be final, conclusive and binding on
  all parties to the contract upon all questions relating to the meaning of
  specifications, drawings and instructions hereinbefore mentioned and as to
  the quality of workmanship or materials used on the work, or as to any ·
  other question, claim, right, matter or thing whatsoever in any way arising
D out of or relating to the contract.. ...... or otherwise concerning the works
  or the execution or failure to execute the same ..........." This Court held that
  this clause ·did not spell out any intention to refer any disputes and
  differences between the parties to arbitration.

         The wording of the clause in the present case is very similar to the
E wording which was interpreted as not an arbitration clause in the above
  case. Both the above judgments of this Court have relied upon an earlier
  decision of this Court in the case of State of U.P. v. Tipper Chand, [1980]
  2 SCC 341. The clause which was interpreted in the above case was also
  materially similar to the clause before us. Clause 22 of the contract in that
F case provided; "except where otherwise specified in the contract the
  decision of the Superintending Engineer for the time being shall be final,
  conclusive and binding on all parties to the contract upon all questions
  relating to t~e meaning of the specifications, designs, drawings and instruc-
  tions hereinbefore mentioned. The decision of such engineer as to the
  quality of workmanship or materials used on the work or as to any other
G question claim, right, matter or thing whatsoever in any way arising out of
  or relating to the contract, designs, drawings, specifications ......... or other-
  wise concerning the works, or the execution or failure to execute the
  same .........shall also be final, conclusive and binding on the contractor''.
  This Court held that the clause did not contain an arbitration agreement
H either expressly or by implication. The intention was to vest the Superin-
       .   .,.._



                            RR BANSAL v_ U.P. SMALL INDUS. CORPN. LTD. [SUJATA V. MANOHAR, J.]   187

.--+               tending Engineer with supervision and administrative control over the               A
                   work.

                         In Hudson's Building and Engineering Contracts, Eleventh Edition,
                   Volume 1, in Paragraph 6.065, while making a distinction between a
                   Certifier and an Arbitrator in a building contract, it has been emphasised
                   that essentially the Certifier in a construction contract will often be per-        B
                   forming an administrative rather than a judicial function, and when doing
                   so there may often be no formulated dispute before him at all. He has been
                   described as a "preventer of disputes" in contradistinction to an Arbitrator
                   whose function can only arise once a dispute is in existence. He is not under
                   the same obligation to afford the parties or their representatives a full           C
                   hearing and receive evidence from them. Thus each contractual provision
                   may need to be carefully scrutinised to see into which category the person
                   named falls.

                          In the present case the Managing Director is more in the category
                   of an expect who will decide claims, rights, on matters in any way pertaining       D
                   to the contract. The intention appears to be more to avoid disputes than
                   to decide formulated disputes in a quasi-judicial manner. In paragraph
                   18.067 of Volume 2 of Hudson on Building and Engineering Contracts,
                   Illustration (8) deals with the case where, by the terms of a contract it was
                   provided that the engineer "shall be the exclusive judge upon all matters           E
                   relating to the construction, incidents and the consequence of these
                   presents, and of the tender, specifications, schedule and drawings of the
                   contract, and in regard to the execution of the works or otherwise arising
                   out of or in connection with the contract, and also as regards all matters
                   of account, including the final balance payable to the contractor, and the
                   certificate of the engineer for the time being, given under his hand, shall         F
                   be binding and conclusive on both parties". It was held that this clause was
                   not an arbitration clause and that the duties of the engineer were ad-
                   ministrative and not judicial.

                         Since Clause 24 does not contemplate any arbitration, the application         G
                   of the appellant under Section 8 of the Arbitration Act, 1940 was miscon-
                   ceive. The appeal is, therefore, dismissed though for reasons somewhat
                   different from the reasons given by the High Court. There will, however,
                   be no order as to costs.

                   v.s.s.                                                         Appeal dismissed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "arbitration agreement"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.