Created byFuzzy Cloud

Supreme Court of India

ASSOCIATE BUILDERSversusDELHI DEVELOPMENT AUTHORITY

Citation
2014 INSC 809
Decided
25 November 2014
Disposal
Appeal(s) allowed

Holding

An arbitral award may be set aside only on the specific grounds listed in Section 34(2) and (3) of the Arbitration and Conciliation Act, 1996, and the Division Bench exceeded its jurisdiction by interfering with the arbitrator's factual findings, so the award is upheld.

Summary

Associate Builders entered into a construction contract with the Delhi Development Authority (DDA) for a housing project. After completing only part of the work, the contractor filed 15 claims for overheads, damages and price escalations, which were largely awarded by an arbitrator. The Single Judge of the Delhi High Court upheld the award, but a Division Bench set aside several claims and reduced others, alleging errors in the arbitrator's application of Hudson's formula and contract clauses. On appeal, the Supreme Court held that under the Arbitration and Conciliation Act, 1996 an award can be set aside only on the limited grounds in Section 34(2) and (3); the Division Bench had exceeded its jurisdiction by re‑examining factual findings and the award’s reasoning. Consequently, the award was reinstated in full and the Division Bench’s order was set aside.

Issues considered

  • Whether the Division Bench could set aside the arbitral award beyond the grounds enumerated in Section 34(2) and (3) of the Arbitration and Conciliation Act, 1996.
  • Whether the award was in conflict with the public policy of India.
  • Whether the court may interfere with the arbitrator's application of Hudson's formula and other factual determinations.
  • Whether clauses 10C, 1OC and 22 of the contract were correctly applied to the claims.
  • Whether there was duplication or overlap among the awarded claims.

Legislation cited

Subjects

ArbitrationSection 34Public policyArbitral awardJudicial interventionConstruction contractHudson formulaPatent illegalityJustice and morality

Judgment

                    [2014] 13 S.C.R. 895


                  ASSOCIATE BUILDERS                              A
                               v.
           DELHI DEVELOPMENT AUTHORITY
              (Civil Appeal No.10531of2014)
                                                                  B
                   NOVEMBER 25, 2014.
[RANJAN GOGOi AND ROHINTON FALi NARIMAN, JJ.]
      Arbitration and Conciliation Act, 1996:
      ss. 5 and 34(2) and (3) - Arbitral award - Judicial C
intervention with - Scope of-Award of arbitrator- In favour
of the appellant-contractor- Upheld by Single Judge of High
 Court - Division Bench of High Court in exercise of
jurisdiction uls.34 setting aside the order of Single Judge
 negating four of the claims of the contractor in toto and scaling D
 down three of the claims - On appeal, held: An arbitration
 award can be set qside only on the grounds mentioned u/
 s.34(2) and (3) - None of the grounds contained in sub-
 clause 2(a) of the Act deal with the merits of the decision
 rendered by the arbitral award - It is only when the award is in E
 conflict with the public policy of India that the merits of an
 arbitral award are to be looked into under specified
 circumstances - The Division Bench of High Court in
 exercise of its jurisdiction u/s. 34 has exceeded its jurisdiction F
 by interfering with the possible view of arbitrator on the facts
 -Arbitral award is upheld.
     'Public policy'- Meaning of, in the context ofArbitration
and Conciliation Act, 1996 - Discussed.
      Words and Phrases- 'Justice' and 'morality' - Meaning G
of.
      Allowing the appeal, the Court
     HELD: 1. Section 34 in conjunction with s.5 of the
Arbitration and Conc.iliation Act, 1996, makes it clear that H
                            895
896      SUPREME COURT REPORTS               [2014] 13 S.C.R.


A an arbitration award that is governed by part I of the Act,
  can be set aside only on the grounds mentioned under
  Section 34 (2) and (~), and not otherwise. None of the
  gnJunds conta'ined in sub-clause 2 (a) deal with the
  merits of the decision rendered by an arbitral award. It
B is only when the award is in conflict with the public
  policy of India that the merits of an arbitral award are to
  be looked into under certain specified circumstances.
  [Para 12][915-C-D; G-H; 916-A]
        Renusagar Power Co. Ltd. v. General Electronic
c
        Co. 1993 (3) Suppl. SCR 22: 1994Supp (1) SCC
        644; ONGC v. Saw Pipes 2003 (3) SCR 691 :
        2003 (5) SCC 705; Hindustan Zinc Ltd. v. Friends
        Coal Carbonisation (2006) 4 SCC 445;
D       McDermott International Inc. v. Burn Standard Co.
        Ltd. 2006 (2) Suppl. scR 409 : (2006) 11 sec
        181; Centro trade Minerals & Metals Inc. v.
        Hindustan Copper Ltd. 2006 (2) Suppl. SCR 146
        : (2006) 11 SCC 245; ODA v. R.S. Sharma and
E       co. 2008 (12) scR 785: (2008} 13 sec 80; J.G.
        Engineers (P) Ltd. v. Union of India 2011 (8)
        SCR 486 : (2011) 5 SCC 758; Union of India v.
        Col. L.S.N. Murthy2011 (13) SCR 295: (2012) 1
        sec 718 - relied on.
F       2. Violation of the Foreign Exchange Act and
  disregarding orders of superior courts in India would be
  regarded as being contrary to the fundamental policy of
  Indian law. The binding effect of the judgment of a
G superior court being disregarded would be equally
  violative of the fundamental policy of Indian law. The
  juristic principle of a "judicial approach" demands that
  a decision be fair, reasonable and objective. On the
  obverse side, anything arbitrary and whimsical would
H obviously not be a deter_mination which would either be
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                897
                   AUTHORITY

fair, reasonable or objective. The Audi Alteram Partem A
 principle which undoubtedly is a fundamental juristic
 principle in Indian law is also contained in Sections 18
 and 34 (2) (a) (iii) of the Arbitration and Conciliation Act.
 A decision which is perverse or so irrational that no
 reasonable person would have arrived at the same, is B
.important and requires some degree of explanation. It is
 settled law that where - a finding is based on no
 evidence, or an arbitral tribunal takes into account
 something irrelevant to the decision which it arrives at;
 or ignores vital evidence in arriving at its decision, such c
 decision would necessarHy be perverse. The other
 ground on which an award may be set aside is that it is
 contrary to the interest of India. [Para 12][925-C-D;
 928-A-C; F-H; 931-A]
      ONGC Ltd. v. Western Geco International Ltd.          D
      2014 (9) SCC 263; H.B. Gandhi, Excise and
      Taxation Officer-cum-Assessing Authority v. Gopi
      Nath & Sons 1992 Supp (2) SCC 312; Ku/deep
      Singh v. Commr. of Police 1998 (3) Suppl.
      SCR 594: (1999) 2 SCC 10 - relied on.                 E
      3. If an award is against justice or morality, it is
against public policy. An award can be said to be against
justice only when it shocks the conscience of the court.
Morality, in the context of an arbitral award would mean
the enforcement of an award say for specific F
performance of a contract involving prostitution.
"Morality" would, if it is to go beyond sexual morality
necessarily cover such agreements as are not illegal but
would not be enforced given the prevailing mores of the
day. However, interference on this ground would also G
 be only if something shocks the court's conscience.
 [Para 12][931-C-D; 934-E-G]
      Gherulal Parekh v. Mahadeo Dass Maiya 1959
      Supp (2) SCR 406 - referred to.                        H
898         SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A            4. 'Patent illegality' would also fall under public
       policy. Under the explanation to section 34(2)(b), an
      award is said to be in conflict with the public policy of
       India if the making of the award was induced or affected
       by fraud or corruption. This ground is perhaps the earliest
B     ground on which courts in England set aside awards
       under English law. Added to this. ground (in 1802) is the
      ground that an arbitral award would be set aside if there
      were an error of law by the arbitrator. The 'patent illegality'
      principle contains three sub heads: (a) a contravention
C     of the substantive law of India would result in the death
      knell of an arbitral award. This must be understood in
      the sense that such illegality must go to the root of the
      matter and cannot be of a trivial nature. This is a
      contravention of Section 28(1 )(a) of the Act; (b) a
0
      contravention of the Arbitration Act itself would be
      regarded as a patent illegality- for example if an arbitrator
      gives no reasons for an award in contravention of
      sect.ion 31 (3) of the Act, such award will be liable to be
E     set aside; and (c) a contravention of Section 28 (3) of the
      Arbitration Act. This last contravention must be
      understood with a caveat that if an arbitrator construes
      a term of the contract in a reasonable manner, it will not
      mean that the award can be set aside on this ground.
F     Construction of the terms of a contract is primarily for
      an arbitrator to decide unless the arbitrator construes
      the contract in such a way that it could be said to be
      something that no fair minded or reasonable person
      could do. (Para 12)(934-G-H; 935-A, 937-C-H; 938-B·D]
G          McDermott International Inc. v. Bum Standard Co.
           Ltd. 2006 (2) Suppl. SCR 409: (2006) 11 sec
           181; MSK Projects (/) (JV) Ltd. v. State of
           Rajasthan 2011 (9) SCR 402 : (2011) 10 SCC
           573; Rashtriya /spat Nigam Ltd. v. Dewan Chand
H
   ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                899
                  AUTHORITY

    Ram Saran 2012 (4) SCR 1 : (2012) 5 SCC 306           A
    -relied on.
     R v. Northumberland Compensation Appeal
     Tribunal. Ex Parte Shaw 1952 1 All ER 122;
     Champsey Bhara Company v. The Jivraj Ba/loo
                                                           B
     Spinning and Weaving Company Ltd. AIR 1923
     PC 66 - referred to.
       5. When a court is applying the "public policy" test
to an arbitration award, it does not act as a court of
appeal and consequently errors of fact cannot be C
corrected: A possible view by the arbitrator on facts has
necessarily to pass muster as the arbitrator is the
ultimate master of the quantity and quality of evidence
to be relied upon when he delivers his arbitral award.
Thus an award based on little evidence or on evidence D
which does not measure up in quality to a trained legal
mind would not be held to be invalid on this score. Once
it is found that the arbitrator's approach is not arbitrary
or capricious, then he is the last word on facts.
[Para 12][929-F-H; 930-A]                                   E
     P.R. Shah, Shares & Stock Brokers (P) Ltd. v.
     B.H.H. ·Securities (P) Ltd. 2011 (16) SCR
     87 : (2012) 1 sec 594- relied on.
     6. ·In the present case, the Division Bench while F
considering claim Nos. 9, 10, 11 and 15, found fault with
the application of Hudson's formula which was set out
by the Arbitrator in order to arrive at the claim made under
these heads. The Division Bench said that it was not
possible for an Arbitrator to mechanically apply~ certain G
formula, however well understood in the trade. This itself
is going outside the jurisdiction to set aside an award u/
s.34. The Division Bench has exceeded its jurisdiction
in interfering with a possible view of the Arbitrator on
facts, forgetting that the Arbitrator is the sole Judge of H
900         SUPREME COURT REPORTS               [2014] 13 S.C.R.


A the quantity and quality of evidence before him and
  unnecessarily bringing in facts which were neither
  pleaded nor proved and ignoring the vital completion
  certificate granted by the DOA itself. The Division Bench
  also went wrong in stating that as the work completed
B was c>nly to the extent of Rs. 62,84,845/-, Hudson's
  formula should have been applied taking this figure
  into account and not the entire contract value of
  Rs.87 ,66,678/- into account. To apply this formula one
  has t.o take into account the contract value that is
C awarded and not the work completed. [Paras 15, 16, 18,
  20][941-G-H; 942-A; 945-D; 948-C-E; 949-A]
           McDermott International Inc. v. Burn Standard Co.
           Ltd. 2006 (2) suppl. scR 409: (2006) 11 sec
o          181 - relied on.
            7. The Division Bench has interfered wrongly with
      the arbitral award on several counts. It had no business
      to enter into a pure question of fact to set aside the
      Arbitrator for having applied a formula of 20 months
E     instead of 25 months. The Division Bench found that an
      adjustment would have to be made with claims awarded
      under claim Nos.2, 3 and 4 which are entirely separate
      and independent claims and have nothing to do with
      claim Nos.12 and 13. The formula then applied by the
F     Division Bench was that it would itself do "rough and
      ready justice". This cannot be done by any court under
      the jurisdiction exercised under Section 34 of the
      Arbitration Act. The expression "justice" when it comes
G     to setting aside an award under the public policy ground,
      can only mean that an award shocks the conscience of
      the court. It cannot possibly include what the court thinks.
      is unjust on the facts of a case for which it then seeks to
      substitute its view for the Arbitrator's view and does what
H     it considers to be "justice. The Division Bench lost sight
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                  901
                   AUTHORITY

of the fact that it is not a first appellate court and cannot A
interfere with errors of fact. [Para 22][951-E-H; 952-A·C]
     8. The Arbitrator considered clause 1OC of the
agreement in detail and only awarded amounts under
this clause in excess of 10 percent as required by the
                                                           8
clause, when it came to awarding amounts under claim
Nos.2, 3 and 4, which fell within the ambit of clause 1OC.
The arbitrator has not applied the said clause to claim
Nos.9, 10, 11 and 15, as no occasion for applying the
same arose. The award cannot be faulted on this c
ground.[Paras 24, 25][954-B-E]
      9. Clause 22 of the agreement does not operate
automatically. It only operates if an objection is taken
stating that part of the site is not available for any reason.
Nowhere has the ODA stated which part of the site is not D
available for any reason. The object of this clause is that
no claim for extras should be granted only if there is an
unavoidable delay. The delay was entirely avoidable and
caused solely by the DOA itself. [Para 26][955-B-C]
                                                               E
      KochharConstruction Works v. DOA &Anr. (1998)
      2 Arb. LR 209; Harsha Constructions v. Union of
      India & Ors. (2014) 9 SCC 246- referred to.
      10. There has not been a duplication of claims
·awarded. None of the claims are overlapping. They are        F
 all contained under separate heads. [Paras 27, 28]
 [955-0; 956-B]
                     Case Law Reference:
      1993 (3) Suppl. SCR 22       relied on    Para 12       G

      2003 (3) SCR 691             relied on    Para 12
      (2006) 4 sec 445             relied on    Para 12
      2006 (2) Suppl. SCR 409      relied on    Para 12
                                                              H
902        SUPREME COURT REPORTS              [2014] 13 S.C.R.


A          2006 (2) Suppl. SCR 146    relied on .   Para 12
           2.008 (12) SCR 785         relied on     Para 12
           2011 (8) SCR 486           relied on     Para 12
           2011 (13) SCR 295          relied on     Para 12
B
           2014 (9) sec 263           relied on     Para 12
           ·1992 Supp (2) sec 312     relied on     Para 12
           1998 (3) Suppl. SCR .594 relied on       Para 12

c          2011 (16) SCR 87           relied on     Para 12
           1959 Supp (2) SCR 406      referred to   Para 12
           1952 1 All ER 122          referred to   Para 12
           AIR 1923 PC 66             referred to   Para 12
D
           2006 (2) Suppl. SCR 409    relied on     Para 12
           2011 (9) SCR 402.          relied on     Para 12
           2012 (4) SCR 1             relied on     Para 12

E          (1998) 2 Arb. LR 209       referred to   Para 26
           (2014) 9 sec 246           referred to   Para 26
          CIVIL APPELLATE JURISDICTION: Civil Appeal No.
      10531 of2014.
 F         From the Judgment and Order dated 08-02-2012 of the
      High Court of Delhi at New Delhi in FAO (O.S.) No. 667 of
      2006.

                                                          .
       M.L. Varma, Sr. Adv., Sc:itvik Varma, Abhishek, Ambar
G Qamaruddin, Ad vs. with him for the Appellant.
       A. Sharan, Sr. Adv., Ms. Binu Tamta, Pankaj Pandy, Dhruv
  Tamta, Advs. with him for the Respondent.


 H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                         903
                   AUTHORITY

     The Judgment of the Court was delivered by                     A
     R. F. NARIMAN, J. 1. Leave granted.
       2. The appellant herein was awarded a certain
construction work contract by the DOA vide a letter of award
dated 141h May, 1992. DOA was building a colony consisting B
of 7 ,000 houses in Trilok Puri in the trans-Yamuna area. 168
Middle Income Group houses and 56 Lower Income Group
houses, Grade-A Pocket- !3 (balance work) was awarded for
the tendered amount of Rs.87 ,66,678/-. The contract was to
be completed in 9 months. Admittedly, it was ultimately C
completed only in 34 months, the contractor completing 166
Middle Income Group houses and 36 Lower Income Group
houses. The total value of work that was done amounted to
Rs.62,84,845/-. As many as 15 claims were made by the
 contractor and the High Court of Delhi appointed one Shri K.D. D
 Bali.to arbitrate the present dispute .
     . 3: We are concerned here with claims 9, 10, 11 and 15,
for these claims have been allowed by the Arbitrator and the
DDA's objections have been dismissed by the learned Single           E
Judge of the High Court of Delhi. The Division Bench in an
appeal u~der Section 37 of the Arbitration Act, 1996 has
stepped in to set aside the judgment of the Single Judge and
negative these claims. We are also concerned with claims 12
and 13 which have been scaled down by the Division Bench.            F
      4. Claims 9, 10, 11 and 15 read as follows:
      "Claim No.9: Claimants claim Rs. 20,950/- on account
      of hire charges of centering shuttering due to delay in
      laying of conduiting.                                          G
      a) That the respondents had granted certain work of
      electrification but the said agency did not lay the conduit
      resulting in delay in removing the shuttering and causing
      hire charges. This fact was reported to the respondents
                                                                     H
904    SUPREME COURT REPORTS                  (2014] 13 S.C.R.



A     vide claimant's letter dated 30.10.92 followed by
      reminders and also found place in hindrance register.
      b) That this is the actual expenditure incurred and thus
      the claimant is entitled for its refund.
B     c) That the detailed break-up of this claim has been
      appended separately.
      Claim No.10: Claimants claim Rs.33,450/- being the hire
      charges of shuttering due to stoppage of work in block
      no.100and 101.
c
      a) That the department had virtually stopped the work in
      block 100 & 101 on 20.7.93 and it continued up to
      26.2.94. During this period no work was allowed to be
      executed in these two blocks resulting in blockade or
D     centering and shuttering in the said two blocks.
      b) That by stoppage of work in these two blocks the
      claimants had suffered hire charges of shuttering due to
      respondent's lapses and defaults.                  ·

E     c) It is further stated that there was no justification for
      stoppage of work ar:id the action was arbitrary and totally
      unjust.
      d) That the detail of this claim has been outlined and
      appended separately and the same shall from part of
F
      the statement of facts.
      Claim No. 11: Rs.2.00.000/- payable as damages on
      account of hire charges of tools &plants and scaffolding.
      a) That due to prolongation of the contract on account of
G     the respondents the claimants had to maintain tools &
      plants, scaffolding etc, during the prolongation of the
      contract resulting in expenditure forthe same.


H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                       905
       AUTHORITY [R. F. NARIMAN, J.]

b) That the said articles remained at site beyond the         A
stipulated period and the claimants suffered loss due to
the said prolongation.
 Claim No. 15: Claimants claim damages Rs.6,25,979/-
 on account of establishment due to prolongation of the
                                                              8
 contract.
 a) That the claimants had contemplated maintenance of
 establishment during stipulated period of completion but
 the work was prolonged due to various delays and
 defaults on the part of the respondents.                     C
 b) It is further stated that the claimants had to pay the
 establishment payment during prolongation and the said
 expenditure was unproductive and un contemplated.
 c) It is further stated that the claimants had maintained    D
 establishment beyond the stipulated completion due to
 the respondent's breach and thus entitled for payment.
  d) That the respondents were also aware that the claimant
 .has maintained regular establishment and thus, incurred      E
  expenditure and the claimants had also made several
  representations."
 Claims 12 a.nd 13 read as follows:
 "Claim No. 12: Claimants claim Rs. 7. 12.394/- as             F
 damages @20% for execution of the work.
 a) That the work was delayed because of the
 Respondents for the reasons as set out in the letter
 indicating hindrances encountered during execution of ·
 the work resulting delay in execution of the work for a G
 period of 25 months.
 b) It is further stated that the claimants incurred
 unproductive after stipulated date of completion.

                                                               H
906          SUPREME COURT REPORTS                    [2014].13 S.C.R.


A           c) It is further stated that during prolongation there had
            been steep rise in cost of material and labour.
            d) That the claim of 20% is also lent support from the
            cost index as issued by the competent authority and only
            applicable on the work which was executed during
B
           .prolongation.
            e) That as per cost index it comes to more than 30%
            whereas the claimants had claimed 20 & being highly
            rational and just.                   '
c          f) That the claimants had appended the details of this
           claim separately based on cost index to show that the
           claimant had actually incurred this additional expenditure
           due to the respondents. Copy of the hindrances
D          encountered during the execution of the work at the hands
           of the respondents has been enclosed.
           g) That the respondents had committed breach and thus
           liable for damages.
           h) It is further stated that the cost of material issued by
E
           the department has been deducted by assessing the cost.
           Claim No. 13: Claimants claim Rs.97.5000/- being the
           extra at 35% for the work executed in block 100 & 101
           effective from 28.2.94 till actual completion.
F
           a) It is further stated that due to delayed execution of the
           work of these two blocks the claimants had to incur extra
           expenditure as the stoppage of work was utterly arbitrary.
           b) That the detailed break-up of this claim is appended
G          with the statement of facts."
             5. Though the challenge to claims 2, 3 and 4 were given
      up before the Division Bench, they are also relevant and read
      as follows:
H                                               \..
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                        907
       AUTHORITY [R. F. NARIMAN, J.]

"Claim .No.2: Claimants claim Rs.1 ,62,387/- being the         A
reimbursement of statutory increase in labour under
clause 10-C
a) That the claimants submitted the tender on 6.2.92
and said 9ffer was accepted on 14.5.92. The date of
                                                               8
commencement was to be reckoned from 24.5.92. The
date of stipulated completion was 9 months i.e. 23.2.93
but the work could be completed on 28.3.95.
b) It is further stated that the claimants had submitted the
bill for the value to the extent the work was executed till    C
4.10.94 for a sum of Rs.1,12,067/-as per the formula
applicable.
 c) That the respon~ents however, did not make a single
 payment though, the work was executed after submission        D
 of the said bill.
 d) That however, a consolidated bill was furnished the
 respondents for a sum of Rs. 1,62,287/-. Even the said
 payment has not been liquidated so far.
                                                               E
 e) That the claimants advised the statutory increase as
 and when enforced and the claimants also submitted the
 labour reports indicating the nature of the labour
 employed at site.
 f) That the respondents had also certified on the bill that   F
 the labour payment has been made as per the. labour
 rate.
 g) That it is further stated that since it is a statutory
 increase, the same is payable by the respondents. Copy        G
 of the both the bills attached. And thus the claimants be
 awarded a sum of Rs. 1,62,287/-to the claimants.
 Claim No.3: Claimants claim Rs.1.49.862/- being the
 increase in cost of stone grit on account closure of the
 quarrv by the order of the Supreme Court.                     H
908         SUPREME COURT REPORTS                    [2014] 13 S.C.R.


A          a) That it is stated that the claimants had submitted the
           tender on the basis of the rate prevailing but due to the
           Hon'ble Court's directions for closure of the stone quarry
           resulting in shortage of stone chips in the market and
           consequently rates increased.
B
          · b) That the claimants informed the quantum of the
            increase on 22.6.92 and followed by reminders.
           c) That the respondents had agreed in principle to pay
           the increase which was prevailing in the market.
c          d) That the detailed break-up of this claim has been
           appended separately.
           e) It is further stated that the claimant was not instrumental
           for increase in cost but due to the interference of the
D          Hon'ble Supreme Court. And the said increase has been
           taken into account till the stipulated completion dated
           23.2.93.
           f) That the claimant is entitled for recovery of the said
           increase.
E
           Claim No. 4: Claimants claim Rs.12.922/- payable by
           virtue of clause 10-C of the agreement and up to the
           stipulated period
           a) That there was steep rise in cost of steel and the
 F
           claimant was exposed and the respondents were liable
           to pay the increase in steel.
           b) lhat the detailed break-up of this claim has been
           prepared and appended.
G           6. The Arbitrator by a reasoned award dated 23'd May,
      2005 held that the entire delay of 25 months in the execution
      of tho project was thanks to the ODA, none of this delay being
      attributable to the contractor. The learned Arbitrator found:
 H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                         909
       AUTHORITY[R. F. NARIMAN, J.]

"That all the above four claims are inter linked being          A
related to the overhead expenses and therefore dealt
together.
That the date of commencement of work was 24.5.92
and the period for completion was 9 months and                  B
therefore, the disputed date of completion was 23.2.93
but the work could be actually completed on 28.3.95.
That there was delay of 25 months in completion of the
work beyond the stipulated date of completion.
That the Claimants urged that there had been various C
delays in the execution of work due to the lapses and
defaults of the Respondents from the very
commencement of work. The progress was held up time
and again and the claimants therefore, as back as D
17.2.93 advised the Respondents (C-9page167)that
the Claimants are not interested to execute the work
beyond the stipulated date of completion and therefore,
their contract be finalized on the stipulated date of
completion as the Claimants shall be exposed to incur E
heavy expenditure in overheads for maintaining
establishment watch and ward and tools and plants and
other shuttering material but the Respondents did not
refute. The chief reasons for delay are highlighted below:-
 1) Delay in supply of structural and architectural drawings.   F
 11) That out of 9 Blocks 2 blocks are abnormally delayed
 as the site of the said 21 blocks was made available in
 piecemeal which stretched till 26.2.94 whereas the
 stipulated completion was 23.2.93.                             G
 Ill) Delay in laying the conduit by the electrical agency
 resulting in delay in casting of RCC slab and plastering
 work besides development work. The said hindrance
 was removed lastly on 28.3.95.
                                                                H
910   SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A     IV) Abnormal delay in making availability of the alignment
      sketch for electrical cables.
      V) Inordinate delay in supply of stipulated material such
      as cement, steel and pipes.
B     VI) Delay in decision of finishing· work in kitchen and
      bath rooms.
      VII) There was inordinate delay in making availability.of
      colour scheme.

 c    VIII) That the Respondents also abnormally delayed the
      supply of door shutters which were to be supplied by the
      Respondents. The same were supplied as late as
      8.11.94.
      IX) Inordinate delay in writing in the electrical conduits
 D    resulting in delay in completion offinishing work:
      X) Suspension of work by the Respondents for the period
      17.1.94 to 25.2.94 and from 7.8.94 to 22.3.95 because
      of non-removal of hindrances.
 E    XI) Delayed payment due to non-sanction of
      Administrative Approval and Expenditure Sanction.
      That all the delays as set out had been duly recorded
      733 to 739 and M.A.S. register pages from 747 to 768
 F    as highlighted by the Claimants. The Claimants also
      relied upon certain documents of MAS Register supplied
      by the Respondents.
      That the Claimants further stated that the Claimants had
      also filed reasons for delay and hold up of the work
 G    various defaults of the Respondents inAnnexure pages
      740 to 746. The Claimants also highlighted the
      correspondence made by the Claimants with
      Respondents.

 H
        ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                      911
               AUTHORITY [R. F. NARIMAN, J.]

         That the Claimants further stated that the said hindrances A
         were avoidable but the Respondents did not take timely
         steps.
         That the Claimants also referred the contents of the letter
         dated 10. 7.95 (page 885) wherein it was observed that
                                                                     B
         the Superintending Engineer appreciated the working
         of the Claimants and also observed that there was no
         fault of the. contractor and they have successfully
         completed the work. The Claimants further stated that,
         they had incurred heavy expenditure on overheads of the c
         lapses and default of the Respondents.
         As against this the Respondents stated that there was
         poor planning of the claimants and also contended that
         since the compensation has been levied under Clause
         2 of the agreement therefore, claim of the claimants D
         deserves to be rejected.
         That on record it .is conclusively proved that the
         Respondents committed breach of contract as they failed
         to discharge their obligations in time resulting in E
         prolongations did not deny the deployment of the tools
         and plants and machinery at site besideswatch and ward
         during the prolongation."
          7. It is important to note that before the Division Bench,
    the learned counsel for the DDA conceded that this being a F
    pure finding of fact, he would not be challenging it before the
    Division Bench.
          8. Of the total claim of Rs.37.28 lakhs, the learned
    Arbitrator awarded an amount of Rs.23.39 lakhs. Further, the G
    learned Arbitrator has laboriously gone through all the evidence
    and answered each claim giving reasons forthe same .
•       9. By a judgment dated 3rd April, 2006, the learned Single
    Judge of the High Court of Delhi dismissed the objections of .
                                                                     H
912        SUPREME COURT REPORTS                 [2014] 13 S.C.R.


A the ODA and upheld the award. In an appeal filed under Section
   37 of the Arbitration Act, vide the impugned judgment dated
   8th February, 2012, a Division Bench of the High Court of Delhi
   set aside the judgment of the Single Judge on claims 9, 10, 11
   and 15, and negatived these claims in toto. Further, claims 12
 B and 13 were scaled down doing "rough and ready justice".
   Resultantly, the awarded amount of Rs.7,20,000/-was scaled
   down to Rs. 5,57, 137.50/-.
          10. We have heard learned counsel forthe parties. Shri
 c M. L. Verma, learned Senior Advocate appearing on behalf of
   the appellant, submitted that the Division Bench has lost sight
   of the law laid down by this Hon'ble Court when it comes to
   challenges made to arbitral awards under Section 34 of the
   Act. He has submitted that the Division Bench has acted as if
 o this was a first appeal from the award and has further submitted
   that the Division Bench has taken into account facts which were
   neither plead~d nor proved before the learned Arbitrator in
   order to negative certain claims. He further submitted that it is
   not possible for a Bench hearing an objection against an arbitral
 E award to do "rough and ready justice" - it is bound by the law
   laid down by this Hon'ble Court. In particular, he argued that
   the conceded position is that 25 months delay was due to the
    DDA alone. The award read as a whole is just, fair and
    reasonable as only certain claims have been granted and every
 F claim granted has been supported with reasons. The Arbitrator
    is the sole judge of the quality and quantity of evidence before
    him and he has decided on that evidence. No errors of law
    arise from the award and the award has, therefore, been
    wrongly set aside.
 G
         11. Mr. Amarendra Sharan, learned Senior Advocate
   appearing on behalf of the DDA has relied strongly on clause
   1OC and clause 22 to support the judgment of the Division
   bench and has further argued that there has been duplication
 H so far as certain claims are concerned. He argued that an
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                          913
           AUTHORITY [R. F. NARIMAN, J.]

award in the teeth of clause 1OC and clause 22 would be a A
jurisdictional error which would vitiate the award.
      12. In as much as serious objections have been taken to
the Division Bench judgment on the ground that it has ignored
the parameters laid down in a series of judgments by this Court B
as to the limitations which a Judge hearing objections to an
arbitral award under Section 34 is subject to, we deem it
necessary to state the law on the subject.
       Section 34 of the Arbitration and Conciliation Act reads
as follows-                                                          c
     "Application for setting aside arbitral award.-(1)
     Recourse to a Court against an arbitral award may be
     made only by an application for setting aside such award
     in accordance with sub-section (2) and sub-section (3). · D
     (2) An arbitral award may be set aside by the Court only
     if-
     (a) the party making the application furnishes proof that-
     (1) a party was under some incapacity; or                       E
     (ii) The arbitration agreement is not valid under the law
     to which the parties have subjected it or, failing any
     indication thereon, under the law for the time being in
     force; or
                                                                      F
     (iii) the party making the application was not given proper
     notice of the appointment of an arbitrator or of the arbitral
     proceedings or was otherwise unable to present his case;
     or
                                                                     .G
     (iv) the arbitral award deals with a dispute not
     contemplated by or not falling within the terms of the
     submission to arbitration, or it contains decisions on
     matters beyond the scope of the submission to
     arbitration:
                                                                      H
914   SUPREME COURT REPORTS                      [2014] 13 S.C.R.


A     Provided that, if the decisions on matters submitted to
      arbitration can be separated from those not so submitted,
      only that part of the arbitral award which contains
      decisions on matters not submitted to arbitration may
      be set aside; or
B
      (v) the composition of the arbitral tribunal or the arbitral
      procedure was not in accordance with the agreement of
      the parties, unless such agreement was in conflict with a
      provision of this Part from which the parties cannot
 c    derogate, or, failing such agreement, was not in
      accordance with this Part; or
      (b) the Court finds that-
      (i) the subject-matter of the dispute is not capable of
      settlement by arbitration under the law for the time being
 D
      in force, or
      (ii) the arbitral award is in conflict with the public policy of
      India.
      Explanation.-Without prejudice to the generality of sub-
 E
      clause (ii), it is hereby declared, for the avoidance of any
      doubt, that an award is in conflict with the public policy of
      India if the making of the award was induced or affected
      by fraud or corruption or was in violation of Section 75 or
 F    Section 81.
      (:~) An application for setting aside may not be made
      after three months have elapsed from the date on which
      the party making that application had received the arbitral
      award or, if a request had been made under Section 33,
 G    from the date on which that request had been disposed
      of by the arbitral tribunal:
      Provided that if the Court is satisfied that the applicant
      was prevented by sufficient cause from making the
 H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                          915
           AUTHORITY[R. F. NARIMAN, J.]

     application within the said period of three months it may       A
     entertain the ap~ication within a further period of thirty
     days, but not thereafter.
     (4) On receipt of an application under sub-section (1 ),
     the Court may, where it is appropriate and it is so
                                                                     8
     requested by a party, adjourn the proceedings for a
     period of time determined by it in order to give the arbitral
     tribunal an opportunity to resume the arbitral proceedings
     or to take such other action as in the opinion of arbitral
     tribunal will eliminate the grounds for setting aside the       c
     arbitral award."
      This Section in conjunction with Section 5 makes it clear
that an arbitration award that is governed by part I of the .
Arbitration and Conciliation Act, 1996 can be set aside only
on grounds mentioned under Section 34 (2) and (3), and not D
otherwise. Section 5 reads as follows:
     "5. Extent of judicial intervention.-Notwithstanding
     anything contained in any other law for the time being in ·
     force, in matters governed by this Part, no judicial E
     authority shall intervene except where so provided in this
     Part."
      It is important to note that the 1996 Act was enacted to
replace the 1940 Arbitration Act in order to provide for an
arbitral procedure which is fair, efficient and capable of meeting   F
the needs of arbitration; also to provide that the tribunal gives
reasons for an arbitral award; to ensure that the tribunal remains
within the limits of its jurisdiction; and to minimize the
supervisory roles of courts in the arbitral process.
                                                                     G
     It will be seen that none of the grounds contained in sub-
clause 2 (a) deal with the merits of the decision rendered by
an arbitral award. It is only when we come to the award being
in conflict with the public policy of India that the merits of an
                                                                     H
916         SUPREME COURT REPORTS                   [2014113 S.C.R.

A arbitral award are to be looked into under certain specified
  circumstances.
       In Renusagar Power Co. Ltd. v. General Electronic
  Co., 1994 Supp (1) SCC 644, the Supreme Court construed
B Section 7 (1 )(b) (ii) of the Foreign Award (Recognition and
  Enforcement)Act, 1961.
          · "7. Conditions for enforcement of foreign awards.-
            (1) A foreign award may not be enforced under this Act-
            (b) if the Court dealing with the case is satisfied that-
c
            (ii) the enforcement of the award will be contrary to the
           public policy"
             In construing the expression "public policy" in the context
      of a foreign award, the Court held that an award contrary to
D
             1. The fundamental policy of Indian law
             2. The interest of India
             3. Justice or morality,
E        would be set aside on the ground that it would be contrary
  to the public policy of India. It went on further to hold that a
  contravention of the provisions of the Foreign Exchange
  Regulation Act would be contrary to the public policy of India in
  that the statute is enacted for the national economic interest to
F ensure that the nation does not lose foreign exchange which
  is essential for the economic survival of the nation (see para
  75). Equally, disregarding orders passed by the superior
  courts in India could also be a contravention of the fundamental
  policy of Indian law, but the recovery of compound interest on
G interest, being contrary to statute only, would not contravene
  any fundamental policy of Indian law (see paras 85,95).
            When it came to construing the expression "the public
      policy of India" contained in Section 34 (2) (b) (ii) of the
 H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                   917
           AUTHORITY [R. F. NARIMAN, J.]

Arbitration Act, 1996, this Court in ONGC v. Saw Pipes, 2003 A
(5) sec 705, held-
     "31. Therefore, in our view, the phrase "public policy of
     India" used in Section 34 in context is required to be
     given a wider meaning. It can be stated that the concept
                                                                8
     of public policy connotes some matter which concerns
     public good and the public interest. What is for public
     good or in public interest or what would be injurious or
     harmful to the public good or public interest has varied
     from time to time. However, the award which is, on the    c
     face of it, patently in violation of statutory provisions
     cannot be said to be in public interest. Such .award/
     judgment/decision is likely to adversely affect the
     administration ofjustice. Hence, in our view in addition
      to narrower meaning given to the term ''public policy" D
     in Renusagar case [1994 Supp (1) SCC 644) it is
      required to be held that the award could be set aside if
      it is patently illegal. The result would be - award could
      be set aside if it is contrary to:
                                                               E·
     (a) Fundamental policy of Indian law; or
     (b) The interest of India; or
     (c) Justice or morality, or
     (d) in addition, if it is patently illegal.               F
     I/legality must go to the root of the matter and if the
     illegality is of trivial nature it cannot be held that award
     is against the public policy. Award could also be set
     aside if it is so unfair and unreasonable that it shocks
     the conscience of the court. Such award is opposed to G
     public policy and is required to be adjudged void.
     74. In the result, it is held that:

                                                               H
918   SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A     (A) (1) The court can set aside the arbitral award under
      Section 34(2) of the Act if the party making the
      application furnishes proof that:
      (i) a party wa~ under some incapacity, or
B     (ii) the arbitration agreement is not valid under the law
      to which the parties have subjected it or, failing any
      indication thereon, under the law for the time being in
      force; or
      (iii) the party making the application was not given
c     proper notice of the appointment of an arbitrator or of
      the arbitral proceedings or was otherwise unable to
      present his case; or
      (iv) the arbitral award deals with a dispute not
D     contemplated by or not falling within the terms of the
      submission to arbitration, or it contains decisions on
      matters beyond the scope of the submission to
      arbitration.
      (2) The court may set aside the award:
E
      (i)(a) if the composition of the Arbitral Tribunal was not
      in accordance with the agreement of the parties,
      (b) failing such agreement, the composition of the
      Arbitral Tribunal was not in accordan~e with Part I of the
F
      Act.
      (ii) ifthe arbitral procedure was not in accordance with:
      (a) the agreement of the parties, or

G     (b) failing such agreement, the arbitral procedure was
      not in accordance with Part I of the Act.
      However, exception for setting aside the award on the
      ground of composition of Arbitral Tribunal or illegality
      of arbitral procedure is that the agreement should not
H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                          919 .
       AUTHORITY[R. F. NARIMAN,J.]

be in conflict with the provisions of Part I of the Act from     A
which parties cannot derogate.
(c) If the award passed by the Arbitral Tribunal is in
contravention of the provisions of the Act or any other
substantive law governing the parties or is against the
                                                                 8
terms of the contract.
(3) The award could be set aside if it is against the public
policy of India, that is to say, if it is contrary to:
 (a) fundamental policy of Indian law; or
                                                                 c
 (b) the interest of India; or
 (c) justice or morality; or
 (d) if it is patently illegal.
 (4) It could be challenged:                                     D
 (a) as provided under Section 13(5); and
 (b) Section 16(6) of the Act.
  (8)(1) The impugned award requires to pe set aside             E
· mainly on the groµnds:
 (i) there is specific stipulation in the agreement that the
 time and date of delivery of the goods was of the
 essence of the contract;
 (ii) in case offailure to deliver the goods within the period   F
 fixed for such delivery in the schedule, ONGC was
 entitled to recover from the contractor liquidated
 damages as agreed;
 (iii) it was also explicitly understood that the agreed G
 liquidated damages were genuine pre-estimate of
 damages;
 (iv) on the request of the respondent to extend the time-
 limit for supply of goods, ONGC informed specifically
                                                                 H
920        SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A         that time was extended but stipulated liquidated
          damages as agreed would be recovered;
          (i,~ liquidated damages for delay in supply of goods
          were to be recovered by paying authorities from the bills
          for payment of cost of material supplied by the
B
          contractor;
          (vi) there is nothing on record to suggest that stipulation
          for recovering liquidated damages was by way ofpenalty
          or that the said sum was in any way unreasonable.
c         (vii) In certain contracts, it is impossible to assess the
          damages or prove the same. Such situation is taken
          care of by Sections 73 and 74 of the Contract Act and
          in the present case by specific terms of the contract."
D          The judgment in ONGC v. Saw Pipes has been
      consistently followed till date.
          In Hindustan Zinc Ltd. v. Friends Coal
      Carbonisation, (2006) 4 SCC 445, this Court held:
E         "14. The High Court did not have the benefit of the
          principles laid down in Saw Pipes [(2003) 5 SCC 705],
          and had proceeded on the assumption that award
          cannot be interfered with even if it was contrary to the
          terms of the contract. It went to the extent of holding that
 F        contract terms cannot even be looked into for examining
          the correctness of the award. This Court in Saw
          Pipes [(2003) 5 SCC 705] has made it clear that it is
          open to the court to consider whether the award is
          against the specific terms of contract and if so, interfere
 G        with it on the ground that it is patently illegal and
          opposed to the public policy of India."
            In McDermott International Inc. v. Burn Standard Co.
      Ltd., (2006) 11 SCC 181, this Court held:
 H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                        921
       AUTHORITY[R. F. NARIMAN, J.]

 "58. In Renusagar Power Co. Ltd. v. General Electric A
Co. [1994 Supp (1) SCC 644] this Court laid down that
the arbitral award can be set aside if it is contrary to (a)
fundamental policy of Indian law; (b) the interests of
India; or (c) justice or morality. A narrower meaning to
the expression "public policy" was given therein by            B
confining judicial review of the arbitral award only on
the aforementioned three grounds. An apparent shift
can, however, be noticed from the decision of this Court
in ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705] (for
short "ONGC'J. This Court therein referred to an earlier       C
decision of this Court in Central Inland Water Transport
Corpn. Ltd. v. Brojo Nath Ganguly [(1986) 3 SCC 156:
 1986 SCC (L&S) 429: (1986) 1ATC103} wherein the
applicability of the expression "public policy" on the         D
touchstone of Section 23 of the Indian Contract Act and
Article 14 of the Constitution of India came to be
considered. This Court therein was dealing with
unequal bargaining power of the workmen and the
employer and came to the conclusion that any term of           E
the agreement which is patently arbitrary and/or
 otherwise arrived at because of the unequal bargaining
power would hot only be ultra vires Article 14 of the
 Constitution of India but also hit by Section 23 of the
 Indian Contract Act. In ONGC [(2003) 5 SCC 705] this          F
 Court, apart from the three grounds stated
 in Renusagar [1994 Supp (1) SCC 644], added another
 ground thereto for exercise of the court's jurisdiction in
 setting aside the award if it is patently arbitrary.
  59. Such patent illegality, however, must go to the root G
 of the matter. The public policy violation, indisputably,
 should be so unfair and unreasonable as to shock the
 conscience of the court. Where the arbitrator, however,
 has gone contrary to or beyond the expressed law of H
922        SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A         the contract or granted relief in the matter not in dispute
          would come within the purview of Section 34 of the Act.
          However, we would consider the applicability of the
          aforementioned principles while noticing the merits of
          the matter.
 B
           60. What would constitute public policy is a matter
          dependent upon the nature of transaction and nature
          of statute. For the said purpose, the pleadings of the
          parties and the materials brought on record would be
c         relevant to enable the court to judge what is in public
          good or public interest, and what would otherwise be
          injurious to the public good at the relevant point, as
          contradistinguished from the policy of a particular
          Government. (See State of Rajasthan v. Basant
 D        Nahata [(2005) 12 sec 77].)"
           In Centrotrade Minerals & Metals Inc. v. Hindustan
      Copper Ltd., (2006) 11SCC245, Sinha, J., held:
           "103. Such patent illegality, however, must go to the root
 E         of the matter. The public policy, indisputably, should
           be unfair and unreasonable so as to shock the
           conscience of the court. Where the arbitrator, however,
           has gone contrary to or beyond the expressed law of
           the contract or granted relief in the matter not in dispute
 F         would come within the purview of Section 34 of the Act."
           "104. What would be .a public policy would be a matter
           which would again depend upon the nature of
           transaction and the nature of statute. For the said
           purpose, the pleadings of the parties and the materials
 G
           /Jrought on record would be relevant so as to enable
           the court to judge the concept of what was a public good
           or public interest or what would otherwise be injurious
           to the public good at the relevant point as
           contradistinguished by the policy of a particular
 H
    ASSOCIATE BUILDERSv. DELHI DEVELOPMENT                          923
           AUTHORITY [R. F. NARIMAN, J.]

     government. (See State of Rajasthan v. Basant A .
     Nahata {(2005) 12 SCC 77].)"
     In DOA v. R.S. Sharma and Co., (2008) 13 SCC 80,
the Court summarized the law thus:
     "21. From the above decisions, the following principles B
     emerge:
     (a) An award, which is
     (i) contrary to substantive provisions of law; or ·
     (ii) the provisions of the Arbitration and Conciliation Act,   C
     1996; or
     (iii) against the terms of the respective contract; or
     (iv) patently illegal; or
                                                                    D
     (v) prejudicial to the rights of the parties;
     is open to interference by the court under Section 34(2)
     of the Act.
     ({J) The award could be set aside if it is contrary to:
                                                                    E
     (a) fundamental policy of Indian law; or
     (b) the interest of India; or
     (c) justice or morality.
     (c) The award could a/so be set aside if it is so unfair F
     and unreasonable that it shocks the conscience of the ·
     court.
     (d) It is open to the court to consider whether the award
     is against the spe"cific terms of contract and if so, G
     interfere with it on the ground that it is patently illegal
     and opposed to the public policy of India.
     With these principles and statutory provisions,
     particularly, Section 34(2) of the Act, let us consider
                                                                    H
924         SUPREME COURT REPORTS                    [2014] 13 S.C.R.


A          whether the arbitrator as well as the Division Bench of
           the High Court were justified in granting the award in
           respect of Claims 1 to 3 and Additional Claims 1 to 3 of
           the claimant or the appellant DOA has made out a case
           for setting aside the award in respect of those claims .
 B         with reference to the terms of the agreement duly
           executed by both parties."
           ,J.G. Engineers (P) Ltd. v. Union of India, (2011) 5 SCC
      758, held:
 c         "27. Interpreting the said provisions, this Court
           in ONGC Ltd. v. Saw Pipes Ltd.[(2003) 5 SCC 705] held·
           that a court can set aside an award under Section
           34(2)(b)(ii) of the Act, as being in conflict with the public
           policy of India, if it is (a) contrary to the fundamental
 D         policy of Indian law; or (b) contrary to the interests of
           India; or (c) contrary to justice or morality; or (d) patently
           illegal. This Court explained that to hold an award to be
           opposed to public policy, the patent illegality should
           go to the very root of the matter and not a trivial illegality.
 E         It is also observed that an award could be set aside if it
           is so unfair and unreasonable that it shocks the
            conscience of the court, as then it would be opposed to
           public policy."

 F         Union of India v. Col. L.S.N. Murthy, (2012) 1 SCC
      718, held:
           "22. In ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705]
           this Court after examining the grounds on which an
           award of the arbitrator can be- set aside under Section
 G         34 of the Act has said: (SCC p. 727, para 31)
           "31 . ... However, the award which is, on the face of it,
           patently in violation of statutory provisions cannot be
           said to be in public interest. Such award/judgment!
 H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                     925
           AUTHORITY [R. F. NARIMAN, J.]

     decision is likely to adversely affect the administration A
     of justice. Hence, in our view in addition to narrower
     meaning given to the term 'public policy' in Renusagar
     case [Renusagar Power Co. Ltd. v. General Electric Co.,
     1994 Supp (1) SCC 644] it is required to be held that
     the award could be set aside if it is patently illegal".  B
     Fundamental Policy of Indian Law
      Coming to each of the heads contained in the Saw Pipes
judgment, we will first deal with the head "fundamental policy .
of Indian Law". It has already been seen from the Renusagar C
judgment that violation of the Foreign Exchange Act and
disregarding orders of superior courts in India would be
regarded as being contrary to the fundamental policy of Indian
law. To this it could be added that the binding effect of the
judgment of a superior court b~ing disregarded would be D
equally violative of the fundamental policy of Indian law.
      In a recent judgment, ONGC Ltd. v. Western Geco
International Ltd., 2014 (9) SCC 263, this Court added three
other distinct and fundamental juristic principles which must E
be understood as a part and parcel of the fundamental policy-
of Indian law. The Court held-
     "35. What then would constitute the ''fundamental policy
     of Indian law" is the question. The decision
     in ONGC [ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC F
     705] does not elaborate that aspect. Even so, the
     expression must, in our opinion, include all such
     fundamental principles as providing a basis for
     administration ofjustice and enforcement of law in this
     country. Without meaning to exhaustively enumerate G
     the purport of the expression "fundamental policy of
     Indian law", we may refer to three distinct and
     fundamental juristic principles that must necessarily be
     understood as a part and parcel of the fundamental H
926    SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A     policy of Indian law. The first and foremost is the
      principle that in every determination whether by a court
      or other authority that affects the rights of a citizen or
      leads to any civil consequences, the court or authority
      concerned is bound to adopt what is in legal parlance
B     called a 'judicial approach" in the matter. The duty to
      adopt a judicial approach arises from the very nature
      of the power exercised by the court or the authority dqes
      not have to be separately or additionally enjoined upon
      the fora concerned. What must be remembered is that
 c    the importance of a judicial approach in judicial and
      quasi-judicial determination lies in the fact that so long
      as the court, tribunal or the authority exercising powers
      that affect the rights or obligations of the parties before
      them shows fidelity to judicial approach, they cannot
 D
      act in an arbitrary, capricious or whimsical manner.
      Judicial approach ensures that the authority acts bona
       fide and deals with the subject in a fair, reasonable and
       objective manner and that its decision is not actuated
       by any extraneous consideration. Judicial approach in
 E
       that sense acts as a check against flaws and faults that
       can render the decision of a court, tribunal or authority
       vulnerable to challenge.
        38. Equally important and indeed fundamental to the
 F      policy of Indian law is the principle that a court and so .
        a/so a quasi-judicial authority must, while determining
        the rights and obligations of parties before it, do so in
      · accordance with the principles of natural justice.
        Besides the celebrated audi alteram partem rule one
 G      of the facets of the principles of natural justice is that
        the court/authority deciding the matter must apply its
        mind to the attendant facts and circumstances while
        taking a view one way or the other. Non-application of
        mind is a defect that is fatal to any adjudication.
 H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                    927
       AUTHORITY[R. F. NARIMAN, J.]

Application of mind is best d~monstrated by disclo~ure A
of the mind and disclosure of mind is best done by
recording reasons in support of the decision which the
court or authority is taking. The requirement that an
adjudicatory authority must apply its mind is, in that
view, so deeply embedded in our jurisprudence that it B
can be described as a fundamental policy of Indian law.
 39. No less important is the principle now recognised
as a salutary juristic fundamental in administrative law
 that a decision which is perverse or so irrational that no c
reasonable person would have arrived at the same will
 not be sustained in a co.urt of law. Perversity or
irrationality of decisions is tested on the touchstone of
 Wednesbury principle [Associated Provincial Picture
 Houses Ltd. v. Wednesbury Corpn., (1948) 1KB223: D
 (1947) 2All ER 680 (CA)] of reasonableness. Decisions
that fall short of th/3 standards of reasonableness are
open to challenge in a court of law often in writ
jurisdiction of the superior courts but no less in statutory
processes wherever the same are available.                   E
40. It is neither ne.cessary nor proper for us to attempt
an exhaustive enumeration of what would constitute the
fundamental policy of Indian law nor is it possible to
place the expression in the straitjacket'of a definition.
                                                            F
What is important in the context of the case at hand is
that if on facts proved before them the arbitrators fail to
draw an inference which ought to have been drawn or if
they have drawn an inference which is on the face of it,
untenable resulting in miscarriage of justice, the G
adjudication even when made by an Arbitral Tribunal
that enjoys considerable latitude and play at the joints
in making awards will be open to challenge and may
be cast away or modified depending upon whether the
offending part is or is not severable from the rest."       H
928          SUPREME COURT REPORTS                     [2014) 13 S.C.R.


A          It is clear that the juristic principle of a "judicial approach"
      demands that a decision be fair, reasonable and objective.
      On the obverse side, anything arbitrary and whimsical would
      obviously not be a determination which would either be fair,
      reasonable or objective.
 B
             The Audi Alteram Partem principle which undoubtedly
      is a fundamental juristic principle in Indian law is also contained
      in Sections 18 and 34 (2) (a) (iii) of the Arbitration and
      Conciliation Act. These Sections read as follows:
 c          "18. Equal treatment of parties.- The parties shall
      be treated with equality and each party shall be given a full
      opportunity to present his case.
            34. Application for setting aside arbitral award.-
 D           (2) An arbitral award may be set aside by the Court
            only if.-
             (a) the party making the application furnishes proof
            that-
 E            (iii) the party making the application was not given
            proper notice of the appointment of an arbitrator or of
            the arbitral proceedings or was otherwise unable to
            present his case; "
 F          The third juristic principle is that a decision which is
      perverse or so irrational that no reasonable person would have
      arrived at the same is important and requires some degree of
      explanation. It is settled law that where-
             1. a finding is based on no evidence, or
 G          2. an arbitral tribunal takes into account something
               irrelevant to the decision which it arrives at; or
            ~3. ignores vital evidence in arriving at its decision,

        such decision would necessarily be perverse. A good
 H working test of perversity is contained in two judgments. In H.B.
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                                     929
           AUTHORITY[R. F. NARIMAN, J.]

Gandhi, Excise and Taxation Officer-cum-Assessing A
Authority v. Gopi Nath & Sons, 1992 Supp (2) SCC 312 at
p. 317, it was held:
      "7. .. ................. It is, no doubt, true that if a finding offact
      is arrived at by ignoring or excluding relevant material
                                                                 8
      or by taking into consideration irrelevant material or if
      the finding so outrageously defies logic as to suffer from
      the vice of irrationality incurri~g the blame of being
      perverse, then, the finding is rendered infirm in law."
      In Kuldeep Singh v. Commr. of Police, (1999) 2 SCC C
10 at para 10, it was held:
      "10. A broad distinction has, therefore, to be maintained
      between the decisions which are perverse and those
      which are not. If a decision is arrived at on no evidence D
      or evidence which is thoroughly unreliable and no
      reasonable person would act upon it, the order would
      be perverse. But if there is some evidence on record
      which is acceptable and which could be relied upon,
     .howsoever compendious it may be, the conclusions E
      would not be treated as perverse and the findings would
      not be interfered with."
        It must clearly be understood that when a court is applying
the "public policy" test to an arbitration award, it does not act
as a court of appeal and consequently errors of fact cannot be F
corrected. A possible view by the arbitrator on facts has
necessarily to pass muster as the arbitrator is the ultimate
master of the quantity and quality of evidence to be relied upon
when he delivers his arbitral award. Thus an award based on
                                                                    G
little evidence or on evidence which does not measure up in
quality to a trained legal mind would not be held to be invalid
on this score 1• Once it is found that the arbitrators approach is
1 Very often an arbitrator is a lay person not necessarily trained in law.

Lord Mansfield, a famous English Judge, once advised a high military            H
officer in Jamaica who needed to act as a Judge as follows:
930         SUPREME COURT REPORTS                          [2014] 13 S.C.R.


A not arbitrary or capricious, then he is the last word on facts. In
  P.R. Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H.
  Securities (P) Ltd., (2012) 1 SCC 594, this Court held:
            "21. A court does not sit in appeal over the award of an
          · Arbitral Tribunal by reassessing or reappreciating the
B
            evidence. An award can be challenged only under the
            grounds mentioned in Section 34(2) of the Act. The
            Arbitral Tribunal has examined the facts and held that
            both the second respondent and the appellant are liable.
c           The case as put forward by the first respondent has been
            accepted. Even the minority view was that the second
            respondent was liable as claimed by the first
            respondent, but the appellant was not liable only on the
            ground that the arbitrators appointed by the Stock
 D          Exchange under Bye-law 248, in a claim against a non-
            member, had no jurisdiction to decide a claim against
            another member. The finding of the majority is that the
            appellant did the transaction in the name of the second
            respondent and is therefore, liable along with th~
 E          second respondent. Therefore, in the absence of any
            ground under Section 34(2) of the Act, it is not possible
            to re-examine the facts to /ind out whether a different
            decision can be arrived at."
 F           It is with this very important caveat that the two
      fundamental principles which form part of the fundamental
      policy of Indian law (that the arbitrator must have a judicial
      approach and that he must not act perversely) are to be
      understood.
           "General, you have a sound head, and a good heart; take courage
 G         and you will do very well, in your occupation, in a court of equity.
           My advice is, to make your decrees as your head and your heart
           <lictate, to hear both sides patiently, to decide with firmness in the
           best manner you can; but be careful not to assign your reasons,
           since your determination may be substantially right, although your
           reasons may be very bad, or essentially wrong".
 H         It is very important to bear this in mind when awards of lay arbitrators
           are challenge~.
     ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                             931
            AUTHORITY [R. F. NARIMAN, J.]

      Interest of India                                                  A
        The next ground on which an award may be set aside is
that it is contrary to the interest of India. Obviously, this concerns
itself with India as a member of the world community in its
relations with foreign powers. As at present advised, we need
                                                                         8
not dilate on this aspect as this ground may need to evolv~ on
a case by case basis.
      Justice
      The third ground of public policy is, if an award is against
justice or morality. These are two different concepts in law. An C
award can be said to be against justice only when it shocks
the conscience of the court. An illustration of this can be given.
A claimant is content with restricting his claim, let us say to Rs.
30 lakhs in a statement of claim before the arbitrator and at no D
point does he seek to claim anything more. The arbitral award
ultimately awards him 45 lakhs without any acceptable reason
or justification. Obviously, this would shock the conscience of
the court and the arbitral award would be liable to be set aside
on the ground that it is contrary to "justice".                     E
      Morality
      The other ground is of "morality". Just as the expression
"public policy" also occurs in Section 23 of the Indian Contract
Act, so does the expression "morality". Two illustrations to the F
said section are interesting for they explain to us the scope of
the expression "morality".
      "(j) A, who is B's Mukhtar, promises to exercise his
      influence, as such, with B in favour of C,
      and C promises to pay 1, 000 rupees to A. The G
      agreement is void, because it is immoral.
      (k) A agrees to let her daughter to hire to B for
      concubinage. The agreement is void, because it is
                                                                         H
932        SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A         immoral, though the letting may not be punishable
          under the Indian Penal Code (XLV of 1860)."
           In Gherulal Parekh v. Mahadeo Dass Maiya, 1959
      Supp (2) SCR 406, this Court explained the concept of
      "morality" thus-
 8
         . "Re. Point 3-lmmorality: The argument under this head
           is rather broadly stated by-the learned Counsel for the
           appellant. The learned counsel attempts to draw an
           analogy from the Hindu Law relating to the doctrine of
 c         pious obligation of sons to discharge their father's debts
           and contends that what the Hindu Law considers to be
           immoral in that context may appropriately be applied
           to a case under s. 23 of the Contract Act. Neither any
           authority is cited nor any legal basis is suggested for
 D          importing the doctrine of Hindu Law into the domain of
            contracts. Section 23 of the Contract Act is inspired by
            the common law of England and it would be more useful
            to refer to the English Law than to the Hindu Law texts
            dealing with a different matter. Anson in his Law of
 E          Contracts states at p. 222 thus:
            "The only aspect of immorality with which Courts of
           Law have dealt is sexual immorality. .......... . "
            Halsbury in his Laws of England, 3rd Edn., Vol. 8,
 F         makes a similar statement,. at p. 138:
             "A contract which is made upon an immoral
           consideration or for 0 an immoral purpose is
           unenforceable, and there is no distinction in this respect
 G         between immoral and illegal contracts. The immorality
           ht~re alluded to is ·sexual immorality."

              In the Law of Contract by Cheshire and Fifoot, 3rd Edn.,
           it is stated at p. 279:

 H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                   933
       AUTHORITY[R. F. NARIMAN, J.]

  ''Although Lord Mansfield laid it down that a contract A
contra bonos mores is illegal, the law in this connection
gives no extended meaning to morality, but concerns
itself only with what is sexually reprehensible."
 In the book on the Indian Contract Act by Pollock and
                                                          8
Mui/a it is stated at p. 157:
  "The epithet "immoral" points, in legal usage, to
conduct or purposes which the State, though
disapproving them, is unable, or not advised, to visit
with direct punishment."                               C
   The learned authors confined its operation to acts
 which are considered to be immoral according to the
 standards of immorality approved by Courts. The case
 law both in England and India confines the operation of D
 the doctrine to sexual immorality. To cite only some
 instances: settlements in consideration of
 concubinage, contracts of sale or hire of things to be
 used in a brothel or by a prostitute for purposes
 incidental to her profession, agreements to pay money E
 for future illicit cohabitation, promises in regard to
 marriage for consideration, or contracts facilitating
 divorce are all held to be void on the grouhd that the
 object is immoral.
   The word "immoral" is a very comprehensive word. F
 Ordinarily it takes in every aspect of personal conduct
 deviating from the standard norms of life. It may also
 be said that what is repugnant to good conscience is
 immoral. Its varying content depends upon time, place
 and the stage of civilization of a particular society. In G
 short, no universal standard can be laid down and any
 law based on such fluid concept defeats its own purpose ..
 The provisions of S. 23 of the Contract Act indicate the
 legislative intention to give it a restricted meaning. Its H
934        SUPREME COURT REPORTS                    [2014] 13 S.C.R.


A         juxtaposition with an equally illusive concept, public
          policy, indicates that it is used in a restricted sense;
           otherwise there would be overlapping of the two
           concepts. In its wide sense what is immoral may be
           against public policy, for public policy covers political,
B         social and economic ground of objection. Decided
           cases and authoritative text-book writers, therefore,
           confined it, with every justification, only to sexual
          immorality. The other limitation imposed on the word
           by the statute, namely, "the court regards it as immoral';
c         brings out the idea that it is also a branch of the
           common law like the doctrine of public policy, and,
           therefore, should be confined to the principles
           recognized and settled by Courts. Precedents confine
           the said concept only to sexual immorality and no case
D
           has been brought to our notice where it has been applied
           to any head other than sexual immorality. In the
           circumstances, we cannot evolve a new head so as to
           bring in wagers within its fold."
E        This Court has confined morality to sexual morality so
   far as section 23 of the Contract Act is concerned, which in the
   context of an arbitral award would mean the enforcement of
   an award say for specific performance of a contract involving
   prostitution. "Morality" would, if it is to go beyond sexual morality
 F necessarily cover such agreements as are not illegal but would
   not be enforced given the prevailing mores of the day. However,
   interference on this ground would also be only if something
   shocks the court's conscience.
G          Patent Illegality
        We now come to the fourth.head of public policy namely,
  patent illegality. It must be remembered that under the
  explanation to section 34 (2) (b ), an award is said to be in
  conflict with the public policy of India if the making of the award
H was induced or affected by fraud or corruption. This ground is
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                   935
           AUTHORITY[R. F. NARIMAN, J.]

perhaps the earliest ground on which courts in England set A
aside awards under English law. Added to this ground (in 1802)
is the ground that an arbitral award would be set aside if there
were an error of law by the arbitrator. This is explained by Lord
Justice Denning in R v. Northumberland Compensation
Appeal Tribunal. Ex Parte Shaw., 1952 1 All ER 122 at page B
130:
     "Leaving now the statutory tribunals, I turn to the awards
     of the arbitrators. The Court of King's Bench never
     interfered by certiorari with the award of an arbitrator, c
     because it was a private tribunal and not subject to the
     prerogative writs. If the award was not made a rule of
     court, the only course available to an aggrieved party
     was to resist an action on the award or to file a bill in
     equity. If the award was made a rule of court, a motion D
     could be made· to the court to set it aside for misconduct
     of the arbitrator on the ground that it was procured by
     corruption or other undue means: see the statute 9 and
      10 Will. Ill, c. 15. At one time an award could not be
     upset on the ground of error of law by the arbitrator E
     because that could not be said to be misconduct or
     undue means, but ultimately it was held in Kent v.
     Elstob, (1802) 3 East 18, that an award could be set
     aside for error of law on the face of it. This was regretted
     by Williams, J., in Hodgkinson v. Fernie, (1857) 3 F
      C. 8. N. S. 189, but is now well established."
      This, in turn, led to the famous principle laid down in
Champsey Shara Company v. The Jivraj Balloo Spinning
and Weaving Company Ltd., AIR 1923 PC 66, where the G
Privy Council referred to Hodgkinson and then laid down:
      "The Jaw on the subject has never been more clearly
      stated than by Williams, J. in the case of Hodgkinson
      v. Fernie (1857) 3 C.B.N.S. 189.
                                                               H
936   SUPREME COURT REPORTS                   [2014] 13 S.C.R.


A     ''The law has for many years been settled, and remains
      so at this day, that, where a cause or matters in
      difference are referred to an arbitrator a lawyer or a
      layman, he is constituted the sole and final judge of all
      questions both of law and of fact ...... The only
B     exceptions to that rule are cases where the award is the
      result of corruption or fraud, and one other, which though
      it is to be regretted, is now, I think firmly established
      viz., where the question of law necessarily arises on the
      face of the award or upon some paper accompanying
c     and forming part of the award. Though the propriety of
      this latter may very well be doubted, I think it may be
      considered as established."
       "Now the regret expressed by Williams, J. in Hodgkinson
D      v. Fernie has been repeated by more than one learned
      Judge, and it is certainly not to be desired that the
      exception should be in any way extended. An error in
      law on the face of the award means, in their Lordships'
       view, that you can find in the award or a document
 E    actually incorporated thereto, as for instance, a note
      appended by the arbitrator stating the reasons for his
      judgment, some legal proposition which is the basis of
       the award and which you can then say is erroneous. It
       does not mean that if in a narrative a reference is made
 F     to a contention of one party that opens the door to seeing
       first what that contention is, and then going to the
       contract on which the parties' rights depend to see if
       that contention is sound. Here it is impossible to say,
       from what is shown on the face of the award, what
 G     mistake the arbitrators made. The only way that the
       learned judges have arrived at finding what the mistake
       was is by saying: "Inasmuch as the Arbitrators awarded
       so and so, and inasmuch as the letter shows that then
       buyer rejected the cotton, the arbitrators can only have
H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                            937
           AUTHORITY [R. F. NARIMAN, J.] .

     arrived at that result by totally misinterpreting Cl.52." A
     But they were entitled to give their own interpretation to
     Cl. 52 or any other article, and the award will stand
     unless, on the face of it they have tied themselves down
     to some special legal proposition which then, when
     examined, appears to be unsound. Upon this point, B
     therefore, their Lordships think that the judgment of
     Pratt, J was right and the conclusion of the learned
     Judges of the Court of Appeal erroneous."
      This judgment has been consistently followed in India to         c
test awards under Section 30 of the Arbitration Act, 1940.
       In the 1996 Act, this principle is substituted by the 'patent
illegality' principle which, in turn, contains three sub heads -
       (a) a contravention of the substantive law of India would D
result in the death knell of an arbitral award. This must be
understood in the sense that s1.,1ch illegality must go to the root
of the matter and cannot be of a trivial nature. This again is a
really a contravention of Section 28(1)(a) of the Act, which reads
as under:                                                           E
      "28. Rules applicable to substance of dispute.-(1)
      Where the place of arbitration is situated in India,-
      ( a) in an arbitration other than an international
      commercial arbitration, the arbitral tribunal shall decide       F
      the dispute submitted to arbitration in accordance with
      the substantive law for the time being in force in India;"
     (b) a contravention of the Arbitration Act itself would be
regarded as a patent illegality- for example if an arbitrator gives
no reasons for an award in contravention of section 31 (3) of G
the Act, such award will be liable to be set aside.
     (c) Equally, the third sub-head of patent illegality is really
a contravention of Section 28 (3) of the Arbitration Act, which
reads as under:                                                        H
938        SUPREME COURT REPORTS                    [2014] 13 S.C.R.

A          "28. Rules applicable to substance of dispute.- (3)
           In all cases, the arbitral tribunal shall decide in
           accordance with the terms of the contract and shall take
           into account the usages of the trade applicable to the
           transaction."
B
        This last contravention must be understood with a caveat.
  An arbitral tribunal must decide in accordance with the terms
  of the contract, but if an arbitrator construes a term of the
  contract in a reasonable manner, it will not mean that the award
C can be set aside on this ground. Construction of the terms of a
  contract is primarily for an arbitrator .to decide unless the
  arbitrator construes the contract in such a way that it could be
  said to be something that no fair minded or reasonable person
  could do.
D           In McDermott International Inc. v. Burn Standard Co.
      Ltd., (2006) 11 SCC 181, this Court held as under:
           "112. It is trite that the terms of the contract can be
           express or implied. The conduct of the parties would
 E         also be a relevant faCtor in the matter of construction of
           a contract. The construction of the contract agreement
           is within the jurisdiction of the arbitrators having regard
           to the wide nature, scope and ambit of the arbitration
           agreement and they cannot be said to have misdirected
 F         themselves in passing the award by taking into
           consideration the conduct of the parties. It is also trite
           that correspondences exchanged by the parties are
           required to be taken into consideration for the purpose
           of construction of a contract. Interpretation of a contract
 G         is a matter for the arbitrator to determine, even if it gives
           rise to determination of a question of law. (See Pure
           Helium India (P) Ltd. v. ONGe [(2003) 8 sec 593]
           and 0.0. Sharma v. Union of India [(2004) 5 sec 325]).

 H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                        939
           AUTHORITY[R. F. NARIMAN, J.]

     113. Once, thus, it is held that the arbitrator had the A
    jurisdiction, no further question shall be raised and the
     court will not exercise its jurisdiction unless it is found
     that there exists any bar on the face of the award."
     In MSK Projects (I) (JV) Ltd. v. State of Rajasthan,
                                                                   8
(2011) 10 SCC 573, the Court held:
     "17. If the arbitrator commits an error in the construction
     of the contract, that is an error within his jurisdiction.
     But if he wanders outside the contract and deals with
     matters not allotted to him, he commits a jurisdictional      C
     error. Extrinsic evidence is admissible in such cases
     because· the dispute is not something which arises
     under or in relation to the contract or dependent on the
     construction of the contract or to be determined within
     the award. The ambiguity of the award can, in such            D
      cases, be resolved by admitting extrinsic evidence. The
     rationale of this rule is that the nature of the dispute is
     something which has to be determined outside and
     independent of what appears in the award. Such a
     jurisdictional error needs to be proved by evidence           E
      extrinsic to the award. (See Gobardhan Oas v. Lachhmi
     Ram [AIR          1954      SC      689],     Thawardas
      Pherumal v. Union of India [AIR 1955 SC 468], Union
      of India v. Kishori/al Gupta & Bros. [AIR 1959 SC 1362],     F
     Alopi Parshad & Sons Ltd. v. Union of India [AIR 1960
      SC 588], Jivarajbhai Ujamshi Sheth v. Chintamanrao
      Balaji [AIR 1965 SC 214] and Renusagar Power Co.
      Ltd. v. General Electric Co. [(1984) 4 SCC 679 : AIR
      1985SC1156])."                                               G
    In Rashtriya lspat Nigam Ltd. v. Dewan Chand Ram
Saran, (2012) 5 SCC 306, the Court held:
     "43. In any case, assuming that Clause 9.3 was capable
     of two interpretations, the view taken by the arbitrator      H
940   SUPREME COURT REPORTS                   [2014] 13 S.C.R.


A     was clearly a possible if not a plausible one. It is not
      possible to say that the arbitrator had travelled outside
      his jurisdiction, or that the view taken by him was against
      the terms of contract. That being the position, the High
      Court had no reason to interfere with the award and
B     substitute its view in place of the interpretation accepted
      by the arbitrator.
      44. The legal position in this behalf has been
      summarised in para 18 of the judgment of this Court
c     in SAIL v. Gupta Brother Steel Tubes Ltd. [(2009) 10
      SCC 63: (2009) 4 SCC (Civ) 16] and which has been
      referred to above. Similar view has been taken later
      in Sumitomo Heavy Industries Ltd. v. ONGC
      Ltd. u2010) 11 sec 296: (2010) 4 sec (Civ) 459] to
D     which one of us (Gokhale, J.) was a party. The
      observations in para 43 thereof are instructive in this
      behalf.
      45. This para 43 reads as follows: (Sumitomo
      case [(2010) 11 sec 296: (2010) 4 sec (Civ) 459],
E     sec p. 313)
         "43 . ... The umpire has considered the fact situation
         and placed a construction on the clauses of the
         agreement which according to him was the correct
 F       one. One may at the highest say that one would have
         preferred another construction of Clause 17. 3 but that
         cannot make the award in any way perverse. Nor can
         one substitute one's own view in such a situation, in
         place of the one taken by the umpire, which would
G        amount to sitting in appeal. As held by this Court
         in Kwality Mfg. Corpn. v. Central Warehousing
         Corpn. [(2009) 5sec142: (2009) 2 sec (Civ) 406]
         the Court while considering challenge to arbitral
         award does not sit in appeal over the findings and
H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                        941
           AUTHORITY[R. F. NARIMAN, J.]

        decision of the arbitrator, which is what the High Court A
        has practically done in this matter. The umpire is .
        legitimately entitled to take the view which he holds
        to be the correct one after considering the material
        before him and after interpreting the provisions of
        the agreement. If he does so, the decision of the B
        umpire has to be accepted as final and binding."
       13. Applying the tests laid down by this Court, we have
to examine whether the Division Bench has exceeded its
jurisdiction in setting aside the arbitral award impugned before   c
it.
      14. A large part of the judgment is an extract from the
arbitral award. It is important to note that the Division Bench
held:
                                                                D
     "9. A perusal of the award would reveal, from the portions
     extracted herein above, that with reference to evidence
     led before him the learned Arbitrator has held delay
     attributable to ODA, a finding of fact which is based on
     evidence and rightly conceded to by Sh. Bhupesh E
     Narula, Advocate who appears for ODA as being
     beyond judicial review power of this Court pertaining to
     a reasoned award. But, while awarding Rs.8,27,9601-
     the reasoning adopted by the learned Arbitrator is
     questioned as being the result of ignoring the well- F
     recognized legal principles on the subject, Learned
     counsel argued that the reasoning is the ipse dixit of
     the learned Arbitrator."
       15. The Division Bench while considering claims 9, 10,
11 and 15 found fault with the application of Hudson's formula G
which was set out by the learned Arbitrator in order to arrive at
the claim made under these heads. The Division Bench said
that it was not possible for an Arbitrator to mechanically apply
a certain formula however well understood in the trade. This H
942          SUPREME COURT REPORTS                  [2014] 13 S.C.R.


A       itself is going outside the jurisdiction to set aside an award
        under Section 34 in as much as in McDermott's case (supra),
      · it was held:
            "104. It is not in dispute that Mil had examir:ted one Mr
            D.J. Parson to prove the said claim. The said witness
B
            calculated the increased overheads and loss of profit
            on the basis of the formula laid down in a manual
            published by the Mechanical Contractors Association
            of America entitled "Change Orders, Overtime,
c           Productivity" commonly known as the Emden Formula.
            The said formula is said to be widely accepted in
            construction contracts for computing increased
            overheads and loss of profit. Mr D.J. Parson is said to
            have brought out the additional project management
D           cost at US$ 1, 109,500. We may at this juncture notice
            the different formulas applicable in this behalf.
            (a) Hudson Formula: In Hudson's Building and
            Engineering Contracts, Hudson Formula is stated in
            the following terms:
E
            "Contract head      x   Contract         x     Period
            office overhead         sum                     of
            and profit              Contract               delay"
F           percentage              period


            In the Hudson Formula, the head office overhead
            percentage is taken from the contract. Although the
            Hudson Formula has received judicial support in many
G
            cases, it has been criticised principally because it
            adopts the head office overhead percentage from the
            contract as the factor for calculating the costs, and this
            may bear little or no relation to the actual head office
            costs of the contractor.
H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                    943
       AUTHORITY [R. F. NARI MAN, J.]

(b) Emden Formula: In Emden's Building Contracts and A
Practice, the Emden Formula is stated in the following
terms:
"Head office    x     Contract     x     Period
overhead and            sum                of
profit                                    delay"           B


 100                     Contract
                          period
Using the Emden Formula, the head office overhead C
percentage is arrived at by dividing the total overhead
cost and profit of the contractor's organisation as a whole
by the total turnover. This formula has the advantage
of using the contractor's actual head office overhead
and profit percentage rather than those contained in D
the contract. This formula has been widely applied and
has received judicial support in a number of cases
including Norwest Holst Construction Ltd. v. Coop.
Wholesale Society Ltd. [Decided on 17-2-1998, [1998]
EWHC Technology 339], Beechwood Development Co. E
(Scotland) Ltd. v. Mitchell [Decided on 21-2-2001,
(2001) GILL 1727] and Harvey Shopfitters Ltd. v. Adi
Ltd. [Decided on 6-3-2003, (2004) 2 All ER 982: [2003]
EWCA Civ 1757].
 (c) Eichleay Formula: The Eich/eay Formula was            F
 evolved in America and derives its name from a case
 heard by the Armed Services Board of Contract
 Appeals, Eichleay Corporation. It is applied in the
 following manner:
 Contract       x      Total          =      Overhead      G
 bH/ings               overhead              allocable
                       for                   to      the
                       contract              contract
                       period
 Total
 bfllings for
 contract                                                  H
 period
944     SUPREME COURT REPORTS                [2014) 13 S.C.R.


A     Sep2
                                         =       Daily overhead rfie
      ADocal:ie ovethead

      Total days of cmtract

B      Step3
      Daily                x   N.Jmber       =         Armt.nt    d
      CCX'ltract               d days                  unciJsorbed
      overhead                 dde/ay                  overhead'
      rate

c      This formula is used where it is not possible to prove
       loss of opportunity and the claim is based on actual
       cost. It can be seen from the formula that the total head
       office overhead during the contract period is first
       determined by comparing the value of work carried out
D      in the contract period for the project with the value of
       work carried out by the contractor as a whole for the
       contract period. A share of head office overheads for
       the contractor is allocated in the same ratio and
       expressed as a lump sum to the particular contract. The
E      amount of head office overhead allocated to the
       particular contract is then expressed as a weekly
       amount by dividing it by the contract period. The period
       of delay is then multiplied by the weekly amount to give
       the total sum claimed. The Eich/eay Formula is
F      regarded by the Federal Circuit Courts of America as
       the exclusive means for compensating a contractor for
       overhead expenses.
       105. Before us several American decisions have been
G      referred to by Mr. Dipankar Gupta in aid of his
       submission that the Emden Formula has since been
       widely accepted by the American courts being Nicon
       Inc. v. United States [Decided on 10-6-2003 (USCA
       Fed Cir), 331 F. 3d 878 (Fed. Cir. 2003)], G/adwynne
H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                      945
           AUTHORITY [R. F. NARI MAN, J.]

     Construction Co. v. Mayor and City Council of A
     Baltimore [Decided on 25-9-2002, 807 A. 2d 1141
     (2002) : 147 Md. App. 149] and Charles G. William
     Construction Inc. v. White [271 F 3d 1055 (Fed. Cir.
     2001)].
                                                               B
     106. We do not intend to delve deep into the matter as
     it is an accepted position that different formulae can be
     applied in different circumstances and the question as
     to whether damages should be computed by taking
     recourse to one or the other formula, having regard to       c
     the facts and circumstances of a particular case, would
     eminently fall within the domain of the arbitrator."
      16. Obviously, the ~ivision Bench has exceeded its
jurisdiction in interfering with a possible view of the Arbitrator
on facts.                                                          D
      17. The Division Bench then went on to hold:
     "17. There is admitted/¥ no evidence that the contractor
     i.e. the respondent had a central establishment. It
     appears to be a case where the contractor is petty E
     contractor and the only expenses incurred are at the
     site. The claim is towards hire charges paid for
     centering and shuttering, hiring tools, plants and
     scaffoldings i.e. the claim is not for the contractor's own
     equipment lying idle. There is just no evidence that the F
     contractor paid charges as claimed by him. Not a single
     bill raised by the alleged person who let on hire the
     equipment to the contractor has been filed nor any
     evidence adduced for the payment made. Except for G
     listing a 10 HP Water Pump, 4 number 1 HP water
     pump, 3 mixers, 250 scaffolding bamboos, 150 bal/is
     and 2 vibrators in Annexure-J to the Statement of Claim,
     no document proving hiring the same  '      and brought at
     the site has been led. We highlight that the claim is on H
946   SUPREME COURT REPORTS                   [2014] 13 S.C.R.


A     account of hire Charges paid and there is no evidence
      of said payment. It does happen that where a work is
      stopped, the person who taken an equipment on hire
      returns the same and re-hires the same when work
      recommences. Thus, Claim No. 9, 10 and 11 cannot
B     be allowed because there is no evidence to support the
      claims. Damages on account of establishment
      expenses incurred during period contract got prolonged
      have certainly to be recompensed, but we find no
      evidence in the form of books of accounts, vouchers
c     etc. to show payments to the staff or expenses incurred
      in maintaining an establishment at site in the form of a
      site office. The wages register, photocopy whereof was
      filed before the ArbitratOr, pertains to wages paid to the
      unskilled, semi-skilled and skilled labour deployed to
 D
      execute the works. yp The pleadings pertaining to the
      claim would show that as per the contractor he had
      deployed one Executive Officer, one Graduate
      Engineer, one Junior Engineer, one Accountant, one
      Storekeeper and Supervisor and one Mechanic at the
 E
      site and had also deployed watch and ward. Details of
      the persons employed have been listed in Annexure-
      N to the Statement of Claim and the documents filed to
      establish the same would evidence that the contractor
 F    has filed photocopies of the salary register, which are
       available from pages No. 1255 to 1322, but
       unfortunately for the contractor, the cat is out of the bag
       when we look at the documents. They pertain to
      payments made for a site at Mayur Vihar. We highlight
 G     that the contract in question pertains to flats and houses
       at Tri/okpuri and not Mayur Vihar. It is apparent that the
       contractor has tried to pull the wool on the eyes of the
       primary adjudicator of the claim. It is not the case of the
       contractor that these persons were simultaneously
 H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                         947
           AUTHORITY [R. F. NARIMAN, J.]

     supervising the work at two sites. Assuming this was the A
     case, the matter would then have been adjudicated with
     reference to same number of persons supervising two
     sites and the time spent at each site by them.
     18. . Thus, the award pertaining to Claim Nos. 9, 10, 11 B
     and 15 is liable to be sent aside and it is so set aside.
     We need not therefore take corrective action on the
     apparent error i.e. the learned Arbitrator has worked out
     the claim on the original contract value of
     Rs. 87,66,6781-, of course by reducing it by 15%, but c
     ignoring that final work executed was only in sum of
     Rs. 62, 84, 845/-."
       18. Mr. Verma argued correctly that there is nothing on
record to show that the contractor is a petty contrador and
that the only expenses incurred are at the site. He has shown       D
us that the contract itself required execution of the work by a
Class-I contractor and has further shown us that Class-I
contractors require to have certain stipulated numbers of works
worth large amounts before they can apply for the tender and
that their financial soundness has to be attested too by banker's   E
certificate showing that their worth is over 10 crores of rupees.
Further, he has pointed out from the statement of claims before
the Arbitrator that there was evidence for claims 9, 10 and 11
laid before the Arbitrator which the Arbitrator has in fact         F
accepted. Also establishment expenses were set out in great
detail before the Arbitrator and it is only on this evidence that
the Arbitrator ultimately has awarded these claims. Mr. Verma
is also right in saying that the Division Bench was completely
wrong in stating that the establishment expenses pertained to       G
payments for a site at Mayur Vihar as opposed to Trilok Puri
which were where the aforesaid houses were to be
constructed. He pointed out that in. the completion certificate
 dated· 301h May, 1997 given by the ODA to the appellant, it is
                                                                    H
948          SUPREME COURT REPORTS                     [2014] 13 S.C.R.


A clear that the houses that were, in fact, to be constructed were
  in Mayur Vihar, Phase-II, which is part of the Trilok Puri trans-
  Yamuna area.
            It is most unfortunate that the Division Bench did not
      advert to this crucial document at all. This document shows
8
      not only that the Division Bench was wholly incorrect in its
      conclusion that the contractor has tried to pull the wool over
      the eyes over the DDA but it should also have realized that the
      DDA itself has stated that the work has been carried out
C     generally to its satisfaction barring some extremely minor
      defects which are capable of rectification. It is clear, therefore,
      that the Division Bench obviously exceeded its jurisdiction in
      interfering with a pure finding of fact forgetting that the Arbitrator
      is the sole Judge of the quantity and quality of evidence before
 D    him and unnecessarily bringing in facts which were neither
      pleaded nor proved and ignoring the vital completion certificate
      granted by the DDA itself. The Divisio,n Bench also went wrong
      in stating that as the work completed was only to the extent of
      Rs. 62,84,845/-, Hudson's formula should have been applied
 E    taking this figure into account and not the entire contract value
      of Rs.87,66,678/- into account.




         "Contract     head       x   Contract              x         Period
 G       office    overhead           §.Yl!l                          of
         and           profit                                         delay"
       , percentage                    Contract
                                       period

            In the Hudson Formula, the head office overhead
 H          percentage is taken from the contract. Although the
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                        949
           AUTHORITY [R. F. NARI MAN, J.]

     Hudson Formula has received judicial support in many A
     cases, it has been criticised principally because it
     adopts the head office overhead percentage from the
     contract as the factor for calculating the costs, and this
     may bear little or no relation to the actual head office
     costs of the contractor."                                  B
      20. It is clear that to apply this formula one has to take
into account the contract value that is awarded and not the
work completed. On this score again, the Division Bench is to
be faulted.                                                        c
      21. In dealing with claims 12 and 13, the Division Bench
stated:          ·
     "19. Pertaining to Claim No.12 and 13, the learned
     Arbitrator has recompensed the contractor 20% price D
     hike in the cost of material and labour noting, that there
     was a steep hike in the period in question when the
     contract got prolonged by 25 months. We highlight that
     though the Arbitrator has found the delay to be 25
     months, recompense has been restricted to only 20 E
     months.
      20. As noted herein above, partial recompense under
      Clause 1OC, has been granted to the contractor, but
      the same i.e. the Clause in question requiring
      applicability during contract stipulated period, it is       F
    . apparent that the contractor would be entitled to full
      recompense for price hike during the extended 25
      months period and not the 20 months to which the
      learned Arbitrator has restricted the recompense to.
                                                                   G
      21. But, for the benefit granted under Clause. 10C
      wherein Rs. 1,62,3871-, Rs.46, 1841- and Rs.12,9221-
      have been awarded under Claim Nos. 2, 3 and 4, said
      amounts have to be adjusted, but not in full, for the
                                                                   H
950        SUPREME COURT REPORTS                  (2014] 13 S.C.R.


A         reason these include the amounts payable during the
          contract stipulated period.
          22. The total of the three sums comes to Rs, 2, 21, 4931-.
          We have another problem. Neither counsel could help
          us identify the components thereof i.e. the component
B
          relatable to the 9 months during which the work had to
          be completed and the 25 months during which the
          contract got prolonged. Thus, we apply the Rule of
          'Rough and Ready Justice'. We divide the sum by 34
c         to work out the proportionate increase per month. Rs.
                                     =
          2,21,4931-divided by 34 Rs.6,514.50and multiplying
          the same by 25, the figure comes to Rs.1,62,862.50.
          23. Adopting, for the reasons given by the Arbitrator,
          that 20% hike in the balance work done after the contract
D         stipulated period i.e. benefit to be granted under this
          head for work done in sum of Rs.37,02,0661- and
          accepting the sum of Rs. 7, 20, 0001- being the resultant
          figure, subtracting Rs.1,62,862.50, the figure arrived at
          is Rs. 5, 57, 137. 50."
 E
          22. Here again, the Division Bench has interfered wrongly
   with the arbitral award on several counts. It had no business
   to enter into a pure question of fact to set aside the Arbitrator
   for having applied a formula of 20 months instead of 25 months.
 F Though this would inure in favour of the appellant, it is clear
   that the appellant did not file any cross objection on this score.
   Also, it is extremely curious that the Divisior;i Bench found that
   an adjustment would have to be made with claims awarded
   under claims 2, 3 and 4 which are entirely separate and
 G independent claims and have nothing to do with claims 12 and
   13. The formula then applied by the Division Bench was that it
   would itself do "rough and ready justice". We are at a complete
   loss to understand how this can be done by any court under
   the jurisdiction exercised under Section 34 of the Arbitration
 H
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                      951
           AUTHORITY [R. F. NARIMAN, J.]

Act. As has been held above, the expression "justice" when it A
comes to setting aside an award under the public policy ground
can only mean that an award shocks the conscience of the
court. It cannot possibly include what the court thinks is unjust
on the facts of a case for which it then seeks to substitute its
view for the Arbitrator's view and does what it considers to be B
"justice". With great respect to the Division Bench, the whole
approach to setting aside arbitral awards is incorrect.' The
Division Bench has lost sight of the fact that it is not a first
appellate court and cannot interfere with errors of fact.
                                                                 c
      23. We come now to the arguments of Mr. Sharan in
support of the Division Bench judgment. The learned counsel
strongly relied on clause 1OC and clause 22. These two clauses
are set out as below:
     Clause 1OC of the agreement reads as follows:               D
     "If during the progress of the works, the price of any
     material incorporated in the works,· yp(not being a
     material supplied from the Engineer-in-Charge 's stores
     in accordance with Clause 10 hereof and/or wages of E
     labour increases as direct result of the coming into force
     of arw fresh law, or statutory rule or order (but not due to
     any changes in sales tax) and such increase exceed
     ten per cent of the price and/or wages prevailing at the
     time of receipt of the tender for the work, and contractor F
     thereupon necessarily and properly pays in respect of
     the material (incorporated in the work) such increased
     price and/or in respect of labour engaged on the
     execution of the work such increased wages, then the
     amount of the contract shall accordingly be varied G
     provided always that any increase so payable is not, in
     the opinion of the Superintending Engineer (whose
     decision shall be final and binding) attributable to delay
     in execution of the contract within the control of the
                                                                 H
952   SUPREME COURT REPORTS                    [2014) 13 S.C.R.


A     contractor. Provided, however, no reimbursements shall
      be made if the increase is not more than 10% of the
      said prices/wages and if so the reimbursements shall
      be made only on the excess over 10% and provided
      further that any such increase shall not be payable if
 B    such increase has become operative after the contract
      .or extended date of completion of the work in question.
      If during the progress of the works, the price of any
      material incorporated in the works (not being a material
 c    supplied from the Engineer-in-Charge's stores in
      accordance with Clause 10 hereof) and/or wages of
      lal>aur is decreased as a direct result of the coming
      into force of any fresh law or statutory rule or order (but
      not due to any changes in sales tax) and such decrease
 D    exceeds ten per cent of the prices and/or wages
      prevailing at the time of receipt of the tender for the work,
      Delhi Development Authority shall in respect of
      materials incorporated in the work (not being materials
       supplied from the Engineer-in-Charge's stores in
 E    accordance with Clause 10 hereof) and/or labour
      engaged on the execution of the work after the date of
      coming into force of such law, statutory rule ororder be
      entitled to deduct from the dues of the contractor such
       amount as shall be equivalent of difference between
 F     the prices of materials and/ or wages as they prevailed
       at the time of receipt of tender for the work minus ten
       per cent thereof and the prices of materials and/ or
       wages of labour on the coming into force of such law,
       statutory rule or order.
 G
      The contractor shall for the purpose of this condition
      keep such books of account and other documents as
      are necessary to show the amount of any increase
      claimed or reduction available and shall allow
 H
ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                    953
       AUTHORITY [R. F. NARI MAN, J.]

inspection of the same by a duly authorised A
representative of Delhi Development Authority and
further shall, at the request of the Engineer-in-Charge
furnish, verified in such a manner as the Engineer-in-
Charge may require. Any document, so kept and such
other information as the Engineer-in-Charge may B
require.
The contractor shall, within a reasonable time of his
becoming aware of any alteration in the prices of any
such materials and/ or wages of labour give notice         c
thereof to the Engineer-in- Charge stating that the same
is given in pursuance to the condition together with all
information relating thereto which he may be in a
position to supply."
Clause 22 reads as follows:                                D

"All sums payable by way of compensations under any
of these conditions shall be, considered as reasonable
compensation to be applied to this use of Delhi
Development Authority without reference to the actual E
loss or damage sustained, and whether or not any
damage shall have been sustained.
 Specifications and Conditions:
1. The contractor must get acquainted with the F
proposed site for the works and study specifications and
conditions carefully before tendering. The work shall
be executed as per programme approved by the
Engineer-in-Charge. If part of site is not available for
any reasons or there is some unavoidable delay in G
supply of materials stipulated by the Departments, the
programme of construction shall be modified
accordingly and the contractor shall have no claim for
any extras or compensation on this account."
                                                         H
954         SUPREME COURT REPORTS                 [2014] 13 S.C.R.


A         24. Clause 1OC concerns itself with the price of material
   incorporated in the works or wage or labour increases. It has
   been seen that claims 9, 10 and 11 have nothing to do with
   either of the aforesaid subjects. In seeking to apply this clause
   to claim 15, the simple answer is that this clause will not apply
 B when a claim for damages is made. Further, the Arbitrator
   considered this clause in d.etail and only awarded amounts
   under this clause in excess of 10 percent as required by the
   clause when it came to awarding amounts under claims 2, 3
   and 4, which fell within the ambit of clause 1OC. The DDA in
 C the appeal before the Division Bench correctly gave up any
   challenge to these claims as has been recorded in paragraph
   4 of the order under appeal.
         25. The Arbitrator has dealt with this clause in detail and
 D has construed and applied the same correctly while dealing
   with claims 2, 3 and 4 and has obviously not applied the said
   clause to claims 9, 10, 11 and 15 as no occasion for applying
   the same arose. The award cannot be faulted on this ground.
            26.Also, so far as clause 22 is concerned, the DDAdid
 E    not raise any argument based on this clause before the learned
      Arbitrator. However, it must in fairness be stated that it was
      argued before the learned Single Judge. In para 15 of his
      judgment, the learned Judge sets the clause out and then
 F    follows a judgment of the High Court of Delhi in Kochhar
      Construction Works v. DOA & Anr., (1998) 2 Arb. LR 209.
      Apart from the fact that a learned Single Judge of the same
      court is bound by a previous judgment of a Single Judge, the
      conclusion of the learned Single Judge that if the appellant is
 G    at fault and the contract is prolonged for an inordinate period
      of time, it cannot be said that the respondents cannot be
      compensated for the same is correct. Besides, this point was
       not urged before the Division Bench and must be taken to be
      given up. Mr. Sharan cited Harsha Constructions v. Union
 H    of India & Ors., (2014) 9 sec 246 to say that in respect of
    ASSOCIATE BUILDERS v. DELHI DEVELOPMENT                      955
           AUTHORITY [R. F. NARIMAN, J.]

excepted matters, no arbitration is possible, and that this being A
a jurisdictional point, he should be allowed to raise it before
us. Unfortunately for Mr. Sharan, the clause does not operate
automatically. It only operates if an objection is taken stating
that part of the site is not available for any reason. Nowhere
has the DDA stated which part-of the site is not available for B
any reason. Further, the learned Single Judge's reason for
rejecting an argument based on this clause also commends
itself to us as the object of this clause is that no claim for extras
should be granted only if there is an unavoidable delay. We
have seen that the delay was entirely avoidable and caused C ·
solely by the DDA itself.
      27. One more point needs to be noted. An argument was
made before the learned Single Judge that there has been a
duplication of claims awarded. The learned Judge dealt with D
this argument as follows:
     "18. Learned counsel for the petitioner in respect of
     ground P, once again makes a reference to the issue
     that there is overlapping of the claim. I am unable to
     accept the submission made by the learned counsel. E
     The consequence of delay may have more than one
     ramifications including the cost of material the
     supervision required at the site, the inability of the
     contractor to utilise the manpower at some other place, F
     the inability of the contractor to make, profits from some
     other contract by utilisation of the same resources. All
     these aspects are liable to be considered. The Arbitrator
     has considered the claims separately and has dealt
     with, claims 9, 10, 11 & 15 together. Claims 12 & 13 G
     have been thereafter dealt with on the same principles
     since it was found that it was not the respondent, who
     was responsible for the delay for a period of 25 months
     beyond the stipulated condition of 9 months.
                                                                 H
956          SUPREME COURT REPORTS                 [2014] 13 S.C.R.


A            19. There is thus no question of overlapping in different
            l1eads and the grievance of the petitioner is rejected."
         28. The Single Judge is clearly right. We have gone
   through all the 15 claims supplied to us and we find that none
 B of these claims are in fact overlapping. They are all contained
   under separate heads. This argument, therefore, must also
   fail.
         29. The appeal is, therefore, allowed and the judgment
   of the Division Bench is set aside. The judgment of the Single
 C Judge is upheld and consequently, the Arbitral award dated
   23'd May, 2005 is as a whole upheld. There will be no order as
   to costs.


      Kalpana K. Tripathy                               Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.