Created byFuzzy Cloud

Supreme Court of India

ALPHA CORP DEVELOPMENT PRIVATE LIMITEDversusGREATER NOIDA INDUSTRIAL DEVELOPMENT AUTHORITY (GNIDA) AND OTHERS

Citation
2026 INSC 449
Decided
5 May 2026
Disposal
Disposed off

Holding

The Court held that the subsidiaries were mere fronts for EIL, the corporate veil was lifted, the lease‑hold lands could be treated as assets in the CIRP, GNIDA must be a party to the process, and the resolution plans of Alpha and Roma were restored with GNIDA’s dues to be paid without penal interest.

Summary

The Supreme Court examined the Corporate Insolvency Resolution Process (CIRP) of Earth Infrastructures Limited (EIL) and whether the lease‑hold lands held by its subsidiaries could be treated as assets of the corporate debtor. The Court found that the subsidiaries were merely fronts for EIL, which was the real developer, and therefore the corporate veil could be lifted. Consequently, the assets of the subsidiaries could be dealt with in the CIRP, and GNIDA, as the lessor, had to be made a party to the proceedings. The Court restored the resolution plans of Alpha Corp and Roma, directing them to pay GNIDA’s dues without penal interest and to complete the projects within stipulated time‑frames. It also ordered GNIDA to recalculate its dues, barred it from claiming interest for the 24‑month period, and dismissed several intervenor applications, while allowing the main appeals.

Issues considered

  • Whether, in the CIRP of Earth Infrastructures Limited, the assets of its land‑holding subsidiaries can be treated as assets of the corporate debtor.
  • Whether the resolution plans could lawfully include transfer of lease‑hold rights of the subsidiaries without GNIDA's prior permission.
  • Whether assets of subsidiary companies can be dealt with in the CIRP of the holding company.
  • Whether GNIDA should have been made a party to the CIRP and heard before approval of any resolution plan affecting the leased lands.
  • Whether the Resolution Professional acted within the ambit of the IBC while certifying the resolution plans.
  • Whether GNIDA was aware of EIL's development activities on the leased lands before the CIRP commenced.
  • What appropriate remedial measures should be taken in the facts and circumstances of the case.

Legislation cited

Headnote

Issue for Consideration Issues arose inter alia as to whether in the Corporate Insolvency Resolution Process (CIRP) proceedings of the Corporate Debtor- Earth Infrastructures Limited, the assets of the land holding companies, i.e., subsidiary of the treated to be assets of the Corporate Debtor; whether assets of the subsidiary companies can be dealt with in CIRP of holding Company; whether the present is a fit case to lift the corporate veil. Headnotes† Insolvency and Bankruptcy Code, 2016 – CIRP of holding Company –

Subjects

Lifting of corporate veilCorporate Insolvency Resolution Process of holding CompanyAssets of subsidiary companiesHolding companiesSubsidiary companiesAssociated companiesGroup of companiesSubsidiary of Corporate DebtorHomebuyersCIRP in real estate casesResolution of real estate insolvencyGreater Noida Industrial Development Authority (GNIDA)Earth Infrastructures LimitedHomes/office spacesHome/office space buyersApprobate and reprobateStalled projectsStalled real estate projectsResidential projectScope of s.25A(3A) IBCDevelopment projectAssets of subsidiary companyLeasehold rights

Judgment

                  [2026] 5 S.C.R. 364 : 2026 INSC 449

          Alpha Corp Development Private Limited
                             v.
  Greater Noida Industrial Development Authority (GNIDA)
                        and Others
                       (Civil Appeal No. 1526 of 2023)
                                  05 May 2026
                [Sanjay Kumar* and Alok Aradhe, JJ.]


                            Issue for Consideration
       Issues arose inter alia as to whether in the Corporate Insolvency
       Resolution Process (CIRP) proceedings of the Corporate Debtor-
       Earth Infrastructures Limited, the assets of the land holding
       companies, i.e., subsidiary of the Corporate Debtor could be
       treated to be assets of the Corporate Debtor; whether assets of
       the subsidiary companies can be dealt with in CIRP of holding
       Company; whether the present is a fit case to lift the corporate veil.

                                   Headnotes†
       Insolvency and Bankruptcy Code, 2016 – CIRP of holding
       Company – Lifting of corporate veil – In the CIRP proceedings
       of the Corporate Debtor-Earth Infrastructures Limited (EIL),
       whether the assets of the land holding companies-subsidiary
       of the Corporate Debtor can be treated to be assets of
       the Corporate Debtor – Whether assets of the subsidiary
       companies can be dealt with in CIRP of holding Company –
       Whether present is a fit case to lift the corporate veil – NCLAT
       inter alia held that the assets of the three subsidiary companies
       of EIL, the CD, could not be treated as its assets:
       Held: When, in reality, associated or group companies are
       inextricably connected so as to form part of one concern, the
       corporate veil should be lifted – Where protection of public interest
       is of paramount importance or where a company has been formed
       to evade obligations enforced by law and by the Courts, the
       Court would disregard the corporate veil – This principle would
       be applied even to group companies so that one is able to look
       at the economic entity of the group as a whole – Neo Multimedia
       Limited and Nishtha Software Private Limited were both wholly
       owned subsidiaries of EIL, the CD – They had leases over
* Author
[2026] 5 S.C.R.                                                               365

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     the lands in which EIL was to develop the projects, viz., Earth
     TechOne and Earth Sapphire Court – Earth Towne Infrastructures
     Private Limited (ETIPL) was incorporated only to enable GNIDA’s
     (Greater Noida Industrial Development Authority) leasing of land
     for development of Earth Towne and was controlled by EIL, with a
     98% shareholding – Therefore, ETIPL stands on a different footing
     from the other two companies, insofar as GNIDA is concerned –
     All three companies either share common directors with EIL and/
     or have their relations as directors – The only assets of the three
     companies were the lands leased out to them by GNIDA for the
     projects in question – The companies’ shareholdings indicate
     that EIL was the dominant and majority shareholder – Further, on
     facts, GNIDA cannot claim ignorance of the constructions by EIL
     in relation to all three projects – This was an eminently fit case for
     lifting the corporate veil, as EIL was the main driving force in the
     development of the projects and in payment of GNIDA’s dues –
     The subsidiary companies were only a front – Given the fact that
     GNIDA is responsible for this litigation to a great extent, owing
     to its failure in monitoring the development of the projects and in
     taking timely measures to realise its dues from EIL, it would not
     be entitled to any interest on the principal amounts due for the
     extended period of twenty four months, during which the successful
     resolution applicants, Alpha and Roma, are required to clear its
     dues – The resolution plans of Alpha and Roma restored – The
     successful resolution applicants shall endeavour to complete the
     projects within the time frames indicated by them in their resolution
     plans – Companies Act, 2013 – s.2(87) – Uttar Pradesh Industrial
     Area Development Act, 1976 – s.3. [Paras 54-56, 68]

     Approbation and Reprobation – Impermissibility:
     Held: It is not open to GNIDA to approbate and reprobate – On
     the one hand, GNIDA contends that EIL, the CD, had nothing to
     do with the lands leased out by it to the three companies and
     that those lands ought not to have formed part of EIL’s assets
     during the CIRP proceedings – On the other hand, GNIDA raised
     claims before the IRP and the RP and it also complained of not
     being kept abreast of CIRP proceedings against EIL – GNIDA
     contributed greatly to the present imbroglio by its persistent inaction
     and ineptitude all through – Having executed lease deeds for
     development of the lands, it failed to keep track of and monitor
     the development being undertaken on such lands to ensure timely
366                                                            [2026] 5 S.C.R.

                           Supreme Court Reports


       completion thereof within the stipulated period of seven years –
       Long prior to initiation of the CIRP proceedings against EIL, the
       CD, GNIDA was informed by the aggrieved home/office space
       buyers of the tardy progress in the construction of the projects
       but failed to take necessary coercive steps against the lessees
       and/or the developer, EIL – GNIDA cannot claim ignorance of the
       fact that it was EIL that was executing the development of the
       projects on all three plots of land leased out by GNIDA to the three
       companies – Having addressed a letter to the police authorities
       in relation to EIL’s construction on the land leased out to ETIPL,
       GNIDA cannot now seek to claim ignorance of the reality that it
       was EIL that was undertaking the construction of the projects on
       all three leased lands. [Paras 45, 49]

       Insolvency and Bankruptcy Code, 2016 – s.25A(3A):
       Held: s.25A(3A) provides that an authorised representative
       u/s.21(6A) of the Code would cast his vote on behalf of the
       class of financial creditors he represents, such as homebuyers,
       in accordance with the decision taken by a vote of more than
       50% of the voting share of the financial creditors he represents,
       who have cast their vote – The homebuyers of Earth Copia were,
       accordingly, represented by their authorised representative, who
       voted in favour of Alpha’s resolution plan dated 15.10.2019, as per
       the desire of majority of those homebuyers as a class – Therefore,
       it is not open to individual homebuyers, who may have been
       part of the minority that dissented thereto, to gain a foothold by
       opposing the majority’s decision – A few persons within such class
       cannot dissent with the majority vote in favour of the resolution
       plan. [Para 30]

                                Case Law Cited
       Indiabulls Asset Reconstruction Company Limited v. Ram Kishore
       Arora and Others, AIR 2023 SC 2273; Mansi Brar Fernandes v.
       Shubha Sharma and Another [2025] 10 SCR 169 : (2025)
       259 Comp Cas 769 : 2025 SCC OnLine SC 1972; Vodafone
       International Holdings BV v. Union of India and Another [2012]
       1 SCR 573 : (2012) 6 SCC 613; Jaypee Kensington Boulevard
       Apartments Welfare Association and Others v. NBCC (India)
       Limited and Others [2021] 12 SCR 603 : (2022) 1 SCC 401 : 2021
       SCC OnLine SC 253; Municipal Corporation of Greater Mumbai
       (MCGM) v. Abhilash Lal and Others : [2019] 14 SCR 659 : (2020)
[2026] 5 S.C.R.                                                                        367

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     13 SCC 234; Noida Entrepreneurs Association v. Noida and Others
     [2011] 8 SCR 25 : (2011) 6 SCC 508; Greater Noida Industrial
     Development Authority v. Prabhjit Singh Soni and Another [2024]
     2 SCR 258 : (2024) 6 SCC 767; RPS Infrastructure Limited v.
     Mukul Kumar and another [2023] 12 SCR 150 : (2023) 10 SCC
     718; BRS Ventures Investments Limited v. SREI Infrastructure
     Finance Limited and Another [2024] 7 SCR 2143 : (2025) 1 SCC
     456; Life Insurance Corporation of India v. Escorts Ltd. and Others
     [1985] Supp. 3 SCR 909 : (1986) 1 SCC 264; Arcelormittal India
     Private Limited v. Satish Kumar Gupta and Others [2018] 12 SCR
     362 : (2019) 2 SCC 1 – referred to.

                                     List of Acts
     Insolvency and Bankruptcy Code, 2016; Constitution of India;
     Insolvency and Bankruptcy Board of India (Insolvency Resolution
     Process for Corporate Persons) Regulations, 2016; Uttar Pradesh
     Industrial Area Development Act, 1976.

                                 List of Keywords
     Lifting of corporate veil; Corporate Insolvency Resolution Process
     of holding Company; Assets of subsidiary companies; Holding
     companies; Subsidiary companies; Associated companies; Group
     of companies; Subsidiary of Corporate Debtor; Homebuyers;
     CIRP in real estate cases; Resolution of real estate insolvency;
     Greater Noida Industrial Development Authority (GNIDA); Earth
     Infrastructures Limited; Homes/office spaces; Home/office space
     buyers; Approbate and reprobate; Stalled projects; Stalled real
     estate projects; Residential project; Scope of s.25A(3A) IBC;
     Development project; Assets of subsidiary company; Leasehold
     rights.

                                Case Arising From
     C I V I L A P P E L L AT E J U R I S D I C T I O N : C i v i l A p p e a l N o .
     1526 of 2023
     From the Judgment and Order dated 30.01.2023 of the National
     Company Law Apellate Tribunal in CAAT(I) No. 629 of 2022.
     With
     C.A. No(s). 1743, 2491, 2466, 2406-2407, 3438, 3435-3437, 2756,
     2763, 4619 of 2023 and C.A. (Diary) No. 19132 of 2023
368                                                          [2026] 5 S.C.R.

                          Supreme Court Reports


                          Appearances for Parties
       Advs. for the Appellant(s):
       Dr. Abhishek Manu Singhvi, Dhruv Mehta, Dr. Menaka Guruswamy,
       Ms. Meenakshi Arora, Nakul Dewan, Sr. Advs., Sameer Abhyankar,
       Sandeep Bhuraria, Ms. Vatsala Pandey, Rahul Kumar, Aakash
       Thakur, Somesh Dhawan, Sumit Srivaastava, Nand Kishor Jha,
       Satyam Sinha, Ms. Vagisha Kashyap, Sarvesh Singh Baghel,
       Anshuman Sharma, Rahul Kumar, Vishesh Kumar, Ms. Prity Kumari,
       Jay Kishor Singh, Devendra Kumar Shukla, Shashank Raghav,
       Ms. Shubhangini Yadav, Rakesh Kumar Tewari, Ankur Saraswat,
       Dinesh Kumar Bhati, Kanchan Kumar Jha, Shubhranshu Padhi,
       Ekansh Sisodia, Jay Nirupam, D. Girish Kumar, Pranav Giri, Ritik
       Sharma, V.M. Kannan, Mayank Singh, Ekansh Mishra, Mahesh
       Agarwal, Sumesh Dhawan, Ankur Saigal, Ms. Vastala Kak, Nishant
       Rao, Naman Gupta, Ms. Kavya Tekriwal, Shaurya Shyam, Sagar
       Thakkar, E.C. Agrawala, Binay Kumar Das.

       Advs. for the Respondent(s):
       Ravinder Kumar, Nakul Dewan, Ms. Meenakshi Arora, Dhruv
       Mehta, Chakradhari Sharan Singh, Anupam Lal Das, Sr. Advs.,
       Birendra Kumar Mishra, Sarvesh Singh Baghel, Anshuman Sharma,
       Devendra Kumar Shukla, Binay Kumar Das, Ekansh Mishra,
       Gunjan Kumar, Somesh Dhawan, Sumit Srivaastava, Mahesh
       Agarwal, Sumesh Dhawan, Ankur Saigal, Ms. Vastala Kak, Nishant
       Rao, Naman Gupta, Ms. Kavya Tekriwal, Shaurya Shyam, Sagar
       Thakkar, E.C. Agrawala, Sameer Abhyankar, Sandeep Bhuraria,
       Ms. Vatsala Pandey, Rahul Kumar, Aakash Thakur, Pushpinder Singh,
       Kumar Kartikay, Ms. Neelu Sharma, Kartik Hooda, E. Vinay Kumar,
       Ms. Surbhi Singh, Siddhartha Makhija, Ranjit Balasaheb Raut,
       Sonit Sinhmar, Bhupender Dalal, Ms. Sunayana Pawar, Saurabh
       Trivedi, Prashant Jain, Varun Garg, Shubham Paliwal, Bharat
       Sood, P.S. Sudheer, Rishi Maheshwari, Ms. Anne Mathew,
       Ms. Sunaina Phul, Ms. Komal Bihani, Ms. Kinjal Sharma, Ms. Rupam
       Sharma, Shiv Mangal Sharma, Abhishek Sharma, M/s Aura & Co.,
       Ms. Anuja Pethia, Noor Shergill, Rishabh Nigam, Ms. Kshirja
       Agarwal, Rishabh Govila, Ms. Amisha Aggarwal, Prashant Jain,
       Varun Garg, Shubham Paliwal, Bharat Sood, P.S. Sudheer, Rishi
       Maheshwari, Ms. Anne Mathew, Ms. Sunaina Phul, Ms. Komal
       Bihani, Ms. Kinjal Sharma, Ms. Rupam Sharma, Ms. Supriya Juneja,
       Durga Dutt, Priyanshu Upadhyay, Ajay Kumar, Pradeep Yadav,
       Susant Kumar Mallik, Rohit Priyadarshi, Devendra Rao Madhav,
       Amrendra Choubey, Himanshu Yadav, Satya Kam Sharma , Anirudh
       Singh, Gunjan Sharma, Kumar Mihir, Devendra Kumar Shukla.
[2026] 5 S.C.R.                                                        369

                Alpha Corp Development Private Limited v.
    Greater Noida Industrial Development Authority (GNIDA) and Others

                       Judgment / Order of the Supreme Court

                                    Judgment

       Sanjay Kumar, J

1.     By judgment dated 30.01.2023, the National Company Law Appellate
       Tribunal, Principal Bench, New Delhi1, disposed of three company
       appeals filed by Greater Noida Industrial Development Authority
       (GNIDA), viz., Company Appeal (AT) (Ins) Nos. 180, 629 and 630
       of 2022, and set aside the orders dated 05.04.2021, 08.06.2021
       and 07.12.2021 passed by the National Company Law Tribunal,
       Bench III, New Delhi2.
2.     By the order dated 05.04.2021 passed in C.A. No. 751 of 2019 in
       CP(IB)-401(ND)/2017, the NCLT had approved the resolution plan
       submitted by Roma Unicon Designex Consortium (Roma). This
       order was challenged by GNIDA in Company Appeal (AT) (Ins) No.
       630 of 2022. By its order dated 08.06.2021 in IA No. 05 of 2020 in
       CP(IB)-401(ND)/2017, the NCLT had approved the resolution plan
       submitted by Alpha Corp Development Private Limited (Alpha). This
       order was assailed by GNIDA in Company Appeal (AT) (Ins) No.
       629 of 2022. By the order dated 07.12.2021 in IA No. 4235 of 2021
       filed by Roma in CP(IB)-401(ND)/2017, the NCLT directed GNIDA to
       give effect to the resolution plan approved by it by the order dated
       05.04.2021. This order was challenged before the NCLAT by GNIDA
       in Company Appeal (AT) (Ins) No. 180 of 2022.
3.     Aggrieved by the NCLAT’s judgment dated 30.01.2023, the present
       appeals were filed under Section 62 of the Insolvency and Bankruptcy
       Code, 20163. We may now note the details of these appeals. Civil
       Appeal Nos. 1526 and 1743 of 2023 were filed by Alpha and one
       Sanjay Bhalla respectively in so far as the judgment pertained to
       Company Appeal (AT) (Ins) No. 629 of 2022. Roma and Earth Towne
       Flat Buyers Welfare Association filed Civil Appeal Nos. 2491 and 2466
       of 2023 respectively against the judgment in the context of Company
       Appeal (AT) (Ins) No. 630 of 2022. Civil Appeal Nos. 2406-2407 of


1    For short, ‘the NCLAT’
2    For short, ‘the NCLT’
3    For short, ‘the Code’
370                                                         [2026] 5 S.C.R.

                          Supreme Court Reports


       2023 were filed by Earth Infrastructures Limited, the corporate debtor
       (CD), against the judgment in the context of Company Appeal (AT)
       (Ins) Nos. 629 and 630 of 2022. Civil Appeal No. 3438 of 2023 was
       filed by Earth Copia Owners Society in relation to Company Appeal
       No. (AT) (Ins) No. 629 of 2022. Civil Appeal Nos. 3435-3437 of
       2023 were filed by Earth United Consumer Association assailing
       the judgment apropos all three appeals. Civil Appeal No. 2756 of
       2023 was filed by GNIDA aggrieved by denial of certain reliefs by
       the NCLAT in Company Appeal (AT) (Ins) No. 629 of 2022. Civil
       Appeal No. 2763 was also filed by GNIDA on similar grounds in
       relation to Company Appeal (AT) (Ins) No. 630 of 2022. Civil Appeal
       No. 4619 of 2023 was filed by Unific TechOne Patrons Independent
       Association (UTOPIA) against the judgment insofar as it pertained to
       Company Appeal (AT) (Ins) No. 629 of 2022. Lastly, Earth Property
       Buyers Association filed Civil Appeal (Diary) No. 19132 of 2023 in
       relation to all three appeals.
4.     As regards the appeals filed under Civil Appeal (Diary) No. 19132 of
       2023, we find that there is a delay of 34 days in their filing. These
       appeals were filed only on 04.05.2023 against the judgment dated
       30.01.2023. Section 62(2) of the Code empowers this Court to
       condone delay in filing up to 15 days but not more. These appeals
       are, thus, clearly barred by time and cannot be entertained. The
       appeals filed under Civil Appeal (Diary) No. 19132 of 2023 are,
       therefore, dismissed on this short ground.
5.     By order dated 13.04.2023 passed in Civil Appeal No. 1526 of 2023
       and batch, this Court directed the parties to maintain status quo.
6.     The ostensible genesis of this litigation is the corporate insolvency
       resolution process (CIRP) initiated by one Deepak Khanna, a financial
       creditor, against Earth Infrastructures Limited (EIL), the CD, vide
       Company Petition IB-401(ND)/2017, under Section 7 of the Code.
       However, long prior thereto, GNIDA, an authority constituted under
       Section 3 of the Uttar Pradesh Industrial Area Development Act,
       1976, allotted 73,942 square metres of land in Large Group Housing/
       Builders’ Residential Plot No. GH-04, Sector 01, Greater Nodia, Uttar
       Pradesh, to a consortium, comprising EIL, Raus Infras Limited and
       Shalini Holdings Limited, under allotment letter dated 19.03.2010.
       The letter indicated that the Builders Scheme [Scheme Code
       BRS-01/2010-(I)] would form part of the allotment letter and would
[2026] 5 S.C.R.                                                           371

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     be binding on the allotees. GNIDA had formulated this scheme for
     plots of over 60,000 square metres area, inviting tenders for allotment
     of such plots on lease for 90 years. The terms and conditions for
     allotment/lease of such plots were detailed in the scheme. In the
     event the bidder was a consortium, Clause 8 thereof had application.
     Clause 8 reads thus: -
           ‘8. In case bidders have formed a consortium: -
           (a) Members of the consortium will have to specify one Lead
           Member who alone shall be authorized to correspond with
           the Authority. The Lead member should be the single largest
           shareholder having at least 26% share in the consortium.
           The shareholding of the lead member in the consortium
           shall retain at least 26% till the completion certificate of
           at least one phase of the project is obtained from the
           Greater Noida Authority. Each member of the consortium
           with equity stake of at least 10% will be considered as a
           “relevant member”. The Lead Member of the consortium
           must necessarily be a Firm/Company registered in India
           with the appropriate statutory Authority.
           (b) The lead member and the relevant members should
           jointly fulfil the minimum requirement of net worth,
           solvency, turnover and experience. In case the tenderer/
           consortium member is a company, the qualifications of
           the holding company(ies) of the lead member and the
           relevant members or their subsidiary companies shall
           also be considered as the qualifications of the applying
           company/consortium member.
           (c) In case of a Consortium, the members shall submit
           a Memorandum of Agreement (MOA) conveying their
           intent to jointly apply for the scheme(s), and in case a
           plot is allotted to them, the MOA shall clearly define the
           role and responsibility of each member in the consortium,
           particularly with regard to arranging debt and equity for the
           project and its implementation. MOA should be submitted
           in original duly registered/notarized with the appropriate
           authority.
           (d) The members shall submit a registered/notarized
           Memorandum of Agreement (MOA) conveying their intent
372                                                         [2026] 5 S.C.R.

                          Supreme Court Reports


            to jointly apply for the scheme, and in case a plot is
            allotted to them, to form Special Purpose Company(ies),
            hereinafter called SPCs, that will subsequently carryout
            all responsibilities as the allottee. The registered MOA
            must specify the equity shareholding of each member of
            the Consortium in the proposed SPCs. The SPCs must
            necessarily be a Firm/Company registered in India with
            the appropriate statutory Authority.
            (e) Execution of the lease deed will be made in favour
            of either the relevant member(s) or the Special Purpose
            Company(ies) (SPC)(s), which should be a registered
            firm or an incorporated company. The relevant members/
            SPC’s may, separately, or together in any combination,
            sub-divide this allotted plot. However, the area of each of
            such sub divided plots proposed for execution of lease
            deed, as described above, should not be less than 20,000
            sq. mtrs and the said sub division should be in accordance
            with the planning norms of the GNIDA. The lead member
            of the consortium shall have to retain at least 26% of the
            shareholding as per MOA, till the completion certificate of
            at least one phase of the project is obtained from Greater
            NOIDA Authority.’
7.     Thus, Clause 8(e) of the scheme required a consortium to form a
       ‘Special Purpose Company’ (SPC) to undertake development on the
       allotted plot. Accordingly, the consortium of EIL, Raus Infras Limited
       and Shalini Holdings Limited incorporated Earth Towne Infrastructures
       Private Limited (ETIPL) on 21.07.2010 as the SPC. Lease deed
       dated 01.09.2010 was thereupon executed by GNIDA leasing out the
       subject plot to ETIPL for 90 years, commencing from 01.09.2010. The
       lease deed recorded that GNIDA had approved the name and status
       of ETIPL on the request of the consortium to develop and erect the
       project on the plot. It was also noted that the lessee, ETIPL, was
       a SPC, comprising EIL (78% shareholding – lead member), Raus
       Infras Limited (11% shareholding – relevant member) and Shalini
       Holdings Limited (11% shareholding – relevant member). The lease
       deed also recorded that GNIDA had been informed that the SPC
       members had agreed amongst themselves that EIL would always
       remain the lead member of the SPC and its shareholding therein
       would remain unchanged till the occupancy/completion certificate of at
[2026] 5 S.C.R.                                                       373

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     least one phase of the project was obtained from GNIDA. The lease
     deed, however, permitted the SPC to transfer/sell up to 49% of its
     shareholding, again subject to the same aforestated condition. The
     total premium payable under the lease deed was ₹74,26,95,000/-.
     The lease deed noted that 10% of the premium plus the excess
     area amount, adding up to ₹7,46,91,000/-, was paid by the lessee,
     ETIPL. There was to be a moratorium of 24 months, during which
     period, only the interest was payable in half-yearly instalments and
     upon expiry of said period, the balance 90%, i.e., ₹66,84,25,500/-,
     was to be paid in 16 half-yearly instalments. Instalment Nos. 1 to 4,
     the half-yearly interest payments, commenced from 19.09.2010,
     and the premium payments started from 19.09.2012, with the final
     instalment payable on 19.03.2020. After execution of the lease
     deed, an unregistered development agreement was entered into
     on 09.09.2010 between ETIPL and EIL, whereby ETIPL conferred
     the right to develop the land upon EIL. The area-sharing ratio was
     stipulated as 18% to ETIPL and 82% to EIL.
8.   Separately and much earlier, GNIDA had allotted 60,705 square
     metres of land in Plot No. 1 at Sector Tech Zone area in Greater
     Nodia Industrial Development Area, District Gautam Budh Nagar,
     to NIIT Multimedia Limited for development of IT industries and IT
     enabled services for 90 years. Pursuant thereto, lease deed dated
     04.02.2008 was executed by GNIDA in favour of NIIT Multimedia
     Limited over a reduced area of 58,866 square metres. Pertinently, this
     company became a subsidiary of EIL in 2011 and its change of name
     as Neo Multimedia Limited was approved by GNIDA on 21.02.2011.
     Development Agreement dated 25.04.2011 was executed by and
     between Neo Multimedia Limited and EIL, whereby the development
     on the subject plot of land was to be undertaken by EIL.
9.   GNIDA had also allotted 20,235 square metres of land in Plot No. 48,
     Sector Knowledge Park-V, in Greater Nodia Industrial Development
     Area, District Gautam Budh Nagar, to Nishtha Software Private
     Limited, another subsidiary of EIL, for development of facilities
     relating to IT and IT enabled services. Pursuant thereto, GNIDA
     executed lease deed dated 01.09.2009 in its favour for 90 years
     for an increased area of 20,911.24 square metres. Memorandum
     of Understanding (MoU) dated 20.02.2010 was executed between
     Nishtha Software Private Limited and EIL, whereby development on
     the plot was to be undertaken by EIL.
374                                                       [2026] 5 S.C.R.

                        Supreme Court Reports


10. In effect, EIL was to undertake the development on all three plots
    of land leased out by GNIDA. The residential project on the land
    leased out to ETIPL was named ‘Earth Towne’ while the project to
    be developed on the land leased to Neo Multimedia Limited was
    named ‘Earth TechOne’ and the project on the land leased to Nishtha
    Software Private Limited was called ‘Earth Sapphire Court’. Building
    permissions were obtained by the respective lessees of these plots
    from GNIDA and a large number of home/office space buyers booked
    homes/office spaces in these projects, paying substantial monies to
    the developer, EIL, and in some cases, to the lessees. The projects
    were also registered with the Uttar Pradesh Real Estate Regulatory
    Authority.
11. While so, at the instance of Deepak Khanna, a financial creditor,
    CIRP was initiated against EIL. His application under Section 7 of the
    Code was admitted by the NCLT on 06.06.2018. Initially, one Surinder
    Kumar Juneja was appointed as the Interim Resolution Professional
    (IRP) for EIL, the CD. The NCLT caused public announcement of
    initiation of the CIRP against EIL under Section 13 of the Code on
    12.06.2018. The Committee of Creditors (CoC) was constituted and
    its first meeting was held on 05.12.2018. Later, Akash Singhal was
    substituted as the Resolution Professional (RP) by the CoC. The
    CoC comprised the HDFC Bank and 4,229 allottees, i.e., home/
    office space buyers.
12. ‘Invitation for Expression of Interest’ in Form G was issued by the
    RP on 19.04.2019 in respect of all the projects. However, there
    was no response thereto and the RP then invited resolution plans
    project-wise also, as an alternative, in addition to plans for all the
    projects. The revised Form G was published on 22.05.2019. In this
    regard, we may refer to the ‘Clarification’ to Regulation 36A (1) of
    the Insolvency and Bankruptcy Board of India (Insolvency Resolution
    Process for Corporate Persons) Regulations, 2016, whereby a
    Resolution Professional, after approval of the CoC, is empowered
    to invite a resolution plan for each real estate project or group of
    projects of the corporate debtor. This clarification was inserted with
    effect from 15.02.2024, vide Notification dated 15.02.2024. Even
    before this amendment, the NCLAT and this Court have affirmed that
    the CIRP in real estate cases can be project-specific, limiting such
    insolvency process to projects in default so as to ensure protection of
    homebuyers in other projects, which still remain viable. In Indiabulls
[2026] 5 S.C.R.                                                        375

                Alpha Corp Development Private Limited v.
    Greater Noida Industrial Development Authority (GNIDA) and Others

       Asset Reconstruction Company Limited vs. Ram Kishore Arora
       and others4, this Court refused to interfere with the NCLAT’s order
       permitting insolvency process project-wise. More recently, in Mansi
       Brar Fernandes vs. Shubha Sharma and another5, this Court
       observed that resolution of real estate insolvency should, as a rule,
       proceed on a project-specific basis rather than against the corporate
       debtor in its entirety, unless circumstances justify otherwise, as
       this would protect solvent projects and genuine homebuyers from
       collateral prejudice.
13. Pursuant to the revised Form G, three resolution applicants came
    forward, viz., BPT Infra Projects Private Limited, Roma and Alpha.
    BPT Infra Projects Limited’s plan was rejected by the CoC. Roma’s
    resolution plan for ‘Earth Towne’ was approved by the CoC in its
    14th meeting held on 26.08.2019. After the CoC’s approval, GNIDA
    addressed letter dated 18.09.2019 to the RP, stating that the dues
    payable to it by ETIPL were ₹148,37,46,148/-. The NCLT approved the
    acceptance of Roma’s resolution plan, vide order dated 05.04.2021
    passed in C.A. No. 751 of 2019 in CP (IB)-401(ND)/2017.
14. At this stage, we may note that, apart from the projects that were to
    be developed by EIL on the plots leased out by GNIDA, a separate
    project named ‘Earth Copia’ was also being undertaken by it on
    freehold land in Sector 112, Gurugram, Dwarka Expressway, Haryana.
    This land had nothing to do with GNIDA and, in consequence, no
    dues were payable to it in relation thereto. Alpha’s resolution plan
    covered four projects of EIL, including Earth Copia. Alpha’s resolution
    plan was approved by the CoC at its 19th meeting held on 11.11.2019.
    Thereafter, it was approved by the NCLT on 08.06.2021 in relation to
    three projects, viz., Earth TechOne, Earth Sapphire and Earth Copia.
    The fourth project, viz., Earth Iconic, was dealt with separately by the
    NCLT in another CIRP initiated by Celestial Estates Private Limited
    and Alpha’s resolution plan was approved for that project in that case.
    The order dated 08.06.2021 passed by the NCLT, therefore, covered
    the remaining three projects. However, as stated earlier, Earth Copia
    had nothing to do with GNIDA. Notably, one of the appeals filed
    before the NCLAT by GNIDA assailed NCLT’s order dated 08.06.2021,


4    AIR 2023 SC 2273
5    (2025) 259 Comp Cas 769 : 2025 SCC OnLine SC 1972
376                                                        [2026] 5 S.C.R.

                          Supreme Court Reports


       but no distinction was drawn by GNIDA between the projects that it
       had an interest in and Earth Copia, which had nothing to do with it.
       The impugned judgment dated 30.01.2023 passed by the NCLAT
       also lost sight of this aspect, as reference was made therein to only
       two projects, i.e., Earth Sapphire and Earth TechOne, as being the
       subject matter of NCLT’s order dated 08.06.2021 in the context of
       Alpha’s resolution plan.
15. IA No. 4235 of 2021 was filed by Roma in CP (IB) No. 401(ND)/2017
    seeking a direction to GNIDA to transfer the leased land in its favour.
    The application was opposed by GNIDA contending that such transfer
    would be against the terms of ETIPL’s lease deed. However, the
    NCLT allowed the IA by order dated 07.12.2021, leading to GNIDA
    challenging it by way of Company Appeal (AT) (Ins) No. 180 of 2022.
    The NCLAT passed an interim order on 01.06.2022 in GNIDA’s
    appeals to the effect that GNIDA was not obliged to transfer the
    leasehold lands in favour of the successful resolution applicants
    pursuant to the NCLT’s orders. This interim order attained finality
    on 14.07.2022, when this Court dismissed Civil Appeal No. 4748 of
    2022 filed by Earth Towne Flat Buyers Welfare Association.
16. The above sequence of events indicates that the land leases were
    in favour of the CD’s two subsidiaries. As regards Earth Towne, the
    land allotment was in favour of the consortium, comprising EIL, Raus
    Infras and Shalini Holdings Limited. However, as per GNIDA’s own
    scheme, the SPC, viz., ETIPL, came to be incorporated and a lease
    was executed by GNIDA in its favour. The lease deed, however, made
    it clear that the lead member, EIL, was to retain the major shareholding
    therein, initially shown as 78%, and was to retain its status as the
    lead member till issuance of the occupancy/completion certificate in
    relation to at least one phase of the project. We may also note that
    EIL, the lead member with 78% shareholding in ETIPL, thereafter
    increased it to 98%. As per the lease deed, it was the lessee, ETIPL,
    that was to undertake payment of the interest/premium as per the
    schedule therein. The paid-up capital of ETIPL was, however, only
    ₹1 lakh and it was EIL that paid ₹51.88 crores to GNIDA against the
    interest/premium payable under the lease deed. Admittedly, there
    was default thereafter in such payments. GNIDA issued notices to
    ETIPL in that regard on 04.04.2019, 16.07.2019, 29.01.2020 and
    01.05.2020. By the year 2016, EIL had constructed only twelve towers
    and completed foundation work of five towers in Earth Towne.
[2026] 5 S.C.R.                                                      377

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

17. GNIDA’s complaint before the NCLAT was that the RP did not keep
    it informed of the proceedings in the CIRP and it was only after
    approval of Roma’s resolution plan, vide order dated 05.04.2021,
    that GNIDA was informed of the same by the RP, vide letter dated
    26.07.2021. As per GNIDA, as on 31.03.2022, ETIPL was to pay it
    ₹215,87,18,190/-. GNIDA also claimed that, as on 24.03.2022, Neo
    Multimedia Private Limited was liable to pay it ₹19,76,10,064/- and
    Nishtha Software Private Limited had to pay it ₹11,15,15,009/-. That
    apart, additional compensation and lease rentals were also allegedly
    payable. GNIDA claimed that several notices of defaults in payment
    were issued to these lessees also.
18. Per contra, the other side contended before the NCLAT that GNIDA
    was fully aware of the fact that the projects were being executed
    by EIL, as evidenced by its letter dated 11.05.2015 to the Senior
    Superintendent of Police, Gautam Budh Nagar, wherein GNIDA itself
    mentioned that EIL was engaged in the construction work. In this
    context it was argued before the NCLAT that ETIPL was nothing
    but an alter ego of EIL and this was a fit case to pierce and lift the
    corporate veil. It was also contended that the companies had common
    directors and promoters and ETIPL had no separate business of
    its own. It was pointed out that the RP sought relevant information/
    documents from GNIDA in respect of all three projects, viz., Earth
    TechOne, Earth Sapphire Court and Earth Towne, under his letter
    dated 28.05.2019 and, therefore, GNIDA could not claim ignorance
    of the CIRP proceedings. On this basis, it was argued that GNIDA,
    having kept silent all through the proceedings, could not seek to
    overturn the orders passed by the NCLT approving the resolution
    plans, which were binding on all the stakeholders. Alpha contended
    before the NCLAT that its resolution plan had been approved at the
    19th CoC meeting held on 11.11.2019 with a whopping 91.39% vote
    share. According to it, GNIDA filed its claim at a belated stage only
    on 11.11.2021 with the IRP and not the RP, despite being aware of
    the CIRP proceedings.
19. Earth Towne Flat Buyers Welfare Association got impleaded before
    the NCLAT. Its grievance was that the construction of Earth Towne
    stood stalled since 2016 and members of the association, being
    homebuyers, were suffering irreparable loss. The association pointed
    out that the RP had admitted the claims of 1,878 homebuyers,
    amounting to ₹438 crore. It stated that its members had met the
378                                                           [2026] 5 S.C.R.

                           Supreme Court Reports


       Additional Chief Executive Officer of GNIDA on 28.06.2017, long
       before initiation of the CIRP against EIL, but despite the same no steps
       were taken by GNIDA to either recover its dues or hasten completion
       of the project. According to it, the Additional Chief Executive Officer
       of GNIDA had told them that it would recalculate the principal and
       interest and check if it could waive the penal interest from 2016
       onwards, so as to bring in a new developer for a settlement.
20. The NCLAT also permitted Earth TechOne Patrons Independent
    Association and Sapphire Patrons Independent Common Association,
    which claimed to be registered associations of office space buyers in
    those projects, to participate in the proceedings. Their complaint was
    that Earth Sapphire Court had been launched in the year 2010 while
    Earth TechOne was commenced in the year 2012, whereupon EIL
    had collected monies from the prospective buyers in both projects.
    According to them, EIL had promised 12% assured returns which were
    paid till September, 2015, but no payments were made thereafter.
    They claimed that a meeting had been held on 20.05.2016, wherein
    the Chief Executive Officer of GNIDA had warned EIL that action
    would be taken against it in the light of the grievances put forth by
    the members of the associations. They further claimed that they had
    given a representation on 27.07.2016 to GNIDA praying that strict
    action be taken against EIL, followed by meetings on 08.05.2017
    and 16.05.2017. They claimed that despite such steps being taken,
    GNIDA had failed to take action against EIL. They contended before
    the NCLAT that Alpha’s resolution plan contemplated waiver of the
    dues payable to GNIDA, but if GNIDA refused to waive such dues,
    the office space buyers undertook to bear the liability. They pointed
    out that Alpha undertook to complete construction and deliver units
    to the buyers in five years but the same stood compromised by
    GNIDA’s stance.
21. Though it was also argued by the contesting respondents before the
    NCLAT that GNIDA’s appeals were time-barred, in terms of Section
    61(2) of the Code, the NCLAT rejected their contention, as extension
    of time had been granted by this Court, by freezing limitation, in Suo
    Moto Writ Petition (Civil) No. 3 of 2020, titled ‘In re: Cognizance
    for Extension of Limitation’, owing to the Covid-19 pandemic. The
    appeals were, therefore, held to be within time. Having considered
    the matter on merits, the NCLAT framed the following issues for
    consideration:
[2026] 5 S.C.R.                                                           379

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

           (I) Whether in the CIRP proceedings of the Corporate
           Debtor, i.e. Earth Infrastructures Limited, the assets of the
           land holding companies, i.e., subsidiary of the Corporate
           Debtor can be treated to be assets of the Corporate Debtor?
           (II) Whether, in the Resolution Plans submitted by the
           Successful Resolution Applicants, i.e., Roma Unicon
           Designex Consortium and Alpha Corp Development
           Private Limited, the assets of the subsidiary, i.e., lease
           lands could have been dealt and the Resolution Plan
           could legally contain a clause for transfer of the lease hold
           rights by the Appellant in favour of Successful Resolution
           Applicant without there being any prior permission from
           the Appellant?
           (III) Whether assets of the subsidiary companies can be
           dealt with in Corporate Insolvency Resolution Process of
           holding Company?
           (IV) Whether the Appellant was required to be made party
           to the CIRP proceedings and heard before approval of any
           resolution plan dealing with the Project land?
           (V) Whether, Resolution Professional acted within the ambit
           of I & B Code in giving a certificate that Resolution Plans
           submitted by Roma Unicon Designex Consortium and
           Alpha Corp Development Private Limited are in accordance
           with the provisions of the Code?
           (VI) Whether Appellant was aware of the development
           carried out by the Corporate Debtor on the lease land before
           commencement of the CIRP of the Corporate Debtor?
           (VII) What is the way out in the facts and circumstances
           of the present case?
22. Issues I, II and III were taken up together. The NCLAT noted that, in
    terms of the ‘Explanation’ to Section 18, the assets of a subsidiary of
    the corporate debtor could not be included within the term ‘assets’.
    This observation was made in the context of the leasehold rights
    having been conferred by GNIDA, not upon EIL, the CD, but upon
    ETI, which was practically its subsidiary. The same logic was applied
    to the leasehold rights held by the other subsidiary companies of EIL,
    viz., Neo Multimedia Limited and Nishtha Software Private Limited.
380                                                        [2026] 5 S.C.R.

                              Supreme Court Reports


23. The NCLAT also noted that the Information Memorandum brought
    out by the RP did not include the project lands as the assets of EIL.
    The NCLAT, therefore, opined that there was no occasion for the
    resolution applicants to include such project lands in their resolution
    plans. According to the NCLAT, the resolution plans sought to transfer
    not only the development rights over the project lands but also the
    title over the lands in favour of third parties, without obtaining prior
    approval of the lessor, GNIDA. The NCLAT noted that transfer of
    lands by GNIDA was subject to the terms in the lease deeds and
    the permission to transfer the lands was to be granted by GNIDA
    on fulfilment of the conditions mentioned therein. Ignoring the same,
    the resolution plans contained provisions, whereby GNIDA was
    obligated to transfer the project lands to the successful resolution
    applicants. Observing that GNIDA was not a party to the development
    agreements/MoU that EIL had with the lessees, its subsidiaries,
    whereby it undertook the development on the subject lands, the
    NCLAT held that GNIDA was neither the creditor of EIL, the CD,
    nor was it a stakeholder in the resolution plans and was, therefore,
    not bound by them in any manner.
24. Adverting to the contention that this was a fit case for lifting the
    corporate veil, reference was made by the NCLAT to the decision
    of this Court in Vodafone International Holdings BV vs. Union of
    India and another6, which took note of the legal status of holding
    companies and subsidiary companies as they were, in essence,
    separate legal entities. Reference was also made to Jaypee
    Kensington Boulevard Apartments Welfare Association and
    others vs. NBCC (India) Limited and others7, wherein this Court
    held that only the assets of the corporate debtor could be subjected
    to the resolution plan and not the assets of its subsidiary. That was
    also a case involving the grant of leasehold rights to a corporate
    debtor by the Yamuna Expressway Industrial Development Authority
    (YEIDA), an authority constituted under Section 3 of the Uttar
    Pradesh Industrial Area Development Act, 1976, like GNIDA. This
    Court held that, without the approval of that authority, no transfer
    could have taken place even by way of a sub-lease. Reference was
    also made to the decision of this Court in Municipal Corporation


6   (2012) 6 SCC 613
7   (2022) 1 SCC 401 : 2021 SCC OnLine SC 253
[2026] 5 S.C.R.                                                      381

                Alpha Corp Development Private Limited v.
    Greater Noida Industrial Development Authority (GNIDA) and Others

       of Greater Mumbai (MCGM) vs. Abhilash Lal and others8, which
       held to the same effect.
25. The NCLAT then referred to the condition pertaining to transfer in
    the lease deed dated 01.09.2010 and opined that the resolution plan
    could not have contained a clause for transfer of that land without
    GNIDA approving such transfer. The NCLAT, accordingly, answered
    Issue No. I, holding that the assets of the three subsidiary companies
    of EIL, the CD, could not be treated as its assets. Issue No. II was
    also answered in the negative, holding that the resolution plans of
    Roma and Alpha could not have dealt with the project lands which
    were leased out to EIL’s subsidiary companies by GNIDA. Issue No.
    III was answered on the same lines, holding that the assets of the
    subsidiary companies could not have been dealt with in the CIRP
    of the holding company, EIL, without the permission of the lessor,
    GNIDA.
26. On Issue No. IV, the NCLAT held that GNIDA ought to have been
    made a party to the CIRP proceedings before approval of any
    resolution plan involving GNIDA’s project lands. On Issue No. V, the
    NCLAT found fault with the RP for not keeping GNIDA informed of
    the progress of the CIRP despite GNIDA’s letter dated 18.09.2019.
    The NCLAT concluded that the RP failed to act within the ambit
    of the Code while certifying that the resolution plans submitted by
    Roma and Alpha were in accordance with the provisions thereof.
    The NCLAT, accordingly, directed its Registry to forward a copy of
    the judgment to the IBBI to examine the work and conduct of the
    RP and take action as it deemed fit and proper. On Issue No. VI,
    the NCLAT held that knowledge of GNIDA about the development
    being carried out by EIL was not sufficient to be treated as consent
    for transfer of the lands to the successful resolution applicants.
27. On Issue No. VII, the NCLAT took note of the fact that the homebuyers
    had approached the Allahabad High Court, which passed an order
    on 23.02.2016 directing them to represent the matter to the Chief
    Executive Officer of GNIDA, which was then required to deal with the
    matter. Pursuant thereto, complaints were made by two associations
    of buyers, i.e., of Earth Sapphire Court and Earth TechOne, to the
    Chief Executive Officer of GNIDA on 27.07.2016, 02.08.2016 and


8    (2020) 13 SCC 234
382                                                          [2026] 5 S.C.R.

                          Supreme Court Reports


       20.06.2017. Reference was also made to the meeting held with the
       Chief Executive Officer of GNIDA and the Minister concerned on
       11.05.2017. Despite the buyers doing all this, no action was taken
       by GNIDA. The NCLAT also noted that during the meetings held
       with the allottees, it was stated on behalf of GNIDA that the issue
       of penal interest would be considered favourably. The NCLAT also
       noted that one of the obligations under the lease deeds that GNIDA
       had executed in favour of the lessees was that GNIDA would monitor
       development of the projects. The obligation to monitor the projects,
       per the NCLAT, included the obligation to ensure that the projects
       were completed in time and that necessary action would be initiated
       against defaulting parties. Reference was made by the NCLAT to
       the decision of this Court in Noida Entrepreneurs Association vs.
       Noida and others9, wherein this Court had observed the ‘public trust
       doctrine’ is a part of the law of the land and has grown from Article
       21 of the Constitution. It was noted therein that the power vesting in
       a public authority should be viewed as a trust coupled with duty, to be
       exercised in larger public and social interest, and public authorities
       could not play fast and loose with the powers vested in them. The
       NCLAT observed that the facts brought on record demonstrated
       that hundreds of crores were received from the allottees, who were
       waiting for the past several years to take possession of the units
       allotted to them, but the projects stood stalled since 2016. The NCLAT
       also noted the offer made by the associations of buyers of Earth
       Sapphire Court and Earth TechOne that they were ready to pay the
       dues of GNIDA in the interest of development of the projects. The
       NCLAT concluded that GNIDA had not been diligent in taking steps
       for recovery of its dues and was, therefore, not entitled to charge
       penal interest. The NCLAT, accordingly, directed GNIDA to waive
       the penal interest and recalculate its dues.
28. The NCLAT opined that the way out for the RP was to make an
    application along with the associations of buyers of the respective
    projects to GNIDA, seeking permission for transfer of the lands to
    prospective resolution applicants who were then to execute the
    projects after payment of GNIDA’s dues. The NCLAT left it open to
    GNIDA to enter into arrangements with such resolution applicants
    and buyers’ associations for payment of the dues, whereupon it


9   (2011) 6 SCC 508
[2026] 5 S.C.R.                                                          383

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     could transfer the lands so that the projects could be developed by
     the resolution applicants. The RP was directed to publish a fresh
     Form G, inviting resolution plans with the specific condition that the
     resolution plans would be presented to the CoC for consideration only
     after GNIDA’s dues were paid and its permission was obtained for
     transfer of the leasehold lands. Roma and Alpha were also permitted
     to file their resolution plans. GNIDA was directed to recalculate its
     dues and communicate the same to the RP and the associations,
     without charging penal interest, within a time frame. The fresh
     resolution plans submitted by the resolution applicants were to be
     examined by the RP and placed before the CoC for consideration
     and approval. GNIDA was made a party to the CIRP proceedings and
     was held entitled to participate in the process thereafter. The steps to
     be taken pursuant to the judgment, till submission of an application
     by the RP to the NCLT for approval of the plans, if any, were to be
     completed within six months. The CIRP period was extended by six
     months from that date. The appeals were disposed of with these
     directions, setting aside the orders dated 05.04.2021, 08.06.2021
     and 07.12.2021 passed by the NCLT.
29. This being the factual milieu, we may first take up the issue of
    EIL’s Gurugram project, viz., Earth Copia. The land on which
    Earth Copia was to be developed was acquired by Aurochem
    Buildtech Private Limited, a wholly owned subsidiary of EIL, through
    Collaboration Agreement dated 30.07.2010 with eight landowners.
    Tripartite Agreement dated 04.05.2012 was then executed, whereby
    possession and full development rights were transferred to EIL and
    the landowners’ claims stood fully settled. According to Earth Copia
    Owners Society, the appellant in Civil Appeal No. 3438 of 2023, it
    comprised 393 homebuyers of 536 units in Earth Copia and majority
    of those homebuyers voted in favour of Alpha’s resolution plan dated
    15.10.2019. Earth Copia Owners Society pointed out that GNIDA’s
    appeals before the NCLAT were only in relation to lands leased
    out by it to the subsidiary companies of EIL and, therefore, Earth
    Copia was not part of that litigation. It further pointed out that Alpha’s
    resolution plan dated 15.10.2019 was severable, as it provided
    that any portion thereof which was held invalid would not affect the
    remaining parts, which would survive independently. It also pointed
    out that three blocks of the project had been completed up to 90%
    and the remaining blocks were still in the range of 40-80% completion.
384                                                          [2026] 5 S.C.R.

                          Supreme Court Reports


       The Society contended that the NCLAT erroneously set aside the
       approval of Alpha’s entire resolution plan without noticing that the
       order dated 08.06.2021 passed by the NCLT included approval of
       that resolution plan in relation to Earth Copia also, which had nothing
       whatsoever to do with GNIDA. We find considerable force in this
       argument, as GNIDA had no grievance apropos this project and
       ought to have clarified this aspect in its appeal before the NCLAT
       filed against the NCLT’s order dated 08.06.2021.
30. An intervenor, Earth Buyers Association for Justice, seeks to come
    on record before us so as to challenge Alpha’s resolution plan in so
    far as it relates to Earth Copia also. Alpha’s resolution plan had been
    approved by 91.39% voting share of the CoC and the intervenor,
    was not a member of the CoC. Twenty-nine homebuyers who had
    not voted for the plan are members of the intervenor. In this regard,
    Section 25A(3A) of the Code assumes importance. It provides that
    an authorised representative under Section 21(6A) of the Code
    would cast his vote on behalf of the class of financial creditors he
    represents, such as homebuyers, in accordance with the decision
    taken by a vote of more than 50% of the voting share of the financial
    creditors he represents, who have cast their vote. The homebuyers
    of Earth Copia were, accordingly, represented by their authorised
    representative, who voted in favour of Alpha’s resolution plan dated
    15.10.2019, as per the desire of majority of those homebuyers as
    a class. It is, therefore, not open to individual homebuyers, who
    may have been part of the minority that dissented thereto, to gain
    a foothold by opposing the majority’s decision. A few persons within
    such class cannot dissent with the majority vote in favour of the
    resolution plan. In Jaypee Kensington Boulevard Apartments
    Welfare Association (supra), this Court held that allottees, even if
    not a homogeneous group, could vote either to approve or disapprove
    the resolution plan and even if divergence of views within the class
    may exist, when casting a vote in the CoC, the vote would have to
    be cast as a class.
31. Significantly, this intervenor had raised objections to the approval
    of Alpha’s resolution plan but the same were rejected by the NCLT
    in its order dated 08.06.2021. Aggrieved thereby, the intervenor
    filed Company Appeal (AT) (Ins) No. 283 of 2022 but the same was
    dismissed by the NCLAT, vide order dated 12.10.2022. Therein,
    the NCLAT noted that, if some of the homebuyers had not voted
[2026] 5 S.C.R.                                                           385

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     in favour of the plan, they still had to sail with the majority and the
     procedural violations alleged by them were not sufficient to interfere
     with the order approving the resolution plan. The NCLAT noted that
     the resolution plan was approved by 91.39% voting share in the CoC
     and the Earth Buyers Association for Justice was not a member of
     the CoC. Out of the 35 homebuyers who were sought to be brought
     on record individually by way of an application, 29 homebuyers had
     not voted for the plan. The NCLAT referred to Section 25A(3A) of
     the Code and observed that once the authorised representative of
     that class of voters cast his vote on behalf of the financial creditors
     he represents as per the decision taken by a vote of more than
     50% of the voting share of those financial creditors, who had cast
     their vote, there is no possibility for the dissenting financial creditors
     in that class to maintain a separate voice of dissent against the
     majority vote. The NCLAT, accordingly, held that no grounds were
     made out to interfere with the order approving the resolution plan
     and dismissed the intervenor’s appeal. This order attained finality
     as the intervenor did not choose to approach this Court by filing an
     appeal against the said dismissal order.
32. Though Earth Buyers Association for Justice claims that it represents
    949 buyers in EIL’s four projects, as of April, 2025, the fact remains
    that it was unsuccessful in its attempts before the NCLT and the
    NCLAT in raising objections against Alpha’s resolution plan. We are,
    therefore, of the opinion that Earth Buyers Association for Justice
    has no locus to seek intervention in these appeals and again raise
    objections to the approval of the resolution plans of Alpha and Roma.
33. We may also note that, upon a complaint, the Insolvency and
    Bankruptcy Board of India (IBBI) issued show-cause notice dated
    27.10.2023 to Akash Singhal, the RP of EIL. Thereupon, the
    IBBI passed order dated 06.02.2025 suspending Akash Singhal’s
    registration for three years, effective from 06.03.2025. WP(C) No.
    2906 of 2025 was filed by Akash Singhal against the aforestated
    order dated 06.02.2025 and the same is pending before the Delhi
    High Court. However, while suspending the RP’s registration, the
    IBBI left it to the CoCs/Stakeholders Consultation Committees of all
    the corporate debtors in whose cases Akash Singhal was providing
    services to decide about his continuation with those existing
    assignments. Pursuant to the liberty granted by the IBBI, the CoC of
    EIL decided to continue Akash Singhal as the RP, in terms of Section
386                                                         [2026] 5 S.C.R.

                          Supreme Court Reports


       23 of the Code, i.e., in relation to managing EIL’s affairs, including
       the maintaining of bank accounts, preservation of assets and records,
       representing EIL before judicial and quasi-judicial fora, etc.
34. As regards the other three projects on GNIDA’s leased lands, we
    may note that GNIDA is empowered under Section 7 of the Uttar
    Pradesh Industrial Area Development Act, 1976, to allot land on
    lease basis subject to the terms and conditions determined by it. It
    is pursuant to this power that the subject lands were leased out by
    it to the companies under the control of EIL. We find that the lease
    deeds executed by GNIDA in favour of the lessees, viz., the three
    companies, specifically provided that the lessees would develop and
    erect the proposed buildings on the demised premises in accordance
    with the plans approved by it, duly ensuring compliance with the
    requirements set out in the schedules to the lease deeds. The lessees
    were not to erect or permit to be erected any new building without
    the permission in writing of GNIDA and except in accordance with
    the terms of such permission in writing and the plan, if any, approved
    by GNIDA. The lessees were to develop the projects meeting the
    stipulated norms of development as set out in the lease deeds. The
    lessees were to complete construction of the projects within the
    stipulated time frames, as set out in the lease deeds - seven years
    for all the three lessees. The lease deeds also provided that, in the
    event the lessees failed to complete construction within that time, it
    was lawful for GNIDA, without prejudice to other rights, to re-enter
    upon the premises and determine the leases. The lease deeds
    specifically provided that GNIDA would monitor implementation of
    the projects.
35. Insofar as the lease deed dated 01.09.2010 executed by GNIDA in
    favour of ETIPL is concerned, the same provided that the lessee
    was to use the allotted plot for construction of group housing/flats/
    plots and that it was entitled to allot the dwelling units on sub-lease
    basis to its allotees. Further transfer/sub-lease was, however, to be
    governed by GNIDA’s transfer policy. The sub-lessees were to use
    the premises only for residential use. The construction was to be
    completed within seven years from the date of execution of the lease
    deed but, prior to that, the lessee had to complete construction of a
    minimum 50% of the total floor area ratio of the allotted plot, as per
    the approved lay out plan, and get a completion/occupancy certificate
    of the first phase within three years from the date of execution of
[2026] 5 S.C.R.                                                         387

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     the lease deed. Extension of time for completion of the project was
     contemplated up to a maximum period of another three years only,
     coupled with penalty.
36. As already stated supra, after initiation of the CIRP proceedings
    against EIL on 06.06.2018, the NCLT caused public announcement
    of the same on 12.06.2018. The CoC was constituted and its first
    meeting was held on 05.12.2018. A public announcement was made
    by the IRP on 13.12.2018, inviting claims against EIL, the CD. On
    19.12.2018, the IRP informed GNIDA about the initiation of CIRP
    proceedings against EIL. The RP was appointed on 18.03.2019 by
    the CoC. On 28.05.2019, the RP wrote to GNIDA, calling for its dues
    in relation to all three projects. GNIDA did not respond to these letters
    or submit claims at that time. On 21.06.2019, the RP published the
    Information Memorandum for the three projects on GNIDA’s leased
    lands and the project on the freehold land in Gurgaon. As GNIDA
    had not intimated its dues in time, the Information Memorandum
    mentioned only the estimated dues payable to GNIDA.
37. Roma’s resolution plan was approved by the CoC on 26.08.2019 and
    the RP filed an application before the NCLT on 03.09.2019 seeking
    its approval. It was only thereafter, on 18.09.2019, that GNIDA
    addressed a letter to the RP stating its claimed dues in relation to
    Earth Towne. On 11.11.2019, Alpha’s resolution plan was approved
    by the CoC for Earth TechOne, Earth Sapphire Court and Earth
    Copia. No claim was filed by GNIDA in relation to Earth Sapphire.
    On 11.11.2021, GNIDA filed a claim in relation to its dues for Earth
    TechOne, not before the RP, but before the IRP, who had exited
    from the picture long prior thereto.
38. GNIDA, being an operational creditor of Neo Multimedia Limited
    and Nishtha Software Private Limited, could file its claims during the
    CIRP proceedings against EIL, under Section 60(5)(b) of the Code.
    NCLT had jurisdiction thereunder to entertain claims by or against the
    corporate debtor, including claims by or against its subsidiary situated
    in India. Despite such entitlement, GNIDA failed to file its claims with
    the RP. It was only on 11.11.2021 that GNIDA filed its claim with the
    displaced IRP about its dues from Neo Multimedia Limited but no
    steps were taken by it in relation to Nishtha Software Private Limited.
39. This Court had directed the parties to maintain status quo, vide
    its order dated 13.04.2023 in Civil Appeal No. 1526 of 2023 and
388                                                         [2026] 5 S.C.R.

                          Supreme Court Reports


       batch. However, unmindful of the said order, GNIDA cancelled the
       allotment of lands in favour of Neo Multimedia Limited and Nishtha
       Software Private Limited, by order dated 16.06.2023. This order was
       communicated to the RP only on 22.07.2023 but was not informed
       to this Court on 04.07.2023, 11.07.2023 and 17.07.2023, when the
       matters were listed. It was only after the RP filed IA No. 180402 of
       2023 in Civil Appeal Nos. 2406-2407 of 2023, that GNIDA withdrew
       the aforestated cancellation order on 19.08.2025.
40. This Court also passed a separate order on 17.07.2023 in Civil
    Appeal No. 4619 of 2023, filed by UTOPIA, calling upon GNIDA to
    file an affidavit stating whether it was ready and willing to take up the
    projects and complete the construction so as to give homes/office
    spaces to the buyers on the terms agreed between such buyers
    and the builders. In the event GNIDA was not ready to do so, it was
    called upon to indicate how it intended to protect the interests of the
    buyers in the context of the rules and regulations framed by it or in
    terms of the policy decisions taken by it apropos situations where
    the builder committed default or was liquidated.
41. Pursuant to the order dated 17.07.2023, GNIDA filed affidavit
    dated 24.12.2024. Therein, its Manager stated that, owing to the
    limited infrastructure available with it, GNIDA would not be able to
    take up the projects and complete the construction. Details were
    furnished of the payments made by the lessees from time to time.
    We find that, insofar as Neo Multimedia Limited is concerned, no
    payments were made after 06.01.2011 but the payments made
    earlier to that date were in excess of what was required to be paid.
    As regards Nishtha Software Private Limited, payments stopped on
    20.09.2010. Again, the payments made prior to that date were in
    excess of the required payments. Lastly, ETIPL stopped payments
    after 28.02.2013. However, payments made by it earlier to that
    date were also in excess of the required payments. GNIDA stated
    that no details were available with it as to development of the land
    by Neo Multimedia Limited but insofar as Nishtha Software Private
    Limited was concerned, a site inspection was said to have been
    carried out in 2018 and it was found that a boundary wall had been
    constructed and the buildings were under construction. As regards
    ETIPL, a site inspection was stated to have been carried out by an
    auditor on 28.02.2018, which reflected that the project was lagging
    behind, but no steps were taken.
[2026] 5 S.C.R.                                                         389

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

42. GNIDA also furnished details of the notices issued by it to the
    lessees in the context of defaults in payment. Notices were issued
    to Neo Multimedia Limited on 08.10.2012, 09.01.2019, 08.02.2019,
    25.04.2019, 06.05.2019 and 04.03.2020. Nishtha Software Private
    Limited was issued notices on 28.09.2016, 19.06.2017, 12.10.2018,
    02.01.2019, 08.02.2019, 18.03.2019, 22.10.2019 and 04.03.2020.
    ETIPL was issued notices on 15.10.2013, 25.05.2015, 08.07.2016,
    06.09.2016, 30.09.2016 and 13.07.2018. GNIDA stated that a public
    notice was put up on its website on 05.10.2017, listing defaulting
    builders, which included Neo Multimedia Limited, with dues of
    ₹7,65,48,821/-; Nitisha Software Private Limited, with dues of
    ₹2,09,12,037/-; and ETIPL, with dues of ₹105,02,87,896/-.
43. Thereafter, the Chairman of GNIDA filed an affidavit, notarised on
    25.09.2025. He stated therein that he was holding office as an
    additional duty as there was no full-time Chairman appointed for
    GNIDA. He stated that the Chief Executive Officer of GNIDA was its
    highest full-time officer. He apologized for the order dated 16.06.2023
    passed by GNIDA cancelling the allotment of lands to Neo Multimedia
    Limited and Nishtha Software Private Limited. He referred to the order
    dated 19.08.2025, recalling the same, and stated that no further action
    with regard to resumption of possession or refund of amounts was
    taken thereafter. According to him, the outstanding dues, including
    interest, payable to GNIDA as on 31.08.2025, stood as follows:
    Neo Multimedia Limited - ₹31,82,88,309/-; Nishtha Software Private
    Limited - ₹17,57,25,184/-; and ETIPL - ₹309,79,44,038/-. We may
    note that insofar as Neo Multimedia Limited is concerned, out of
    the total dues of ₹31,82,88,309/-, ₹1,97,91,781/- was penal interest
    payable on the premium dues; ₹1,23,18,440/- was the penal interest
    payable on the additional compensation; and ₹11,34,81,931/- was
    the time-extension penalty. Therefore, ₹14,55,92,152/-, in all, was
    attributable to penal interest/penal charges. Similarly, out of the
    total dues of ₹17,57,25,184/- payable by Nishtha Software Private
    Limited, ₹43,12,694/- was the penal interest on the additional
    compensation; ₹87,29,431/- was the penal interest on the lease
    rent; and ₹8,31,69,781/- was the time-extension penalty. Thus,
    ₹9,62,11,906/- out of the total ₹17,57,25,184/- was attributable to penal
    interest/penal charges. We may also note that there was no default in
    payment of premium by Nishtha Software Private Limited. As regards
    ETIPL, out of the total dues of ₹309,79,44,039/-, the penal interest
390                                                          [2026] 5 S.C.R.

                          Supreme Court Reports


       on the premium dues was ₹31,88,34,014/- while ₹5,48,38,863/- was
       the penal interest on the additional compensation and ₹4,26,96,421/-
       was the penal interest on the lease rent along with time-extension
       penalty of ₹18,02,05,897/-, totalling to ₹59,65,75,195/-. Therefore,
       devoid of penal interest/penal charges, the dues of ETIPL were just
       over ₹250 crore.
44. GNDIA is in appeal against the judgment dated 30.01.2023, insofar as
    the NCLAT denied it entitlement to claim penal interest. According to
    it, the finding of NCLAT that there was delay and inaction on its part
    is incorrect, as sufficient notices were sent by it to the lessees raising
    claims in that regard. GNIDA, therefore, has a grievance apropos
    the direction of the NCLAT to drop its penal interest/penal charges
    and to recalculate its dues. According to GNIDA, the terms of its
    lease deeds are sacrosanct and ought not to be interfered with, be
    it during the CIRP proceedings or thereafter. Though GNIDA would
    contend that the cost at which the successful resolution applicants,
    Alpha and Roma, would be selling the homes/office spaces would
    include the cost of the land and construction apart from a profit
    component, the fact remains that the land would not be sold to the
    home/office space buyers, but they would only assume the status of
    sub-lessees. The ownership of the land would not stand transferred
    and would remain with GNIDA. This was the original intent of the
    scheme of allotment, and it does not stand altered even if the
    resolution plans are given effect to. What is contemplated under
    the resolution plans is merely transfer of possession of the lands
    to the successful resolution applicants to enable them to complete
    the projects and to deliver the units to the allottees, as sub-lessees.
45. In Greater Noida Industrial Development Authority vs. Prabhjit
    Singh Soni and another10, a 3-Judge Bench of this Court opined
    that, in terms of the Section 13-A of the Uttar Pradesh Industrial
    Area Development Act, 1976, GNIDA has to be treated as a secured
    creditor in respect of the amount payable to it by a corporate debtor
    and in that regard, a charge is statutorily created on the assets of
    such corporate debtor. Though reliance is placed on this decision
    by GNIDA, it is not open to it to approbate and reprobate. On the
    one hand, GNIDA contends that EIL, the CD, had nothing to do with


10   (2024) 6 SCC 767
[2026] 5 S.C.R.                                                       391

                 Alpha Corp Development Private Limited v.
     Greater Noida Industrial Development Authority (GNIDA) and Others

        the lands leased out by it to the three companies and that those
        lands ought not to have formed part of EIL’s assets during the CIRP
        proceedings. On the other hand, GNIDA raised claims before the
        IRP and the RP and it also complained of not being kept abreast of
        CIRP proceedings against EIL.
46. Significantly, it was only on 11.11.2021 that GNIDA filed a claim in
    relation to Earth TechOne but, surprisingly, GNIDA addressed its
    letter to the IRP and not to the RP, though the IRP was replaced as
    long back as in March, 2019. This claim was also belated as Alpha’s
    resolution plan was approved by the CoC on 11.11.2019 and by
    the NCLT on 08.06.2021. As noted by the NCLAT itself, there was
    no error made in the Information Memorandum which specifically
    recorded that the landholding entities for Earth Sapphire Court,
    Earth TechOne and Earth Towne were Nishtha Software Private
    Limited, Neo Multimedia Limited and ETIPL, the subsidiaries of EIL,
    to whom lands were leased out by GNIDA. Further, the resolution
    plans of both Alpha and Roma unequivocally recorded that only the
    development rights in relation to those projects formed part thereof
    and not the title to the underlying lands. It may be noted that the CoC
    approved Roma’s resolution plan on 26.08.2019 and the RP filed
    an application before the NCLT seeking its approval on 03.09.2019.
    However, it was only on 18.09.2019 that GNIDA raised a claim for
    ₹148 crore. Surprisingly, in the said letter, GNIDA projected itself
    as a financial creditor of EIL; requested processing of its claims
    during the CIRP; and sought that the leasehold rights should not be
    transferred without securing its dues. As this claim was, in any event,
    belated it could not have been considered in view of the decision of
    this Court in RPS Infrastructure Limited vs. Mukul Kumar and
    another11. Surprisingly, GNIDA never raised a claim for its alleged
    dues in relation to Earth Sapphire Court.
47. Further, we may note that GNIDA is conveniently ignoring certain
    crucial facts. Two letters had been addressed to GNIDA after
    initiation of the CIRP proceedings against EIL - the IRP sent letter
    dated 19.12.2018 while the RP, after his appointment by the CoC,
    addressed letter dated 28.05.2019. These letters reflect that GNIDA
    was informed about the initiation of the CIRP proceedings against


11    (2023) 10 SCC 718
392                                                        [2026] 5 S.C.R.

                          Supreme Court Reports


       EIL; that the development rights over the project lands leased out by
       GNIDA to the three companies controlled by EIL were also included
       in the CIRP proceedings; and GNIDA was called upon to inform its
       dues. Despite the non-submission of claims by GNIDA within time,
       the RP intimated the dues of GNIDA to the prospective resolution
       applicants after gathering the same from the resources available.
       The RP’s Information Memorandum clearly specified that only the
       development rights and leasehold rights of the lessees, which were
       100% subsidiaries of EIL, were included therein.
48. Intermittent and sporadic notices with regard to defaults in payment
    are all that GNIDA has to offer at this stage. We may note that,
    though payments were allegedly stopped by the lessees, viz., Neo
    Multimedia Limited, Nishtha Software Private Limited and ETIPL,
    on 06.01.2011, 20.09.2010 and 28.02.2013 respectively, GNIDA
    did not bother to follow up on such defaults on a regular basis and
    only occasional notices were issued to the lessees. As regards Neo
    Multimedia Limited, the first notice was issued only in October, 2012
    followed by a notice, over 8 years later, on 09.01.2019 and three
    notices, thereafter, in February, April and May, 2019, and the last
    notice on 04.03.2020. All the notices, except the first one, were issued
    after commencement of the CIRP proceedings! As regards Nishtha
    Software Private Limited, the last payment was allegedly made on
    20.09.2010 but default notices were issued by GNIDA only in 2016,
    i.e., on 28.09.2016, followed by a notice more than 8 months later
    on 19.06.2017. Thereafter, with a gap of over one year and three
    months, GNIDA issued a notice on 12.10.2018. Later notices were
    in the year 2019 and the last was in March, 2020. Insofar as ETIPL
    is concerned, the last payment was stated to have been made on
    28.02.2013 and the first default notice was issued by GNIDA on
    15.10.2013. However, having issued the aforestated notice within
    a short period of time after the default, GNIDA took no steps till
    25.05.2015, when the second notice was issued. Again, GNIDA slept
    over the matter for a year and issued the next notice on 08.07.2016
    followed by two notices in September, 2016. Then, with a hiatus of
    nearly two years, GNIDA issued the last notice on 13.07.2018.
49. We are, therefore, of the opinion that GNIDA contributed greatly
    to the present imbroglio by its persistent inaction and ineptitude
    all through. Having executed lease deeds for development of the
    lands, it failed to keep track of and monitor the development being
[2026] 5 S.C.R.                                                          393

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     undertaken on such lands to ensure timely completion thereof
     within the stipulated period of seven years. We may also note that
     long prior to initiation of the CIRP proceedings against EIL, the CD,
     GNIDA was informed by the aggrieved home/office space buyers
     of the tardy progress in the construction of the projects but failed
     to take necessary coercive steps against the lessees and/or the
     developer, EIL. In this regard, we may also note that GNIDA cannot
     claim ignorance of the fact that it was EIL that was executing the
     development of the projects on all three plots of land leased out by
     GNIDA to the three companies. Having addressed a letter to the
     police authorities in relation to EIL’s construction on the land leased
     out to ETIPL, GNIDA cannot now seek to claim ignorance of the
     reality that it was EIL that was undertaking the construction of the
     projects on all three leased lands. This is further fortified by the fact
     that all three lessees submitted documents to GNIDA while seeking
     approval of building plans/sanctions based on the certification secured
     from various authorities by EIL itself. Though GNIDA would contend
     that it was not a party to the applications made by EIL for obtaining
     permissions/NOCs from various authorities, there is no escaping
     the fact that the lessees submitted all such documents to GNIDA for
     securing sanction and permission for building plans. The question
     of GNIDA claiming ignorance of EIL’s role in the development of the
     projects, therefore, does not arise.
50. Turning a blind eye to all that was going on and also not going
    on, GNIDA did not even choose to be vigilant after initiation of the
    CIRP proceedings against EIL. GNIDA was informed of the same
    by the IRP in December, 2018 and by the RP in March, 2019, but
    took no steps to participate in the proceedings. On the other hand,
    GNIDA seeks to blame the RP for not informing it of the progress of
    the CIRP proceedings!! GNIDA’s correspondence was inconsistent
    and impulsive, unmindful of the strict timelines contemplated by the
    Code. The lack of responsibility and application of mind on the part
    of GNIDA is manifest from the fact that even when it did submit its
    hugely belated claim on 11.11.2021 in relation to its alleged dues
    from Neo Multimedia Limited, it addressed it to the IRP who had
    long before exited from the scene upon appointment of the RP by
    the CoC. GNIDA never ever raised a claim in relation to the dues
    of Nishtha Software Private Limited. Even as regards its dues from
    ETIPL, we may note that GNIDA addressed its letter to the RP
394                                                         [2026] 5 S.C.R.

                          Supreme Court Reports


       only on 18.09.2019, after the approval of Roma’s resolution plan
       by the CoC on 26.08.2019. The same non-application of mind is
       demonstrated by GNIDA’s failure to point out to the NCLAT that its
       appeal against the NCLT’s order dated 08.06.2021 was limited only
       to the projects on its own leased lands and did not extend to the
       approval of Alpha’s resolution plan in relation to Earth Copia, EIL’s
       project on freehold land in Gurugram.
51. Having allowed so much water to flow under the bridge not only to
    its own detriment but also to the detriment of the innocent home/
    office space buyers who had invested their hard-earned monies for
    securing their own homes/office spaces, it is not open to GNIDA to
    portray itself as an uninformed and injured victim at this late stage.
    We may also note that, even before this Court, GNIDA chose to
    approbate and reprobate continuously. This incoherency and lack
    of consistency on its part is again illustrative of its continued failure
    to take timely measures, despite being fully aware of the situation.
    On one hand, GNIDA contends that it has no role to play as EIL,
    the CD, had no interest in the lands leased out by it to the three
    companies but, on the other, GNIDA did raise a claim in relation to
    two out of the three projects on those leased lands. In fact, it raised
    a claim before the RP in September, 2019, claiming to be a financial
    creditor and that its dues of ₹149 crore had to be admitted.
52. Before this Court, GNIDA attempted to bring in a third party, viz.,
    Engineering Projects (India) Limited (EPIL), at the behest of the
    Earth Buyers Association for Justice, to complete EIL’s stalled
    projects. We may note that EPIL, itself, has not come forward to
    stand by any such offer and only a letter addressed by it is relied
    upon. Perusal of the letter dated 23.12.2024 addressed to GNIDA
    by EPIL reflects that, pursuant to a meeting held on 21.12.2024, the
    Executive Director of EPIL stated that they were ready and willing to
    complete the stalled projects of EIL situated at Greater Noida. Having
    stated so, he said that this was an ‘in-principle approval’ which was
    contingent upon further study of the financial and other documents/
    information of the projects that would be made available to the
    company. It was, therefore, not a firm or unconditional commitment
    by EPIL. Significantly, EPIL did not even choose to come before
    us, if it was really keen on pursuing its offer. Therefore, EPIL’s offer
    is not worthy of consideration and is, accordingly, eschewed from
    consideration.
[2026] 5 S.C.R.                                                               395

                 Alpha Corp Development Private Limited v.
     Greater Noida Industrial Development Authority (GNIDA) and Others

53. The sheet anchor of GNIDA’s case is that the assets of subsidiary
    companies cannot be made part of the assets of the holding company
    that was subjected to CIRP proceedings. Section 2(87) of the
    Companies Act, 2013, defines a subsidiary company or subsidiary to
    mean a separate legal entity. Reliance was placed by GNIDA upon
    the recent judgment of this Court in BRS Ventures Investments
    Limited vs. SREI Infrastructure Finance Limited and another12,
    which reiterated that a holding company and its subsidiaries are
    distinct legal entities and merely because the holding company
    owns the entire shareholding in the subsidiary company, it would
    not dilute its separate legal existence. No doubt, the concept of
    holding companies and subsidiary companies is firmly entrenched
    in our corporate scenario and once it is established that the holding
    and subsidiary companies are independent legal entities in their own
    right, the sanctity of such legal status has to be maintained unless
    circumstances exist that require lifting/piercing of the corporate
    veil. The question that arises is whether this was a fit case to lift
    the corporate veil. Though the NCLAT was averse to doing so, we
    are inclined to hold otherwise. In that regard, we may refer to the
    observations of a Constitution Bench in Life Insurance Corporation
    of India vs. Escorts Ltd. and others13 in the context of lifting of
    the corporate veil:
              ‘…..Generally and broadly speaking, we may say that
              the corporate veil may be lifted where a statute itself
              contemplates lifting the veil, or fraud or improper conduct is
              intended to be prevented, or a taxing statute or a beneficent
              statute is sought to be evaded or where associated
              companies are inextricably connected as to be, in reality,
              part of one concern. It is neither necessary nor desirable
              to enumerate the classes of cases where lifting the veil
              is permissible, since that must necessarily depend on the
              relevant statutory or other provisions, the object sought to
              be achieved, the impugned conduct, the involvement of
              the element of public interest, the effect on parties who
              may be affected, etc.’



12    (2025) 1 SCC 456
13    (1986) 1 SCC 264
396                                                       [2026] 5 S.C.R.

                        Supreme Court Reports


54. As is clear from the aforestated observations when, in reality,
    associated or group companies are inextricably connected so as
    to form part of one concern, the corporate veil should be lifted.
    Applying this principle in ArcelorMittal India Private Limited vs.
    Satish Kumar Gupta and others14, this Court affirmed that where
    protection of public interest is of paramount importance or where
    a company has been formed to evade obligations enforced by law
    and by the Courts, the Court would disregard the corporate veil. It
    was further observed that this principle would be applied even to
    group companies so that one is able to look at the economic entity
    of the group as a whole.
55. Neo Multimedia Limited and Nishtha Software Private Limited were
    both wholly owned subsidiaries of EIL, the CD. They had leases
    over the lands in which EIL was to develop the projects, viz., Earth
    TechOne and Earth Sapphire Court. ETIPL was incorporated only to
    enable GNIDA’s leasing of land for development of Earth Towne and
    was controlled by EIL, with a 98% shareholding. ETIPL, therefore,
    stands on a different footing from the other two companies, insofar
    as GNIDA is concerned. In any event, we may note that all three
    companies either share common directors with EIL and/or have
    their relations as directors. The only assets of the three companies
    were the lands leased out to them by GNIDA for these projects. The
    companies’ shareholdings indicate that EIL was the dominant and
    majority shareholder.
56. Further, GNIDA was clearly aware that it was EIL, the CD, that was
    developing the projects on the lands leased out by it to the three
    companies. GNIDA cannot claim ignorance of this on the mere ground
    that it was not a party to the development agreements/MoU. This
    was the situation in relation to two projects – Earth Sapphire Court
    as well as Earth TechOne. Insofar as Earth Towne is concerned,
    as already stated, GNIDA itself required the consortium of the
    three companies to incorporate a SPC and it was pursuant to this
    requirement, that ETIPL was brought into existence. Further, the
    lease deed executed by GNIDA in favour of ETIPL made it clear
    that EIL was to be the lead member of ETIPL, retaining its majority
    shareholding as well as its lead role. It is an admitted fact that EIL,


14   (2019) 2 SCC 1
[2026] 5 S.C.R.                                                         397

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     which had a 78% shareholding in ETIPL, increased it to 98%. ETIPL
     executed an agreement conferring the right to develop the project
     on the leased land in favour of EIL. GNIDA cannot, therefore, look
     askance at the role played by EIL in the development of Earth
     Towne. More so, in the light of its own letter to the police authorities
     acknowledging EIL’s role in the development of Earth Towne, which
     we have already referred to. In effect, GNIDA cannot claim ignorance
     of the constructions by EIL in relation to all three projects. Each case
     that comes before a Court, in the context of lifting of the corporate
     veil, would have to turn upon its own individual facts. Given the
     facts obtaining presently, we are of the firm view that this was an
     eminently fit case for lifting the corporate veil, as EIL was the main
     driving force in the development of the projects and in payment of
     GNIDA’s dues. The subsidiary companies were only a front. In the
     light of this finding, we deem it unnecessary to deal with the issue
     raised in the context of Sections 18 and 25 of the Code, apropos
     the scope of the term ‘assets’.
57. Alpha’s resolution plan, which was approved by the CoC on 11.11.2019
    and by the NCLT on 08.06.2021, provided under Clause 4 thereof,
    that it would seek a waiver from GNIDA of its dues but added that
    if such waiver was not granted, the dues would be proportionately
    distributed amongst all the allottees. Clause 12.1 of the resolution
    plan contemplated issuance of a ‘No Dues Certificate’ by GNIDA
    prior to conveyances in relation to Earth Sapphire Court as well as
    Earth TechOne. Alpha, however, stated before this Court that it was
    willing to pay GNIDA its dues without penal interest/penal charges,
    given sufficient amount of time, without burdening the homebuyers.
58. In EIL’s CoC, HDFC Bank and the home/office space buyers were the
    only financial creditors. HDFC Bank, which claimed to be a secured
    financial creditor, dissented with Alpha’s resolution plan. Its objection
    to the acceptance of the resolution plan was rejected by the NCLT
    and that order became final. Therefore, the Monitoring Committee
    comprised only the buyers. The Monitoring Committee was impleaded
    as a party respondent by GNIDA in Company Appeal (AT)(Ins) No.
    629 of 2022 filed before the NCLAT. Sanjay Bhalla, the authorized
    representative of the Monitoring Committee, is supporting Alpha’s
    resolution plan and filed Civil Appeal No. 1743 of 2023 assailing
    the judgment dated 30.01.2023 in relation to Earth Sapphire Court
    and Earth TechOne. He supports Alpha, whose resolution plan was
398                                                         [2026] 5 S.C.R.

                          Supreme Court Reports


       approved by the order dated 08.06.2021 and seeks restoration thereof.
       Notably, the Minutes of the Monitoring Committee’s meeting held on
       10.08.2025 evidence that Alpha undertook that it would absorb the
       dues payable to GNIDA and the same would not be burdened upon
       the allottees/buyers.
59. Earth Towne Flat Buyers Welfare Association represents about 1600
    homebuyers of Earth Towne, of whom 1222 homebuyers are its
    registered members. The total number of homebuyers in the project
    are stated to be around 1,878. The majority of the homebuyers are,
    therefore, represented by this association, which supports Roma’s
    resolution plan. We may also note that Roma, being the successful
    resolution applicant, expressed its willingness to settle the dues
    of GNIDA given sufficient time. Roma does not propose to charge
    GNIDA’s dues from the homebuyers of Earth Towne and is willing
    to bear the entire burden by itself.
60. Earth Towne Flat Buyers Welfare Association filed Civil Appeal No.
    2466 of 2023, aggrieved by the judgment dated 30.01.2023 insofar
    as it pertained to Company Appeal (AT) (Ins) No. 630 of 2022. This
    association participated in the proceedings before the NCLAT and
    contributed substantially, by bringing out relevant facts reflecting upon
    the somnolence and delay on the part of GNIDA in taking appropriate
    steps against EIL, despite its failures on all counts.
61. Civil Appeal No. 2491 of 2023 was filed by Roma assailing the
    judgment dated 30.01.2023 insofar as it related to Company Appeal
    (AT) (Ins) No. 630 of 2022,. Roma seeks restoration of the order
    dated 05.04.2021 approving its resolution plan.
62. UTOPIA is the association of allottees of the Earth TechOne, while
    Sapphire Patrons Independent Common Association (SPICA) is
    the associtation of allottees of Earth Sapphire Court. Both these
    associations participated in the proceedings before the NCLAT and
    supported the NCLT orders approving the resolution plans. On the
    same lines, they now support the said plans and seek setting aside
    of the judgment dated 30.01.2023 passed by the NCLAT, insofar as
    it pertained to Company Appeal (AT) (Ins) No. 629 of 2022.
63. Civil Appeal Nos. 3435-3437 of 2023 were filed by the Earth United
    Consumer Association, assailing the judgment dated 30.01.2023 in
    relation to all three appeals and supporting the orders approving
    the resolution plans of Roma and Alpha. The association claimed
[2026] 5 S.C.R.                                                         399

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     to be a consumer association, representing the buyers/allottees of
     EIL’s projects. Significantly, this association was not a party to the
     earlier proceedings. In any event, as it is only playing a supporting
     role, reiterating the grounds taken by the parties to the litigation, we
     need not entertain the same.
64. Of relevant significance is the fact that the Ministry of Housing and
    Urban Affairs, Government of India, constituted a committee under
    the chairmanship of Mr. Amitabh Kant, former Chief Executive Officer
    of the Policy Commission, vide order dated 31.03.2023, in relation
    to stalled real estate projects. This Committee was to recommend
    measures to protect the interests of homebuyers and to complete
    such stalled projects in a timely manner. The Committee submitted
    its report on 24.07.2023. The Committee noted that real estate was
    an important sector and more than 200 industries were linked to it,
    creating a large number of jobs. It was also noted that as per the
    estimate of the Indian Banks Association, about 4.12 lakh houses
    across the country were not completed due to financial constraints of
    the developers. Of these, around 2.4 lakh houses were stated to be in
    the National Capital Region under Authorities, such as NOIDA, GNIDA
    and YEIDA. Upon the recommendations made by the Committee, the
    Government of Uttar Pradesh was stated to have formulated a policy/
    package so as to protect the interests of all parties while promoting
    development. It was recorded that the main objective of the policy/
    package was to provide houses/flats with registry to the homebuyers
    as early as possible. Group housing projects were covered thereby
    but not projects that were commercial, industrial, etc.
65. The scheme of the policy/package envisages co-developers
    being given permission to complete the projects after recognizing
    them in the records of the Authority concerned and, thereupon,
    the responsibility for paying the dues of the said Authority and
    completing the project would be jointly shared by the co-developer
    and the allottee. All outstanding amounts were to be re-verified by
    an independent chartered accountant/ third party and recalculated
    as per the conditions of the lease deed and the orders issued by the
    Authority from time to time. Time extension to complete the project
    was to be given, free of cost, subject to a maximum period of three
    years. Net outstanding amounts of upto ₹100 crore were to be paid
    in a maximum of one year while net dues of upto ₹500 crore could
    be cleared over two years. If the outstanding amount exceeded ₹500
400                                                            [2026] 5 S.C.R.

                           Supreme Court Reports


       crore, it could be paid within three years. In the event the developer
       failed to complete the project within the stipulated three years, penalty
       of 20% was to be levied on the remaining dues and efforts were to
       be made by the Authority concerned to get the project completed.
       If the dues were already paid in full to the Authority, then no fine
       was to be imposed. This policy/package was communicated by the
       Infrastructure and Industrial Development Commissioner, Government
       of Uttar Pradesh, to the Chief Executive Officers of the Authorities,
       including GNIDA and YEIDA.
66. Though, the aforestated policy/package would have application only
    to Earth Towne, being a residential project, and may not apply stricto
    sensu to the other two projects, which are commercial in nature, we
    may note the higher objective underlying this policy, i.e., to secure
    completion of stalled development projects. As that was the very
    aim of the CIRP proceedings initiated against EIL, the CD, we are
    of the opinion that by adopting the policy to some extent to suit the
    present situation, the successful resolution applicants, Alpha and
    Roma, can be permitted to proceed with their resolution plans to
    complete the projects, viz., Earth Towne, Earth Sapphire Court and
    Earth TechOne, while protecting the interests of GNIDA also.
67. As rightly pointed out by the NCLAT, the inertia on the part of GNIDA
    and its failure to protect the interests of the home/office space
    buyers, apart from its own interests, clearly disentitles it from levying
    penal interest/penal charges/time-extension penalties at this stage.
    However, notwithstanding the lapses on its part, GNIDA would still
    be entitled to recover the principal amounts due to it, after deducting
    the penal interest, penal charges and time-extension penalties. The
    dues in that regard shall be recalculated by GNIDA, as indicated
    hereinabove, and communicated to Alpha and Roma within two weeks
    from the date of this judgment. Once such amounts are quantified,
    the resolution applicants shall make necessary arrangements for
    payment of those dues. We would expect Alpha and Roma, the
    successful resolution applicants, to stand by their commitment that
    such dues would not be burdened upon the home/office space
    buyers who have already suffered sufficiently by the delay in the
    execution of the projects. The said dues shall be cleared by Alpha
    and Roma on their own. The payments in that regard, in equated
    monthly instalments, shall be made over twenty four months. The first
    such payment shall be made on or before the 7th day of July, 2026.
[2026] 5 S.C.R.                                                          401

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

     Registration of the homes/office spaces in favour of the allottees
     shall be undertaken only after payment of the dues of GNIDA in
     totality and with its active participation, so as to confer the status of
     sub-lessees upon the buyers.
68. Given the fact that GNIDA is responsible for this litigation to a great
    extent, owing to its failure in monitoring the development of the
    projects and in taking timely measures to realise its dues from EIL,
    it would not be entitled to any interest on the principal amounts due
    for the extended period of twenty four months, during which the
    successful resolution applicants, Alpha and Roma, are required to
    clear its dues. The resolution plans of Alpha and Roma shall stand
    restored. The successful resolution applicants shall endeavour to
    complete the projects within the time frames indicated by them in
    their resolution plans. Those time frames shall commence from the
    1st day of June, 2026.
69. On the above analysis, Civil Appeal Nos. 1526 of 2023, 1743 of 2023,
    2491 of 2023, 2466 of 2023, 3438 of 2023 and 4619 of 2023 are
    allowed. Civil Appeal Nos. 2406-07 of 2023 are disposed of in the
    above terms. Civil Appeal Nos. 3435-3437 of 2023 and Civil Appeal
    (Diary) No. 19132 of 2023 are dismissed and lastly, Civil Appeal Nos.
    2756 and 2763 of 2023 filed by GNIDA are also dismissed.
70. IA No. 174061 of 2023 was filed by Surinder Kumar Juneja, the
    erstwhile IRP who was appointed on 06.06.2018, at the time of
    admission of the CIRP against EIL. He sought intervention in this
    appeal only because of the status quo order dated 13.04.2023
    passed by this Court. Owing to the said order, his application in
    IA No. 1194 of 2021 pending before the NCLT, filed under Section
    60(5) of the Code, for payment of his professional fees, has also
    been put on hold. As the appeals are being disposed of, the status
    quo order shall cease to operate. His application can, therefore, be
    considered by the NCLT, independently and on its own merits, in
    accordance with law.
71. IA No. 1878 of 2024 was filed by Airwil Intellicity Social Welfare
    Society, seeking to come on record on the ground that the issue
    raised in the present appeals is similar to that in the CIRP proceedings
    that it is interested in. The application is misconceived and is,
    accordingly, rejected. Similarly, IA No. 137704 of 2023 was filed by
    the consortium of One City Infrastructure Private Limited and APM
402                                                       [2026] 5 S.C.R.

                         Supreme Court Reports


       Infrastructure Private Limited, seeking to intervene on the ground
       that their resolution plan, which was pending approval before the
       adjudicating authority, has been kept on hold owing to the pendency
       of these appeals. This application is equally misconceived and is,
       accordingly, dismissed.
72. IA No. 137215 of 2023 was filed by one Ms. Manish Rawat, Resolution
    Professional of Earth Gracia Buildcon Private Limited, seeking to
    intervene in these appeals on the ground that she is the Resolution
    Professional of a group company of EIL, which is also facing CIRP
    proceedings, and has a direct interest in the outcome of these cases,
    as the decision in these appeals would decide the fate of numerous
    allottees in the project, which was the subject matter of the CIRP
    against that group company. However, we are not inclined to accept
    her intervention in these appeals and the application is dismissed.
73. IAs for intervention and relief filed by Sanjeev Kumar Singh and
    Beena Singh, claiming to be affected homebuyers of Earth Towne,
    are not considered as they were not parties before the NCLAT. In any
    event, their interests are adequately protected by their association.
    The applications are, accordingly, dismissed. IA Nos. 217541-217542
    are also rejected, as the interest of the intervenor is sufficiently
    represented.
74. IA Nos. 166202 of 2023 and 50758 of 2025, filed by Jambey Tashi
    (deceased, represented by LRs) and others, seeking to intervene
    and also praying for a direction to NBCC (India) Limited or any other
    competent public sector undertaking to submit its detailed proposal for
    completion of the projects of EIL and to take over and complete such
    projects, so as to hand over the units to the buyers is also rejected.
75. IA No. 77861 of 2023, filed by Earth Buyers Association for Justice,
    seeking to come on record, is misconceived as its appeal against
    the order dated 08.06.2021 was dismissed and attained finality.
    Significantly, it did not disclose this fact in its application for
    impleadment. Its applications for directions are also rejected.
76. Apart from the aforestated applications, we may note that several
    intervention applications were filed by home/office space buyers
    seeking to be heard. However, as their interests are sufficiently
    represented by the associations which had participated in the
    proceedings before the NCLAT, we are not inclined to entertain such
    individual intervention applications.
[2026] 5 S.C.R.                                                      403

             Alpha Corp Development Private Limited v.
 Greater Noida Industrial Development Authority (GNIDA) and Others

77. Similarly, applications have been filed by persons claiming to be
    home/office space buyers, who had failed to submit their claims
    before the IRP/RP within time and now seek to be impleaded in these
    appeals to air their grievances in that regard. As they failed to take
    necessary steps at the relevant time by filing applications before the
    NCLT, if their claims were not admitted or entertained by the IRP/
    RP and as such issues are outside the scope of these appeals,
    we are not inclined to entertain the same. Intervention applications
    filed by such intervenors and their applications for directions are,
    accordingly, rejected.
     All other applications shall also stand closed.
     Parties shall bear their own costs.

     Result of the case: Appeals disposed of.




     †
         Headnotes prepared by: Divya Pandey


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Lifting of corporate veil"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.