Created byFuzzy Cloud

Supreme Court of India

ALKA CHANDEWARversusSHAMSHUL ISHRAR KHAN

Citation
2017 INSC 593
Decided
6 July 2017
Disposal
Appeal(s) allowed

Holding

Section 27(5) empowers the arbitral tribunal to seek contempt of any order it passes during the conduct of arbitral proceedings, and the 2015 amendment to Section 17 renders such orders enforceable as court orders, rendering the High Court's restrictive interpretation untenable.

Summary

The sole arbitrator, on 7 October 2010, issued an interim order under Section 17 of the Arbitration and Conciliation Act, 1996 prohibiting the disposal of any flats without its leave. The respondent transferred five flats on 14 October 2010, breaching that order, and the arbitrator later found the breach and, on 5 May 2014, made a representation to the Bombay High Court under Section 27(5) seeking contempt proceedings. The High Court held that Section 27(5) only allowed the tribunal to seek contempt in respect of taking evidence and dismissed the petition as time‑barred. On appeal, the Supreme Court read Section 27(5) literally, holding that it empowers the tribunal to seek contempt for any breach of its orders during the arbitral proceedings, not merely for evidence‑related matters, and noted that the 2015 amendment to Section 17 makes such orders enforceable as court orders. Consequently, the Court set aside the High Court judgment and remanded the matter to the High Court to determine on facts whether contempt occurred. The appeal was allowed.

Issues considered

  • Whether Section 27(5) of the Arbitration and Conciliation Act, 1996 empowers an arbitral tribunal to make a representation to a court for contempt of its interim orders beyond matters of taking evidence.
  • Whether the amendment introduced by Section 17(2) (2015) provides a complete remedy for enforcement of arbitral tribunal's interim orders, thereby affecting the scope of Section 27(5).
  • Whether the contempt petition filed by the tribunal is barred by limitation.

Legislation cited

Subjects

ArbitrationContempt of CourtInterim MeasuresSection 27(5)Section 17(2)Enforcement of Arbitral OrdersArbitral Tribunal Powers

Judgment

                        [2017] 6 S.C.R. 533


                      ALKA CHANDEWAR                                  A
                                 v.
                  SHAMSHUL TSHRAR KHAN
                  (Civil Appeal No. 8720 of 2017)
                          JULY06, 2017                                B

    [R. F. NARIMAN AND SANJAY KISHAN KAUL, JJ.]
        Arbitration and Conciliation Act, 1996 - ss. 2 7 (5) and 17(2)
- Courts power to punish for contempt of orders made by Arbitral
tribunal - Scope and ambit of - Held: Section 27(5) specifically C
states that persons guilty of any contempt to the arbitral tribunal
during the conduct of the arbitral proceedings is within its ken -
Entire object of providing that a party may approach the arbitral
tribunal instead of the Court for interim reliefs would be stultified if
interim orders passed by such tribunal are toothless - It is to give
teeth to such orders that an express provision is made in s. 27(5) - D
More so, s. 17(2) was added, so that the cumbersome procedure of
arbitral tribunal having to apply every time to the High Court for
contempt of its orders would no longer be necessmy - On facts, the
order passed by the High Court that s.27(5) does not empower the
arbitral tribunal to make representation to the court for contempt E
of the orders including interim order unless they are in respect of
taking evidence, set aside - Matter remanded back to decide the
alleged .contempt on facts.
       Allowing the appeal, the Court
        HELD: 1.1 On reading Section 27(5) of the Arbitration         F
and Conciliation Act, 1996 literally, persons failing to attend in
accordance with the court process fall under a separate category
from "any other default". Further, the Section is not confined to
a person being guilty of contempt only when failing to attend in
accordance with such process. The Section specifically states that
persons guilty of any contempt to the Arbitral Tribunal during        G
the conduct of the Arbitral proceedings is within its ken. The
said language is, in fact, in consonance with the Chapter heading
of Chapter V, "Conduct of arbitral proceedings". Further, it is
well settled that a marginal note can be used as an internal aid to
                                                                      H
                              533
534            SUPREME COURT REPORTS                      [2017] 6 S.C.R.


A     interpretation of sta'tutes only in order to show what is the general
      drift of the section. It may also be resorted to when the plain
      meaning of the section is not clear. In the instant case, the plain
      meaning of sub-section (5) is resorted to. This being the case, it
      is difficult to appreciate the reasoning of the High Court. Also, in
      consonance with the modern rule of interpretation of statutes,
B
      the entire object of providing that a party may approach the
      Arbitral Tribunal instead of the C9urt for interim reliefs would
      be stultified if interim orders passed by such Tribunal are
      toothless. It is to give teeth to such orders that an express
      provision is made in Section 27(5) of the Act. [Para 7) [539-E-G)
c         1.2 Sub-section(2) to Section 17 was added by the
  Amendment Act 2015, so that the cumbersome procedure of an
  Arbitral Tribunal having to apply every time to the High Court
  for contempt of its orders would no longer be necessary. Such
  orders would now be deemed to be orders of the Court for all
D purposes and would be enforced under the Civil Procedure Code,
  1908 in the same manner as if they Were orders of the Court.
  The submission that sub-section (2) of section 17 introduced by
  the 2015 Amendment Act now provides for the necessary remedy
  against infraction of interim orders by tribunal is of no substance
  in view of the fact that Section 17(2) was enacted for the purpose
E of providing a "complete solution" to the problem. [Para 10)
  [541-F-G]
             1.3 The judgment of the High Court is set aside. The
      matter is remanded to decide the alleged contempt on facts.
      [Para 11] [542-A-B)
 F
            Maruti Udyog Limited v. Mahinder C Mehta & Ors
            [2007) 10 SCR 933: 2007 (13) SCC 220; Mis Ambalal
            Sarabhai Enterprises v. Mis Amrit Lal & Co. & Anr.
            [20011 2 Suppl. scR 195 : (2001) s sec 397 -
            referred to.
 G
                             Case Law Reference
      [2007] 10 SCR 933               referred to             Para4
      [2001] 2 Suppl. SCR 195         referred to             Paras

 H
     ALKA CHANDEWAR v. SHAMSHUL ISHRAR KHAN                                     535


       CIVIL APPELLATE JURISDICTION: Civil Appeal No.8720                       A
of 2017.
        From the Judgment and Order dated 27.10.2015 of the High
Court ofJudicature at Bombay in Contempt Petition No.102 of2015.
         B. H. Marlapalle, Sr. Adv. S. Y. Chi tale, Abhijat P. Medh, Advs.
                                                                                B
for the Appellant.
       Rana Mukherjee, Sr. Adv., Partha Sil, Tavish B. Prasad,
Ms. Subhoshree Sil, Advs. for the Respondent.
        The Judgment of the Court was delivered by
         R. F. NARIMAN, J. 1. Leave granted.                                    c
         2. The present appeal arises from the judgment of the Bombay
High Court dated 271h October, 2015, in which the High Court has
construed Section 27(5) of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as "the Act") in a somewhat restrictive manner.
The facts necessary to appreciate the point involved in this appeal are         D
that on 7'h October, 2010, the sole Arbitrator appointed by the parties
passed an interim order under Section 17 of the said Act, in which it was
mentioned that no further flats were to be disposed of without the leave
of the Arbitral Tribunal. In breach of this order, it is alleged that on 14'h
October, 2010 the respondent in fact transferred five such flats. By the        E
order passed on 22"d March, 2012, it was held by the learned Arbitrator
that the order of 71h October, 2010 had, in fact, been breached by the
respondent and certain other interim directions were made by the
aforesaid order. Ultimately, by an order dated 5'h May, 2014, the learned
Arbitrator referred the aforesaid contempt of the order dated 7•h October,
2010 to the High Court to pass necessary orders thereon under Section           F
27(5) of the Act.
         3. In the judgment under appeal, the High Court held:
         "In view of the above discussion, Section 27(5) of the Arbitration
       and Conciliation Act, 1996 does not empower the Tribunal to make
       representation to the Court for contempt if the orders including G
       the interim orders passed by the Arbitrator except in respect of
       taking evidence are violated by the party. The Contempt Petition
       being the representation made by the Tribunal is beyond the period
       of limitation and is not maintainable in law. Moreover, the final
                                                                            H
536            SUPREME COURT REPORTS                           [2017] 6 S.C.R.


A           award ofRs.8 crores is granted in favour of the petitioner by the
            Arbitrator."
             4. We have heard learned counsel for the parties. Shri B.H.
      Marlapalle, learned senior counsel appearing on behalf of the appellant,
      has argued that Sections 9 and 17 being alternative remedies available
B     to the parties before the Tribunal, if orders made under Section-17 were
      unenforceable, they would be mere ropes of sand as a result of which
      the provision would be rendered otiose. He also argued that Section 27
      of the Act does not leave any doubt as to the scope and ambit of the
      Court's power to punish for contempt of orders made by the Arbitral
      Tribunal. He relied upon a Delhi High Court judgment, and a judgment
 C    delivered by this Court reported in 2007 ( 13) SCC 220.
             5 .On the other hand, Shri Rana Mukherjee, learned senior counsel
      appearing on behalf of the respondent, has supported the High Court
      judgment. However, he very fairly states before us that he does not
      support the High Court judgment on the aspect oflimitation. According
 D    to him, the marginal note of Section 27 makes it clear that Section 27(5)
      would only apply to assistance in taking evidence and not to any other
      contempt that may be committed. According to him, this lacuna in the
      law has now been filled pursuant to the 246'h Law Commission Report,
      which he has referred to and relied upon, after which Section 17(2) has
 E    been inserted by the Amendment Act of 2015.
             6. Having heard learned counsel for the parties, we first set out
      the relevant statutory provisions as under:
             9. Interim measures, etc. by Court -(I) A party may, before, or
      during arbitral proceedings or at any time after the making of the arbitral
 F    award but before it is enforced in accordance with section 36, apply to a
      court:
            (i) for the appointment of a guardian for a minor or person of
            unsound mind for the purposes of arbitral proceedings; or
             (ii) for an interim measure of protection in respect of any of the
 G
             following matters, namely:
             (a) the preservation, interim,custody or sale of any goods, which
             are the subject matter of the arbitration agreement;
             (b) securing the amount in dispute in the arbitration;
 H
ALKA CHANDEWAR v. SHAMSHUL ISHRAR KHAN                                   537
            [R. F. NARIMAN, J.]

(c) the detention, preservation or inspection of any property or         A
thing which is the subject-matter of the dispute in arbitration, or
as to which any question may arise therein and authorising for
any of the aforesaid purposes any person to enter upon any land
or building in the possession of any party, or authorising any samples
to be taken or any observation to be made, or experiment to be           B
tried, which may be necessary or expedient for the purpose of
obtaining full information or evidence;
(d) interim injunction or the appointment of a receiver;
(e) such other interim measure of protection as may appear to the
court to be just and convenient,                                         c
and the Court shall have the same power for making orders as it
has for the purpose of, and in relation to, any proceedings before
it.
[(2) Where, before the commencement of the arbitral proceedings,
a Court passes an order for any interim measure of protection            D
under sub-section (1 ), the arbitral proceedings shall be commenced
within a period of ninety days from the date of such order or
within such further time as the Court may determine.
(3) Once the arbitral tribunal has been constituted, the Court
shall not entertain an application under sub-section (I), unless the     E
Court finds that circumstances exists which may not render the
remedy provided under section 17 efficacious.]
17. Interim measures ordered by arbitral tribunal- [(!)A party
may, during the arbitral proceedings or at any time after the making
of the arbitral award but before it is enforced in accordance with       F
section 36, apply to the arbitral tribunal-
(i) for the .appointment of a guardian for a minor or person of
unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of the
following matters, namely:-                                              G

( a) the preservation, interim custody or sale of any goods which
are the subject matter of the arbitration agreement;
(b) securing the amount in dispute in the arbitration;
                                                                         H
538      SUPREME COURT REPORTS                            [2017] 6 S.C.R.


.A    (c) the detention, preservation or inspection of any property or
      thing which is the subject matter of the dispute in arbitration, or as
      to which any question may arise therein and authorising for any
      of the aforesaid purposes any person to enter upon any land or
      building in the possession of any party, or authorising any samples
      to be taken, or any observation to be made, or experiment to be
B
      tried, which may be necessary or expedient for the purpose of
      obtaining full information or evidence;
      (d) interim injunction or the appointment of a receiver;
      (e) such other interim measure of protection as may appear to
C     the arbitral tribunal to be just and convenient,
      and the arbitral tribunal shall have the same power for making
      orders, as the court has for the purpose of, and in relation to, any
      proceedings before it.
.D    (2) Subject to any orders passed in an appeal under section 37,
      any order issued by the arbitral tribunal under this section shall be
      deemed to be an order of the Court for all purposes and shall be
      enforceable under the Code of Civil Procedure, 1908 (5of1908),
      in the same manner as if it were an order of the Court.]
 E    27. Court assistance in taking evidence-( l) The arbitral tribunal,
      or a party with the approval of the arbitral tribunal, may apply to
      the court for assistance in taking evidence.
      (2) the application shall specify-
      ( a) the names and addresses of the parties and the arbitrators;
 F
      (b) the general nature of the claim and the relief sought;
      (c) the evidence to be obtained, in particular, -
      (i) the name and address of any person to be heard as witness or
      expert witness and a statement of the subject-matter of the
 G
      testimony required;
      (ii) the description of any document to be produced or property
      to be inspected.


 H
     ALKA CHANDEWAR v. SHAMSHUL ISHRAR KHAN                                 539
                 [R. F. NARIMAN, J.]

      (3) The Court may, within its competence and according to its         A
      rules on taking evidence, execute the request by ordering that the
      evidence be provided directly to the arbitral tribunal.
      (4) The Court may, while making an order under sub-section (3),
      issue the same processes to witnesses as it may issue in suits
      tried before it.                                                       B
      (5) Persons failing to attend in accordance with such process, or
      making any other default, or refusing to give their evidence, or
      guilty of any contempt to the arbitral tribunal during the conduct
      ofarbitral proceedings, shall be subject to the like disadvantages,
      penalties and punishments by order of the court on the                c
      representation of the arbitral tribunal as they would incur for the
      like offences in suits tried before the Court.
      (6) In this section the expression "Processes" includes summonses
      and commissions for the examination of witnesses and summonses
      to produce documents.                                                  D
     7. If Section 27(5) is read literally, there is no difficulty in accepting
the plea of learned senior advocate for the appellant, because persons
failing to attend in accordance with the court process fall under a separate
category from "any other default". Further, the Section is not confined
to a person being guilty of contempt only when failing to attend in E
ac.cordance with such process. The Section specifically states that persons
guilty ofany contempt to the Arbitral Tribunal during the conduct of the.
Arbitral proceedings is within its ken. The aforesaid language is, in fact,
in consonance with the Chapter heading of Chapter V, "Conduct of arbitral
proceedings". Further, it is well settled that a marginal note can be used
as an internal aid to interpretation of statutes only in order to show what F
is the general drift of the section. It may also be resorted to when the
plain meaning of the section is not clear. In the present case we must go
by the plain meaning of sub-section (5). This being the case, we find it
difficult to appreciate the reasoning of the High Court. Also, in
consonance with the modem rule of interpretation of statutes, the entire G
object ofproviding that a party may approach the Arbitral Tribunal instead
of the Court for interim reliefs would be stultified ifinterim orders passed
by such Tribunal are toothless. It is to give teeth to such orders that an
express provision is made in Section 27(5) of the Act.

                                                                             H
540             SUPREME COURT REPORTS                          [2017] 6 S.C.R.


A              8. In fact, the Delhi High Court by the judgment dated 18 11'
      August, 2009, reported in 2009 (112) Delhi Reported Judgments 657,
      has correctly construed Section 27(5) of the Act. Further, it must be
      remembered that this Court in Mis Ambalal Sarabhai Enterprises vs. M/
      s Amrit Lal & Co. & Anr. (2001) 8 SCC 397 has held that parties to
      arbitration proceedings are put to an election as to whether to apply for
B
      interim relief before the Tribunal under Section 17 or before the Court
      under Section 9. Such election would be meaningless ifinterim orders
      passed by the Arbitral Tribunal were to be written in water, as all parties
      would then go only to the Court, which would render Section 17 a dead
      letter.
 C              9. Coming to Shri Rana Mukherjee's submission that sub-section
      (2) of Section 17 introduced by the 2015 Amendment Act now provides
      for the necessary remedy against infraction of interim orders by Tribunal,
      suffice it to state that the Law Commission itself, in its 246'" report,
      found the need to go one step further than what was provided in Section
D     27(5) as construed by the Delhi High Court (supra). The Commission,
      in its report, had this to say:
        POWERS OF TRIBUNAL TO ORDER INTERIM MEASURES
               46. Under section 17, the arbitral tribunal has the power to order
      interim measures of protection unless the parties have excluded such
 E    power by agreement. Section 17 is an important provision, which is
      crucial to the working of the arbitration system, since it ensures that
      even for the purposes of interim measures, the parties can approach the
      arbitral tribunal rather than await orders from a Court.
              The efficacy of section 17 is however, seriously compromised
      given the lack of any suitable statutory mechanism for the enforcement
 F
      of such interim orders of the arbitral tribunal.
               47. In Sundaram Finance Ltd. v. NEPC India Ltd., (1999) 2
      SCC 479, the Supreme Court observed that though section 17 gives the
      arbitral tribunal the power to pass orders, the same cannot be enforced
      as orders of a court and it is for this reason only that section 9 gives the
 G    court power to pass interim orders during the arbitration proceedings.
      Subsequently, in M.D. Army Welfare Housing Organisation v.
      Sumangal Services Pvt. Ltd., (2004) 9 SCC 619 the Court had held
      that under section 17 of the Act no power is conferred on the arbitral
      tribunal to enforce its order nor does it provide for judicial enforcement
 H    thereof.
     ALKA CHANDEWAR v. SHAMSHUL ISHRAR KHAN                                      541
                [R. F. NARIMAN, J.]

         48. In the face ofsucli c~tegorical judicial opinion, the Delhi         A
High Court attempted to find a suitable legislative basis for enforcing the
orders of the arbitral tribunal under Section 17 in the case of Sri Krishan
v. Anand, (2009) 3 Arb LR 447 (Del) (followed in Indiabulls Financial
Services v. Jubilee Plots, OMP Nos.452-453/2009 Order dated
18.08.2009). The Delhi High Court held that any person failing to comply         B
with the order of the arbitral tribunal under section 17 would be deemed
to be "making any other default" or "guilty" of any contempt to the
arbitral tribunal during the conduct of the proceedings" under section
27(5) of Act. The remedy of the aggrieved party would then be to apply
to the arbitral tribunal for making a representation to the Court to mete
out appropriate punishment. Once such a representation is received by            C
the Court from the arbitral tribunal, the Court would be competent to
deal with such party in default as if it is in contempt of an order of the
Court, i.e., either under the provisions of the Contempt of Courts Act or
under the provisions of Order 39 Rule 2A Code of Civil Procedure,
1908.
                                                                                 D
          49. The Commission believes that while it is important to provide
teeth to the interim orders of the arbitral tribunal as well as to provide for
their enforcement, the judgment of the Delhi High Court in Sri Krishan
v. Anand is not a complete solution. The Commission has, therefore,
recommended amendments to section 17 of the Act which would give
teeth to the orders of the Arbitral Tribunal and the same would be               E
statutorily enforceable in the same manner as the Orders of a Court. In
this respect, the views of the Commission are consistent with (though do
not go as far as) the 2006 amendments to Article 17 of the UNCITRAL
Model Law.
        10. Pursuant to this report, sub-section(2) to Section 17 was            F
added by the Amendment Act 2015, so that the cumbersome procedure
of an Arbitral Tribunal ·having to apply every time to the High Court for
contempt of its orders would no longer be necessary. Such orders would
now be deemed to be orders of the Court for all purposes and would be
enforced under the Civil Procedure Code, 1908 in the same manner as if           G
they were orders of the Court. Thus we do not find Shri Rana
Mukherjee's submission to be of any substance in view of the fact that
Section 17(2) was enacted for the purpose of providing a "complete
solution" to the problem.

                                                                                 H
542                SUPREME COURT REPORTS                    [2017] 6 S.C.R.


A             11.Accordingly, we allow the appeal and set aside the judgment
      of the Bombay High Court. The matter is remanded to decide the alleged
      contempt on facts. It would be open for the respondent to argue before
      the High Court that he has, on the facts of the case, not committed any
      contempt.


      Nidhi Jain                                               Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.